CN106129993A - 10kV电缆化率较高的配电网络中性点接地结构及其接地方法 - Google Patents
10kV电缆化率较高的配电网络中性点接地结构及其接地方法 Download PDFInfo
- Publication number
- CN106129993A CN106129993A CN201610539594.2A CN201610539594A CN106129993A CN 106129993 A CN106129993 A CN 106129993A CN 201610539594 A CN201610539594 A CN 201610539594A CN 106129993 A CN106129993 A CN 106129993A
- Authority
- CN
- China
- Prior art keywords
- point
- resistance
- parallel
- suppression coil
- arc suppression
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02H—EMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
- H02H9/00—Emergency protective circuit arrangements for limiting excess current or voltage without disconnection
- H02H9/08—Limitation or suppression of earth fault currents, e.g. Petersen coil
Abstract
本发明涉及一种电网中性点接地方法,具体为10kV电缆化率较高的配电网络中性点接地结构及其接地方法,接线点A与接地点之间并联有消弧线圈L和多个电阻Rbn;每个电阻Rbn由一个开关控制投切。在发生故障的瞬间开始依次接入电阻Rbn。该方法将原有的一个时刻的突变为现在的一个过程的变化,缩短了电容电流保持较高值的时间,消弧线圈并联的电阻值为梯度减小而非突变,从而达到减小对系统的冲击的效果。
Description
技术领域
本发明涉及一种电网中性点接地方法,具体为10kV电缆化率较高的配电网络中性点接地结构及其接地方法。
背景技术
近年来,随着电网的发展,电网的电缆应用逐步增多。电缆化率的增大,给电网带来了很大的威胁。例如,电缆增多使得电容电流增大。当发生单相接地故障时,产生电弧难以自熄,可能产生过电压等级较高的间歇性弧光接地过电压,且持续时间长,对电网设备的安全有危害,有可能发展成相间故障,事故范围扩大。
为了解决以上问题,中性点接地方式由之前的中性点不接地方式、消弧线圈接地方式变为小电阻接地方式。该方法可以有效降低工频过电压,限制弧光接地过电压,且故障选线也更为容易。之后又有人提出采用消弧线圈并联小电阻接地的方式,这种方法是说,当系统正常运行时,中性点经消弧线圈接地,发生故障瞬间,将小电阻接入中性点,与消弧线圈并联,达到故障选线和降低过电压的效果。然而这一方法带来了一些问题,如故障电流大,对系统的冲击大,有功损耗增多等。
发明内容
针对上述技术问题,本发明提供一种对系统的冲击小的配电网络中性点接地方法。
具体的技术方案为:
10kV电缆化率较高的配电网络中性点接地结构,包括接线点A,接线点A与接地点之间并联有消弧线圈L和多个电阻Rbn;每个电阻Rbn由一个开关控制投切。
10kV电缆化率较高的配电网络中性点接地结构的接地方法,包括以下过程:
接线点A点接入系统的中性点;消弧线圈L与接线点A点连接,消弧线圈L在正常运行和故障时一直保持接在中性点处;与消弧线圈L并联的电阻Rbn,n为并联的分段数,在发生故障的瞬间开始依次接入。
接入的电阻并联总值与现有技术方案并联的小电阻相同,每个并联的电阻间隔相同时间一个一个依次接入中性点,与消弧线圈并联。变原有的一个时刻的突变为现在的一个过程的变化,缩短了电容电流保持较高值的时间。防止系统受到冲击。
本发明提供的10kV电缆化率较高的配电网络中性点接地结构及其接地方法,有益效果:
(1)中性点阻值的变化由突变优化为逐渐变小的过程,缩短了电容电流保持较高值的时间。
(2)防止系统受到冲击,改变中性点处阻值的突变情况
具体分析如下:设当直接并联一个小电阻时,中性点处电阻分支的电流可以表示为:
式(1)中,为中性点处电压,为并联的电阻。由公式可以看出,需要对接入的电阻值进行控制,防止故障电流过大。那么当直接并入一个小电阻时,故障电流突然变大,对系统有冲击性。如果将这个小电阻等效为n个电阻时,故障电流为
式(2)中,为每次并联的阻值,n为并联的次数,为故障发生时的时刻,为并联电阻的总时间段。比较式(1)和式(2)两式可以看出,式(1)的故障电流的增大为一个时刻,式(2)的故障电流的增大为一个过程,所以不存在突变问题,减小了对系统的冲击,而且电流保持较大值的时间有所缩短。
