CN106129819A - Device framework structure and use the prefabricated cabin frame of this structure - Google Patents
Device framework structure and use the prefabricated cabin frame of this structure Download PDFInfo
- Publication number
- CN106129819A CN106129819A CN201610531101.0A CN201610531101A CN106129819A CN 106129819 A CN106129819 A CN 106129819A CN 201610531101 A CN201610531101 A CN 201610531101A CN 106129819 A CN106129819 A CN 106129819A
- Authority
- CN
- China
- Prior art keywords
- frame
- equipment
- plate
- shaped plate
- front side
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02B—BOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
- H02B1/00—Frameworks, boards, panels, desks, casings; Details of substations or switching arrangements
- H02B1/01—Frameworks
- H02B1/013—Profiles for cabinet frames
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02B—BOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
- H02B1/00—Frameworks, boards, panels, desks, casings; Details of substations or switching arrangements
- H02B1/01—Frameworks
- H02B1/011—Open support bases
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Patch Boards (AREA)
Abstract
本发明公开了一种设备框架结构及使用该结构的预制舱机架,所述设备框架结构包括用于可拆连接于机架本体上的左框架、用于可拆连接于机架本体上的右框架和安装于所述左框架与所述右框架之间的横撑板,所述左框架上设置有用于设备左端安装的第一设备安装孔,所述右框架上对应所述第一设备安装孔设置有用于设备右端安装的第二设备安装孔,所述右框架或左框架上设置有附件安装区。设备框架结构在使用时,将机架内设备、端子安装于设备框架结构中,完成设备和端子间的内部配线,再将其安装在机架中实现机架内设备及其端子快速装配,还实现了预制舱的生产和机架内设备的安装、配线工作并行开展,避免了人员在狭小预制舱内进行设备安装和配线工作。
The invention discloses an equipment frame structure and a prefabricated cabin frame using the structure. The equipment frame structure includes a left frame for detachable connection to the frame body, a left frame for detachable connection to the frame body The right frame and the cross brace installed between the left frame and the right frame, the left frame is provided with a first equipment installation hole for the left end of the equipment, and the right frame corresponds to the first equipment The installation hole is provided with a second equipment installation hole for installation at the right end of the equipment, and the right frame or the left frame is provided with an accessory installation area. When the equipment frame structure is in use, install the equipment and terminals in the rack in the equipment frame structure, complete the internal wiring between the equipment and the terminals, and then install it in the rack to realize the rapid assembly of the equipment and its terminals in the rack. It also realizes the parallel development of the production of the prefabricated cabin and the installation and wiring of the equipment in the rack, avoiding the equipment installation and wiring work in the small prefabricated cabin.
Description
技术领域technical field
本发明涉及二次设备预制舱领域,尤其涉及一种设备框架结构及使用该结构的预制舱机架。The invention relates to the field of secondary equipment prefabricated cabins, in particular to an equipment frame structure and a prefabricated cabin frame using the structure.
背景技术Background technique
二次设备预制舱是变电站二次设备的替换产品,近年来在变电行业的到了极为广泛的应用。目前常见的二次设备预制舱包括:舱体和舱体内的二次保护屏柜,这种模式需要在舱内焊接高强度支架,存在盘柜进舱的繁重操作,还需要保持不同厂家的盘柜规格尺寸统一,增加舱体重量的同时也增加了成本。The secondary equipment prefabricated cabin is a replacement product for the secondary equipment of the substation, and it has been widely used in the power substation industry in recent years. At present, the common prefabricated cabins for secondary equipment include: cabins and secondary protection screen cabinets inside the cabins. This mode requires welding high-strength brackets in the cabins, and there is a heavy operation for the panels to enter the cabins. It is also necessary to maintain the panels of different manufacturers. The specifications and sizes of the cabinets are uniform, which increases the weight of the cabin and also increases the cost.
