CN106184626B - The pier mooring method of tension leg platform (TLP) - Google Patents

The pier mooring method of tension leg platform (TLP) Download PDF

Info

Publication number
CN106184626B
CN106184626B CN201610609639.9A CN201610609639A CN106184626B CN 106184626 B CN106184626 B CN 106184626B CN 201610609639 A CN201610609639 A CN 201610609639A CN 106184626 B CN106184626 B CN 106184626B
Authority
CN
China
Prior art keywords
tlp
barge
leg platform
tension leg
mooring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610609639.9A
Other languages
Chinese (zh)
Other versions
CN106184626A (en
Inventor
陈广宁
张艳芳
窦星慧
李强
宋立新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Offshore Oil Corp CNOOC
Offshore Oil Engineering Co Ltd
Offshore Oil Engineering Qingdao Co Ltd
Original Assignee
China National Offshore Oil Corp CNOOC
Offshore Oil Engineering Co Ltd
Offshore Oil Engineering Qingdao Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Offshore Oil Corp CNOOC, Offshore Oil Engineering Co Ltd, Offshore Oil Engineering Qingdao Co Ltd filed Critical China National Offshore Oil Corp CNOOC
Priority to CN201610609639.9A priority Critical patent/CN106184626B/en
Publication of CN106184626A publication Critical patent/CN106184626A/en
Application granted granted Critical
Publication of CN106184626B publication Critical patent/CN106184626B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/50Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
    • B63B21/502Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers by means of tension legs
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/50Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
    • B63B2021/505Methods for installation or mooring of floating offshore platforms on site

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Revetment (AREA)

Abstract

A kind of pier mooring method of tension leg platform (TLP), using following mooring step:One:Further the size of device according to the column spacing of tension leg platform (TLP) and tension force muscle, completes the design of barge and prefabricated;Two:According to the arrangement of bollard on harbour, corresponding several anchor points are set on barge;Three:Fixed along the length direction of barge in the both sides of barge and lean on ball;Four:Anchor point is fixed in the bollard of wharf apron;Five:Tension leg platform (TLP) is drawn to barge, and makes to be in close contact by the column of ball and tension leg platform (TLP);Six:Tension leg platform (TLP) is fixed in bollard, and fastened;Seven:By the anchor point set on barge, will be connected between barge and tension leg platform (TLP).The present invention can not only by tension leg platform (TLP) mooring on harbour, solve tension leg platform (TLP) mooring stability and easily with harbour collision problem;Moreover, also assures that the safe distance between tension force muscle take-up device and harbour, substantially increase pier mooring process stablizes emerging and security.

