CN106194137A - A kind of based on steam injection allocation and the gathering and transporting device of oil gas metering - Google Patents

A kind of based on steam injection allocation and the gathering and transporting device of oil gas metering Download PDF

Info

Publication number
CN106194137A
CN106194137A CN201610780801.3A CN201610780801A CN106194137A CN 106194137 A CN106194137 A CN 106194137A CN 201610780801 A CN201610780801 A CN 201610780801A CN 106194137 A CN106194137 A CN 106194137A
Authority
CN
China
Prior art keywords
metering
steam
connects
oil
turn
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610780801.3A
Other languages
Chinese (zh)
Other versions
CN106194137B (en
Inventor
李书江
关晓明
熊晓庆
曾俊武
胡晓阳
秦丽英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING PETRODAMO ENGINEERING TECHNOLOGY Co Ltd
Original Assignee
BEIJING PETRODAMO ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING PETRODAMO ENGINEERING TECHNOLOGY Co Ltd filed Critical BEIJING PETRODAMO ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201610780801.3A priority Critical patent/CN106194137B/en
Publication of CN106194137A publication Critical patent/CN106194137A/en
Application granted granted Critical
Publication of CN106194137B publication Critical patent/CN106194137B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/16Enhanced recovery methods for obtaining hydrocarbons
    • E21B43/24Enhanced recovery methods for obtaining hydrocarbons using heat, e.g. steam injection
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B34/00Valve arrangements for boreholes or wells
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geophysics (AREA)
  • Measuring Volume Flow (AREA)
  • Pipeline Systems (AREA)

Abstract

The present invention discloses a kind of based on steam injection allocation and the gathering and transporting device of oil gas metering, including main pipe line, multiple well multiple-way valve, steam measurement device, electric control valve, adopt liquid dynamoelectric switching valve, metering-separating device and oil-collecting header, main pipe line connects with multiple well multiple-way valve, steam measurement device one end is connected with main pipe line by metering arm, the steam measurement device other end connects with multiple well multiple-way valve, multiple well multiple-way valve connects with at least two individual well, connected by steam branch line between each individual well with multiple well multiple-way valve, electric control valve is positioned on steam branch line, adopt liquid dynamoelectric switching valve to be positioned on oil-collecting branch line, metering-separating device one end connects with individual well, the metering-separating device other end connects with oil-collecting header, individual well connects with oil-collecting header.The present invention based on steam injection allocation and the gathering and transporting device of oil gas metering, operational process is simple, maximum reduces that individual well collection is defeated, the repeated construction of injection allocation pipeline, effectively reduces project total cost.

