Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610547477.0A
Other languages
Chinese (zh)
Other versions
CN106184610B (en
Inventor
林德齐
夏宇
繁王兰
李光兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Wenchong Shipyard Co Ltd
Original Assignee
Guangzhou Wenchong Shipyard Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Wenchong Shipyard Co Ltd filed Critical Guangzhou Wenchong Shipyard Co Ltd
Priority to CN201610547477.0A priority Critical patent/CN106184610B/en
Publication of CN106184610A publication Critical patent/CN106184610A/en
Application granted granted Critical
Publication of CN106184610B publication Critical patent/CN106184610B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B71/00Designing vessels; Predicting their performance

Abstract

The invention provides a kind of sternpost and tail fin installation method, including step: the pre-assembling platform of level of building, the pre-assembling platform of level draws cross coordinate centrage and angle line;Draw the front end face of sternpost and the central cross line of rear end face;The pre-assembling platform of level places sternpost leveling, and the cross centre line of just pre-to the level assembling platform of the central cross line of sternpost with the rear end face of sternpost for basal plane;Tail fin is contained on sternpost in advance, the maximum section of tail fin and sternpost is the most at grade, the end points of the maximum section of tail fin is projected to the pre-assembling platform of level, by the coordinate of subpoint with theoretical coordinate compared with, regulates and close up mouth until Two coordinate overlaps between tail fin and sternpost;To zygonema at drawing the rib position prepackage inspection line overlapped with maximum section after prepackage and holding together mouthful;According to rib bit trial line and zygonema to be come assembly welding sternpost and tail fin.The present invention can directly assemble sternpost and tail fin by guide field, improves installation accuracy, saves installation period.