Description

The pier mooring method of tension leg platform (TLP)
Technical field
The present invention relates to a kind of pier mooring method of the anchoring method of floating platform, more particularly to tension leg platform (TLP), category Yu Haiyang petroleum works field.
Background technology
Tension leg platform (TLP) has obtained more and more extensive application as a kind of typical deepwater oil-gas development platform.Semi-submersible type Platform is similar with tension leg platform (TLP), but its drinking water is typically small, and its buoyancy tank is normally at more than the water surface, is squeezed typically by buoyancy tank By formulating corresponding mooring scheme by ball;And tension leg platform (TLP) is typically small due to absorbing water, therefore, the Major Difficulties of its mooring It is:
1. tension leg platform (TLP) drinking water is larger, buoyancy tank is normally at below the water surface, with leaning on squeezing for ball etc. when being difficult to mooring , therefore, can only be by circular abutment with being born against by ball etc. by effect, and circular column and the contact area by ball are smaller, by The less stable of the effects such as stormy waves;
2. the tension force muscle take-up device of tension leg platform (TLP) bottom is the position of tension leg platform (TLP) most critical, it is in mooring process In easily with harbour collide, cause the mooring difficulty of tension leg platform (TLP) to increase.
The content of the invention
It is a primary object of the present invention to overcome disadvantages mentioned above existing for prior art, and provide a kind of tension leg platform (TLP) Pier mooring method, its can not only by tension leg platform (TLP) mooring on harbour, solve tension leg platform (TLP) mooring stability and Easily with harbour collision problem;Moreover, also assures that the safe distance between tension force muscle take-up device and harbour, code is substantially increased Head mooring process stablizes emerging and security, reduces tension force muscle take-up device and the risk of harbour collision during mooring, is Tension leg platform (TLP) carries out mooring on harbour, there is provided technical guarantee.
The purpose of the present invention is realized by following technical scheme:
A kind of pier mooring method of tension leg platform (TLP), it is characterised in that:Using following mooring step:
The first step:Further the size of device according to the column spacing of tension leg platform (TLP) and tension force muscle, completes the design of barge It is and prefabricated;
Second step:According to the arrangement of bollard on harbour, corresponding several anchor points are set on barge;
3rd step:Fixed along the length direction of barge in the both sides of barge and lean on ball;
4th step:Anchor point is fixed in the bollard of wharf apron;
5th step:Tension leg platform (TLP) is drawn to barge, and makes to be in close contact by the column of ball and tension leg platform (TLP);
6th step:Tension leg platform (TLP) is fixed in bollard, and fastened;
7th step:By the anchor point set on barge, will be connected between barge and tension leg platform (TLP).
It is described concordant with the water line of barge by ball centre of buoyancy.
Beneficial effects of the present invention:The present invention is because using above-mentioned technical proposal, it can not only be by tension leg platform (TLP) system Pool on harbour, solve tension leg platform (TLP) mooring stability and easily with harbour collision problem;Moreover, it also assures that tension force muscle is drawn The tightly safe distance between device and harbour, substantially increase pier mooring process stablizes emerging and security, reduces mooring During the collision of tension force muscle take-up device and harbour risk, mooring is carried out on harbour for tension leg platform (TLP), there is provided technology Ensure.
Brief description of the drawings
Fig. 1 is tension leg platform (TLP) overall structure diagram of the present invention.
Fig. 2 is that the anchor point on barge of the present invention arranges schematic diagram.
For the present invention, ball schematic diagram is leaned in the installation on barge to Fig. 3.
Fig. 4 is that barge of the present invention fixes schematic diagram by bollard in harbour.
Fig. 5 is that tension leg platform (TLP) of the present invention bears against schematic diagram with barge.
Fig. 6 is tension leg platform (TLP) of the present invention and the connection diagram of bollard on harbour.
Fig. 7 is the connection diagram of tension leg platform (TLP) of the present invention and barge.
Major Symbol explanation in figure:
1. tension leg platform (TLP), 2. columns, 3. tension force muscle take-up devices, 4. barges, 5. anchor points, 6. are by ball, 7. harbours, 8. Bollard, 9. hawsers.
Embodiment
As shown in Fig. 1-Fig. 7, the present invention uses following mooring step:
The first step:Further the size of device 3 according to the spacing of column 2 of tension leg platform (TLP) 1 and tension force muscle, completes barge 4 Design and prefabricated;
Second step:According to the arrangement of bollard 8 on harbour 7, corresponding several anchor points 5 are set on barge 4;
3rd step:Fixed along the length direction of barge 4 in the both sides of barge 4 and lean on ball 6, and lean on eating for the centre of buoyancy of ball 6 and barge 4 Waterline is concordant;
4th step:By the several anchor points 5 being arranged on barge 4, before anchor point 5 is fixed on into harbour 7 using hawser 9 In the bollard 8 on edge;
5th step:Tension leg platform (TLP) 1 is drawn to the outside of barge 4, and makes the column 2 by ball 6 and tension leg platform (TLP) 1 close Contact;
6th step:Tension leg platform (TLP) 1 is fixed in bollard 8 using hawser 9, and fastened;
7th step:By the anchor point 5 set on barge 4, will be connected between barge 4 and tension leg platform (TLP) 1 by hawser 9 Connect.
Mentioned strain leg platform, tension force muscle further device, column, barge, anchor point, by ball, be prior art, do not say Bright technology is prior art, therefore is repeated no more.
The above described is only a preferred embodiment of the present invention, any formal limitation not is made to the present invention, it is all It is any simple modification, equivalent change and modification made according to the technical spirit of the present invention to above example, still falls within In the range of technical solution of the present invention.

Claims (1)

1. a kind of pier mooring method of tension leg platform (TLP), it is characterised in that:Using following mooring step:
The first step:Further the size of device according to the column spacing of tension leg platform (TLP) and tension force muscle, completes the design of barge and pre- System;
Second step:According to the arrangement of bollard on harbour, corresponding several anchor points are set on barge;
3rd step:Fixed along the length direction of barge in the both sides of barge and lean on ball;
4th step:Anchor point is fixed in the bollard of wharf apron;
5th step:Tension leg platform (TLP) is drawn to barge, and makes to be in close contact by the column of ball and tension leg platform (TLP);
6th step:Tension leg platform (TLP) is fixed in bollard, and fastened;
7th step:By the anchor point set on barge, will be connected between barge and tension leg platform (TLP);
It is described concordant with the water line of barge by ball centre of buoyancy.
CN201610609639.9A 2016-07-29 2016-07-29 The pier mooring method of tension leg platform (TLP) Active CN106184626B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610609639.9A CN106184626B (en) 2016-07-29 2016-07-29 The pier mooring method of tension leg platform (TLP)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610609639.9A CN106184626B (en) 2016-07-29 2016-07-29 The pier mooring method of tension leg platform (TLP)