Description

A kind of based on steam injection allocation and the gathering and transporting device of oil gas metering
Technical field
The present invention relates to steam soak develop oil fields technical field, particularly relate to a kind of based on steam injection allocation and oil gas meter The gathering and transporting device of amount.
Background technology
At present, the general development schemes using steam to drive of domestic and international viscous crude field exploitation more.It is typically the oil in oil district Well, first injects a number of steam by several times in batches, then carries out vexed well.When closed time reaches the predetermined time, will This well transfers oil recovery to.The output object of oil well can be transported to measuring station by pipe special.
The development scheme using steam to drive, typically builds multiple steam injection allocation station and multiple collection in administrative oily district respectively Defeated measuring station.The task that steam injection allocation station owner wants is to receive steam boiler (master station) to manage the defeated high-pressure and high-temperature steam come, and will connect The steam received passes through injection allocation manifold, and through the flow-meter of individual well and flow control valve, (every mouthful of well is respectively mounted a stream Amount measuring instrument and a set of flow control valve), distribute to the oil well that this station is administered.The task of measuring station has been only to every mouthful The oil-producing aerogenesis of oil well carries out the metering of necessity and manages defeated.
Owing in the oily district that employing is administrative, steam injection allocation station and oil gas metering station distributed points are many, jet chimney and oil extraction pipeline Intersect and lay, form complicated oil district pipe network.
Summary of the invention
The present invention completes to solve deficiency of the prior art, it is an object of the invention to provide a kind of operation and flows Journey reduces that individual well collection is defeated, the repeated construction of injection allocation pipeline simply, to greatest extent, and makes complicated oil district pipe network smooth and easy In order, thus effectively reduce project total cost based on steam injection allocation and the gathering and transporting device of oil gas metering.
The present invention a kind of based on steam injection allocation and the gathering and transporting device of oil gas metering, including main pipe line, multiple well multiple-way valve, Steam measurement device, electric control valve, adopt liquid dynamoelectric switching valve, metering-separating device and oil-collecting header, described main pipe line and institute Stating the connection of multiple well multiple-way valve formula able to turn on or off, described steam measurement device one end is able to turn on or off with described main pipe line by metering arm Formula connects, and the described steam measurement device other end connects with described multiple well multiple-way valve formula able to turn on or off, described multiple well multiple-way valve Formula able to turn on or off with at least two individual well connects, and is connected by steam branch line between each described individual well and described multiple well multiple-way valve Logical, described electric control valve is positioned on described steam branch line, described in adopt liquid dynamoelectric switching valve and be positioned on oil-collecting branch line, Described metering-separating device one end formula able to turn on or off with described individual well connects, and the described metering-separating device other end converges with described oil-collecting Managing formula able to turn on or off connection, described individual well connects with described oil-collecting header formula able to turn on or off.
A kind of based on steam injection allocation and oil gas metering the gathering and transporting device of the present invention it may also is that
Described liquid dynamoelectric switching valve of adopting is three-way valve, described in adopt liquid dynamoelectric switching valve one all pass by metering system pipeline with Described metering-separating device formula able to turn on or off connects, described in adopt liquid dynamoelectric switching valve two-way and described oil-collecting header formula able to turn on or off even Logical, described in adopt liquid dynamoelectric switching valve threeway formula able to turn on or off with described branch line and connect.
Described metering-separating device includes metering separator, gas phase flow rate meter and liquid phase stream gauge, described metering separator Top connects with described gas phase flow rate meter formula able to turn on or off by separating gas phase pipeline, described gas phase flow rate meter and described oil-collecting header Formula able to turn on or off connects, and described metering separator bottom connects with described liquid phase stream gauge formula able to turn on or off by separating liquid phase pipeline, Described liquid phase stream gauge connects with described oil-collecting header formula able to turn on or off.
Being provided with blowoff line bottom described metering separator, described blowoff line one end connects with described metering separator, The described blowoff line other end connects with described oil-collecting header.
Described metering separator top is provided with blow-down pipe, and described blow-down pipe one end connects with described metering separator, The described blow-down pipe other end and ft connection.
Described steam measurement device includes steam-flow meter, and described steam-flow meter one end is by described metering arm and institute Stating the connection of main pipe line formula able to turn on or off, the described steam-flow meter other end connects with described multiple well multiple-way valve formula able to turn on or off.
Described main pipe line is provided with pressure transmitter, and described pressure transmitter connects with described main pipe line.
Being additionally provided with temperature transmitter on described main pipe line, described temperature transmitter connects with described main pipe line, described temperature Transmitter is positioned at the rear portion of described pressure transmitter.