中国专利CN105576574A(申请公布日为2016.05.11)公开了一种机架及使用该机架的二次设备预制舱,所述二次设备预制舱包括固定在舱内的机架,所述机架包括机架本体,所述机架本体包括两个以上的左右并列设置的立架,相邻两个立架之间形成用于从前侧装入二次设备的安装间,立架的前侧设有缺口,同一列的立架的缺口形成贯通的供线缆通过的光缆。本发明的机架固定安装在预制舱内,与预制舱一体化设计,避免了传统屏柜整体进舱的繁重操作的问题,解决了要求盘柜规格统一的问题。但是使用所述二次设备预制舱时,预制舱存在舱体生产和舱内设备安装、配线工作串行开展使生产周期延长的问题,并且由于舱内空间有限,在舱内进行设备安装和配线困难。Chinese patent CN105576574A (application publication date is 2016.05.11) discloses a frame and a secondary equipment prefabricated cabin using the frame. The secondary equipment prefabricated cabin includes a frame fixed in the cabin, and the frame It includes a rack body, and the rack body includes more than two vertical stands arranged side by side. An installation room for loading secondary equipment from the front side is formed between two adjacent vertical frames. The front side of the vertical frame is provided with There are gaps, and the gaps of the vertical frames in the same row form through optical cables for cables to pass through. The frame of the present invention is fixedly installed in the prefabricated cabin, and is designed integrally with the prefabricated cabin, avoiding the problem of the heavy operation of the traditional screen cabinet entering the cabin as a whole, and solving the problem of requiring uniform specifications of the panel cabinets. However, when using the prefabricated cabin of the secondary equipment, the prefabricated cabin has the problem that the production of the cabin body and the installation of equipment in the cabin, and the wiring work are carried out in series to prolong the production cycle, and due to the limited space in the cabin, equipment installation and installation in the cabin Wiring is difficult.
发明内容Contents of the invention
本发明的目的在于提供一种设备框架结构,以解决现有技术在使用时出现的二次设备预制舱舱体生产和舱内设备安装工作串行开展使生产周期延长、舱内设备安装配线困难以的问题;本发明还提供了一种使用该结构的预制舱机架。The purpose of the present invention is to provide an equipment frame structure to solve the problem of secondary equipment prefabricated cabin production and equipment installation in the cabin in serial to prolong the production cycle and install wiring for equipment in the cabin when the prior art is in use. Difficult problems; the present invention also provides a prefabricated cabin frame using the structure.
为实现上述目的,本发明设备框架结构的技术方案是:设备框架结构,包括用于可拆连接于机架本体上的左框架、用于可拆连接于机架本体上的右框架和安装于所述左框架与所述右框架之间的横撑板,所述左框架上设置有用于设备左端安装的第一设备安装孔,所述右框架上对应所述第一设备安装孔设置有用于设备右端安装的第二设备安装孔,所述右框架或左框架上设置有附件安装区。In order to achieve the above object, the technical solution of the equipment frame structure of the present invention is: the equipment frame structure, including the left frame for detachable connection on the rack body, the right frame for detachable connection on the rack body and the The cross bracing plate between the left frame and the right frame, the left frame is provided with a first equipment installation hole for installation of the left end of the equipment, and the right frame is provided with a first equipment installation hole corresponding to the first equipment installation hole The second device installation hole is installed at the right end of the device, and the right frame or the left frame is provided with an accessory installation area.
所述左框架包括开口向左的第一U型板,所述第一U型板包括第一前侧板和第一底板,所述第一前侧板上设置有用于将所述左框架固定于机架本体上的第一固定结构,所述第一固定结构包括设置于所述第一前侧板上的第一框架固定孔。The left frame includes a first U-shaped plate with an opening to the left, the first U-shaped plate includes a first front side plate and a first bottom plate, and the first front side plate is provided with a The first fixing structure on the frame body, the first fixing structure includes a first frame fixing hole arranged on the first front side plate.