本发明提供的10kV电缆化率较高的配电网络中性点接地结构及其接地方法,包括消弧线圈部分和并联电阻部分:消弧线圈部分始终连接在中性点,并联电阻为多个电阻并联,每个电阻分别由一个开关控制,在发生故障的瞬间,多个电阻依次并入,每个电阻并入时间间隔相同;此时消弧线圈并联的电阻值为梯度减小而非突变,从而达到减小对系统的冲击的效果。
附图说明
图1是本发明的结构示意图。
具体实施方式
结合附图说明本发明的具体实施方式。
如图1所示,10kV电缆化率较高的配电网络中性点接地结构,包括接线点A,接线点A与接地点之间并联有消弧线圈L和多个电阻Rbn;每个电阻Rbn由一个开关控制投切。
10kV电缆化率较高的配电网络中性点接地结构的接地方法:接线点A点接入系统的中 性点;消弧线圈L与接线点A点连接,消弧线圈L在正常运行和故障时一直保持接在中性点处;与消弧线圈L并联的电阻Rbn,n为并联的分段数,在发生故障的瞬间开始依次接入。
正常运行时,电阻Rbn均不接入,系统为中性点经消弧线圈L接地方式。发生故障瞬间,并联电阻Rbn部分先接入一个,与消弧线圈L并联,过时间后,再接入第二个电阻Rbn,每个电阻接入相隔时间相同,以此类推。设故障发生时间为t0,并联电阻的总时间段为tf,则第n个电阻接入时间为t0+(n-1)tf。
Claims (2)
1.10kV电缆化率较高的配电网络中性点接地结构,其特征在于,包括接线点A,接线点A与接地点之间并联有消弧线圈L和多个电阻Rbn;每个电阻Rbn由一个开关控制投切。
2.根据权利要求1所述的10kV电缆化率较高的配电网络中性点接地结构的接地方法,包括以下过程:接线点A点接入系统的中性点;消弧线圈L与接线点A点连接,消弧线圈L在正常运行和故障时一直保持接在中性点处;与消弧线圈L并联的电阻Rbn,n为并联的分段数,在发生故障的瞬间开始依次接入。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610539594.2A CN106129993A (zh) | 2016-07-11 | 2016-07-11 | 10kV电缆化率较高的配电网络中性点接地结构及其接地方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610539594.2A CN106129993A (zh) | 2016-07-11 | 2016-07-11 | 10kV电缆化率较高的配电网络中性点接地结构及其接地方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106129993A true CN106129993A (zh) | 2016-11-16 |
Family
ID=57282749
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610539594.2A Pending CN106129993A (zh) | 2016-07-11 | 2016-07-11 | 10kV电缆化率较高的配电网络中性点接地结构及其接地方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106129993A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108321784A (zh) * | 2018-01-15 | 2018-07-24 | 中国矿业大学 | 一种基于消弧线圈并恒定有功电流的中性点接地方法 |
CN110336265A (zh) * | 2019-06-17 | 2019-10-15 | 赵子云 | 中压电网中性点消弧线圈与电阻组合接地方法 |
CN112103934A (zh) * | 2020-08-19 | 2020-12-18 | 许继电气股份有限公司 | 一种小电流选线并联中电阻投切装置及方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2894024Y (zh) * | 2006-04-25 | 2007-04-25 | 河北旭辉电气股份有限公司 | 调匝式随调消弧线圈 |
CN101950958A (zh) * | 2010-09-27 | 2011-01-19 | 思源电气股份有限公司 | 一种调容式消弧线圈成套设备以及消弧线圈的运行方式 |
CN102593808A (zh) * | 2012-03-23 | 2012-07-18 | 上海市电力公司 | 一种中性点经电抗和电阻组合的接地系统 |
CN102623984A (zh) * | 2012-03-23 | 2012-08-01 | 上海市电力公司 | 一种电力网内中性点经可控电抗与电阻组合接地的系统 |
CN103222145A (zh) * | 2010-07-20 | 2013-07-24 | 恩普里默斯有限责任公司 | 用于电力系统保护的连续不间断ac接地系统 |
-
2016