Description

A kind of sternpost and tail fin installation method
Technical field
The invention belongs to shipbuilding technology field, particularly relate to a kind of sternpost and tail fin installation method.
Background technology
28000DWT bulk freighter and conventional bulk freighter have a difference the biggest, it is simply that stern foundry goods, with former phase Many three tail fins of ratio, and sternpost and tail fin foundry goods be separately cast in, and causes sternpost and 3 tail fin leaves to need assembling, by Complicated in sternpost and caudal-fin models so that assembling process is extremely difficult, it is difficult to ensure that required precision, foundry goods installation period is longer.
Summary of the invention
The technical problem to be solved is, it is provided that a kind of sternpost and tail fin installation method, it is possible to guide field Directly assembling sternpost and tail fin, reduces and installs foundry goods difficulty, reduces foundry goods installation accuracy problem, saves foundry goods installation period.
In order to solve above-mentioned technical problem, the invention provides a kind of sternpost and tail fin installation method, it includes walking as follows Rapid:
Step one, the pre-assembling platform of level of building, the pre-assembling platform of level draws cross coordinate centrage and angle line, uses In location sternpost and tail fin;
Step 2, after sternpost foundry goods casts out, draws the front end face of sternpost and the central cross line of rear end face and beats ocean Rush a little;
Step 3, places in sternpost leveling, and sternpost with the rear end face of sternpost for basal plane on the pre-assembling platform of level The cross centre line of just pre-to the level assembling platform of crux of heart line;
Step 4, is contained on sternpost in advance by tail fin, the maximum section of tail fin with the maximum section of sternpost all same In plane, the end points of the maximum section of tail fin is projected to the pre-assembling platform of level, by level pre-assembling platform upslide shadow Point coordinate, compared with theoretical coordinate, regulation tail fin and sternpost between close up mouth, until the end points of tail fin projection sit Mark and theoretical coordinate overlap, i.e. prepackage puts in place;
Step 5, after sternpost is pre-installed with tail fin, draws, at sternpost and tail fin surface, the rib position overlapped with maximum section pre- Dress inspection line is also beaten ocean and is rushed a little, draw sternpost and tail fin close up mouthful to zygonema and beat ocean and rush a little;
Step 6, the rib bit trial line drawn when sternpost and tail fin are according to prepackage and close up at mouth to zygonema, assemble Welding, completes whole installation process.
As preferred technical scheme, in described step 6, sternpost and the assembly welding step of tail fin: first on lifting stern Segmentation, welds sternpost on stern, then for basal plane, sectional turn-over on stern is placed on dress with the rear end face of sternpost in segmentation On trim platform and leveling, the rib bit trial line that draws during finally according to prepackage and close up at mouth to zygonema, sternpost assembles 3 Sheet tail fin.
As preferred technical scheme, before described step one, also include the preparation process before prepackage: make sternpost Big cross section detection model, inspection sternpost line style before prepackage;Make sternpost and detect model with tail fin incision position section, inspection before prepackage Test tail fin sectional line style.
Implement a kind of sternpost and the tail fin installation method of the present invention, compared with prior art, have the advantages that
The present invention prepackage technique by above-mentioned sternpost and tail fin, guide field directly assembles sternpost and tail fin, reduces peace Dress foundry goods difficulty, reduces foundry goods installation accuracy problem, saves foundry goods installation period, thus shortens the sectional construction cycle.Through statistics, The present invention can save the time about 2 day set-up time of sternpost and tail fin, and precision controlling quality is good.
Accompanying drawing explanation
In order to be illustrated more clearly that the technical scheme of the embodiment of the present invention, the accompanying drawing of embodiment will be situated between simply below Continue.
Fig. 1 is the setting-out schematic diagram on the pre-assembling platform of level;
Fig. 2 is the schematic diagram that sternpost is installed on the pre-assembling platform of level;
Fig. 3 is the setting-out schematic diagram on the front end face of sternpost;
Fig. 4 is the setting-out schematic diagram on the rear end face of sternpost;
Fig. 5 is the schematic diagram of the maximum section A-A after sternpost assembles with tail fin;
Fig. 6 be in structure B shown in Fig. 5 to partial schematic diagram.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Describe, it is clear that described embodiment is only a part of embodiment of the present invention rather than whole embodiments wholely.Based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under not making creative work premise Embodiment, broadly falls into the scope of protection of the invention.
In conjunction with seeing Fig. 1 to Fig. 6, the preferred embodiments of the present invention, a kind of sternpost and tail fin installation method, it includes as follows Step:
Step one, the pre-assembling platform of level of building 1, the pre-assembling platform of level 1 draws cross coordinate centrage 11 and 45° angle Degree line 12, is used for positioning sternpost 2 and tail fin 3, as shown in Figure 1;
Step 2, after sternpost foundry goods casts out, draws the front end face 21 of sternpost 2 and the central cross line 23 of rear end face 22 And beat ocean and rush a little, as shown in Figure 2, Figure 3 and Figure 4;
Step 3, places sternpost 2 leveling, and sternpost with the rear end face 22 of sternpost 2 for basal plane on the pre-assembling platform of level 1 The cross centre line 11 of just pre-to the level assembling platform 1 of the central cross line 23 of 2, sternpost 2 surrounding suitably increases diagonal brace frock 4 and prevents Sternpost 2 collapses, as shown in Figure 2, Figure 3 and Figure 4;
Step 4, is contained on sternpost 2 in advance by tail fin 3, and the maximum section of tail fin 3 all exists with the maximum section of sternpost 1 On same plane A-A, ceiling hammer at the end points 31 of the maximum section of tail fin 3, the end points of tail fin is projected to level On pre-assembling platform 1, by the coordinate of subpoint on the pre-assembling platform of level 1, compared with theoretical coordinate, regulation tail fin 3 and sternpost 2 Between close up mouth 5, until the projection coordinate of the end points 31 of tail fin 3 and theoretical coordinate overlap, i.e. prepackage puts in place, such as Fig. 2 and Shown in Fig. 5;
Step 5, after sternpost 2 is pre-installed with tail fin 3, draws, at sternpost 2 and tail fin 3 surface, the rib overlapped with maximum section Prepackage inspection line 24,32 in position is also beaten ocean and is rushed a little, draws and closes up at mouth 5 zygonema 51 and beat ocean and rush a little, as shown in Figure 6;
Step 6, the rib bit trial line 24,32 drawn when sternpost 2 and tail fin 3 are according to prepackage and close up at mouth 5 to zygonema 51, carry out assembly welding, complete whole installation process.
Thus, the present invention prepackage technique by above-mentioned sternpost and tail fin, guide field directly assembles sternpost and tail fin, fall Low installation foundry goods difficulty, reduces foundry goods installation accuracy problem, saves foundry goods installation period, thus shortens the sectional construction cycle.Warp Statistics, the present invention can save the time about 2 day set-up time of sternpost and tail fin, and precision controlling quality is good.
In described step 6, sternpost 2 and the assembly welding step of tail fin 3: first segmentation on lifting stern, segmentation on stern Upper welding sternpost 2, is then placed on sectional turn-over on stern on mounting plate and leveling for basal plane with the rear end face of sternpost 2, Finally according to the rib bit trial line 24,32 that draws during prepackage and close up at mouth 5 to zygonema 51, sternpost assembles 3 tail fins 3.The effect using this scheme is: first assembling sternpost 2, does not affect and stands up welding on stern about segmentation, then will be on stern point Section stands up placement, and (segmentation weight about 7.3t, sternpost and tail fin weight about 11.6t on stern, on the stern compared, segmentation weight is very Gently, only several channel steel supports need to be found), 3 tail fins 3 of assembling, not only can guarantee that assembly precision requirement but also can the most on the ground Facilitate welding job.
For ensureing sternpost 2 and the casting accuracy of tail fin 3 and installation accuracy, before described step one, before also including prepackage Preparation process: make sternpost maximum section detection model, prepackage before inspection sternpost line style;Make sternpost and tail fin incision position Section detection model, inspection tail fin sectional line style before prepackage.
The above disclosed presently preferred embodiments of the present invention that is only, can not limit the right of the present invention with this certainly Scope, the equivalent variations therefore made according to scope of the present invention patent, still belong to the scope that the present invention is contained.

Claims (3)

1. a sternpost and tail fin installation method, it is characterised in that comprise the steps:
Step one, the pre-assembling platform of level of building, the pre-assembling platform of level draws cross coordinate centrage and angle line, for fixed Position sternpost and tail fin;
Step 2, after sternpost foundry goods casts out and, draws the front end face of sternpost and the central cross line of rear end face and beats ocean and rush a little;
Step 3, places sternpost leveling, and the center ten of sternpost with the rear end face of sternpost for basal plane on the pre-assembling platform of level The cross centre line of just pre-to the level assembling platform of wordline;
Step 4, is contained on sternpost in advance by tail fin, and the maximum section of tail fin and the maximum section of sternpost are all at same plane On, the end points of the maximum section of tail fin is projected to the pre-assembling platform of level, by level pre-assembling platform upslide shadow point Coordinate, compared with theoretical coordinate, regulation tail fin and sternpost between close up mouth, until the projection coordinate of the end points of tail fin and Theoretical coordinate overlaps, i.e. prepackage puts in place;
Step 5, after sternpost is pre-installed with tail fin, draws the rib position prepackage inspection overlapped with maximum section at sternpost and tail fin surface Test line and beat ocean and rush a little, draw sternpost and tail fin close up mouthful to zygonema and beat ocean and rush a little;
Step 6, the rib bit trial line drawn when sternpost and tail fin are according to prepackage and close up at mouth to zygonema, carry out assembly welding, Complete whole installation process.
2. sternpost as claimed in claim 1 and tail fin installation method, it is characterised in that in described step 6, sternpost and tail fin Assembly welding step:
First segmentation on lifting stern, welds sternpost, then by sectional turn-over on stern with the rear end of sternpost on stern in segmentation Face is that basal plane is placed on mounting plate and leveling, the rib bit trial line that draws during finally according to prepackage and close up at mouth involutory Line, assembles 3 tail fins on sternpost.
3. sternpost as claimed in claim 1 and tail fin installation method, it is characterised in that before described step one, also include Preparation process before prepackage: make sternpost maximum section detection model, inspection sternpost line style before prepackage;Make sternpost and tail fin Incision position section detection model, inspection tail fin sectional line style before prepackage.
CN201610547477.0A 2016-07-11 2016-07-11 A kind of sternpost and tail fin installation method Active CN106184610B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610547477.0A CN106184610B (en) 2016-07-11 2016-07-11 A kind of sternpost and tail fin installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610547477.0A CN106184610B (en) 2016-07-11 2016-07-11 A kind of sternpost and tail fin installation method

Publications (2)

Publication Number Publication Date
CN106184610A true CN106184610A (en) 2016-12-07
CN106184610B CN106184610B (en) 2018-06-08

Family

ID=57478001

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610547477.0A Active CN106184610B (en) 2016-07-11 2016-07-11 A kind of sternpost and tail fin installation method

Country Status (1)

Country Link
CN (1) CN106184610B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110466671A (en) * 2019-08-15 2019-11-19 广州文冲船厂有限责任公司 A kind of manufacturing method of ship large size tail casting structure
CN111498049A (en) * 2020-04-10 2020-08-07 中船澄西扬州船舶有限公司 Mounting method of energy-saving stator
CN113859476A (en) * 2021-11-10 2021-12-31 上海外高桥造船有限公司 Energy-saving stator installation tool and construction process thereof
CN113879483A (en) * 2021-11-10 2022-01-04 上海外高桥造船有限公司 Mounting method of energy-saving stator
CN115214859A (en) * 2022-08-05 2022-10-21 招商局金陵船舶(南京)有限公司 Mounting and positioning method for guide fins and tail columns