所述右框架包括开口向左的第二U型板和开口向前的第三U型板,所述第二U型板包括第二前侧板、第二底板、后侧板,所述后侧板垂直连接有向后延伸的第二竖板; 所述第三U型板包括左侧板、第三底板、右侧板,所述右侧板上垂直连接有向右延伸的右固定板,所述右固定板上设置有第二固定结构,所述第二固定结构包括设置于所述右固定板上的第二框架固定孔,所述第三U型板的第三底板上设置有一列附件安装孔,所述第三U型板内部的空间形成所述附件安装区,所述连接框架的第二U型板的底板与所述第三U型板的左侧板可拆连接。The right frame includes a second U-shaped plate with an opening to the left and a third U-shaped plate with an opening forward. The second U-shaped plate includes a second front side plate, a second bottom plate, and a rear side plate. The side plate is vertically connected with a second vertical plate extending backward; the third U-shaped plate includes a left side plate, a third bottom plate, and a right side plate, and the right side plate is vertically connected with a right fixing plate extending to the right , the right fixing plate is provided with a second fixing structure, the second fixing structure includes a second frame fixing hole arranged on the right fixing plate, and a third bottom plate of the third U-shaped plate is provided with a The accessory installation hole is arranged in a row, the space inside the third U-shaped plate forms the accessory installation area, and the bottom plate of the second U-shaped plate of the connecting frame is detachably connected to the left side plate of the third U-shaped plate.
所述第一设备安装孔设置于所述第一前侧板上,所述第二设备安装孔设置于所述第二前侧板上。The first equipment installation hole is arranged on the first front side plate, and the second equipment installation hole is arranged on the second front side plate.
所述左框架的第一底板和所述右的第二竖板上对应设置有多排散热孔。The first bottom plate of the left frame and the second right vertical plate are correspondingly provided with multiple rows of cooling holes.
所述横撑板两端分别安装于所述第一底板和所述第二竖板的所述散热孔中,所述横撑板的上表面形成用于支撑设备的支撑面。Both ends of the cross brace are respectively installed in the heat dissipation holes of the first bottom plate and the second vertical plate, and the upper surface of the cross brace forms a supporting surface for supporting equipment.
本发明预制舱机架的技术方案是:预制舱机架,包括机架本体,还包括安装于机架本体内部的设备框架结构,所述设备框架结构如上述设备框架结构的任一技术方案所述。The technical solution of the prefabricated cabin frame of the present invention is: the prefabricated cabin frame includes a frame body, and also includes an equipment frame structure installed inside the frame body, and the equipment frame structure is as described in any technical solution of the above equipment frame structure. stated.
本发明的有益效果是:所述设备框架结构在使用时,将机架内设备、端子安装于所述设备框架结构中,完成设备和端子间的内部配线,再将此框架安装在机架中从而实现机架内设备及其端子快速装配,还实现了预制舱的生产和机架内设备的安装配线并行开展,同时避免了人员在狭小预制舱内进行设备安装和配线工作,减少装配时间,提高接线效率。The beneficial effects of the present invention are: when the equipment frame structure is in use, the equipment and terminals in the rack are installed in the equipment frame structure, the internal wiring between the equipment and the terminals is completed, and then the frame is installed on the rack In this way, the equipment and its terminals in the rack can be quickly assembled, and the production of the prefabricated cabin and the installation and wiring of the equipment in the rack can be carried out in parallel. Reduce assembly time and improve wiring efficiency.
附图说明Description of drawings
图1为本发明设备框架结构具体实施例的结构示意图;Fig. 1 is the structural representation of the concrete embodiment of equipment frame structure of the present invention;
图2为图1中左框架的结构示意图;Fig. 2 is a schematic structural view of the left frame in Fig. 1;
图3为图1中右框架的第二U型板的结构示意图;Fig. 3 is the structural representation of the second U-shaped plate of the right frame in Fig. 1;
图4为图1中右框架的第三U型板的结构示意图。Fig. 4 is a schematic structural diagram of a third U-shaped plate of the right frame in Fig. 1 .