- 2016-07-11 CN CN201610539594.2A patent/CN106129993A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2894024Y (zh) * | 2006-04-25 | 2007-04-25 | 河北旭辉电气股份有限公司 | 调匝式随调消弧线圈 |
CN103222145A (zh) * | 2010-07-20 | 2013-07-24 | 恩普里默斯有限责任公司 | 用于电力系统保护的连续不间断ac接地系统 |
CN101950958A (zh) * | 2010-09-27 | 2011-01-19 | 思源电气股份有限公司 | 一种调容式消弧线圈成套设备以及消弧线圈的运行方式 |
CN102593808A (zh) * | 2012-03-23 | 2012-07-18 | 上海市电力公司 | 一种中性点经电抗和电阻组合的接地系统 |
CN102623984A (zh) * | 2012-03-23 | 2012-08-01 | 上海市电力公司 | 一种电力网内中性点经可控电抗与电阻组合接地的系统 |
Non-Patent Citations (2)
Title |
---|
薛军等: "10KV全电缆出线变电站中性点新型接地装置的仿真研究", 《陕西电力》 * |
郭东斌: "消弧方法及其新思路", 《科技情报开发与经济》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108321784A (zh) * | 2018-01-15 | 2018-07-24 | 中国矿业大学 | 一种基于消弧线圈并恒定有功电流的中性点接地方法 |
CN110336265A (zh) * | 2019-06-17 | 2019-10-15 | 赵子云 | 中压电网中性点消弧线圈与电阻组合接地方法 |
CN112103934A (zh) * | 2020-08-19 | 2020-12-18 | 许继电气股份有限公司 | 一种小电流选线并联中电阻投切装置及方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6833972B2 (ja) | 高圧直流遮断器の閉極制御方法 | |
CN103424669B (zh) | 一种利用故障馈线零序电流矩阵主成分分析第一主成分的选线方法 | |
CN103023000B (zh) | 电网限流装置及电网限流器和电网限流系统 | |
EP2732521B1 (de) | Gleichspannungs-leitungsschutzschalter | |
CN108512226B (zh) | 一种灾害下电力系统恢复力评估的方法 | |
CN204089187U (zh) | 一种浪涌保护器 | |
CN102364655A (zh) | 多断口真空断路器的动态均压装置及其参数选取方法 | |
CN106129993A (zh) | 10kV电缆化率较高的配电网络中性点接地结构及其接地方法 | |
CN105098748A (zh) | 一种浪涌保护器及提升其暂时过电压耐受能力的方法 | |
CN104158174B (zh) | 电力系统灾难性事故风险评估方法 | |
CN102222897B (zh) | 一种高可靠性可控多重火花放电间隙 | |
CN211529450U (zh) | 电缆故障模拟装置及系统 | |
CN104113187B (zh) | 基于初级脉冲源充电的快响应电脉冲触发系统及方法 | |
CN103293448A (zh) | 基于半周波能量比的单相接地故障与虚幻接地识别方法 | |
CN106443334A (zh) | 一种基于零序电流差分极性比较的配电网故障选线方法 | |
CN109799413A (zh) | 一种配电网单相接地电流与电弧自熄弧时间模拟试验方法 | |
CN207910458U (zh) | 高压直流架空输电线路上虚拟正极诱导式避雷线防雷装置 | |
CN203056563U (zh) | 电网限流装置及电网限流器和电网限流系统 | |
CN106786521B (zh) | 一种计及单相断线谐振过电压的配电网薄弱支路判断方法 | |
CN104967107B (zh) | 一种抑制间歇性弧光接地过电压的方法 | |
CN103675540A (zh) | 并联电容器组放电装置 | |
CN114647921A (zh) | 一种模拟中压配电电缆潜伏性故障的方法 | |
CN106532662A (zh) | 一种自适应电容限压式高压直流断路器 | |
DE69731381T2 (de) | Transformator mit schutzeinrichtung | |
CN203193273U (zh) | 智能型调匝式消弧限压装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161116 |
|