CN106192652A - A kind of high steep embankment ruggedized construction preventing differential settlement - Google Patents

A kind of high steep embankment ruggedized construction preventing differential settlement Download PDF

Info

Publication number
CN106192652A
CN106192652A CN201610786432.9A CN201610786432A CN106192652A CN 106192652 A CN106192652 A CN 106192652A CN 201610786432 A CN201610786432 A CN 201610786432A CN 106192652 A CN106192652 A CN 106192652A
Authority
CN
China
Prior art keywords
embankment
differential settlement
high steep
ruggedized construction
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610786432.9A
Other languages
Chinese (zh)
Inventor
梁瑶
侯中学
蔡先庆
吴晓春
唐晓波
鲜苗
向飞
赵洪湖
梁秀雯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Communication Surveying and Design Institute Co Ltd
Original Assignee
Sichuan Communication Surveying and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Communication Surveying and Design Institute Co Ltd filed Critical Sichuan Communication Surveying and Design Institute Co Ltd
Priority to CN201610786432.9A priority Critical patent/CN106192652A/en
Publication of CN106192652A publication Critical patent/CN106192652A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Road Paving Structures (AREA)

Abstract

A kind of high steep embankment ruggedized construction preventing differential settlement, it is applicable to the bottom stab ilization structure of the bigger high steep embankment of both sides hypsography, a gear reliably is provided for the high steep embankment in mountain area, it is prevented effectively from excessive differential settlement, improve highway or the running comfort of high-speed railway, it is to avoid security incident occurs.Including the embankment embankment filled on hypsography larger skirt slope, both sides, in described embankment embankment, longitudinally, laterally interval arranges reinforcing pile, and the lower anchor of each reinforcing pile is in embankment embankment.Arranging rigid structural layer on the end face of described embankment embankment, rigid structural layer consolidates with the stake top of each reinforcing pile.Fill bed course on described rigid structural layer, on bed course, construct pavement structure.