具体实施方式detailed description
本发明的设备框架结构的具体实施例,如图1至图4所示,设备框架结构包括左框架1、横撑板4和右框架,右框架包括开口向左的第二U型板2和开口向前的第三U型板3。左框架1包括开口向左的第一U型板,第一U型板包括第一底板11和第一前侧板12,第一底板11上设置有多排第一散热孔111,相邻第一散热孔111的竖向间距按照1U(U为一种表示服务器外部尺寸的单位)高度的1/n设置。左框架1上的第一前侧板12上开设有一列第一框架固定孔121和一列第一设备安装孔122,第一设备安装孔122用于框架内部标准19英寸设备的左侧安装固定。第一螺栓穿过第一框架固定孔121将左框架固定于预制舱机架本体上,第一螺栓和第一框架固定孔121组成第一固定结构。第二U型板2包括第二底板22、第二前侧板23和后侧板,后侧板垂直连接有向后延伸的第二竖板21,第二竖板21上对应左框架1上的第一散热孔111设置有第二散热孔211,第二U型板2采用向右凹陷的结构增加了结构强度,同时向右凹陷形成的空间方便设备框架安装完毕之后单独拆除设备安装部分或附件安装部分,第二底板22上开设有两个第一连接固定孔221,第二前侧板23上开设有第二设备安装孔231,第二设备安装孔231用于框架内部标准19英寸设备的右侧安装固定。第三U型板3包括第三底板31、左侧板33、右侧板32。第三底板31上开设有一列沿上下方向排列的用于安装端子或附件的附件安装孔311,左侧板33上开设有第二连接固定孔331,右侧板32垂直连接有向右延伸的右固定板34,右固定板34上开设有第二框架固定孔341。第二螺栓穿过第二框架固定孔341将右框架的第三U型板3固定于预制舱机架本体上,第二螺栓和第二框架固定孔341组成第二固定结构。The specific embodiment of the equipment frame structure of the present invention, as shown in Figure 1 to Figure 4, the equipment frame structure comprises a left frame 1, a cross brace 4 and a right frame, and the right frame comprises a second U-shaped plate 2 with an opening to the left and The third U-shaped plate 3 with opening forward. The left frame 1 includes a first U-shaped plate with an opening to the left. The first U-shaped plate includes a first bottom plate 11 and a first front side plate 12. The first bottom plate 11 is provided with multiple rows of first cooling holes 111, adjacent to the first U-shaped plate. The vertical spacing of a cooling hole 111 is set according to 1/n of the height of 1U (U is a unit representing the external size of the server). A row of first frame fixing holes 121 and a row of first equipment installation holes 122 are provided on the first front side plate 12 of the left frame 1. The first equipment installation holes 122 are used for installing and fixing the left side of the standard 19-inch equipment inside the frame. The first bolt passes through the first frame fixing hole 121 to fix the left frame on the frame body of the prefabricated cabin, and the first bolt and the first frame fixing hole 121 form a first fixing structure. The second U-shaped board 2 includes a second bottom board 22, a second front side board 23 and a rear side board. The rear side board is vertically connected with a second vertical board 21 extending backwards. The second vertical board 21 corresponds to the left frame 1. The first heat dissipation hole 111 is provided with the second heat dissipation hole 211, and the second U-shaped plate 2 adopts a rightward recessed structure to increase the structural strength, and at the same time, the space formed by the rightward recess is convenient for removing the equipment installation part or In the accessory installation part, two first connection and fixing holes 221 are opened on the second bottom plate 22, and second equipment installation holes 231 are opened on the second front side plate 23, and the second equipment installation holes 231 are used for standard 19-inch equipment inside the frame The right side of the installation is fixed. The third U-shaped plate 3 includes a third bottom plate 31 , a left side plate 33 and a right side plate 32 . The third bottom plate 31 is provided with a row of attachment mounting holes 311 arranged in the up and down direction for installing terminals or accessories, the left side plate 33 is provided with a second connection fixing hole 331, and the right side plate 32 is vertically connected with a rightward extending The right fixing plate 34 is provided with a second frame fixing hole 341 on the right fixing plate 34 . The second bolt passes through the second frame fixing hole 341 to fix the third U-shaped plate 3 of the right frame on the prefabricated cabin frame body, and the second bolt and the second frame fixing hole 341 form a second fixing structure.