Publications (2)

Publication Number Publication Date
CN106184626A CN106184626A (en) 2016-12-07
CN106184626B true CN106184626B (en) 2017-12-19

Family

ID=57496847

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610609639.9A Active CN106184626B (en) 2016-07-29 2016-07-29 The pier mooring method of tension leg platform (TLP)

Country Status (1)

Country Link
CN (1) CN106184626B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108583786B (en) * 2018-05-16 2019-09-27 江苏金风科技有限公司 Wind-powered electricity generation O&M ship steps on stepping on by method by auxiliary device and wind-powered electricity generation O&M ship
CN110696963A (en) * 2019-09-05 2020-01-17 海洋石油工程(青岛)有限公司 Ship wharf mooring method
CN115626267B (en) * 2022-10-27 2023-05-23 中电建海上风电工程有限公司 Integral construction method for mooring floating offshore wind turbine by pile

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS506959B1 (en) * 1970-03-05 1975-03-19
US5423632A (en) * 1993-03-01 1995-06-13 Shell Oil Company Compliant platform with slide connection docking to auxiliary vessel
FR2755091B1 (en) * 1996-10-30 1998-12-04 Doris Engineering DEVICE FOR CONNECTING TWO MARINE STRUCTURES
US7287484B2 (en) * 2003-05-01 2007-10-30 David Charles Landry Berthing method and system
CN101057042B (en) * 2004-11-11 2010-10-13 辛格尔浮筒系船公司 Soft quay mooring system
CN201092380Y (en) * 2007-04-27 2008-07-30 中国海洋石油总公司 Ship mooring facilities of marine oil-gas production platform
CN202031066U (en) * 2011-02-10 2011-11-09 中国海洋石油总公司 Multiple-floating-body compound rope mooring device

Also Published As

Publication number Publication date
CN106184626A (en) 2016-12-07

Similar Documents

Publication Publication Date Title
CN106184626B (en) The pier mooring method of tension leg platform (TLP)
CN107140138B (en) A kind of dry tree oil storage semi-submersible type production platform of deep drinking water
US8251005B2 (en) Spar structures
CN104743058B (en) The method of tension leg platform (TLP) upper chunk floating support mounting
CN109110057B (en) Pile type mooring device suitable for shallow water floating platform
CN1961120A (en) Ballasting offshore platform with buoy assistance
CN201140778Y (en) Flexible connection mooring apparatus for oil transportation on the sea
CN201309577Y (en) Special installation equipment for installing ocean platforms
WO2004099508A3 (en) Berthing method and system
CN201103116Y (en) Beach oil containment boom
CN203247560U (en) Solid float type rubber floating debris obstructing row
CN201236337Y (en) Warping hawser apparatus for wharf
CN204587223U (en) A kind of floating landing stage testing device
CN202031066U (en) Multiple-floating-body compound rope mooring device
CN205975481U (en) Boats and ships are in shallow water area alongside system
CN206337543U (en) A kind of off-lying sea harbour
JP2003342935A (en) Floating wave-absorbing bank
AU2011101650A4 (en) Self installing tension leg platform and subsea storage tank
CN203889018U (en) Marine drilling platform with two layers of triangular tension legs
CN210395284U (en) Oil containment boom offshore tying and hanging structure and port and pier oil spill emergency equipment
CN209305773U (en) A kind of pilot boat side of a ship escape device
CN103029814A (en) Novel tension leg buoy berthing device
CN201864010U (en) Boarding ladder
CN1302961C (en) Wave-proof type bottom-sitting form floating pier
CN209833907U (en) Arc-shaped limiting and fastening device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee after: Offshore Oil Engineering (Qingdao) Co., Ltd.

Patentee after: China Offshore Oil Group Co., Ltd.

Co-patentee after: Offshore Oil Engineering Co., Ltd.

Address before: 100010 Chaoyangmen North Street, Dongcheng District, Dongcheng District, Beijing

Co-patentee before: Offshore Oil Engineering (Qingdao) Co., Ltd.

Patentee before: China National Offshore Oil Corporation

Co-patentee before: Offshore Oil Engineering Co., Ltd.