CN106193623A - A kind of prefabricated concrete structure construction method - Google Patents

A kind of prefabricated concrete structure construction method Download PDF

Info

Publication number
CN106193623A
CN106193623A CN201610624394.7A CN201610624394A CN106193623A CN 106193623 A CN106193623 A CN 106193623A CN 201610624394 A CN201610624394 A CN 201610624394A CN 106193623 A CN106193623 A CN 106193623A
Authority
CN
China
Prior art keywords
construction
floor
vertical
prefabricated
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610624394.7A
Other languages
Chinese (zh)
Other versions
CN106193623B (en
Inventor
刘祥锦
刘俊彦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610624394.7A priority Critical patent/CN106193623B/en
Publication of CN106193623A publication Critical patent/CN106193623A/en
Application granted granted Critical
Publication of CN106193623B publication Critical patent/CN106193623B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14—Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种装配式混凝土结构施工方法,该施工方法对当前施工楼层的竖向构件的安装采用逆作工序,即在当前施工楼层的水平构件的连接装配还没有完成前,先吊装其上方相连接的竖向构件,最后浇筑连接混凝土一次性将当前施工楼层的水平构件和竖向构件连接成一体。本发明的施工方法采用逆作工序,可以减少施工环节、减少施工工期,其适用于预制剪力墙、复合墙板和框架等结构体系的装配式混凝土建筑施工,具有施工方便、省时、经济、环保等优点;同时实现达到与现浇结构同等性能要求。

The invention discloses a construction method of an assembled concrete structure. The construction method adopts a reverse process for the installation of the vertical components of the current construction floor, that is, before the connection and assembly of the horizontal components of the current construction floor is completed, the other components are hoisted first. For the vertical components connected above, the connecting concrete is finally poured to connect the horizontal components and vertical components of the current construction floor into one. The construction method of the present invention adopts the reverse operation process, which can reduce the construction links and construction period. It is suitable for the construction of prefabricated concrete buildings with structural systems such as prefabricated shear walls, composite wall panels and frames, and has the advantages of convenient construction, time saving and economical construction. , environmental protection and other advantages; at the same time achieve the same performance requirements as the cast-in-place structure.

Description

一种装配式混凝土结构施工方法A construction method for prefabricated concrete structures

技术领域technical field

本发明涉及预制装配式混凝土建筑施工技术,属于建筑工业化生产领域,具体为一种装配式混凝土结构施工方法。The invention relates to a prefabricated concrete building construction technology, belongs to the field of building industrial production, and specifically relates to a construction method of a prefabricated concrete structure.

背景技术Background technique

国家提出智慧城市、绿色建筑及建筑工业化的未来建筑业发展方向;并提出10年左右时间,使装配式建筑占新建建筑的比例达到30%;因此科技部发出《“绿色建筑及建筑工业化”重点专项2016年度项目申报指南具体通知》提到课题研究内容(摘录与本发明相关的部分内容):研究提出新型系列连接节点形式,达到与现浇结构同等性能要求;适用于预制装配式混凝土结构的标准化、工具化吊装与支撑体系等。The country proposes the future development direction of the construction industry of smart cities, green buildings and construction industrialization; and proposes that in about 10 years, the proportion of prefabricated buildings in new buildings will reach 30%; therefore, the Ministry of Science and Technology issued the "Green Building and Construction Industrialization" key The specific notice of the special 2016 annual project declaration guide mentioned the research content of the subject (excerpted part of the content related to the present invention): the study proposes a new series of connection node forms, which meet the same performance requirements as the cast-in-place structure; it is suitable for prefabricated concrete structures. Standardized, tool-based hoisting and support systems, etc.

目前我国的装配式建筑还没有系统上解决上述研究课题内容,或存在优化和需要改进的地方;如《装配式混凝土结构技术规程JGJ1-2014》的装配施工每一层之间采用坐浆和套筒连接竖向构件没有解决达到与现浇结构同等性能要求,套筒连接钢筋的工艺精度要求高、吊装钢筋对接麻烦、施工环节多、造价高;另没有突破装配必需下部装配完成才能进行上部吊装的传统思维的施工模式,装配施工时间长,很难实现“强节点、弱构件”设计原则、无法做到装配结构与现浇结构同等性能要求。At present, my country's prefabricated buildings have not systematically solved the above research topics, or there are areas for optimization and improvement; The vertical components of the tube connection have not been solved to meet the same performance requirements as the cast-in-place structure. The process precision of the sleeve connection steel bar is high, the butt joint of the hoisting steel bar is troublesome, there are many construction links, and the cost is high; there is no breakthrough in the assembly. The lower part must be assembled before the upper part can be hoisted. The construction mode of the traditional thinking, the assembly and construction time is long, it is difficult to realize the design principle of "strong nodes, weak components", and it is impossible to meet the same performance requirements of the assembly structure and the cast-in-place structure.

发明内容Contents of the invention

本发明的目的在于克服现有技术的不足,提供一种装配式混凝土结构施工方法,该施工方法采用逆作工序,可以减少施工环节、减少施工工期,其适用于预制剪力墙、复合墙板和框架等结构体系的装配式混凝土建筑施工,具有施工方便、省时、经济、环保等优点;同时实现达到与现浇结构同等性能要求。The purpose of the present invention is to overcome the deficiencies of the prior art and provide a construction method for prefabricated concrete structures. The construction method adopts the reverse process, which can reduce the construction links and construction period. It is suitable for prefabricated shear walls and composite wall panels The construction of prefabricated concrete buildings with structural systems such as frames and frames has the advantages of convenient construction, time saving, economy, and environmental protection; at the same time, it can achieve the same performance requirements as cast-in-place structures.

本发明的目的通过以下的技术方案实现:The purpose of the present invention is achieved through the following technical solutions:

一种装配式混凝土结构施工方法,其特征在于:该施工方法对当前施工楼层的竖向构件的安装采用逆作工序,即在当前施工楼层的水平构件的装配连接还没有完成之前,先吊装其上方相连接的竖向构件,最后浇筑连接混凝土将当前施工楼层的水平构件和竖向构件连接成一体;具体为:吊装预制楼板上方相连接的竖向构件时,当前施工楼层的水平槽还没有浇筑连接混凝土,吊装的竖向构件下端对着的是水平槽的空域,因而需利用支承物件使吊装的竖向构件下端架立于相对应连接的前一施工楼层已经装配好的竖向构件上端结合面上方,即当前施工楼层的水平槽上方;各个装配构件端部的预留钢筋在对应的水平槽和竖向空洞连接或锚固,并与设置于水平槽和竖向空洞的常规钢筋构成骨架,最后在水平槽和竖向空洞浇筑连接混凝土,把当前施工楼层的水平构件和竖向构件连成整体,进而完成一个结构楼层的施工。A construction method for a prefabricated concrete structure, characterized in that: the construction method adopts a reverse process for the installation of the vertical components of the current construction floor, that is, before the assembly and connection of the horizontal components of the current construction floor is completed, the other components are hoisted first For the vertical components connected above, the connecting concrete is finally poured to connect the horizontal components and vertical components of the current construction floor; specifically: when the vertical components connected above the prefabricated floor are hoisted, the horizontal groove of the current construction floor has not yet When pouring the connecting concrete, the lower end of the hoisted vertical member is facing the airspace of the horizontal groove, so it is necessary to use supporting objects to make the lower end of the hoisted vertical member stand on the upper end of the vertical member that has been assembled on the previous construction floor corresponding to the connection Above the joint surface, that is, above the horizontal groove of the current construction floor; the reserved steel bars at the ends of each assembly member are connected or anchored in the corresponding horizontal grooves and vertical cavities, and form a skeleton with the conventional steel bars arranged in the horizontal grooves and vertical cavities , and finally pour concrete in the horizontal grooves and vertical cavities to connect the horizontal components and vertical components of the current construction floor into a whole, and then complete the construction of a structural floor.

所述的水平槽是由竖向构件上端结合面和若干个水平构件(包括预制楼板和预制叠合梁)的结合面围成的、或由竖向构件上端结合面和若干个水平构件的结合面以及模板围成的水平槽形状空间,是用于浇筑连接浇混凝土的水平空间。The horizontal groove is surrounded by the joint surface of the upper end of the vertical component and the joint surface of several horizontal components (including prefabricated floors and prefabricated composite beams), or is formed by the combination of the upper joint surface of the vertical component and several horizontal components. The horizontal groove-shaped space surrounded by the surface and the formwork is a horizontal space for pouring and connecting poured concrete.

所述的竖向空洞是由需连接的若干个竖向构件的侧结合面围成的、或由需连接的若干个竖向构件的侧结合面和模板围合成的竖向直通围闭空间,是用于浇筑连接浇混凝土的竖向空洞。The vertical cavity is a vertical straight-through enclosed space surrounded by the side joint surfaces of several vertical components to be connected, or formed by the side joint surfaces of several vertical components to be connected and formwork, It is a vertical cavity for pouring and connecting poured concrete.

本发明的装配式混凝土结构施工方法中,同一施工楼层的水平构件和竖向构件吊装临时拼接后,所述用于浇筑连接浇混凝土的水平槽和竖向空洞是相通的,水平槽和竖向空洞的后浇混凝土可以一次性浇筑;这与传统安装的先浇筑水平槽连接混凝土,然后施工其他中间工序,再浇筑竖向连接节点的竖向空洞混凝土的施工方法存在非常大的区别,如《装配式混凝土结构技术规程JGJ1-2014》中的装配施工。In the construction method of the prefabricated concrete structure of the present invention, after the horizontal member and the vertical member of the same construction floor are hoisted and spliced temporarily, the horizontal groove and the vertical cavity for pouring and connecting concrete are connected, and the horizontal groove and the vertical The hollow post-cast concrete can be poured at one time; this is very different from the traditional construction method of pouring the horizontal groove connection concrete first, then constructing other intermediate processes, and then pouring the vertical hollow concrete of the vertical connection nodes, such as " Assembly construction in JGJ1-2014 "Technical Regulations for Prefabricated Concrete Structures".

本发明的装配式混凝土结构施工方法中,所述支承物件是用于逆作工序时把吊装的竖向构件支撑在已经装配的竖向构件上端结合面的上方、即水平槽上方的物件;物件可以是预制结构墙板原有配筋伸出下端或上端结合面弯折成的支撑、或增加配筋伸出下端或上端结合面弯折成的支撑,也可以在预制结构墙板下端或上端与预制结构墙板一起预制的混凝土小柱体,也可以是活动的混凝土预制方块或钢筋弯折成的四方凳,也可以是预制结构墙板预制时在预制结构墙板下端或上端预埋的型钢,所述支承物件件还可以是活动横杠,把吊装的竖向构件抬起在当前施工楼层的还没有浇筑连接混凝土的水平槽上方。In the prefabricated concrete structure construction method of the present invention, the supporting object is an object used to support the hoisted vertical member above the joint surface of the upper end of the assembled vertical member, that is, above the horizontal groove during the reverse operation process; the object It can be the support formed by bending the original reinforcement of the prefabricated structural wall panel protruding from the lower end or the upper end joint surface, or the support formed by adding the reinforcement protruding from the lower end or the upper end joint surface, or it can be used at the lower or upper end of the prefabricated structural wall panel Small concrete columns prefabricated together with the prefabricated structural wall panels, or square stools made of movable concrete prefabricated squares or bent steel bars, or pre-buried at the lower or upper ends of the prefabricated structural wall panels during prefabrication of the prefabricated structural wall panels Sectional steel, the supporting object part can also be a movable horizontal bar, and the vertical component of hoisting is lifted above the horizontal groove of the current construction floor that has not yet poured the connecting concrete.

本发明的装配式混凝土结构施工方法中,所述当前施工楼层包括一个结构楼层平面的水平构件(梁和板、也包括接近水平的构件)以及该结构楼层平面以上的与本层连接的竖向构件(结构墙板和柱、也包括斜度较大的构件);其施工顺序是先吊装水平构件,临时定位固定,再吊装竖向构件,也临时定位固定,连接绑扎钢筋,然后一起浇筑连接,上述当前施工楼层构成一个施工层段。其与传统的施工层段划分不同,传统施工方法的一个施工层段包括当前施工楼层的竖向构件以及该竖向构件上面的水平构件,采用的是常规的从下向上的建造顺序,与本发明的具有逆作施工工序的施工方法存在本质区别。此外,传统的施工方法也有把一层楼层的施工分成两个施工段,即一层楼层的水平构件连接作为单独的施工段,而竖向构件的连接作为另一个单独的施工段,如《装配式混凝土结构技术规程JGJ1-2014》中的装配施工。In the prefabricated concrete structure construction method of the present invention, the current construction floor includes a horizontal component (beam and plate, also including components close to the level) of a structural floor plane and a vertical structure connected to this floor above the structural floor plane. Components (structural wall panels and columns, including components with large slopes); the construction sequence is to hoist the horizontal components first, temporarily position and fix them, then hoist the vertical components, also temporarily position and fix them, connect the binding steel bars, and then pour the joints together , the above-mentioned current construction floor constitutes a construction layer section. It is different from the division of traditional construction layers. A construction layer of the traditional construction method includes the vertical components of the current construction floor and the horizontal components above the vertical components. The conventional construction sequence from bottom to top is adopted, which is different from this There is an essential difference in the construction method invented with reverse construction procedure. In addition, the traditional construction method also divides the construction of one floor into two construction sections, that is, the connection of horizontal components of one floor is regarded as a separate construction section, while the connection of vertical components is regarded as another separate construction section, such as "Assembly The assembly construction in JGJ1-2014 "Technical Regulations for Type Concrete Structures".

本发明施工方法的优选方案一:该优选施工方法不含预制建筑墙板的施工时,具体包括以下步骤:Preferred option one of the construction method of the present invention: when this preferred construction method does not contain the construction of prefabricated building wall panels, it specifically includes the following steps:

a.设计总装配图和预制构件制作施工图,按设计图纸要求生产预制结构构件并运输到现场;a. Design general assembly drawings and prefabricated components to make construction drawings, produce prefabricated structural components according to the requirements of the design drawings and transport them to the site;

b.安装为支撑水平构件的竖向支撑和所需要的模板;要求安装的支撑和模板符合精确的标高要求,使装配的楼板结构面达到建筑精装修前的要求,并要求考虑安装水平构件上的相连竖向构件的荷载;本步骤是在上一施工楼层完成的基础上进行的工序;b. Install the vertical supports and required templates to support the horizontal components; the installed supports and templates are required to meet the precise elevation requirements, so that the assembled floor structure can meet the requirements before the fine decoration of the building, and it is required to consider the installation of horizontal components The load of the connected vertical members; this step is a process carried out on the basis of the completion of the previous construction floor;

c.吊装当前施工楼层的水平构件,并临时固定好;包括预制叠合梁和预制楼板,使它们支承在竖向支撑和模板上。c. Hoist and temporarily fix the horizontal components of the current construction floor; including prefabricated composite beams and prefabricated floor slabs, so that they are supported on vertical supports and formwork.

d.连接水平构件的预留钢筋和绑扎楼层结构面标高以下常规钢筋;除把水平构件的预留钢筋实施连接外,主要是提前绑扎部分不影响下一步竖向构件吊装和竖向构件预留钢筋连接的水平槽的钢筋,包括预制楼板之间的连接钢筋和常规配筋;其好处是在没有吊装上部竖向构件前,钢筋绑扎操作空间大,干扰少,这一步也可在吊装竖向构件后一起绑扎;d. Connect the reserved steel bars of the horizontal components and bind the conventional steel bars below the structural surface elevation of the floor; in addition to the connection of the reserved steel bars of the horizontal components, the main thing is that the binding part in advance will not affect the next step of vertical component hoisting and vertical component reservation The steel bar of the horizontal groove connected by the steel bar, including the connecting steel bar and the conventional reinforcement between the prefabricated floors; the advantage is that before the upper vertical member is hoisted, the steel bar binding operation space is large and the interference is small. This step can also be done during the hoisting vertical After the components are tied together;

e.吊装当前施工楼层楼面以上相连接的竖向构件,使竖向构件准确定位,并通过支承物件使吊装的竖向构件下端架立于相对应连接的前一施工楼层已经装配好的竖向构件上端结合面上方,即当前施工楼层的水平槽上方,这吊装具有逆作施工的工序,并符合垂直度要求,然后用斜撑固定;e. Hoist the connected vertical components above the floor of the current construction floor, make the vertical components accurately positioned, and use supporting objects to make the lower end of the hoisted vertical components stand on the correspondingly connected previous construction floor that has been assembled. Above the joint surface of the upper end of the component, that is, above the horizontal groove of the current construction floor, this hoisting has a reverse construction process and meets the verticality requirements, and then fixed with diagonal braces;

f.连接竖向构件预留钢筋,补充绑扎其它设计图纸需要的钢筋,如果有型钢还包括型钢的安装;具体包括竖向构件在水平槽和竖向空洞的预留钢筋连接和附加常规配筋绑扎,补充绑扎在d步骤无法完成的楼层结构面标高以下钢筋;上述钢筋连接和型钢安装都采用常规现有技术的连接;f. Connect the reserved steel bars for the vertical members, supplement and bind the steel bars required by other design drawings, and if there are section steels, also include the installation of section steel; specifically include the connection of the reserved steel bars and additional conventional reinforcement of the vertical members in the horizontal slots and vertical cavities Binding, supplementing the reinforcing bars below the floor structural surface elevation that cannot be completed in step d; above-mentioned reinforcing bar connection and section steel installation all adopt the connection of conventional prior art;

g.如水平槽的后浇混凝土具有高出楼层结构面标高的部分以及具有超过外墙的外边缘的部分,补充安装模板;这一步不是所有施工项目和每个施工层都有;g. If the post-cast concrete of the horizontal groove has a part higher than the structural surface level of the floor and a part that exceeds the outer edge of the outer wall, supplementary installation formwork; this step is not available for all construction projects and each construction layer;

h.浇筑水平槽和竖向空洞的连接混凝土;所浇筑的混凝土采用和连接构件强度相同或高一级的微膨胀混凝土;h. Pour the connecting concrete of the horizontal groove and the vertical cavity; the poured concrete adopts the micro-expansion concrete with the same or higher strength as the connecting member;

i.现浇连接混凝土强度达到要求后,拆除临时支撑和模板;i. After the strength of the cast-in-place connection concrete meets the requirements, the temporary support and formwork shall be removed;

重复步骤b—i,直至完成整栋楼的结构施工。Repeat steps b-i until the structural construction of the entire building is completed.

本发明施工方法的优选方案二:在结构施工装配阶段把预制建筑墙板也一起进行装配施工,具体包括以下步骤:The second preferred option of the construction method of the present invention: the prefabricated building wall panels are also assembled and constructed in the structure construction assembly stage, specifically including the following steps:

a.设计总装配图和预制构件制作施工图,按设计图纸要求生产预制结构构件和预制建筑墙板并运输到现场;a. Design general assembly drawings and prefabricated components to make construction drawings, produce prefabricated structural components and prefabricated building wall panels according to the requirements of the design drawings and transport them to the site;

b.安装为支撑水平构件的竖向支撑和所需要的模板;要求安装的支撑和模板符合精确的标高要求,使装配的楼板结构面达到建筑精装修前的要求,并要求考虑安装水平构件上的相连竖向构件的荷载;本步骤是在上一施工楼层完成的基础上进行的工序;b. Install the vertical supports and required templates to support the horizontal components; the installed supports and templates are required to meet the precise elevation requirements, so that the assembled floor structure can meet the requirements before the fine decoration of the building, and it is required to consider the installation of horizontal components The load of the connected vertical members; this step is a process carried out on the basis of the completion of the previous construction floor;

c.吊装当前施工楼层的水平构件,并临时固定好;包括预制叠合梁和预制楼板,使它们支承在竖向支撑和模板上。c. Hoist and temporarily fix the horizontal components of the current construction floor; including prefabricated composite beams and prefabricated floor slabs, so that they are supported on vertical supports and formwork.

d.连接水平构件的预留钢筋和绑扎楼层结构面标高以下常规钢筋;除把水平构件的预留钢筋实施连接外,主要是提前绑扎部分不影响下一步竖向构件吊装和竖向构件预留钢筋连接的水平槽的钢筋,包括预制楼板之间的连接钢筋和常规配筋;其好处是在没有吊装上部竖向构件前,钢筋绑扎操作空间大,干扰少,这一步也可在吊装竖向构件后一起绑扎;d. Connect the reserved steel bars of the horizontal components and bind the conventional steel bars below the structural surface elevation of the floor; in addition to the connection of the reserved steel bars of the horizontal components, the main thing is that the binding part in advance will not affect the next step of vertical component hoisting and vertical component reservation The steel bar of the horizontal groove connected by the steel bar, including the connecting steel bar and the conventional reinforcement between the prefabricated floors; the advantage is that before the upper vertical member is hoisted, the steel bar binding operation space is large and the interference is small. This step can also be done during the hoisting vertical After the components are tied together;

e.吊装当前施工楼层楼面以上相连接的竖向构件,使竖向构件准确定位,并通过支承物件使吊装的竖向构件下端架立于相对应连接的前一施工楼层已经装配好的竖向构件上端结合面上方,即当前施工楼层的水平槽上方,这吊装具有逆作施工的工序,并符合垂直度要求,然后用斜撑固定;e. Hoist the connected vertical components above the floor of the current construction floor, make the vertical components accurately positioned, and use supporting objects to make the lower end of the hoisted vertical components stand on the correspondingly connected previous construction floor that has been assembled. Above the joint surface of the upper end of the component, that is, above the horizontal groove of the current construction floor, this hoisting has a reverse construction process and meets the verticality requirements, and then fixed with diagonal braces;

f.连接竖向构件预留钢筋,补充绑扎其它设计图纸需要的钢筋,如果有型钢还包括型钢的安装;具体包括竖向构件在水平槽和竖向空洞的预留钢筋连接和附加常规配筋绑扎,补充绑扎在d步骤无法完成的楼层结构面标高以下钢筋;上述钢筋连接和型钢安装都采用常规现有技术的连接;f. Connect the reserved steel bars for the vertical members, supplement and bind the steel bars required by other design drawings, and if there are section steels, also include the installation of section steel; specifically include the connection of the reserved steel bars and additional conventional reinforcement of the vertical members in the horizontal slots and vertical cavities Binding, supplementing the reinforcing bars below the floor structural surface elevation that cannot be completed in step d; above-mentioned reinforcing bar connection and section steel installation all adopt the connection of conventional prior art;

g.如水平槽的后浇混凝土具有高出楼层结构面标高的部分以及具有超过外墙的外边缘的部分,补充安装模板;这一步不是所有施工项目和每个施工层都有;g. If the post-cast concrete of the horizontal groove has a part higher than the structural surface level of the floor and a part that exceeds the outer edge of the outer wall, supplementary installation formwork; this step is not available for all construction projects and each construction layer;

h.浇筑水平槽和竖向空洞的连接混凝土;所浇筑的混凝土采用和连接构件强度相同或高一级的微膨胀混凝土;h. Pour the connecting concrete of the horizontal groove and the vertical cavity; the poured concrete adopts the micro-expansion concrete with the same or higher strength as the connecting member;

i.现浇混凝土强度达到要求后,拆除临时支撑和模板;i. After the strength of the cast-in-place concrete meets the requirements, remove the temporary support and formwork;

j.吊装安装预制建筑墙板,采用坐浆方式安装,保证其符合要求,并斜撑固定;j. Hoist and install the prefabricated building wall panels, install them by sitting on the slurry to ensure that they meet the requirements, and fix them with diagonal braces;

重复步骤b—j,直至完成整栋楼的结构施工和建筑墙板的施工。Repeat steps b-j until the structural construction of the entire building and the construction of the building wall panels are completed.