设备框架组合安装时,螺栓穿过第三U型板3上的第二连接固定孔331和第二U型板2上的第一连接固定孔221将第三U型板3与第二U型板2固定连接组成右框架,多个横撑板4左侧安装于左框架1的第一散热孔111中、右侧安装于第二U型板2的第二散热孔211中。将标准19英寸设备放置于横撑板4上,以实现横撑板4对不同高度设备的辅助支撑,横撑板4的数量和安装高度可根据需要进行调整。When the equipment frame is assembled and installed, the bolt passes through the second connection and fixing hole 331 on the third U-shaped plate 3 and the first connection and fixing hole 221 on the second U-shaped plate 2 to connect the third U-shaped plate 3 and the second U-shaped plate. The boards 2 are fixedly connected to form the right frame, and the left side of a plurality of cross braces 4 is installed in the first cooling hole 111 of the left frame 1 , and the right side is installed in the second cooling hole 211 of the second U-shaped plate 2 . The standard 19-inch equipment is placed on the cross brace 4 to realize the auxiliary support of the cross brace 4 for equipment of different heights. The number and installation height of the cross brace 4 can be adjusted as required.
设备安装框架组合完成后,左框架1、右框架的第二U型板2和横撑板4构成设备安装区,右框架的第三U型板3向后凹陷形成附件安装区,第三U型板3的沿上下方向延伸的U型结构形成上下贯通的布缆通道,设备安装区和附件安装区的可灵活左右调整。将标准19英寸设备安装于设备框架结构的设备安装区内,将端子或其他附件安装于设备框架结构的附件安装区内的附件安装孔311中,再完成设备和端子之间的线缆连接,从而完成整个设备框架结构内部的安装工作,将设备框架结构安装于预制舱内机架相应高度上,实现预制舱内设备及端子的安装、配线。第一前侧板12上的第一设备安装孔122和第二前侧板23上的第二设备安装孔231的数量可根据实际需要设置。第三底板31上的附件安装孔331的数量可根据实际需要设置。使用所述设备框架结构大大缩短了机架式二次设备预制舱的整体生产周期,并将预制舱的生产和机架内设备的安装配线变成并行关系,既保留了盘柜式二次设备舱的并行生产模式,又保留了机架式二次设备舱成本低、空间利用率高、内部空间大、检修运维方便的特点,同时在中远期设备改扩建的过程中使用所述设备框架结构利于设备的进舱操作,已经完成内部端子配线的设备框架结构又能大大降低后期的设备施工周期,提高改扩建操作效率,操作简单。After the assembly of the equipment installation frame is completed, the left frame 1, the second U-shaped plate 2 of the right frame and the cross-bracing plate 4 constitute the equipment installation area, and the third U-shaped plate 3 of the right frame is recessed backward to form an accessory installation area. The U-shaped structure of the template 3 extending in the up and down direction forms a cable routing channel that runs through up and down, and the equipment installation area and the accessory installation area can be flexibly adjusted left and right. Install the standard 19-inch equipment in the equipment installation area of the equipment frame structure, install the terminals or other accessories in the accessory installation holes 311 in the accessory installation area of the equipment frame structure, and then complete the cable connection between the equipment and the terminals, In this way, the installation work inside the entire equipment frame structure is completed, and the equipment frame structure is installed on the corresponding height of the frame in the prefabricated cabin to realize the installation and wiring of the equipment and terminals in the prefabricated cabin. The number of the first equipment installation holes 122 on the first front side plate 12 and the number of second equipment installation holes 231 on the second front side plate 23 can be set according to actual needs. The number of attachment mounting holes 331 on the third bottom plate 31 can be set according to actual needs. The use of the equipment frame structure greatly shortens the overall production cycle of the rack-type secondary equipment prefabricated cabin, and makes the production of the prefabricated cabin and the installation and wiring of the equipment in the rack a parallel relationship, which not only retains the cabinet-type secondary equipment The parallel production mode of the equipment cabin retains the characteristics of low cost, high space utilization rate, large internal space, and convenient maintenance and operation of the rack-mounted secondary equipment cabin. The equipment frame structure is conducive to the operation of equipment entering the cabin. The equipment frame structure that has completed the internal terminal wiring can greatly reduce the later equipment construction period, improve the operation efficiency of reconstruction and expansion, and is easy to operate.