Description

A kind of high steep embankment ruggedized construction preventing differential settlement
Technical field
The present invention relates to railway, Reinforcement of Highway structure, particularly to a kind of high steep embankment reducing differential settlement Reinforce.
Background technology
In recent years, infrastructure construction enters the high-speed developing period, and railway, road event are built on a large scale, are positioned at mountain area Railway, highway, due to the violent fluctuating of landform, inevitably need to drop into filling of walking along the street dike at steep slope section.In landform The low-lying place of landforms, because long-term charge for remittance or farmland planting need, is commonly formed soft foundation, and its sedimentation is higher much larger than physical features The embankment of side.
At present, railway, the desin speed of highway have had and have been substantially improved, and higher design speed per hour not only needs to control embankment Bulk settling, for preventing the cracking of pavement structure, the differential settlement of embankment is also the factor needing to control.For such both sides The high steep embankment that hypsography is bigger, currently mainly uses the embankment to hypsography low-lying side to carry out basement process, reduces work at this Rear sedimentation, does not considers the lateral variation sedimentation that embankment difference in embankment both sides causes.Landform is the highest compared with the embankment raising of downside, due to The impact of soft foundation discharging consolidation, settling amount will be much larger than landform upper side.Due to embankment both sides height of embankment difference, certainly will Cause the relative settlement of embankment both sides, i.e. differential settlement.Differential settlement is the biggest, will result in the cracking destruction of pavement structure, Impact operation comfortableness, excessive differential settlement is also possible to cause security incident.Therefore, rise and fall for both sides landform height High steep embankment, needs to seek a kind of bottom stab ilization structure that can effectively control embankment differential settlement.
Summary of the invention
The technical problem to be solved is to provide a kind of high steep embankment ruggedized construction preventing differential settlement, suitable For the bottom stab ilization structure of the bigger high steep embankment of both sides hypsography, provide a gear reliably for the high steep embankment in mountain area, have Effect avoids excessive differential settlement, improves highway or the running comfort of high-speed railway, it is to avoid security incident occurs.
The technical solution adopted for the present invention to solve the technical problems is as follows:
A kind of high steep embankment ruggedized construction preventing differential settlement of the present invention is bigger including filling in both sides hypsography Embankment embankment in side slope, is characterized in that: in described embankment embankment, longitudinally, laterally interval arranges reinforcing pile, under each reinforcing pile Portion is anchored in embankment embankment;Rigid structural layer, rigid structural layer and each reinforcing pile are set on the end face of described embankment embankment Stake top consolidation;Fill bed course on described rigid structural layer, on bed course, construct pavement structure.
The invention has the beneficial effects as follows, below road surface structare layer, laid adding of bed course, rigid structural layer and its underpart Gu stake, the settlement after construction that the high steep embankment of tunable is horizontal, it is greatly reduced the differential settlement on embankment top, is effectively improved at a high speed Highway or the running comfort of high-speed railway, it is to avoid security incident occurs.
Accompanying drawing explanation
This specification includes following two width accompanying drawings:
Fig. 1 is the cross-sectional view of a kind of lateral pile slab structure being applicable to steep rocky slope embankment of the present invention;
Fig. 2 is the enlarged drawing of A local in Fig. 1
Component shown in figure and corresponding labelling: pavement structure 1, bed course 2, rigid structural layer 3, reinforcing pile 4, embankment is filled out Side 5.
Detailed description of the invention
The present invention is further described with embodiment below in conjunction with the accompanying drawings.
Seeing figures.1.and.2, a kind of high steep embankment ruggedized construction preventing differential settlement of the present invention, including filling in two Embankment embankment 5 on hypsography larger skirt slope, side.In described embankment embankment 5, longitudinally, laterally interval arranges reinforcing pile 4, respectively adds Gu the lower anchor of stake 4 is in embankment embankment 5, embankment embankment is reinforced, make embankment form overall stress, it is to avoid roadbed entirety is horizontal To the difference of rigidity.Rigid structural layer 3, rigid structural layer 3 and each reinforcing pile 4 are set on the end face of described embankment embankment 5 Stake top consolidation, effectively to control the displacement at pile top of reinforcing pile 4, improves stability and the reliability of ruggedized construction.Described rigidity is tied Fill bed course 2 on structure layer 3, construct pavement structure 1 on bed course 2 and reduce the differential settlement of roadbed.
Described bed course 2 usually permeable structure layer, is filled formed by crushed-gravel or sheet rubble, thickness 0.8~2.5m, depending on Depending on the roadbed work area degree of depth of highway or railway, for undertaking the additional stress that vehicular load produces.
Described rigid structural layer 3 generally can use armoured concrete slab, thickness 1~2m, by longitudinal length be 5~7m vertical Constitute to plate, between each longitudinal plate, set expansion joint.The length that the stake top of described reinforcing pile 4 is stretched in rigid structural layer 3 is not less than 100mm。
Described reinforcing pile 4 is the one in reinforced concrete pile, mini pile, reinforced anchor bolt or aggregate pile, depending on high steep embankment Depending on height of embankment, both sides topographical elevation difference and embankment lateral stability.
Certain highway high roadbed work point, left and right sides hypsography is obvious, and left side landform is high, and right side landform is low, in embankment Heart raising 10.63m.Left side height of embankment 5.5m, right side height of embankment 20.5m, both sides embankment slope height difference 15m.Right side base The end is soft foundation, silty clay, soft moulds~stream moulds shape, weak soil thickness about 6m, uses cement mixing pile to process.Left side substrate is covered Cap rock is relatively thin, about 0.3~0.8m, and subterrane is system Soil Developed From Suining Group sand shale on sieve dwarf.
Scheme 1: traditional design, is layered cape rammer to high side slope of embankment.
The non-soft foundation part in left side, owing to height of embankment is relatively low, base property is good, and the settling amount of filler and substrate is relative Less.Right side soft foundation is after complex ground treatment, and under the compaction banketed up, substrate discharging consolidation will produce relatively Big sedimentation;Owing to right side height of embankment is higher, the sedimentation of its filler is also the biggest.Toe, center and slope, right side on the left of embankment The settling amount of foot is respectively 1.35cm, 4.62cm and 10.4cm, and differential settlement is obvious.
Scheme 2: use the technical scheme of the application
Roadbed part below road surface structare layer, changes back-up sand gravel blanket, and sets armoured concrete slab below bed course, under it For mini pile, in stake-middle spacing 3m.On the left of embankment, the settling amount of toe, center and right side toe is respectively 1.25cm, 4.24cm And 7.51cm, differential settlement is greatly reduced.Separately it is arranged at below road surface structare layer due to this structure, uneven in the range of roadbed Sedimentation, much smaller than 1cm, can effectively prevent the pavement cracking caused due to differential settlement from destroying.
The above a kind of Steep Slope Embankment being applicable to prevent differential settlement of the present invention that simply explains through diagrams adds consolidation Some principles of structure, are not intended to the present invention be confined in shown and described concrete structure and the scope of application, therefore every institute The corresponding amendment being likely utilized and equivalent, belong to the apllied the scope of the claims of the present invention.

Claims (5)

1. prevent a high steep embankment ruggedized construction for differential settlement, including filling on hypsography larger skirt slope, both sides Embankment embankment (5), is characterized in that: in described embankment embankment (5), longitudinally, laterally interval arranges reinforcing pile (4), each reinforcing pile (4) Lower anchor in embankment embankment (5);On the end face of described embankment embankment (5), rigid structural layer (3), rigid structure are set Layer (3) consolidates with the stake top of each reinforcing pile (4);Filling bed course (2) on described rigid structural layer (3), bed course is constructed on (2) Pavement structure (1).
A kind of high steep embankment ruggedized construction preventing differential settlement, is characterized in that: described rigidity Structure sheaf (3) is armoured concrete slab, thickness 1~2m, is made up of longitudinal plate that longitudinal length is 5~7m, between each longitudinal plate If expansion joint.
A kind of high steep embankment ruggedized construction preventing differential settlement, is characterized in that: described reinforcing The length in rigid structural layer (3) is stretched into not less than 100mm in the stake top of stake (4).
A kind of high steep embankment ruggedized construction preventing differential settlement, is characterized in that: described reinforcing Stake (4) is the one in reinforced concrete pile, mini pile, reinforced anchor bolt or aggregate pile.
A kind of high steep embankment ruggedized construction preventing differential settlement, is characterized in that: described bed course (2) it is permeable structure layer, is filled formed by crushed-gravel or sheet rubble, thickness 0.8~2.5m.
CN201610786432.9A 2016-08-31 2016-08-31 A kind of high steep embankment ruggedized construction preventing differential settlement Pending CN106192652A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610786432.9A CN106192652A (en) 2016-08-31 2016-08-31 A kind of high steep embankment ruggedized construction preventing differential settlement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610786432.9A CN106192652A (en) 2016-08-31 2016-08-31 A kind of high steep embankment ruggedized construction preventing differential settlement

Publications (1)

Publication Number Publication Date
CN106192652A true CN106192652A (en) 2016-12-07

Family

ID=58087033

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610786432.9A Pending CN106192652A (en) 2016-08-31 2016-08-31 A kind of high steep embankment ruggedized construction preventing differential settlement

Country Status (1)

Country Link
CN (1) CN106192652A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638168A (en) * 2017-01-17 2017-05-10 马鞍山钢铁股份有限公司 Device for treating metallurgy railroad bed defects through reinforcing and grouting and construction method
CN106948233A (en) * 2017-03-15 2017-07-14 温州市阳光建设有限公司 A kind of town road asphalt concrete construction method
CN107119678A (en) * 2017-06-29 2017-09-01 中铁第四勘察设计院集团有限公司 Soft clay area railway station platform sedimentation mini pile repairs structure and construction method
CN110055828A (en) * 2019-04-28 2019-07-26 中铁二院工程集团有限责任公司 A kind of embankment heavy grade cogwheel railway structure and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201962558U (en) * 2011-03-21 2011-09-07 中铁二院工程集团有限责任公司 High-steepness side slope subgrade structure for mountainous area
RU2449075C1 (en) * 2010-11-26 2012-04-27 Общество с ограниченной ответственностью "Финансово-Строительная компания "МостГеоЦентр" Method to strengthen loose natural base for erection of road earth bed
CN202247575U (en) * 2011-09-09 2012-05-30 中铁二院工程集团有限责任公司 Structure for strengthening roadbed in high-speed railway station turnout area with highly developed karst
CN103806347A (en) * 2014-03-11 2014-05-21 四川省交通运输厅交通勘察设计研究院 Lateral pile-plank structure suitable for rocky abrupt-slope embankment
CN206385411U (en) * 2016-08-31 2017-08-08 四川省交通运输厅交通勘察设计研究院 It is a kind of to prevent the steep embankment ruggedized construction of height of differential settlement

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2449075C1 (en) * 2010-11-26 2012-04-27 Общество с ограниченной ответственностью "Финансово-Строительная компания "МостГеоЦентр" Method to strengthen loose natural base for erection of road earth bed
CN201962558U (en) * 2011-03-21 2011-09-07 中铁二院工程集团有限责任公司 High-steepness side slope subgrade structure for mountainous area
CN202247575U (en) * 2011-09-09 2012-05-30 中铁二院工程集团有限责任公司 Structure for strengthening roadbed in high-speed railway station turnout area with highly developed karst
CN103806347A (en) * 2014-03-11 2014-05-21 四川省交通运输厅交通勘察设计研究院 Lateral pile-plank structure suitable for rocky abrupt-slope embankment
CN206385411U (en) * 2016-08-31 2017-08-08 四川省交通运输厅交通勘察设计研究院 It is a kind of to prevent the steep embankment ruggedized construction of height of differential settlement

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638168A (en) * 2017-01-17 2017-05-10 马鞍山钢铁股份有限公司 Device for treating metallurgy railroad bed defects through reinforcing and grouting and construction method
CN106948233A (en) * 2017-03-15 2017-07-14 温州市阳光建设有限公司 A kind of town road asphalt concrete construction method
CN107119678A (en) * 2017-06-29 2017-09-01 中铁第四勘察设计院集团有限公司 Soft clay area railway station platform sedimentation mini pile repairs structure and construction method
CN110055828A (en) * 2019-04-28 2019-07-26 中铁二院工程集团有限责任公司 A kind of embankment heavy grade cogwheel railway structure and construction method
CN110055828B (en) * 2019-04-28 2023-09-26 中铁二院工程集团有限责任公司 Construction method of embankment large-gradient toothed rail railway structure

Similar Documents

Publication Publication Date Title
CN203174453U (en) Light-mass embankment structure for managing bump at bridge head
CN107905089A (en) A kind of reinforcement platform back of the body for preventing bumping at bridge-head and its construction method
CN206385411U (en) It is a kind of to prevent the steep embankment ruggedized construction of height of differential settlement
CN106192652A (en) A kind of high steep embankment ruggedized construction preventing differential settlement
CN103046446B (en) A kind of Expressway Extension Project joint portion treatment structures
CN104746501A (en) Treatment method and structure of bridge-head foundation sliding settlement
CN205399090U (en) On stride highway's pile foundation reinforced concrete railway roadbed structure
CN106676994B (en) The adjustable foam concrete embankment of load and construction method
CN202969393U (en) Ribbing load reduction structure of road high hill culvert
CN104358196B (en) Highway open to traffic Embankment Subsidence disposes the construction method of structure
CN110042715A (en) The construction method of the hard and soft combination soil stabilization system of Abutment Back
CN207727452U (en) A kind of back filling behind abutment structure sheaf for preventing culvert jump vehicle
CN201530961U (en) Transition section structure of liquefying soil foundation anti-seismic road and bridge of high-speed railway ballastless track
CN203334154U (en) Embankment structure for preventing bearing platform of pile foundation from stretching in roadbed under viaduct
CN105804101A (en) Load-reducing retaining system capable of reducing stress of retaining structure, construction method and applications
CN203034328U (en) Joint part treatment structure of reconstruction and extension project of expressway
CN206245155U (en) A kind of firm road structure of embankment
CN107514008A (en) Composite foundation reinforced cantilever retaining wall structure and construction method
CN207452938U (en) Composite foundation reinforced cantilever retaining wall structure
CN213389548U (en) Settlement-preventing roadbed for deep soft soil high fill
CN211340257U (en) Culvert platform back of body road bed reinforced structure
CN216107863U (en) Can reduce uneven indisputable tailing of subsiding and add muscle embankment structure
CN105544334B (en) One kind is used for vehicle jumping at bridge head of highway Treatment Methods
CN213507862U (en) Municipal administration road widen structure
CN209555946U (en) A kind of reparation structure that high embankment collapses

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161207