Being additionally provided with thermometer on described main pipe line, described thermometer connects with described main pipe line, and described thermometer is positioned at institute State the rear portion of temperature transmitter.
The present invention a kind of based on steam injection allocation and the gathering and transporting device of oil gas metering, including main pipe line, multiple well multiple-way valve, Steam measurement device, electric control valve, adopt liquid dynamoelectric switching valve, metering-separating device and oil-collecting header, described main pipe line and institute Stating the connection of multiple well multiple-way valve formula able to turn on or off, described steam measurement device one end is able to turn on or off with described main pipe line by metering arm Formula connects, and the described steam measurement device other end connects with described multiple well multiple-way valve formula able to turn on or off, described multiple well multiple-way valve Formula able to turn on or off with at least two individual well connects, and is connected by steam branch line between each described individual well and described multiple well multiple-way valve Logical, described electric control valve is positioned on described steam branch line, described in adopt liquid dynamoelectric switching valve and be positioned on oil-collecting branch line, Described metering-separating device one end formula able to turn on or off with described individual well connects, and the described metering-separating device other end converges with described oil-collecting Managing formula able to turn on or off connection, described individual well connects with described oil-collecting header formula able to turn on or off.So, carry out steam when steam injection station and need not meter During amount, open the path between main pipe line and multiple well multiple-way valve, close the path between main pipe line and steam measurement device, beat Drive the electric control valve on this individual well steam branch line, close and adopt liquid dynamoelectric switching valve on this individual well oil-collecting branch line, After main pipe line carrys out vapour, after entering multiple well multiple-way valve, it is reallocated to the individual well of required steam supply, thus meets the need of individual well steam injection amount Ask.When steam injection station come steam need metering time, open the path between main pipe line and multiple well multiple-way valve, open main pipe line simultaneously And the path between steam measurement device, opens the electric control valve on this individual well steam branch line, closes this individual well oil-collecting Adopting liquid dynamoelectric switching valve on branch line, after main pipe line carrys out steam, a part of steam enters metering arm pipeline and through steaming After vapour metering device enters multiple well multiple-way valve, then distribute to need the individual well of metering through multiple well multiple-way valve, according to steam The data of display on metering device, constantly adjustment needs the aperture size of the electric control valve on the individual well of metering, with last full The demand of foot steam injection amount, staff just can clearly know the steam injection amount entering this individual well by steam measurement device. The steam that another part main pipe line comes enters multiple well multiple-way valve by the path between main pipe line and multiple well multiple-way valve, steam After, it is reallocated to the required steam supply individual well without metering, thus meets the demand of individual well steam injection amount, both can meet needs The individual well steam supply of metering, it is also possible to meet the individual well steam supply that need not metering.Steam injection is complete when carrying out adopting liquid, if adopting liquid needs During metering, close the electric control valve on this individual well steam branch line, open on this individual well oil-collecting branch line adopt liquid electricity Dynamic switching valve, switching is adopted liquid dynamoelectric switching valve and is gone to connect metering-separating device, enters metering-separating device laggard circulation of qi promoting phase and liquid The separation of phase, finally outer defeated through oil-collecting header.Steam injection is complete when carrying out adopting liquid, if adopting liquid when need not metering, closes this list Electric control valve on well steam branch line, opens and adopts liquid dynamoelectric switching valve on this individual well oil-collecting branch line, will adopt liquid It is outer defeated that dynamoelectric switching valve goes to connect oil-collecting header.The present invention a kind of is based on steam injection allocation and the gathering and transporting device of oil gas metering, phase For prior art, its operational process reduces that individual well collection is defeated, the repeated construction of injection allocation pipeline simply, to greatest extent, and Make complicated oil district pipe network smooth and easy in order, thus effectively reduce project total cost.
Accompanying drawing explanation
Fig. 1 is that the present invention a kind of is based on steam injection allocation and the structure chart of the gathering and transporting device of oil gas metering.
Fig. 2 is another the structure chart of a kind of based on steam injection allocation and oil gas metering gathering and transporting device of the present invention.
Figure number explanation
1 ... main pipe line 2 ... pressure transmitter 3 ... temperature transmitter
4 ... thermometer 6 ... metering arm 7 ... steam-flow meter
8 ... electric control valve 19 ... adopt liquid dynamoelectric switching valve 24 ... remove metering system pipeline
25 ... oil-collecting header 26 ... metering separator 27 ... separate gas phase pipeline
28 ... gas phase flow rate meter 29 ... liquid phase stream gauge 30 ... separate liquid phase pipeline
31 ... blowoff line 32 ... blow-down pipe 33 ... multiple well multiple-way valve
40 ... steam measurement device 50 ... metering-separating device
Detailed description of the invention
Fig. 1-2 below in conjunction with the accompanying drawings a kind of based on steam injection allocation and oil gas metering the gathering and transporting device of the present invention is made into One step describes in detail.