在上述实施例中,左框架1的第一前侧板12上的第一框架固定孔121和右框架3的右固定板34上的第二框架固定孔341用于将设备框架结构安装固定在预制舱机架上,在其它实施例中,可在左框架的第一前侧板上下两端部分各设置一个第一框架固定孔,右框架的右固定板上下两端部分各设置一个第二框架固定孔。In the above embodiment, the first frame fixing hole 121 on the first front side plate 12 of the left frame 1 and the second frame fixing hole 341 on the right fixing plate 34 of the right frame 3 are used to install and fix the equipment frame structure on On the frame of the prefabricated cabin, in other embodiments, a first frame fixing hole can be respectively set on the upper and lower ends of the first front side plate of the left frame, and a second fixing hole can be respectively set on the upper and lower ends of the right fixing plate of the right frame. Frame fixing holes.
在其它实施例中,第二U型板的第二底板可与第三U型板的左侧板一体设置。In other embodiments, the second bottom plate of the second U-shaped plate can be integrated with the left side plate of the third U-shaped plate.
在其它实施例中,第二U型板上可不设置第二竖板,横撑板右端安装于第二U型板的后侧板上。In other embodiments, the second vertical board may not be provided on the second U-shaped board, and the right end of the cross brace is installed on the rear side board of the second U-shaped board.
在其它实施例中,左框架和右框架的位置可以对调,在左框架上设置附件安装区。In other embodiments, the positions of the left frame and the right frame can be reversed, and an accessory installation area is set on the left frame.
本发明预制舱机架的具体实施例,所述预制舱机架包括设备框架结构,设备框架结构的具体实施方式与上述任一实施例中设备框架结构的具体实施方式一致,在此不再详述。A specific embodiment of the prefabricated cabin frame of the present invention, the prefabricated cabin frame includes an equipment frame structure, the specific implementation of the equipment frame structure is consistent with the specific implementation of the equipment frame structure in any of the above-mentioned embodiments, and will not be described in detail here stated.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610531101.0A CN106129819B (en) | 2016-07-07 | 2016-07-07 | Device framework structure and the prefabricated cabin frame using the structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610531101.0A CN106129819B (en) | 2016-07-07 | 2016-07-07 | Device framework structure and the prefabricated cabin frame using the structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106129819A true CN106129819A (en) | 2016-11-16 |
| CN106129819B CN106129819B (en) | 2018-02-16 |
Family
ID=57282622
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610531101.0A Expired - Fee Related CN106129819B (en) | 2016-07-07 | 2016-07-07 | Device framework structure and the prefabricated cabin frame using the structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106129819B (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106451121A (en) * | 2016-12-16 | 2017-02-22 | 国网山西电力设计研究院 | Power station cabin combined with cabinets |
| CN108695754A (en) * | 2018-06-27 | 2018-10-23 | 国网河南省电力公司经济技术研究院 | 220kV substation secondary device prefabricated cabins |
| CN111048999A (en) * | 2018-10-15 | 2020-04-21 | 许继电气股份有限公司 | Secondary equipment integrated installation module and prefabricated cabin using the module |
| CN112421386A (en) * | 2019-08-23 | 2021-02-26 | 许继电气股份有限公司 | Prefabricated cabin frame and prefabricated cabin |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2010267843A (en) * | 2009-05-15 | 2010-11-25 | Nitto Electric Works Ltd | Frame cabinet |
| CN203504019U (en) * | 2013-10-28 | 2014-03-26 | 浙江中能博瑞电器集团有限公司 | Distribution cabinet |
| CN104577772A (en) * | 2015-01-30 | 2015-04-29 | 国家电网公司 | Power distribution cabinet |
| CN104917087A (en) * | 2015-07-01 | 2015-09-16 | 许继集团有限公司 | Prefabricated interlayer module, method employing said module, prefabricated cabin |
| CN204887814U (en) * | 2015-07-10 | 2015-12-16 | 许继电气股份有限公司 | High space utilizes preceding wiring rack of type |
-
2016
- 2016-07-07 CN CN201610531101.0A patent/CN106129819B/en not_active Expired - Fee Related
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2010267843A (en) * | 2009-05-15 | 2010-11-25 | Nitto Electric Works Ltd | Frame cabinet |
| CN203504019U (en) * | 2013-10-28 | 2014-03-26 | 浙江中能博瑞电器集团有限公司 | Distribution cabinet |
| CN104577772A (en) * | 2015-01-30 | 2015-04-29 | 国家电网公司 | Power distribution cabinet |
| CN104917087A (en) * | 2015-07-01 | 2015-09-16 | 许继集团有限公司 | Prefabricated interlayer module, method employing said module, prefabricated cabin |
| CN204887814U (en) * | 2015-07-10 | 2015-12-16 | 许继电气股份有限公司 | High space utilizes preceding wiring rack of type |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106451121A (en) * | 2016-12-16 | 2017-02-22 | 国网山西电力设计研究院 | Power station cabin combined with cabinets |
| CN108695754A (en) * | 2018-06-27 | 2018-10-23 | 国网河南省电力公司经济技术研究院 | 220kV substation secondary device prefabricated cabins |
| CN111048999A (en) * | 2018-10-15 | 2020-04-21 | 许继电气股份有限公司 | Secondary equipment integrated installation module and prefabricated cabin using the module |
| CN111048999B (en) * | 2018-10-15 | 2022-03-11 | 许继电气股份有限公司 | Secondary equipment integrated installation module and prefabricated cabin using the module |
| CN112421386A (en) * | 2019-08-23 | 2021-02-26 | 许继电气股份有限公司 | Prefabricated cabin frame and prefabricated cabin |
| CN112421386B (en) * | 2019-08-23 | 2022-07-05 | 许继电气股份有限公司 | Prefabricated cabin frame and prefabricated cabin |
Also Published As
| Publication number | Publication date |
|---|---|
| CN106129819B (en) | 2018-02-16 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106129819B (en) | Device framework structure and the prefabricated cabin frame using the structure | |
| EP3626124A1 (en) | Apparatus and method for equipment mounting and storage | |
| CN201766793U (en) | General stand for machine cabinet | |
| CN109982540A (en) | A kind of cabinet of 19 inches and 21 inches two kinds of specification servers of compatibility | |
| CN107453264B (en) | Rack-type prefabricated cabin and secondary equipment integration module | |
| CN202524661U (en) | Multifunctional cabinet | |
| CN210052162U (en) | Cabinet for installing data security terminal | |
| CN105576574B (en) | A kind of frame and the secondary device prefabricated cabin using the frame | |
| CN211210138U (en) | Combined vehicle-mounted cabinet | |
| CN203942737U (en) | A kind of communication cabinet | |
| CN207559864U (en) | A kind of rectifier cabinet | |
| CN206283742U (en) | It is easy to data center's integrated box body of two-way reason line | |
| CN204305534U (en) | A kind of module mounting frame and use the industry control cabinet of this installing rack | |
| CN201787298U (en) | Wall-hanging bracket | |
| CN203120305U (en) | Cabinet | |
| CN207475033U (en) | A kind of Modular assembled switchgear | |
| CN219107994U (en) | Cabinet tray convenient to install and detach | |
| CN206283740U (en) | It is easy to data center's integrated box body of positive foliation line | |
| CN210806409U (en) | Power distribution cabinet convenient to disassemble | |
| CN204578909U (en) | The adjustable rack of a kind of frame | |
| CN221807478U (en) | A bracket inside a chassis cabinet | |
| CN205454331U (en) | Supplementary device mount, rack and communication equipment | |
| CN217956411U (en) | Multi-layer adjustable power distribution cabinet | |
| CN202695991U (en) | Cabinet structure for installing equipment | |
| CN203378178U (en) | FCS cabinet terminal module installation structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180216 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |