CN106130045A CN201610712561.3A CN201610712561A CN106130045A CN 106130045 A CN106130045 A CN 106130045A CN 201610712561 A CN201610712561 A CN 201610712561A CN 106130045 A CN106130045 A CN 106130045A
Authority
CN
China
Prior art keywords
phase
load
switch
separate
phase balancing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610712561.3A
Other languages
Chinese (zh)
Inventor
牛晓旭
吕根
秦方宇
苑宝义
梁仕伟
张海丰
刘海彬
朱杰
许家珲
王锟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Baodi Power Supply Co of State Grid Tianjin Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Baodi Power Supply Co of State Grid Tianjin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Baodi Power Supply Co of State Grid Tianjin Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610712561.3A priority Critical patent/CN106130045A/en
Publication of CN106130045A publication Critical patent/CN106130045A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/26Arrangements for eliminating or reducing asymmetry in polyphase networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/50Arrangements for eliminating or reducing asymmetry in polyphase networks
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/242Home appliances

Abstract

The method that the present invention relates to a kind of regulating platform district three-phase load unbalance, at distribution other installation three-phase balancing concentrator, is having installation multiple three-phase balancings switch at the shaft tower of service conductor selectively according to load condition.Real time data is analyzed judging by three-phase balancing concentrator, when distribution transforming three-phase load unbalance degree reaches more than 15%, and continue five minutes, the combined result of all switch loads on statistics peak load is separate, degree of unbalancedness after calculation assumption commutation, issue instructions to after taking optimum peak load separate on respective switch, to switch to target separate from the most separate for the switch real-time bringing onto load not power-off of multiple stage three-phase balancing, thus realize three-phase load and automatically adjust.Similar artificial effectively reduce the intensity of front man, it is provided that work efficiency, reduce line loss automatically to platform district distribution transformer load balancing method by this, have great importance to extending the distribution transforming life-span, thus also make the safe and reliable operation of electrical equipment.

Description

A kind of method of regulating platform district three-phase load unbalance
Technical field
The invention belongs to low-voltage distribution field, relate to three-phase load unbalance regulation, especially a kind of regulating platform district three-phase Load unbalanced method.
Background technology
In current low-voltage network, major part platform district all uses three-phase transformer, but exists big in low-voltage network Amount single-phase load, simultaneously because single-phase load skewness weighing apparatus and the time asynchronism of input so that three-phase load is uneven Weighing apparatus is objective reality.In many cases, three-phase load unbalance is to cause line loss and endanger the main of distribution transforming life-span Reason.Reasonably adjust three-phase load unbalance, for raising quality of voltage, reduction line loss, prolongation distribution transforming life-span, there is weight The meaning wanted, thus also make the safe and reliable operation of electrical equipment.
Existing district's distribution transforming three-phase load unbalance, by great load investigation and analysis dynamics in artificial real work, Wanting often to test load current, separately phase sequence is adjusted, and due to the irregularities of electricity consumption, manual working intensity is big, Adjustment needs to have a power failure, and affects power supply reliability.
Existing district's distribution transforming three-phase load adjusts imbalance automatically, relies primarily on reactive power compensator or with phase-shifting method is The device of principle solves, and is not the three-phase load unbalance on actual solution platform district circuit, and device work itself needs Consume energy, adds additional loss.
Summary of the invention
In place of it is an object of the invention to overcome the deficiencies in the prior art, it is provided that a kind of regulating platform district three-phase load unbalance Method, it is achieved three-phase load autobalance.
The present invention solves technical problem and be the technical scheme is that
A kind of method of regulating platform district three-phase load unbalance, step is as follows:
(1) install: at distribution other installation three-phase balancing concentrator, having service conductor selectively according to load condition Shaft tower at install multiple three-phase balancings switch, in the controlling feel at ease dress three-phase balancing main station system;
(2) data acquisition: the electric current of three-phase balancing concentrator Real-time Collection distribution transforming, voltage, P, Q, COS numerical value, imbalance Degree, the three-phase balancing switch electric current of each service conductor of Real-time Collection, voltage, P, Q, COS numerical value and current belonging to separate;
(3) data transmission: collection data are transferred to three-phase balancing concentrator, three-phase balancing by three-phase balancing switch Concentrator transfers data to three-phase balancing main station system again, and three-phase balancing main station system shows gathered data;
(4) automatic adjusting balance: three-phase balancing concentrator real time data is analyzed judge, when distribution transforming three-phase load not Degree of balance reaches more than 15%, and continues five minutes, the combined result of all switch loads on statistics peak load is separate, Degree of unbalancedness after calculation assumption commutation, issue instructions to after taking optimum peak load separate on respective switch, multiple stage three-phase To switch to target separate from the most separate in balancing switch real-time bringing onto load not power-off, thus realize three-phase load and automatically adjust; If above peak load is separate, do not have three-phase balancing switch separate at this, by separate for second largest load above opening After pass takes optimum combination, three-phase balancing concentrator issue instructions to multiple stage three-phase balancing switch the not power-off of real-time bringing onto load from The most separate to switch to target separate, thus realizes the platform district minimum degree of unbalancedness of distribution transformer load.
And, MANET between three-phase balancing concentrator and three-phase balancing switch, use ZigBee wireless telecommunications skill Art and 2.4G DSSS spread spectrum.
And, three-phase balancing concentrator passes through GPRS wireless telecommunications, transfers data to three-phase balancing main station system.
Advantages of the present invention and good effect be:
1, the distribution transforming of platform district can be monitored by this method in real time, and three-phase balancing concentrator detects three-phase imbalance After, through data analysis, three-phase balancing concentrator sends dependent instruction and switchs to respective three-phase balancing, and three-phase balancing is opened After instruction is received in pass, similar artificial fall load, perform to be switched to target separate on, many table apparatus switch over operation in real time, from And realizing three-phase load autobalance, method is simple, easily carries realization.
2, by this similar artificial automatically to platform district distribution transformer load balancing method, field work people can effectively be reduced The intensity of member, it is provided that work efficiency, reduces line loss, has great importance to extending the distribution transforming life-span, thus also makes electricity consumption The operation that equipment is safe and reliable, promotes power supply enterprise's image.
Detailed description of the invention
Below by specific embodiment, the invention will be further described, and following example are illustrative, is not limit Qualitatively, it is impossible to limit protection scope of the present invention with this.
A kind of method of regulating platform district three-phase load unbalance, step is as follows:
1, installing three-phase balancing concentrator and three-phase balancing switch, three-phase balancing concentrator is installed on distribution transforming Side, three-phase balancing switch is installed at the shaft tower of service conductor selectively according to load condition.
2, data acquisition
The electric current of three-phase balancing concentrator Real-time Collection distribution transforming, voltage, P, Q, COS numerical value, degree of unbalancedness, three-phase leveling The weighing apparatus switch electric current of Real-time Collection service conductor, voltage, P, Q, COS numerical value and current belonging to separate.
3, data transmission
Three-phase balancing concentrator and three-phase balancing switch between MANET, use ZigBee wireless communication technique and 2.4G DSSS spread spectrum, safe and reliable, three-phase balancing switchs and collection data is transferred to three-phase balancing concentrator, and three Phase balancing concentrator receives the data that three-phase balancing switch gathers, and three-phase balancing concentrator passes through GPRS wireless telecommunications, Transfer data to three-phase balancing main station system, show the electric current of distribution transforming, voltage, P, Q, COS numerical value, degree of unbalancedness and connect family The electric current of line, voltage, P, Q, COS numerical value and current belonging to separate.
4, automatic adjusting balance strategy is implemented
Real time data is analyzed judging, when distribution transforming three-phase load unbalance degree reaches 15% by three-phase balancing concentrator More than (can set), and continue five minutes (can set), the combined result of all switch loads on statistics peak load is separate, meter Calculate and suppose the degree of unbalancedness after commutation, issue instructions to after taking optimum peak load separate on respective switch, multiple stage three-phase is adjusted To switch to target separate from the most separate in balance cock real-time bringing onto load not power-off, thus realize three-phase load and automatically adjust.
If above peak load is separate, do not have three-phase balancing switch separate at this, by separate for second largest load After switch above takes optimum combination, three-phase balancing concentrator issues instructions to multiple stage three-phase balancing and switchs real-time bringing onto load To switch to target separate from the most separate in not power-off, thus realizes the platform district minimum degree of unbalancedness of distribution transformer load.
5. feedback
After adjustment terminates, regulation situation and respective branches load can be controlled in real time.
Above-described is only the preferred embodiment of the present invention, it is noted that for those of ordinary skill in the art For, on the premise of without departing from inventive concept, it is also possible to make some deformation and improvement, these broadly fall into the protection of the present invention Scope.