The present invention a kind of based on steam injection allocation and the gathering and transporting device of oil gas metering, refer to Fig. 1-2, including main pipe line 1, Multiple well multiple-way valve 33, steam measurement device 40, electric control valve 8, adopt liquid dynamoelectric switching valve 19, metering-separating device 50 and collection Oil header 25, described main pipe line 1 connects with described multiple well multiple-way valve 33 formula able to turn on or off, and described steam measurement device 40 one end leads to Crossing metering arm 6 to connect with formula able to turn on or off with described main pipe line 1, described steam measurement device 40 other end is many with described multiple well Logical valve 33 formula able to turn on or off connection, described multiple well multiple-way valve 33 formula able to turn on or off with at least two individual well connects, each described individual well Connecting by steam branch line with between described multiple well multiple-way valve 33, described electric control valve 8 is positioned at described steam branched pipe Lu Shang, described in adopt liquid dynamoelectric switching valve 19 and be positioned on oil-collecting branch line, described metering-separating device 50 one end and described individual well Formula able to turn on or off connect, described metering-separating device 50 other end connects with described oil-collecting header 25 formula able to turn on or off, described individual well and Described oil-collecting header 25 formula able to turn on or off connects.So, when steam injection station come steam need not metering time, open main pipe line 1 and Duo Jing Path between formula multiple-way valve 33, closes the path between main pipe line 1 and steam measurement device 40, opens this individual well steam branch Electric control valve 8 on pipeline, cuts out and adopts liquid dynamoelectric switching valve 19 on this individual well oil-collecting branch line, after main pipe line 1 carrys out vapour, After entering multiple well multiple-way valve 33, it is reallocated to the individual well of required steam supply, thus meets the demand of individual well steam injection amount.When steam injection station Come steam need metering time, open the path between main pipe line 1 and multiple well multiple-way valve 33, open main pipe line 1 and steam simultaneously Path between metering device 40, opens the electric control valve 8 on this individual well steam branch line, closes this individual well oil-collecting branch Adopting liquid dynamoelectric switching valve 19 on pipeline, after main pipe line 1 carrys out steam, a part of steam enters metering arm 6 pipeline and through steaming After vapour metering device 40 enters multiple well multiple-way valve 33, then distribute to need the individual well of metering, root through multiple well multiple-way valve 33 According to the data of display on steam measurement device 40, constantly adjustment needs the aperture size of the electric control valve 8 on the individual well of metering, Finally to meet the demand of steam injection amount, staff just can clearly know this individual well of entrance by steam measurement device 40 Steam injection amount.The steam of another part main pipe line 1 is by the path between main pipe line 1 and multiple well multiple-way valve 33, and steam enters After entering multiple well multiple-way valve 33, it is reallocated to the required steam supply individual well without metering, thus meets the need of individual well steam injection amount Ask, both can meet the individual well steam supply of needs metering, it is also possible to meet the individual well steam supply that need not metering.Carry out when steam injection is complete When adopting liquid, if adopt liquid need metering time, close the electric control valve 8 on this individual well steam branch line, open this individual well collection Adopting liquid dynamoelectric switching valve 19 on oil branch line, switching is adopted liquid dynamoelectric switching valve 19 and is gone to connect metering-separating device 50, enters Metering-separating device 50 laggard circulation of qi promoting phase and the separation of liquid phase, finally outer defeated through oil-collecting header 25.Steam injection is complete when carrying out adopting liquid, If adopting liquid when need not metering, closing the electric control valve 8 on this individual well steam branch line, opening this individual well oil-collecting branch Adopting liquid dynamoelectric switching valve 19 on pipeline, adopting liquid dynamoelectric switching valve 19, to go to connect oil-collecting header 25 outer the most defeated.The one of the present invention Based on steam injection allocation and the gathering and transporting device of oil gas metering, in terms of existing technologies, its operational process is simply, to greatest extent Minimizing individual well collection is defeated, the repeated construction of injection allocation pipeline, and makes complicated oil district pipe network smooth and easy in order, thus effectively reduces Project total cost.
The present invention a kind of based on steam injection allocation and the gathering and transporting device of oil gas metering, refer to Fig. 1-2, previously described On the basis of technical scheme it may also is that described in adopt liquid dynamoelectric switching valve 19 for three-way valve, described in adopt liquid dynamoelectric switching valve 19 1 All passing by metering system pipeline connects with described metering-separating device 50 formula able to turn on or off, described in adopt liquid dynamoelectric switching valve 19 two-way Connect with described oil-collecting header 25 formula able to turn on or off, described in adopt liquid dynamoelectric switching valve 19 threeway and described branch line formula able to turn on or off even Logical.So, when carrying out liquid and needing metering, switching adopts liquid dynamoelectric switching valve 19 liquid in the future by going metering system pipeline to enter metering In segregation apparatus 50, carry out the separation of gas phase and liquid phase, finally outer defeated through oil-collecting header.When carrying out liquid and need not metering, switching Adopt liquid dynamoelectric switching valve 19 to connect with oil-collecting header 25, be directly entered oil-collecting header 25 carry out outer defeated by the liquid that comes of individual well.When When individual well is in steam injection state, adopts liquid dynamoelectric switching valve 19 described in switching and be closed with described steam branch line.Also May is that described metering-separating device 50 includes metering separator 26, gas phase flow rate meter 28 and liquid phase stream gauge 29, described metering Separator 26 top connects with described gas phase flow rate meter 28 formula able to turn on or off by separating gas phase pipeline 27, described gas phase flow rate meter 28 Connecting with described oil-collecting header 25 formula able to turn on or off, described metering separator 26 bottom is by separating liquid phase pipeline 30 and described liquid phase Effusion meter 29 formula able to turn on or off connects, and described liquid phase stream gauge 29 connects with described oil-collecting header 25 formula able to turn on or off.So, steam injection is complete When Bi Jinhang adopts liquid, if adopt liquid need metering time, close the electric control valve 8 on this individual well steam branch line, open this Adopting liquid dynamoelectric switching valve 19 on individual well oil-collecting branch line, switching is adopted liquid dynamoelectric switching valve 19 and is gone to connect metering separator 26, Enter metering separator 26 and carry out the separation of gas phase and liquid phase, the gas phase flow rate meter on gas separated gas phase pipeline 27 after separation Entering oil-collecting header 25 after 28 meterings outer defeated, the liquid phase quality effusion meter 29 on the separated liquid phase pipeline of liquid phase 30 after separation is counted After amount, outer defeated also into oil-collecting header 25.Further preferred version is: be provided with blowoff line bottom described metering separator 26 31, described blowoff line 31 one end connects with described metering separator 26, and described blowoff line 31 other end converges with described oil-collecting Pipe 25 connects.So, when equipment needs to clean or safeguard, bottom metering separator 26, blowoff line 31, Ke Yitong it is provided with Cross blowoff line 31 and the sewage in metering separator 26, foreign material etc. are discharged by blowoff line 31, to ensure the normal of equipment Run.It may also is that described metering separator 26 top is provided with blow-down pipe 32, described blow-down pipe 32 one end and described metering Separator 26 connects, described blow-down pipe 32 other end and ft connection.So, if the pressure mistake in metering separator 26 Greatly, can be exhausted by blow-down pipe 32, to ensure the properly functioning of equipment.
The present invention a kind of based on steam injection allocation and the gathering and transporting device of oil gas metering, refer to Fig. 1-2, previously described It may also is that described steam measurement device 40 includes steam-flow meter 7, described steam-flow meter 7 one on the basis of technical scheme End is connected with described main pipe line 1 formula able to turn on or off by described metering arm 6, described steam-flow meter 7 other end and described many wells Formula multiple-way valve 33 formula able to turn on or off connects.So, when steam injection station come steam need metering time, open main pipe line 1 and fill with steam measurement Put the path between 40, open the electric control valve 8 on this individual well steam branch line, close on this individual well oil-collecting branch line Adopt liquid dynamoelectric switching valve 19, after main pipe line 1 carrys out steam, a part of steam enters metering arm 6 pipeline through steam flow After meter 7 entrance multiple well multiple-way valve 33, then distribute to need the individual well of metering through multiple well multiple-way valve 33, according to steam flow The data of display on meter 7, constantly adjustment needs the aperture size of the electric control valve 8 on the individual well of metering, finally to meet need The demand of the steam injection amount of individual well to be measured, staff just can clearly know this individual well of entrance by steam-flow meter 7 Steam injection amount.The steam of another part main pipe line 1 is by the path between main pipe line 1 and multiple well multiple-way valve 33, and steam enters After entering multiple well multiple-way valve 33, it is reallocated to the required steam supply individual well without metering, thus meets the need of individual well steam injection amount Ask, both can meet the individual well steam supply of needs metering, it is also possible to meet the individual well steam supply that need not metering.It may also is that it is described Main pipe line 1 is provided with pressure transmitter 2, and described pressure transmitter 2 connects with described main pipe line 1.So, pressure transmitter 2 is Refer to be output as the pressure transducer of standard signal, be that a kind of pressure variations that accepts is converted to the instrument of standard output signals in proportion Table, the pressure of steam in detecting and measure pipeline, staff can be intuitively by knowing that pressure transmitter 2 understands The pressure of steam is carried out in main pipe line 1.It may also is that be additionally provided with temperature transmitter 3, described temperature transmitter 3 on described main pipe line 1 Connecting with described main pipe line 1, described temperature transmitter 3 is positioned at the rear portion of described pressure transmitter 2.So, temperature transmitter 3 is A kind of instrument that temperature variable is converted to transmissible normalization output signal, arranging temperature transmitter 3 can see intuitively Examine the variations in temperature of steam in pipeline, provide convenient for staff.Further preferred version is: on described main pipe line 1 also Being provided with thermometer 4, described thermometer 4 connects with described main pipe line 1, after described thermometer 4 is positioned at described temperature transmitter 3 Portion.So, arranging thermometer 4, staff can control pipe by the temperature data checked and observe on this thermometer 4 The temperature data of steam in road, to ensure that equipment uses normally.
Above-mentioned only several specific embodiments in the present invention are illustrated, but can not be as the protection model of the present invention Enclose, every zoom in or out according to the equivalence change done by the design spirit in the present invention or modification or equal proportion, all should Think and fall into protection scope of the present invention.