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6033713B2 (en) * 1979-11-22 1985-08-05 三菱重工業株式会社 How to install reaction fins at the stern
CN101439754B (en) * 2008-12-18 2011-05-18 中国长江航运集团江东船厂 Hull section non-allowance healing accuracy control process
KR101365878B1 (en) * 2011-08-22 2014-02-24 현대중공업 주식회사 Forming method for stern structure of a ship attached with asymmetric twisted flow control fin
CN102951260B (en) * 2012-11-02 2015-03-11 福建省马尾造船股份有限公司 Method for installing steering oar on ship body sections
CN103101612B (en) * 2013-01-30 2015-03-25 福建东南造船有限公司 Rudder propeller substrate installation method
CN104149932B (en) * 2014-07-22 2017-09-29 舟山欣臻船舶设计有限公司 Ton bulk goods deadwood pre-installs closure workmanship
CN104908886B (en) * 2015-06-30 2018-09-21 沪东中华造船(集团)有限公司 A kind of installation method of ship energy saving fin keel

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王建平等: "节能型船导流鳍艉柱的放样和制作", 《造船技术》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110466671A (en) * 2019-08-15 2019-11-19 广州文冲船厂有限责任公司 A kind of manufacturing method of ship large size tail casting structure
CN110466671B (en) * 2019-08-15 2021-08-17 广州文冲船厂有限责任公司 Manufacturing method of large-scale ship tail casting structure
CN111498049A (en) * 2020-04-10 2020-08-07 中船澄西扬州船舶有限公司 Mounting method of energy-saving stator
CN113859476A (en) * 2021-11-10 2021-12-31 上海外高桥造船有限公司 Energy-saving stator installation tool and construction process thereof
CN113879483A (en) * 2021-11-10 2022-01-04 上海外高桥造船有限公司 Mounting method of energy-saving stator
CN113879483B (en) * 2021-11-10 2022-12-06 上海外高桥造船有限公司 Mounting method of energy-saving stator
CN115214859A (en) * 2022-08-05 2022-10-21 招商局金陵船舶(南京)有限公司 Mounting and positioning method for guide fins and tail columns
CN115214859B (en) * 2022-08-05 2023-06-09 招商局金陵船舶(南京)有限公司 Installation positioning method for guide fins and tail columns

Also Published As

Publication number Publication date
CN106184610B (en) 2018-06-08

Similar Documents

Publication Publication Date Title
CN106184610A (en) A kind of sternpost and tail fin installation method
CN103057662B (en) Drilling ship anchor platform process for integrally manufacturing and anchor platform structure
CN108177730A (en) A kind of integrated method of construction of topside segmentation
CN107985504A (en) A kind of guide rail bracket two-sided installation method under the positive tire state of container ship transverse bulkhead
CN107323610A (en) Main engine bed, the installation method in gear block block stage
CN104724250B (en) Method for drawing hull section margin line
CN104929097B (en) 300-foot self-elevating drilling platform spud leg and shoe segmented carrying method
CN109184225A (en) Four string prismatic bending circular tube truss structural systems of one kind and assembling method
CN105880940A (en) Method for manufacturing box-type bent-torsional component
CN110341878A (en) A kind of installation method of stern transom plate hinge
CN109779034A (en) A kind of single layer abnormity network modularization installation method
CN107839837A (en) A kind of method of construction of stern segmentation
CN108612235A (en) The construction method of complicated high relief plastic arts stone curtain wall
CN109606544A (en) A kind of LNG ship cargo tank pedestal is got ready and prepackage method
CN103407546A (en) Process for manufacturing bulbous bow in left-right split manner then in combined manner
CN107933825B (en) Test method for anchorage mooring mode selection
CN111017151B (en) Method for positioning by using laser three-dimensional projection in ship body construction
CN103072667B (en) Method for locating tail pipe supporting seat in subsection
CN110525582A (en) One kind large-scale pedestal peculiar to vessel always organizes prepackage accuracy control method
CN110171772A (en) A kind of method that shipbuilding quickly adjusts split fix in the process
CN103200753A (en) X-ray machine focus positioning method using adjustable supports
CN103129701A (en) Positioning method of stream guidance cover on segmentation
CN109202316B (en) Assembly welding process of marine inclined stainless steel oil suction well
CN104389348B (en) A kind of installation method with covering arch structure
CN204700244U (en) A kind of endless belt sand core rod bridge-type connects anti-deforming structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Lin Deqi

Inventor after: Xia Yufan

Inventor after: Wang Lan

Inventor after: Li Guangxing

Inventor before: Lin Deqi

Inventor before: Xia Yu

Inventor before: Fan Wanglan

Inventor before: Li Guangxing

CB03 Change of inventor or designer information
CI02 Correction of invention patent application

Correction item: Inventor

Correct: Lin Deqi|Xia Yufan|Wang Lan|Li Guangxing

False: Lin Deqi|Xia Yufan|Wang Lan|Li Guangxing

Number: 05-01

Volume: 34

CI02 Correction of invention patent application
GR01 Patent grant
GR01 Patent grant