Claims (3)

1. the method for a regulating platform district three-phase load unbalance, it is characterised in that: step is as follows:
(1) install: at distribution other installation three-phase balancing concentrator, having the bar of service conductor selectively according to load condition Multiple three-phase balancings switch is installed, dress three-phase balancing main station system of feeling at ease in the controlling at tower;
(2) data acquisition: the electric current of three-phase balancing concentrator Real-time Collection distribution transforming, voltage, P, Q, COS numerical value, degree of unbalancedness, The three-phase balancing switch electric current of each service conductor of Real-time Collection, voltage, P, Q, COS numerical value and current belonging to separate;
(3) data transmission: collection data are transferred to three-phase balancing concentrator by three-phase balancing switch, and three-phase balancing is concentrated Device transfers data to three-phase balancing main station system again, and three-phase balancing main station system shows gathered data;
(4) automatic adjusting balance: real time data is analyzed judging, when distribution transforming three-phase load unbalance by three-phase balancing concentrator Degree reaches more than 15%, and continues five minutes, the combined result of all switch loads on statistics peak load is separate, calculates Assuming that the degree of unbalancedness after commutation, issue instructions to after taking optimum peak load separate on respective switch, multiple stage three-phase leveling To switch to target separate from the most separate in weighing apparatus switch real-time bringing onto load not power-off, thus realize three-phase load and automatically adjust;If Above peak load is separate, does not has three-phase balancing switch separate at this, separate for second largest load switch above has been taken After optimum combination, three-phase balancing concentrator issues instructions to the switch real-time bringing onto load not power-off of multiple stage three-phase balancing from currently Separate to switch to target separate, thus realizes the platform district minimum degree of unbalancedness of distribution transformer load.
The method of regulating platform district the most according to claim 1 three-phase load unbalance, it is characterised in that: three-phase balancing collection MANET between middle device and three-phase balancing switch, uses ZigBee wireless communication technique and 2.4GDSSS spread spectrum.
The method of regulating platform district the most according to claim 1 three-phase load unbalance, it is characterised in that: three-phase balancing collection Middle device passes through GPRS wireless telecommunications, transfers data to three-phase balancing main station system.
CN201610712561.3A 2016-08-24 2016-08-24 A kind of method of regulating platform district three-phase load unbalance Pending CN106130045A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610712561.3A CN106130045A (en) 2016-08-24 2016-08-24 A kind of method of regulating platform district three-phase load unbalance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610712561.3A CN106130045A (en) 2016-08-24 2016-08-24 A kind of method of regulating platform district three-phase load unbalance

Publications (1)

Publication Number Publication Date
CN106130045A true CN106130045A (en) 2016-11-16

Family

ID=57274259

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610712561.3A Pending CN106130045A (en) 2016-08-24 2016-08-24 A kind of method of regulating platform district three-phase load unbalance

Country Status (1)

Country Link
CN (1) CN106130045A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108933444A (en) * 2017-05-22 2018-12-04 菏泽峥艳电力科技有限公司 Intelligent phase-change switch control circuit
CN108964093A (en) * 2018-06-28 2018-12-07 国网天津市电力公司电力科学研究院 The low-voltage distribution network three-phase imbalance governing system and method for phase-change switch clustered control
CN110518605A (en) * 2019-08-28 2019-11-29 国网上海市电力公司 A kind of area's three-phase equilibrium depth optimization method and system
CN110690718A (en) * 2019-08-29 2020-01-14 国网新疆电力有限公司吐鲁番供电公司 Three-phase load unbalance treatment control method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104092229A (en) * 2014-07-14 2014-10-08 山东卓尔电气有限公司 Distributed type power supply zone branch circuit three-phase load current balance monitoring method and device
CN104659797A (en) * 2015-02-10 2015-05-27 卢松 Intelligent power load three-phase unbalance handling method at distribution network low voltage side
CN104821593A (en) * 2015-05-08 2015-08-05 江西龙跃电子科技有限公司 Low-voltage distribution transformer load intelligent adjustment system and distribution method
CN104852394A (en) * 2015-05-07 2015-08-19 陈鸽 Power load balancing system applied to low-voltage power distribution network
CN105703372A (en) * 2016-04-28 2016-06-22 南京诺联配电科技有限公司 Automatic balance adjustment method for three-phase load unbalance of low-voltage distribution network
CN105846453A (en) * 2016-05-10 2016-08-10 北京泰豪电力科技有限公司 Method for treating three-phase load imbalance of low-voltage distribution network