Claims (9)

1. one kind based on steam injection allocation and the gathering and transporting device of oil gas metering, it is characterised in that: include main pipe line, multiple well manifold Valve, steam measurement device, electric control valve, adopt liquid dynamoelectric switching valve, metering-separating device and oil-collecting header, described main pipe line with Described multiple well multiple-way valve formula able to turn on or off connects, and described steam measurement device one end can be opened with described main pipe line by metering arm Enclosed connects, and the described steam measurement device other end connects with described multiple well multiple-way valve formula able to turn on or off, described multiple well manifold Valve formula able to turn on or off with at least two individual well connects, by steam branch line between each described individual well and described multiple well multiple-way valve Connection, described electric control valve is positioned on described steam branch line, described in adopt liquid dynamoelectric switching valve and be positioned at oil-collecting branch line On, described metering-separating device one end formula able to turn on or off with described individual well connects, the described metering-separating device other end and described collection Oil header formula able to turn on or off connection, described individual well connects with described oil-collecting header formula able to turn on or off.
The most according to claim 1 based on steam injection allocation and the gathering and transporting device of oil gas metering, it is characterised in that described in:, to adopt liquid Dynamoelectric switching valve is three-way valve, described in adopt liquid dynamoelectric switching valve one and all pass by metering system pipeline and described metering-separating device Formula able to turn on or off connects, described in adopt liquid dynamoelectric switching valve two-way and connect with described oil-collecting header formula able to turn on or off, described in adopt that liquid is electronic to be cut Change valve threeway formula able to turn on or off with described branch line to connect.
It is the most according to claim 1 based on steam injection allocation and the gathering and transporting device of oil gas metering, it is characterised in that: described metering Segregation apparatus includes metering separator, gas phase flow rate meter and liquid phase stream gauge, and described metering separator top is by separating gas phase Pipeline connects with described gas phase flow rate meter formula able to turn on or off, and described gas phase flow rate meter connects with described oil-collecting header formula able to turn on or off, institute State metering separator bottom by separate liquid phase pipeline connect with described liquid phase stream gauge formula able to turn on or off, described liquid phase stream gauge and Described oil-collecting header formula able to turn on or off connects.
It is the most according to claim 3 based on steam injection allocation and the gathering and transporting device of oil gas metering, it is characterised in that: described metering Separator bottom is provided with blowoff line, and described blowoff line one end connects with described metering separator, described blowoff line another End connects with described oil-collecting header.
It is the most according to claim 3 based on steam injection allocation and the gathering and transporting device of oil gas metering, it is characterised in that: described metering Separator top is provided with blow-down pipe, and described blow-down pipe one end connects with described metering separator, described blow-down pipe another End and ft connection.
6. according to described in claim 1-5 any one claim based on steam injection allocation and the gathering and transporting device of oil gas metering, It is characterized in that: described steam measurement device includes steam-flow meter, and described steam-flow meter one end is by described metering arm Formula able to turn on or off with described main pipe line connects, and the described steam-flow meter other end connects with described multiple well multiple-way valve formula able to turn on or off.
7. according to described in claim 1-5 any one claim based on steam injection allocation and the gathering and transporting device of oil gas metering, It is characterized in that: described main pipe line is provided with pressure transmitter, described pressure transmitter connects with described main pipe line.
It is the most according to claim 7 based on steam injection allocation and the gathering and transporting device of oil gas metering, it is characterised in that: described house steward Being additionally provided with temperature transmitter on line, described temperature transmitter connects with described main pipe line, and described temperature transmitter is positioned at described pressure The rear portion of power transmitter.
It is the most according to claim 8 based on steam injection allocation and the gathering and transporting device of oil gas metering, it is characterised in that: described house steward Being additionally provided with thermometer on line, described thermometer connects with described main pipe line, after described thermometer is positioned at described temperature transmitter Portion.
CN201610780801.3A 2016-08-30 2016-08-30 A kind of gathering and transporting device based on steam injection allocation and oil gas metering Active CN106194137B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610780801.3A CN106194137B (en) 2016-08-30 2016-08-30 A kind of gathering and transporting device based on steam injection allocation and oil gas metering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610780801.3A CN106194137B (en) 2016-08-30 2016-08-30 A kind of gathering and transporting device based on steam injection allocation and oil gas metering