所述的建筑墙板是用于封闭外围空间或分隔空间的除受力结构墙板以外的起建筑封闭外围空间或分隔空间功能的墙板。The building wall panel is a wall panel used to close the peripheral space or separate space, except for the force-bearing structural wall panel, which has the function of closing the peripheral space or separating space of the building.

上述的两种优选施工方法中,具体施工内容在针对不同工程时可能存在部分不同,施工步骤可能有所增减,但是本领域技术人员在上述施工方法的基础上根据实际情况而做出的调整,显然属于本发明的等同技术方案,落入本发明的保护范围之内。Among the above two preferred construction methods, the specific construction content may be partially different for different projects, and the construction steps may be increased or decreased, but adjustments made by those skilled in the art based on the above construction methods according to the actual situation , obviously belong to the equivalent technical solution of the present invention, and fall within the protection scope of the present invention.

本发明所述预制构件包括竖向预制构件和水平预制构件,所述竖向预制构件为预制柱、预制结构墙板和复合结构板墙,所述水平预制构件为预制叠合梁和预制楼板。The prefabricated components of the present invention include vertical prefabricated components and horizontal prefabricated components, the vertical prefabricated components are prefabricated columns, prefabricated structural wall panels and composite structural panel walls, and the horizontal prefabricated components are prefabricated composite beams and prefabricated floor slabs.

与现有技术相比,本发明的装配式混凝土结构施工方法的有益效果如下:Compared with the prior art, the beneficial effects of the prefabricated concrete structure construction method of the present invention are as follows:

一、实现达到与现浇结构同等性能要求:本发明的装配连接施工全部采用符合混凝土结构的钢筋连接和混凝土连接,连接处后浇筑连接混凝土部分相当于现浇结构的后浇带,通过逆作工序使传统方法无法做到连接的新型节点能够实现;而现有装配连接存在坐浆连接面、钢筋灌浆连接等一些没有被认可达到现浇结构同等性能的连接材料和方式方法。本发明实现了国家科委提出的“提出新型系列连接节点形式,达到与现浇结构同等性能要求”技术课题目标。1. Achieve the same performance requirements as the cast-in-place structure: the assembly and connection construction of the present invention all adopts steel bar connection and concrete connection that conform to the concrete structure, and the post-casting connection concrete part of the joint is equivalent to the post-casting belt of the cast-in-place structure. The process enables the realization of new nodes that cannot be connected by traditional methods; while the existing assembly connections have some connection materials and methods that have not been recognized to achieve the same performance as cast-in-place structures, such as sitting grout connection surfaces and steel grout connections. The invention realizes the technical subject goal of "proposing a new series of connection node forms to achieve the same performance requirements as cast-in-place structures" proposed by the National Science and Technology Commission.

二、本发明的施工方法中提供了一种适用于预制装配式混凝土结构的标准化、工具化吊装施工体系,该体系与现有体系相比具有以下优点:Two, the construction method of the present invention provides a kind of standardization that is applicable to the prefabricated assembled concrete structure, tool hoisting construction system, this system has following advantage compared with existing system:

(一)实现减少垂直临时支撑和模板;由于采用整厚预制楼板刚度大,减少竖向支撑,与现有技术相比可以节省周转材料、省事、经济、环保。(1) Realize the reduction of vertical temporary supports and templates; because the rigidity of the full-thickness prefabricated floor slab is large, the vertical support is reduced, and compared with the prior art, it can save turnover materials, save trouble, be economical and environmentally friendly.

(二)减少施工工序、简化施工难度、减少施工期;实现一个施工平面层只用一次混凝土浇筑,就把所有安装的结构(包括竖向构件墙板和柱、水平构件梁和楼板)全部连接成一整体,减少工序。而现有普遍使用的装配施工技术浇筑连接混凝土时不少于2次,还有灌浆连接工序,步骤多、难度大、工期长。(2) Reduce the construction process, simplify the construction difficulty, and reduce the construction period; to achieve a construction plane layer with only one concrete pouring, all the installed structures (including vertical component wall panels and columns, horizontal component beams and floor slabs) are all connected Into a whole, reduce the process. However, the existing generally used assembly construction technology pours the connecting concrete no less than twice, and also has a grouting connection process, which has many steps, great difficulty and long construction period.

(三)预制率高、施工环保;本发明连接的楼板也可以一次预制完成到位,区别于采用叠合层楼板连接方式,提高预制率(本发明楼板预制率超过80%,而传统叠合板预制率很难达到60%),如果建筑墙板也预制吊装,大为减少现场混凝土量和湿作业量,减少建筑垃圾和粉尘排放。(3) The prefabrication rate is high, and the construction is environmentally friendly; the floor slabs connected by the present invention can also be prefabricated in place at one time, which is different from the connection mode of laminated floor slabs and improves the prefabrication rate (the prefabrication rate of the floor slabs of the present invention exceeds 80%, while the prefabrication of traditional laminated slabs rate is difficult to reach 60%), if the building wall panels are also prefabricated and hoisted, the amount of concrete and wet work on site will be greatly reduced, and construction waste and dust emissions will be reduced.

(四)完成的结构面更平整,减少找平层,更环保;由于本发明的楼板整体厚度预制平整,预制结构墙板面也是带平整翼沿模板,建筑墙板也是预制装配、楼地面和墙面都可以达到不用找平层就可以进行精装修,进一步减少建筑垃圾和粉尘排放。(4) The completed structural surface is smoother, reduces the leveling layer, and is more environmentally friendly; because the overall thickness of the floor slab is prefabricated flat, the prefabricated structure wall panel surface is also a formwork with a smooth wing edge, and the building wall panel is also a prefabricated assembly, floor surface and wall The surface can be finely decorated without leveling, further reducing construction waste and dust emissions.

(五)能够大幅减少工程造价,容易被市场接受,有利于装配式施工的“建筑工业化”的推广。(5) It can greatly reduce the project cost, is easily accepted by the market, and is conducive to the promotion of "building industrialization" of prefabricated construction.

附图说明Description of drawings

图1是本发明的装配式混凝土结构施工方法实施例一的结构平面图。Fig. 1 is a structural plan view of Embodiment 1 of the construction method for a prefabricated concrete structure of the present invention.

图2是图1和图5的A-A剖视图。Fig. 2 is A-A sectional view of Fig. 1 and Fig. 5 .

图3是图1和图5的B-B剖面图。Fig. 3 is a B-B sectional view of Fig. 1 and Fig. 5 .

图4是图1和图5的C-C剖面图。Fig. 4 is a C-C sectional view of Fig. 1 and Fig. 5 .

图5是本发明的装配式混凝土结构施工方法实施例二的结构平面图。Fig. 5 is a structural plan view of Embodiment 2 of the construction method for a prefabricated concrete structure of the present invention.

图6是图5的D-D剖视图。Fig. 6 is a D-D sectional view of Fig. 5 .

图中:1预制结构墙板,2预制叠合梁,3预制楼板,4预制柱,5水平槽,6竖向空洞,7模板,8竖向支撑,9斜撑,10支承物件,11预制建筑墙板,12连接混凝土,13砂浆层,N和N+1表示施工层段。In the figure: 1 prefabricated structural wall panels, 2 prefabricated composite beams, 3 prefabricated floor slabs, 4 prefabricated columns, 5 horizontal grooves, 6 vertical cavities, 7 formwork, 8 vertical supports, 9 diagonal braces, 10 supporting objects, 11 prefabricated Building wall panels, 12 connecting concrete, 13 mortar layers, N and N+1 represent construction layers.

具体实施方式detailed description

下面结合实施例及附图对本发明作进一步详细的描述,但本发明的实施方式不限于此。The present invention will be further described in detail below in conjunction with the embodiments and the accompanying drawings, but the embodiments of the present invention are not limited thereto.

如图1-6所示,该施工方法对当前施工楼层N+1的竖向构件(包括预制结构墙板1和预制柱4)的安装采用逆作工序,即在当前施工楼层N+1的水平构件(包括预制叠合梁2和预制楼板3)的装配连接还没有完成之前,先吊装其上方相连接的竖向构件,最后浇筑连接混凝土12将当前施工楼层的水平构件(包括预制叠合梁2和预制楼板3)和竖向构件的预制结构墙板1和预制柱4连接成一体;具体为:吊装预制楼板3上方相连接的竖向构件的预制结构墙板1和预制柱4时,当前施工楼层N+1的水平槽5还没有浇筑连接混凝土12,吊装的竖向构件的预制结构墙板1和预制柱4下端对着的是水平槽5的空域,因而需利用支承物件10使吊装的竖向构件的预制结构墙板1和预制柱4下端分别架立于相对应连接的前一施工楼层N已经装配好的竖向构件的预制结构墙板1和预制柱4上端结合面上方;各个装配构件端部的预留钢筋在对应的水平槽5和竖向空洞6连接或锚固,并与设置于水平槽5和竖向空洞6的常规钢筋构成骨架,最后在水平槽5和竖向空洞6浇筑连接混凝土12,把当前施工楼层的水平构件的预制叠合梁2和预制楼板3和竖向构件的结构墙板1和柱4连成整体,进而完成一个结构楼层的施工。As shown in Figure 1-6, this construction method adopts the reverse process for the installation of vertical components (including prefabricated structural wall panels 1 and prefabricated columns 4) on the current construction floor N+1, that is, on the current construction floor N+1 Before the assembly and connection of the horizontal components (including the prefabricated composite beam 2 and the prefabricated floor 3 ) is completed, the vertical components connected above it are hoisted first, and finally the connecting concrete 12 is poured to connect the horizontal components (including the prefabricated composite beam 2 ) of the current construction floor. The beam 2 and the prefabricated floor 3) are integrated with the prefabricated structural wall panel 1 of the vertical component and the prefabricated column 4; specifically: when the prefabricated structural wall panel 1 and the prefabricated column 4 of the vertical component connected above the prefabricated floor 3 are hoisted , the horizontal groove 5 of the current construction floor N+1 has not yet poured the connecting concrete 12, and the lower ends of the prefabricated structural wall panels 1 and prefabricated columns 4 of the hoisted vertical components are facing the airspace of the horizontal groove 5, so it is necessary to use the support object 10 The lower ends of the prefabricated structural wall panels 1 and prefabricated columns 4 of the hoisted vertical components are respectively erected on the joint surface of the upper ends of the prefabricated structural wall panels 1 and prefabricated columns 4 of the vertical components that have been assembled on the previous construction floor N that is connected to each other. Above; the reserved steel bars at the ends of each assembly member are connected or anchored in the corresponding horizontal slots 5 and vertical cavities 6, and form a skeleton with the conventional steel bars arranged in the horizontal slots 5 and vertical cavities 6, and finally in the horizontal slots 5 and vertical cavities 6 The vertical cavity 6 is poured with connecting concrete 12, and the prefabricated composite beam 2 and the prefabricated floor slab 3 of the horizontal component of the current construction floor and the structural wall panel 1 and column 4 of the vertical component are connected into a whole, and then the construction of a structural floor is completed.

所述的水平槽:如图3所示:由竖向构件预制结构墙板1上端结合面和二个水平构件预制楼板3的结合面围成的水平槽形状空间;又如图2所示:由竖向构件预制结构墙板1上端结合面和二个水平构件预制楼板3的结合面以及模板7围成的水平槽形状空间,是用于浇筑连接浇混凝土12的水平空间。Described horizontal slot: as shown in Figure 3: the horizontal slot shape space surrounded by the joint surface of the upper end of the vertical component prefabricated structural wall panel 1 and the joint surface of two horizontal component prefabricated floor slabs 3; and as shown in Figure 2: The horizontal groove-shaped space surrounded by the upper joint surface of the vertical component prefabricated structural wall panel 1 and the joint surface of the two horizontal component prefabricated floor slabs 3 and the template 7 is a horizontal space for pouring and connecting poured concrete 12 .

如图1和图5所示:所述的竖向空洞是由需连接的若干个竖向构件预制墙板1的侧结合面围成的是用于浇筑连接浇混凝土的竖向空洞。As shown in Figures 1 and 5: the vertical cavity is surrounded by the side joint surfaces of several vertical member prefabricated wall panels 1 to be connected and is a vertical cavity for pouring and connecting poured concrete.

如图1和图5所示:所述用于浇筑连接浇混凝土的水平槽和竖向空洞是相通的,水平槽和竖向空洞的后浇混凝土可以一次性浇筑。As shown in Fig. 1 and Fig. 5: the horizontal groove and the vertical cavity for pouring and connecting concrete are connected, and the post-pouring concrete of the horizontal groove and the vertical cavity can be poured at one time.

如图2和图6所示:所述当前施工楼层N+1包括一个结构楼层平面的水平构件(梁和板、也包括接近水平的构件)以及该结构楼层平面以上的与本层连接的竖向构件(结构墙板和柱、也包括接倾斜角度较大的构件);之前的一个施工楼层为N。As shown in Figure 2 and Figure 6: the current construction floor N+1 includes a horizontal component (beam and plate, also including components close to the level) of a structural floor plane and a vertical structure connected to this floor above the structural floor plane. oriented components (structural wall panels and columns, also including components with large inclination angles); the previous construction floor is N.

实施例一Embodiment one

如图1-4所示,本实施例的装配式预制混凝土结构施工方法不含预制建筑墙板的施工,具体步骤为:As shown in Figure 1-4, the prefabricated prefabricated concrete structure construction method of this embodiment does not include the construction of prefabricated building wall panels, and the specific steps are:

a.设计总装配图和预制构件制作施工图,按设计图纸要求生产预制结构构件并运输到现场;a. Design general assembly drawings and prefabricated components to make construction drawings, produce prefabricated structural components according to the requirements of the design drawings and transport them to the site;

b.(这是接上一装配施工层段N完成后进入下一施工层段N+1的工序),安装为支撑水平构件的竖向支撑8和所需要的模板7。要求安装的支撑8和模板7符合精确的标高要求,并要求考虑安装水平构件上的相连竖向构件的荷载;b. (this is the operation of entering the next construction layer N+1 after the last assembly construction layer N is completed), install the vertical support 8 and the required formwork 7 for supporting the horizontal member. The installed supports 8 and formwork 7 are required to meet the precise elevation requirements, and the loads of the connected vertical members on the installed horizontal members are required to be considered;

c、吊装当前施工楼层的水平构件中的预制叠合梁2和预制楼板单元3,使它们支承在竖向支撑8和所需要的模板7上并临时固定好;c, hoisting the prefabricated composite beam 2 and the prefabricated floor unit 3 in the horizontal components of the current construction floor, so that they are supported on the vertical support 8 and the required formwork 7 and temporarily fixed;

d.连接水平构件预制楼板3和预制叠合梁2的预留钢筋和绑扎楼层结构面标高以下常规钢筋;除把水平构件的预留钢筋实施连接外,主要是提前绑扎部分不影响下一步竖向构件吊装和竖向构件预留钢筋连接的水平槽的钢筋,包括预制楼板之间的连接钢筋和常规配筋;d. Connect the reserved steel bars of the prefabricated floor 3 and the prefabricated composite beam 2 of the horizontal components and bind the conventional steel bars below the structural surface elevation of the floor; except for the connection of the reserved steel bars of the horizontal components, the main thing is that the binding part in advance does not affect the next vertical Reinforcing bars for hoisting components and reserving horizontal grooves for connecting vertical components, including connecting steel bars and conventional reinforcement between prefabricated floor slabs;

e.如图2所示:吊装当前施工楼层楼面N+1以上相连接的竖向构件(其中的预制墙板1),使竖向构件准确定位,并通过支承物件10使吊装的竖向构件的预制墙板1下端架立于相对应连接的前一施工楼层已经装配好的竖向构件的预制墙板1上端结合面上方,并符合垂直度要求,然后用斜撑固定9;e. As shown in Figure 2: hoist the vertical components (prefabricated wall panels 1) connected above the current construction floor floor N+1, so that the vertical components can be accurately positioned, and the vertical components of the hoisting can be lifted through the support object 10 The lower end of the prefabricated wall panel 1 of the component stands above the joint surface of the upper end of the prefabricated wall panel 1 of the vertical component that has been assembled on the correspondingly connected previous construction floor, and meets the verticality requirements, and then fixed with diagonal braces 9;

f.连接竖向构件预留钢筋,补充绑扎其它设计图纸需要的钢筋,如果有型钢还包括型钢的安装;具体包括竖向构件在水平槽5和竖向空洞6的预留钢筋连接和附加常规配筋绑扎,补充绑扎在d步骤无法完成的楼层结构面标高以下钢筋;上述钢筋连接和型钢安装都采用常规现有技术的连接;f. Connect the reserved steel bars for the vertical members, supplement and bind the steel bars required by other design drawings, and if there are section steels, also include the installation of section steel; specifically include the connection of the reserved steel bars of the vertical members in the horizontal groove 5 and the vertical cavity 6 and additional routines Reinforcement binding, supplement binding the reinforcement below the level of the floor structure surface that cannot be completed in step d; above-mentioned reinforcement connection and section steel installation all adopt the connection of conventional prior art;

g.如水平槽5的后浇混凝土具有高出楼层结构面标高的部分以及具有超过外墙的外边缘的部分,补充安装模板7(本实施例无需执行该步骤)g. If the post-cast concrete of the horizontal groove 5 has a part higher than the level of the floor structure surface and a part with an outer edge exceeding the outer wall, the supplementary installation formwork 7 (the present embodiment does not need to perform this step)

h.浇筑水平槽5和竖向空洞6的连接混凝土;所浇筑的混凝土采用比连接构件强度高一级的微膨胀混凝土;h. Pour the connecting concrete of the horizontal groove 5 and the vertical cavity 6; the poured concrete adopts the micro-expansion concrete of one level higher than the strength of the connecting member;

i.连接混凝土12强度达到要求后,拆除临时支撑8和模板7;i. After the strength of the connecting concrete 12 reaches the requirement, remove the temporary support 8 and the template 7;

重复步骤b—i,直至完成整栋楼的结构施工。Repeat steps b-i until the structural construction of the entire building is completed.

实施例二Embodiment two

如图2-6所示,本实施例的装配式混凝土结构施工方法在结构施工装配阶段把预制建筑墙板11也一起进行装配施工,具体步骤为:As shown in Figure 2-6, the prefabricated building wall panel 11 is also assembled and constructed in the structure construction assembly stage of the prefabricated concrete structure construction method of this embodiment, and the specific steps are:

a.设计总装配图和预制构件制作施工图,按设计图纸要求生产预制结构构件和预制建筑墙板11并运输到现场;a. Design general assembly drawings and prefabricated components to make construction drawings, produce prefabricated structural components and prefabricated building wall panels 11 according to the requirements of the design drawings and transport them to the site;

b.(这是接上一装配施工层段N完成后进入下一施工层段N+1的工序),安装为支撑水平构件的竖向支撑8和所需要的模板7。要求安装的支撑8和模板7符合精确的标高要求,并要求考虑安装水平构件上的相连竖向构件的荷载;b. (this is the operation of entering the next construction layer N+1 after the last assembly construction layer N is completed), install the vertical support 8 and the required formwork 7 for supporting the horizontal member. The installed supports 8 and formwork 7 are required to meet the precise elevation requirements, and the loads of the connected vertical members on the installed horizontal members are required to be considered;

c.吊装当前施工楼层的水平构件中的预制叠合梁2和预制楼板单元3,使它们支承在竖向支撑8和所需要的模板7上并临时固定好;c. hoisting the prefabricated composite beam 2 and the prefabricated floor unit 3 in the horizontal components of the current construction floor, making them supported on the vertical support 8 and the required formwork 7 and temporarily fixed;

d.连接水平构件预制楼板3和预制叠合梁2的预留钢筋和绑扎楼层结构面标高以下常规钢筋;除把水平构件的预留钢筋实施连接外,主要是提前绑扎部分不影响下一步竖向构件吊装和竖向构件预留钢筋连接的水平槽的钢筋,包括预制楼板之间的连接钢筋和常规配筋;d. Connect the reserved steel bars of the prefabricated floor 3 and the prefabricated composite beam 2 of the horizontal components and bind the conventional steel bars below the structural surface elevation of the floor; except for the connection of the reserved steel bars of the horizontal components, the main thing is that the binding part in advance does not affect the next vertical Reinforcing bars for hoisting components and reserving horizontal grooves for connecting vertical components, including connecting steel bars and conventional reinforcement between prefabricated floor slabs;

e.如图2所示:吊装当前施工楼层楼面N+1以上相连接的竖向构件(其中的预制墙板1),使竖向构件准确定位,并通过支承物件10使吊装的竖向构件的预制墙板1下端架立于相对应连接的前一施工楼层已经装配好的竖向构件的预制墙板1上端结合面上方,并符合垂直度要求,然后用斜撑固定9;e. As shown in Figure 2: hoist the vertical components (prefabricated wall panels 1) connected above the current construction floor floor N+1, so that the vertical components can be accurately positioned, and the vertical components of the hoisting can be lifted through the support object 10 The lower end of the prefabricated wall panel 1 of the component stands above the joint surface of the upper end of the prefabricated wall panel 1 of the vertical component that has been assembled on the correspondingly connected previous construction floor, and meets the verticality requirements, and then fixed with diagonal braces 9;

f.连接竖向构件预留钢筋,补充绑扎其它设计图纸需要的钢筋,如果有型钢还包括型钢的安装;具体包括竖向构件在水平槽5和竖向空洞6的预留钢筋连接和附加常规配筋绑扎,补充绑扎在d步骤无法完成的楼层结构面标高以下钢筋;上述钢筋连接和型钢安装都采用常规现有技术的连接;f. Connect the reserved steel bars for the vertical members, supplement and bind the steel bars required by other design drawings, and if there are section steels, also include the installation of section steel; specifically include the connection of the reserved steel bars of the vertical members in the horizontal groove 5 and the vertical cavity 6 and additional routines Reinforcement binding, supplement binding the reinforcement below the level of the floor structure surface that cannot be completed in step d; above-mentioned reinforcement connection and section steel installation all adopt the connection of conventional prior art;

g.如水平槽5的后浇混凝土具有高出楼层结构面标高的部分以及具有超过外墙的外边缘的部分,补充安装模板7(本实施例无需执行该步骤)g. If the post-cast concrete of the horizontal groove 5 has a part higher than the level of the floor structure surface and a part with an outer edge exceeding the outer wall, the supplementary installation formwork 7 (the present embodiment does not need to perform this step)

h.浇筑水平槽5和竖向空洞6的连接混凝土;所浇筑的混凝土采用比连接构件强度高一级的微膨胀混凝土;h. Pour the connecting concrete of the horizontal groove 5 and the vertical cavity 6; the poured concrete adopts the micro-expansion concrete of one level higher than the strength of the connecting member;

i.连接混凝土12强度达到要求后,拆除临时支撑8和模板7;i. After the strength of the connecting concrete 12 reaches the requirement, remove the temporary support 8 and the template 7;

j.吊装安装预制建筑墙板,采用坐砂浆13方式安装,保证其符合要求,并斜撑9固定(如图6所示),该建筑墙板可以作为安装水平构件的支撑用,如图所示其支撑着叠合梁2;注:这一步也可以作为在整个施工层段开始;j. Hoisting and installing the prefabricated building wall panel, install it with mortar 13 to ensure that it meets the requirements, and fix it with diagonal brace 9 (as shown in Figure 6). The building wall panel can be used as a support for installing horizontal components, as shown in the figure Indicates that it supports the composite beam 2; Note: This step can also be started in the entire construction layer;

重复步骤b—j,直至完成整栋楼的结构施工和建筑墙板的施工。Repeat steps b-j until the structural construction of the entire building and the construction of the building wall panels are completed.

上述为本发明较佳的实施方式,但本发明的实施方式并不受上述内容的限制,其他的任何未背离本发明的精神实质与原理下所作的改变、修饰、替代、组合、简化,均应为等效的置换方式,都包含在本发明的保护范围之内。The above is a preferred embodiment of the present invention, but the embodiment of the present invention is not limited by the above content, and any other changes, modifications, substitutions, combinations, and simplifications that do not deviate from the spirit and principles of the present invention are all Replacement methods that should be equivalent are all included within the protection scope of the present invention.

Claims (8)

1. a prefabricated concrete structure construction method, it is characterised in that: this construction method is vertical to current construction floor The installation of component uses against making operation, before i.e. the assembly connection at the horizontal member of current construction floor has not been completed, first Lift the vertical member being connected above it, finally pour and connect concrete by the horizontal member of current construction floor and vertical structure Part links into an integrated entity;Particularly as follows: be connected above hoisting prefabricated floor vertical member time, the horizontal member of current construction floor Level trough does not the most pour connection concrete, and what the vertical member lower end of lifting faced toward is the spatial domain of level trough, thus needs to utilize Articles makes the vertical member lower end frame of lifting stand on the vertical structure that the previous construction floor of corresponding connection has assembled Above the faying face of part upper end, above the level trough of i.e. current construction floor, the reserved steel bar of each mounting structure end is in correspondence Level trough and vertical cavity connect or anchoring, and be arranged at the conventional rebar composition skeleton in level trough and vertical cavity, After pour connection concrete at level trough and vertical cavity, horizontal member and the vertical member of current construction floor are linked to be whole Body, and then complete the construction of a structural floor.
Prefabricated concrete structure construction method the most according to claim 1, it is characterised in that: described level trough be by That the faying face of vertical member upper end faying face and several horizontal members surrounds or by vertical member upper end faying face and some The level trough shape space that the faying face of individual horizontal member and template surround, is for pouring the horizontal blank connecting pouring concrete Between, described horizontal member includes precast floor slab and Prefabricated superposed beam.
Prefabricated concrete structure construction method the most according to claim 1, it is characterised in that: described vertical cavity is That surrounded by the side faying face of several vertical members that need to connect or by the side faying face of several vertical members that need to connect Vertical the leading directly to enclosed with template encloses space, is for pouring the vertical cavity connecting pouring concrete.
Prefabricated concrete structure construction method the most according to claim 1, it is characterised in that: the water of same construction floor After flat component and the interim splicing of vertical member lifting, described is phase for pouring the level trough connecting pouring concrete and vertical cavity Lead to, level trough and the rear pouring concrete primary concreting in vertical cavity.
Prefabricated concrete structure construction method the most according to claim 1, it is characterised in that: described articles is to use In inverse make operation time lifting vertical member be supported on the top of vertical member upper end faying face, the level trough assembled The object of top.
Prefabricated concrete structure construction method the most according to claim 1, it is characterised in that: described current construction floor Including the vertical member being connected with this layer more than horizontal member of a structural floor plane and this structural floor plane.
Prefabricated concrete structure construction method the most according to claim 1, it is characterised in that: this construction method is without pre- During the construction of producing building wallboard, specifically include following steps:
A. design general assembly drawing and prefabricated components make construction drawing, produce prefabricated structural element by design drawing requirement and transport is arrived On-the-spot;
B. the vertical supporting of support level component and required template it are installed as;
C. lift the horizontal member of current construction floor, and fix temporarily;
D. reserved steel bar and the colligation floor structure face following conventional rebar of absolute altitude of horizontal member are connected;
E. lift the vertical member that more than current construction floor flooring is connected, make vertical member be accurately positioned, and by supporting On the vertical member that the previous construction floor that object makes the vertical member lower end frame of lifting stand on corresponding connection has assembled Above end faying face, above the level trough of i.e. current construction floor, this lifting has the operation of adverse construction method, and meets perpendicularity Requirement, then fixes with diagonal brace;
F. connecting vertical member reserved steel bar, supplementing the reinforcing bar that other design drawing of colligation needs, if there being shaped steel also to include type The installation of steel;
G. exceed the part of floor structure face absolute altitude and having exceed the outside of exterior wall as the rear pouring concrete of level trough has The part of edge, supplements installation form;
H. level trough and the connection concrete in vertical cavity are poured;
I., after cast-in-place concrete intensity reaches requirement, temporary support and template are removed;
Repeat step b i, until completing the structure construction of entire building.
Prefabricated concrete structure construction method the most according to claim 1, it is characterised in that: in this construction method, Structure construction assembling stage carries out pre-cast building wall assembling construction the most together, specifically includes following steps:
A. design general assembly drawing and prefabricated components make construction drawing, by design drawing requirements production prefabricated structural element with prefabricated build Walling plate also transports scene;
B. the vertical supporting of support level component and required template it are installed as;Require that the support installed and template meet accurately Absolute altitude requirement, make the floor construction face of assembling reach to build the requirement before fine fitment, and require to consider to install on horizontal member The load of connected vertical member;This step is the operation carried out on the basis of a upper construction floor completes;
C. lift the horizontal member of current construction floor, and fix temporarily;Including Prefabricated superposed beam and precast floor slab, make them It is bearing in vertical supporting and template;
D. reserved steel bar and the colligation floor structure face following conventional rebar of absolute altitude of horizontal member are connected;Pre-except horizontal member Outside staying reinforcing bar to implement to connect, tied part does not affect the lifting of next step vertical member and the connection of vertical member reserved steel bar in advance The reinforcing bar of level trough, including the connection reinforcing bar between precast floor slab and conventional arrangement of reinforcement;This step also can be after lifting vertical member Colligation together;
E. lift the vertical member that more than current construction floor flooring is connected, make vertical member be accurately positioned, and by supporting On the vertical member that the previous construction floor that object makes the vertical member lower end frame of lifting stand on corresponding connection has assembled Above end faying face, above the level trough of i.e. current construction floor, this lifting has the operation of adverse construction method, and meets perpendicularity Requirement, then fixes with diagonal brace;
F. connecting vertical member reserved steel bar, supplementing the reinforcing bar that other design drawing of colligation needs, if there being shaped steel also to include type The installation of steel;Specifically include vertical member and connect and additional conventional arrangement of reinforcement colligation at the reserved steel bar of level trough and vertical cavity, Supplement colligation at the floor structure face following reinforcing bar of absolute altitude that Step d cannot complete;Above-mentioned bar connecting and shaped steel are installed and are all used The connection of conventional prior;
G. exceed the part of floor structure face absolute altitude and having exceed the outside of exterior wall as the rear pouring concrete of level trough has The part of edge, supplements installation form;The not all project under construction of this step and each construction layer have;
H. level trough and the connection concrete in vertical cavity are poured;The concrete that poured use identical with connecting elements intensity or Higher leveled slightly expanded concrete;
I., after cast-in-place concrete intensity reaches requirement, temporary support and template are removed;
J. pre-cast building wallboard is installed in lifting, uses seat slurry mode to install, it is ensured that it meets the requirements, and diagonal brace is fixed;
Repeat step b j, until completing the structure construction of entire building and the construction of building wall board.
CN201610624394.7A 2016-07-29 2016-07-29 A kind of prefabricated concrete structure construction method Expired - Fee Related CN106193623B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610624394.7A CN106193623B (en) 2016-07-29 2016-07-29 A kind of prefabricated concrete structure construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610624394.7A CN106193623B (en) 2016-07-29 2016-07-29 A kind of prefabricated concrete structure construction method

Publications (2)

Publication Number Publication Date
CN106193623A true CN106193623A (en) 2016-12-07
CN106193623B CN106193623B (en) 2018-05-08

Family

ID=57498601

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610624394.7A Expired - Fee Related CN106193623B (en) 2016-07-29 2016-07-29 A kind of prefabricated concrete structure construction method

Country Status (1)

Country Link
CN (1) CN106193623B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661329A (en) * 2018-04-25 2018-10-16 李藏柱 The mounting bracket of prefabricated components, precast wall body and its installation method containing the holder
CN109610648A (en) * 2018-12-20 2019-04-12 五冶集团上海有限公司 Piece processing method before a kind of assembled architecture concrete members pour
CN110439290A (en) * 2019-07-10 2019-11-12 中国十七冶集团有限公司 A kind of prefabricated concrete structure construction method
CN110616800A (en) * 2019-10-20 2019-12-27 中建四局第六建筑工程有限公司 Vertical wall is whole cast-in-place and prefabricated building structure of horizontal structure
CN112983049A (en) * 2021-03-11 2021-06-18 三能集成房屋股份有限公司 Prefabricated wallboard supporting system and using method thereof
CN113309229A (en) * 2021-06-01 2021-08-27 中建八局第一建设有限公司 Grouting reverse-sequence construction method for assembled vertical component
CN113719137A (en) * 2021-09-29 2021-11-30 徐红伟 Construction engineering secondary structure and masonry engineering and main body engineering synchronous construction method
CN113833183A (en) * 2021-09-22 2021-12-24 北京建工四建工程建设有限公司 Prefabricated hollow shear wall panel system and construction method thereof
CN115613707A (en) * 2022-09-23 2023-01-17 重庆欧冠钢结构有限公司 A combination node of vertical and horizontal load-bearing components of walls, beams, and slabs in a prefabricated building
CN119711702A (en) * 2025-02-08 2025-03-28 中建八局第三建设有限公司 Reverse construction method for flat floor structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10331272A (en) * 1997-06-03 1998-12-15 Kajima Corp Construction method of reinforced concrete columns, core walls, top layer wall beams and slabs
CN101806095A (en) * 2010-03-15 2010-08-18 中山市快而居房屋预制件有限公司 Full-fabricated assembly overall reinforced concrete house and building method thereof
JP2013221341A (en) * 2012-04-17 2013-10-28 Ohbayashi Corp Construction method for reinforced concrete structure
CN103485548A (en) * 2013-10-17 2014-01-01 孟凡林 Vertical reinforcement connecting method for fabricated hollow concrete superimposed shear wall
CN105421780A (en) * 2015-10-26 2016-03-23 国强建设集团有限公司 Construction method of prefabricated concrete structure
JP2016084622A (en) * 2014-10-27 2016-05-19 株式会社竹中工務店 Construction method for structure
CN105735522A (en) * 2016-03-25 2016-07-06 中国航天建设集团有限公司沈阳分公司 Reverse operation assembly type shear wall and construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10331272A (en) * 1997-06-03 1998-12-15 Kajima Corp Construction method of reinforced concrete columns, core walls, top layer wall beams and slabs
CN101806095A (en) * 2010-03-15 2010-08-18 中山市快而居房屋预制件有限公司 Full-fabricated assembly overall reinforced concrete house and building method thereof
JP2013221341A (en) * 2012-04-17 2013-10-28 Ohbayashi Corp Construction method for reinforced concrete structure
CN103485548A (en) * 2013-10-17 2014-01-01 孟凡林 Vertical reinforcement connecting method for fabricated hollow concrete superimposed shear wall
JP2016084622A (en) * 2014-10-27 2016-05-19 株式会社竹中工務店 Construction method for structure
CN105421780A (en) * 2015-10-26 2016-03-23 国强建设集团有限公司 Construction method of prefabricated concrete structure
CN105735522A (en) * 2016-03-25 2016-07-06 中国航天建设集团有限公司沈阳分公司 Reverse operation assembly type shear wall and construction method

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661329A (en) * 2018-04-25 2018-10-16 李藏柱 The mounting bracket of prefabricated components, precast wall body and its installation method containing the holder
CN109610648A (en) * 2018-12-20 2019-04-12 五冶集团上海有限公司 Piece processing method before a kind of assembled architecture concrete members pour
CN110439290A (en) * 2019-07-10 2019-11-12 中国十七冶集团有限公司 A kind of prefabricated concrete structure construction method
CN110616800A (en) * 2019-10-20 2019-12-27 中建四局第六建筑工程有限公司 Vertical wall is whole cast-in-place and prefabricated building structure of horizontal structure
CN112983049A (en) * 2021-03-11 2021-06-18 三能集成房屋股份有限公司 Prefabricated wallboard supporting system and using method thereof
CN113309229A (en) * 2021-06-01 2021-08-27 中建八局第一建设有限公司 Grouting reverse-sequence construction method for assembled vertical component
CN113833183A (en) * 2021-09-22 2021-12-24 北京建工四建工程建设有限公司 Prefabricated hollow shear wall panel system and construction method thereof
CN113719137A (en) * 2021-09-29 2021-11-30 徐红伟 Construction engineering secondary structure and masonry engineering and main body engineering synchronous construction method
CN115613707A (en) * 2022-09-23 2023-01-17 重庆欧冠钢结构有限公司 A combination node of vertical and horizontal load-bearing components of walls, beams, and slabs in a prefabricated building
CN119711702A (en) * 2025-02-08 2025-03-28 中建八局第三建设有限公司 Reverse construction method for flat floor structure

Also Published As

Publication number Publication date
CN106193623B (en) 2018-05-08

Similar Documents

Publication Publication Date Title
CN106193623B (en) A kind of prefabricated concrete structure construction method
CN102230315B (en) Prefabricated components of multi-storey building and semi-prefabricated construction method
CN100451263C (en) Two-way steel-laminated slab concrete composite floor
CN201217898Y (en) Concrete prefabricated stairs
CN113123516B (en) Beam-slab integrated precast concrete structure and construction method
CN108360712A (en) A kind of assembled steel reinforced concrete shear force wall and its construction method
CN104032854B (en) Assembled T-shaped mixing coupled wall and construction method thereof
CN104775553A (en) Novel L-shaped edge member for superimposed slab shear walls and connecting method for novel L-shaped edge member
CN103470040A (en) Splicing method of composite floor slab and beam
CN104532953A (en) Prefabricated special-shaped column frame structure and its construction method based on 3D printing
CN104775555B (en) A kind of T-shaped composite plate shear wall edge member and attaching method thereof
CN105220792A (en) A kind of prefabricated concealed bracings energy-consuming shear wall and assemble method thereof
CN110670722A (en) Implementation method of beam-column connecting node of fabricated building
CN208251372U (en) A kind of assembled steel reinforced concrete shear force wall
CN110805144B (en) Full-assembly type high-rise/super high-rise concrete frame support structure system and construction method thereof
CN112593632A (en) Fabricated beam-slab structure suitable for large-span high-clearance building and construction method thereof
CN110439291A (en) A kind of assembled production and construction method suitable for low-rise building
CN207714507U (en) The assembled architecture component system of a set of novel dismountable
CN109518802A (en) Assembled beam-column structure and construction method thereof
CN110512784A (en) A kind of assembled light floor and its construction method
CN207405842U (en) An integral fully prefabricated floor slab unsupported connection structure
CN104032855A (en) Assembly-type cross-shaped mixed coupled wall and construction method thereof
CN104032859B (en) Assembled L-shaped mixing coupled wall and construction method thereof
CN108571065A (en) The assembled steel tendon concrete frame structure of connector is connected to based on steel plate
CN108755938B (en) Steel core area node of assembled concrete frame

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180508