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104092229A (en) * 2014-07-14 2014-10-08 山东卓尔电气有限公司 Distributed type power supply zone branch circuit three-phase load current balance monitoring method and device
CN104659797A (en) * 2015-02-10 2015-05-27 卢松 Intelligent power load three-phase unbalance handling method at distribution network low voltage side
CN104852394A (en) * 2015-05-07 2015-08-19 陈鸽 Power load balancing system applied to low-voltage power distribution network
CN104821593A (en) * 2015-05-08 2015-08-05 江西龙跃电子科技有限公司 Low-voltage distribution transformer load intelligent adjustment system and distribution method
CN105703372A (en) * 2016-04-28 2016-06-22 南京诺联配电科技有限公司 Automatic balance adjustment method for three-phase load unbalance of low-voltage distribution network
CN105846453A (en) * 2016-05-10 2016-08-10 北京泰豪电力科技有限公司 Method for treating three-phase load imbalance of low-voltage distribution network

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108933444A (en) * 2017-05-22 2018-12-04 菏泽峥艳电力科技有限公司 Intelligent phase-change switch control circuit
CN108964093A (en) * 2018-06-28 2018-12-07 国网天津市电力公司电力科学研究院 The low-voltage distribution network three-phase imbalance governing system and method for phase-change switch clustered control
CN110518605A (en) * 2019-08-28 2019-11-29 国网上海市电力公司 A kind of area's three-phase equilibrium depth optimization method and system
CN110518605B (en) * 2019-08-28 2022-10-14 国网上海市电力公司 Three-phase balance depth optimization method and system for transformer area
CN110690718A (en) * 2019-08-29 2020-01-14 国网新疆电力有限公司吐鲁番供电公司 Three-phase load unbalance treatment control method
CN110690718B (en) * 2019-08-29 2023-01-06 国网新疆电力有限公司吐鲁番供电公司 Three-phase load unbalance treatment control method

Similar Documents

Publication Publication Date Title
CN104092229B (en) Distributed district's branch road three-phase load current balance type monitoring method and supervising device
CN106130045A (en) A kind of method of regulating platform district three-phase load unbalance
CN201540676U (en) Factory power supply integrated automatic training device
CN106130027B (en) The two-dimension integrated administering method of low-voltage distribution transformer platform district voltage
CN103762609A (en) Active power regulation and reactive power compensation control system of power distribution network remotely controlled through power frequency communication
CN105720606A (en) Undisturbed loop-closing control method specific to active power distribution network
CN105610169B (en) A kind of low-voltage network voltage control system and method
CN106816883B (en) three-phase unbalance adjusting system parallel input system, control method and device
CN102904270A (en) Three-phase current unbalance adjusting system for power distribution network
CN207442454U (en) Intelligent commutation device
CN202957611U (en) Three-phase current unbalance adjusting system of power distribution network
CN109088420A (en) A kind of low voltage electric network three-phase load unbalance regulator control system
CN107834578A (en) A kind of automatic commutation system and method for low pressure phase-change switch
CN107276098A (en) A kind of power distribution network multilevel coordination control system and method
CN103354361A (en) Low-voltage three-phase load automation balancing device
CN209571835U (en) A kind of commutation device suitable for Building Power Distribution route
CN105703372A (en) Automatic balance adjustment method for three-phase load unbalance of low-voltage distribution network
CN104882885B (en) Control method of multi-machine parallel optimized operation of active power filters
CN116961108A (en) Distributed photovoltaic grid-connected control system and method based on intelligent platform region fusion terminal
CN106992527A (en) The adjusting method and system of voltage pulsation during alternating current filter group switching
CN105449662A (en) Method for determining direct current isolated island operation control measures
CN209675941U (en) Series-type voltage regulating device
CN108701995A (en) Circuit for power conversion, electric system and its method
CN109193669B (en) Intelligent load distribution adjusting device for power distribution network
CN205945085U (en) Three -phase unbalanced load governing system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161116

RJ01 Rejection of invention patent application after publication