Publications (2)

Publication Number Publication Date
CN106194137A true CN106194137A (en) 2016-12-07
CN106194137B CN106194137B (en) 2019-07-16

Family

ID=58086081

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610780801.3A Active CN106194137B (en) 2016-08-30 2016-08-30 A kind of gathering and transporting device based on steam injection allocation and oil gas metering

Country Status (1)

Country Link
CN (1) CN106194137B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114016983A (en) * 2021-11-10 2022-02-08 克拉玛依胜利高原机械有限公司 Oil field injection-production ratio accurate control steam injection pipeline and steam injection process

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4299278A (en) * 1980-06-20 1981-11-10 Beehler Vernon D Control system for well heating by steam
CN1828009A (en) * 2005-03-03 2006-09-06 岳玉全 Overground gathering and transporting system for petroleum exploitation and method thereof
CN201460851U (en) * 2009-06-24 2010-05-12 北京迪威尔石油天然气技术开发有限公司 Skid-mounted steam distribution metering station
CN203905930U (en) * 2014-06-09 2014-10-29 北京大漠石油工程技术有限公司 Steam flow adjusting and allocating device
CN104929609A (en) * 2015-06-30 2015-09-23 西安长庆科技工程有限责任公司 Large cluster well group natural gas gas-liquid separation metering mixed transportation skid-mounted unit
CN205314984U (en) * 2016-01-21 2016-06-15 北京大漠石油工程技术有限公司 Individual well oil gas measurement sledge
CN206035463U (en) * 2016-08-30 2017-03-22 北京大漠石油工程技术有限公司 Defeated device of collection based on evaporate auto parts notes and oil gas measurement

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4299278A (en) * 1980-06-20 1981-11-10 Beehler Vernon D Control system for well heating by steam
CN1828009A (en) * 2005-03-03 2006-09-06 岳玉全 Overground gathering and transporting system for petroleum exploitation and method thereof
CN201460851U (en) * 2009-06-24 2010-05-12 北京迪威尔石油天然气技术开发有限公司 Skid-mounted steam distribution metering station
CN203905930U (en) * 2014-06-09 2014-10-29 北京大漠石油工程技术有限公司 Steam flow adjusting and allocating device
CN104929609A (en) * 2015-06-30 2015-09-23 西安长庆科技工程有限责任公司 Large cluster well group natural gas gas-liquid separation metering mixed transportation skid-mounted unit
CN205314984U (en) * 2016-01-21 2016-06-15 北京大漠石油工程技术有限公司 Individual well oil gas measurement sledge
CN206035463U (en) * 2016-08-30 2017-03-22 北京大漠石油工程技术有限公司 Defeated device of collection based on evaporate auto parts notes and oil gas measurement

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114016983A (en) * 2021-11-10 2022-02-08 克拉玛依胜利高原机械有限公司 Oil field injection-production ratio accurate control steam injection pipeline and steam injection process

Also Published As

Publication number Publication date
CN106194137B (en) 2019-07-16

Similar Documents

Publication Publication Date Title
CN107061997A (en) Set up the method and monitoring system of multichannel water-supply structure leakage loss condition monitoring pipe network
CN206035463U (en) Defeated device of collection based on evaporate auto parts notes and oil gas measurement
CN103016948A (en) Online leak detection device for steam trap of steaming-water pipeline of thermal power plant
CN105569121A (en) Intelligent water feed pipeline system with pressure flow monitoring recording and teletransmission function
CN105917279A (en) Process automation field device
CN106870959A (en) A kind of new hot pipe network leakage monitoring device
CN103900842A (en) Self-suction-type Venturi water scrubber performance testing system
CN106194137A (en) A kind of based on steam injection allocation and the gathering and transporting device of oil gas metering
CN205691241U (en) A kind of transformator operating temperature detection device
CN103939746A (en) Well mouth prizer and integrated device including well mouth prizer
CN106194106B (en) A kind of multiple-way valve mixes liquid injection allocation metering device
CN105065909B (en) A kind of metering method of intelligent metering sled
CN103133871B (en) Pipeline online dynamic smart detection system and detection method thereof
CN102226549A (en) Multifunctional household-based heat metering distribution management device and metering method
CN202000985U (en) Saturated steam regulating and controlling device
CN206300740U (en) Harbour heating power energy monitoring system
CN103184864A (en) Gas well testing safety monitoring and controlling technology
CN109708989A (en) A kind of device and its application method for the measurement of Oil in circulating gas, water and particle content
CN206038058U (en) Transformer station owner becomes medium oil flow on -line measuring early warning system
CN209558041U (en) A kind of well group drops back to pressure metering device
CN202992656U (en) Steam direct-buried pipeline network leak detection and automatic alarm system
CN204327074U (en) Shale gas ground open flow safety monitoring assembly
CN202547737U (en) Online power plant feedwater flow calibration device based on heat balance
CN206053902U (en) A kind of multiple-way valve mixes liquid injection allocation metering device
CN103940473B (en) The method of testing and device of gland leak-off amount between a kind of high intermediate pressure cylinder conjunction cylinder cylinder of steam turbine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant