CN106128531A - A kind of assembly and disassembly methods of fuel assembly base under water - Google Patents

A kind of assembly and disassembly methods of fuel assembly base under water Download PDF

Info

Publication number
CN106128531A
CN106128531A CN201610519456.8A CN201610519456A CN106128531A CN 106128531 A CN106128531 A CN 106128531A CN 201610519456 A CN201610519456 A CN 201610519456A CN 106128531 A CN106128531 A CN 106128531A
Authority
CN
China
Prior art keywords
screw
base
upper base
dismantling device
fuel assembly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610519456.8A
Other languages
Chinese (zh)
Other versions
CN106128531B (en
Inventor
邝刘伟
任亮
张显鹏
余飞扬
江林志
李国云
熊源源
陈哲
陈军
郑星明
周云
江艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nuclear Power Institute of China
Original Assignee
Nuclear Power Institute of China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nuclear Power Institute of China filed Critical Nuclear Power Institute of China
Priority to CN201610519456.8A priority Critical patent/CN106128531B/en
Publication of CN106128531A publication Critical patent/CN106128531A/en
Application granted granted Critical
Publication of CN106128531B publication Critical patent/CN106128531B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G21NUCLEAR PHYSICS; NUCLEAR ENGINEERING
    • G21CNUCLEAR REACTORS
    • G21C19/00Arrangements for treating, for handling, or for facilitating the handling of, fuel or other materials which are used within the reactor, e.g. within its pressure vessel
    • G21C19/26Arrangements for removing jammed or damaged fuel elements or control elements; Arrangements for moving broken parts thereof
    • GPHYSICS
    • G21NUCLEAR PHYSICS; NUCLEAR ENGINEERING
    • G21CNUCLEAR REACTORS
    • G21C19/00Arrangements for treating, for handling, or for facilitating the handling of, fuel or other materials which are used within the reactor, e.g. within its pressure vessel
    • G21C19/19Reactor parts specifically adapted to facilitate handling, e.g. to facilitate charging or discharging of fuel elements
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Plasma & Fusion (AREA)
  • General Engineering & Computer Science (AREA)
  • High Energy & Nuclear Physics (AREA)
  • Hand Tools For Fitting Together And Separating, Or Other Hand Tools (AREA)

Abstract

The invention discloses the assembly and disassembly methods of a kind of fuel assembly base under water, insert the prongs within the hole of base;Screw dismantling device is inserted in screw hole, and gripping apparatus opened by the pneumatic knob of turn, and gripping apparatus closed by the pneumatic knob of turn screw dismantling device, upper base is fixed mobile screw dismantling device after screw screws out and is put in screw storage device by screw;The pin of upper base installation tool inserts in the hole, and presses the upper base of pneumatic switch locking of base installation tool, is removed by upper base from crude fuel assembly;The pneumatic switch pressing base installation tool puts down base, opens pneumatic switch, lock-screw;Removal screw dismantling device, inserts screw crimping tool in screw and successively each screw is carried out crimping process.The present invention realizes quickly disintegrating and installing of fuel assembly base, and disintegration and reparation for damaged fuel assembly provide precondition, for the fuel element that utilizes of economical rationality, improves fuel element utilization rate and provides important technical support.

Description

A kind of assembly and disassembly methods of fuel assembly base under water
Technical field
The invention belongs to nuclear fuel cycle technical field, be specifically related to the assembly and disassembly methods of a kind of fuel assembly base under water.
Background technology
For the fuel element that utilizes of economical rationality, improve fuel original paper utilization rate, to wherein having determined that damaged fuel rod, With fresh fuel rod or other standby rod, it is replaced, makes the damaged fuel assembly of not up to burn-up level can return heap multiplexing, Improve the economy of nuclear power plant, it is thus achieved that considerable economic benefit.In fuel assembly repair process, the dismounting of upper base is fuel assembly The key link disintegrated and repair.
Summary of the invention
It is an object of the invention to provide the assembly and disassembly methods of a kind of fuel assembly base under water, it is achieved upper pipe seat of fuel component Quickly disintegrate and install, for the disintegration of damaged fuel assembly with repair and provide precondition.
The present invention is achieved through the following technical solutions:
The assembly and disassembly methods of a kind of fuel assembly base under water, comprises the following steps:
(1) surface of the supreme base of base setting tool in movement, slowly inserts upper pipe by the pin of upper base setting tool In the hole that seat is corresponding, under press the handle of base setting tool, base in locking;
(2) move directly over the supreme base of screw dismantling device, the lower end of screw dismantling device be inserted into base any one In screw hole, the gripping apparatus of screw dismantling device lower end opened by the pneumatic knob of turn, and slow rotary screw dismantling device can Naturally entering in sleeve and firmly grasp this screw, the compression lock pressing screw dismantling device cuts out gripping apparatus, rotates with torque spanner Screw dismantling device rotates to same direction, upper base is fixed mobile screw dismantling device after screw screws out and is put into by screw In screw storage device, repeat above-mentioned demounting procedure, be all removed and placed in screw storage device to all screws;
(3) remove telescope-srew dismantling device, upper base installation tool is moved the surface of supreme base, upper base erector The pin of expressing of tool slowly inserts in the hole that base is corresponding, presses the upper base of pneumatic switch locking of base installation tool, Base installation tool in lifting, removes upper base from crude fuel assembly;
(4) the upper base dismantled is moved to the surface of fuel assembly to be installed, continuous by upper base installation tool Base position in adjustment, finds the best position of base, and the pneumatic switch pressing base installation tool puts down pipe Seat, then removes base installation tool, screw dismantling device moves to the surface of new screw storage device, tears open with screw The gripping apparatus of a holding tool wherein screw, and this screw is inserted in corresponding screw, open the gas of screw dismantling device Dynamic switch, lock-screw, rotate screw dismantling device with torque spanner and rotate to same direction, repeat above-mentioned installation steps, Until the new screw in all screw holes is all arranged on upper base screwhole position;
(5) after installation, remove screw dismantling device, envelope silicon instrument is placed on and installs directly over the screw of screw, will Screw crimping tool inserts in screw and successively each screw is carried out crimping process.
This programme can realize dismounting and the installation of upper pipe seat of fuel component in pool environment, according to PWR Fuel group Part construction features, devises series of tools and uses, and establishes the fuel assembly technology of base dismounting under water, it is achieved that water Upper pipe seat of fuel component dismounting in pool environment, and achieve quickly disintegrating and installing, for burst slug of fuel assembly base Disintegration and the reparation of assembly provide precondition, and for the fuel element that utilizes of economical rationality, improving fuel element utilization rate provides Important technical support.
According to base structure on PWR fuel assembly, devise base setting tool in one, base regular worker on this Tool includes support bar, and the bottom of support bar is fixed with bracing frame, and bracing frame is provided with brake and several pins, is supporting Being provided with handle on bar, and handle is through support bar, the axis of handle is vertical with the axis of support bar, during use, pin is slow In the hole that in insertion, base is corresponding, under press the handle of base setting tool so that brake is inserted in base, logical Cross multiple pin and the polygon of brake formation thus upper base is locked, avoid upper base spiral shell by restraining moment Upper base deformation in nail disassembly process.
According to upper base bolt structure, devise base screw dismantling device in one, in this screw dismantling device includes The dismounting bar of portion's hollow, the top of dismounting bar is provided with compression lock, and the bottom of dismounting bar is provided with gripping apparatus, the outer wall set of dismounting bar Conjunction has rotary handle and cylinder, and rotary handle is arranged on cylinder and compresses between lock, and cylinder is internal with dismounting bar to be connected, and uses Time first pass through cylinder and open gripping apparatus, slow rotary screw dismantling device can naturally enter in sleeve and promptly this spiral shell Nail, presses compression lock and is pressed in screw by screw, and gripping apparatus closed by the pneumatic knob of turn screw dismantling device, passes through torque spanner Change instrument moment, control moment, it is achieved that the dismounting of upper base screw and installation in underwater environment, it is to avoid screw and screw Hole deforms.
According to base structure on PWR fuel assembly, devise base installation tool in one, base erector on this Tool includes mounting rod, and the bottom of mounting rod is fixed with installing rack, installing rack is provided with and expresses pin and diagonal angle suspension hook, mounting rod Outer wall on be provided with pneumatic switch, by upper base installation tool being moved the surface of supreme base, upper base during use The pin of installation tool slowly inserts in the hole that base is corresponding, presses the upper pipe of pneumatic switch locking of base installation tool Seat, base installation tool in lifting, upper base is removed from crude fuel assembly, is constantly adjusted by upper base installation tool Base position, finds the best position of base, and the pneumatic switch pressing base installation tool puts down base, it is achieved Upper base Fast Installation, it is to avoid upper base deforms.
According to upper base bolt structure, devising a kind of screw crimping tool, this screw crimping tool includes inner hollow Crimping bar, in the bottom of crimping bar, stamping machine is installed, stamping machine is provided with weight, the top of crimping bar is provided with tightens Screw, is sheathed with control cylinder on the outer wall of crimping bar, and control cylinder is connected with stamping machine, is put by envelope silicon instrument during use Put directly over the screw installing screw, screw crimping tool is inserted in screw, make in stamping machine by controlling cylinder Weight move and successively each screw carried out crimping process, by changing threaded end head shapes, fixed fuel assembly guide pipe Position.
The moment of torque spanner is preferably 15N.m, according to the size of parts in nuclear fuel assembly, when dismounting, The moment of 15N.m is fully able to meet use.
The present invention compared with prior art, has such advantages as and beneficial effect: the present invention establishes a kind of fuel stack Part base under water dismounting technology, it is achieved quickly the disintegrating and install of fuel assembly base, for the disintegration of damaged fuel assembly with repair Thering is provided precondition again, for the fuel element that utilizes of economical rationality, raising fuel element utilization rate provides important technology and props up Hold.
Accompanying drawing explanation
Accompanying drawing described herein is used for providing being further appreciated by the embodiment of the present invention, constitutes of the application Point, it is not intended that the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is the structural representation of upper base setting tool;
Fig. 2 is the structural representation of upper base screw dismantling device;
Fig. 3 is the partial schematic diagram of upper base screw dismantling device;
Fig. 4 is the structural representation of upper base installation tool;
Fig. 5 is the structural representation of screw crimping tool;
Fig. 6 is the partial schematic diagram of screw crimping tool.
The parts title of labelling and correspondence in accompanying drawing:
1-pin, 2-brake, 3-handle, 4-support bar, 5-bracing frame, 6-rotary handle, 7-cylinder, 8-dismounts bar, and 9-grabs Tool, 10-mounting rod, 11-installing rack, 12-diagonal angle suspension hook, 13-expresses pin, 14-pneumatic switch, and 15-tightens screw, and 16-is controlled Cylinder processed, 17-crimps bar, 18-stamping machine, 19-weight, and 20-compresses lock.
Detailed description of the invention
For making the object, technical solutions and advantages of the present invention clearer, below in conjunction with embodiment and accompanying drawing, to this Invention is described in further detail, and the exemplary embodiment of the present invention and explanation thereof are only used for explaining the present invention, do not make For limitation of the invention.
Embodiment:
As shown in Figures 1 to 6, the assembly and disassembly methods of a kind of fuel assembly base under water, it uses to upper base setting tool, spiral shell Nail dismantling device, upper base installation tool and screw crimping tool, wherein go up base setting tool and include support bar 4, support bar 4 Bottom be fixed with bracing frame 5, bracing frame 5 is provided with brake 2 and at least 2 pins 1, support bar 4 is provided with handle Hands 3, and handle 3 is through support bar 4, the axis of handle 3 is vertical with the axis of support bar 4;Screw dismantling device includes in inside Empty dismounting bar 8, the top of dismounting bar 8 is provided with compression lock 20, and the bottom of dismounting bar 8 is provided with gripping apparatus 9, outside dismounting bar 8 Wall is sheathed with rotary handle 6 and cylinder 7, and rotary handle 6 is arranged on cylinder 7 and compresses between lock 20, cylinder 7 and dismounting bar 8 Internal connection;Upper base installation tool includes that mounting rod 10, the bottom of mounting rod 10 are fixed with installing rack 11, and installing rack 11 sets It is equipped with and expresses pin 13 and diagonal angle suspension hook 12, the outer wall of mounting rod 10 is provided with pneumatic switch 14, use can also be set simultaneously In the screw storage barrel placing screw;Screw crimping tool includes the crimping bar 17 of inner hollow, in the bottom peace of crimping bar 17 Equipped with stamping machine 18, being provided with weight 19 in stamping machine 18, the top of crimping bar 17 is provided with tightens screw 15, at crimping bar 17 Outer wall on be sheathed with control cylinder 16, and control cylinder 16 be connected with stamping machine 18.
Move screw storage barrel by crane, and be placed on around upper pipe seat of fuel component suitably position, fixing screw storage Deposit bucket;Then move directly over the upper supreme base of base setting tool by crane, by slow for the pin 1 of upper base setting tool In the hole that in insertion, base is corresponding, under press the handle 3 of base setting tool so that brake 2 is inserted in base locking Upper base;Directly over the crane moving sleeve supreme base of screw dismantling device, and telescope-srew dismantling device and crane it Between connection balancer so that telescope-srew dismantling device use will not rock, the gripping apparatus 9 of screw dismantling device is inserted into pipe In any one screw hole of seat, open compression lock 20 turn rotary handles 6 and make cylinder 7 open grabbing of screw dismantling device lower end Tool 9, slow rotary screw dismantling device can naturally enter in sleeve and firmly grasp this screw, presses compression lock 20 and closes Close gripping apparatus 9, rotate to same direction with the torque spanner being set as 15N.m, upper base is fixed mobile spiral shell after screw screws out Screw is put in screw storage barrel by nail dismantling device, repeats above-mentioned demounting procedure, is all removed and placed in spiral shell to 24 screws In nail storage device;Remove telescope-srew dismantling device with crane, upper base installation tool moved the surface of supreme base, The pin 13 of expressing of upper base installation tool slowly inserts in the hole that base is corresponding, presses the pneumatic of base installation tool and opens Close the 14 upper bases of locking, promote upper base installation tool with crane, upper base is removed from crude fuel assembly;With crane by The upper base of dismounting moves to the surface of fuel assembly to be installed, constantly adjusts upper base position by upper base installation tool Put, find the best position of base so that the screw in upper base and the screw one_to_one corresponding on fuel assembly, press The pneumatic switch 14 of upper base installation tool puts down base, then removes base installation tool, is dismounted by screw with crane Instrument moves to the surface of new screw storage device, firmly grasps a wherein screw with the gripping apparatus of screw dismantling device, and should Screw inserts in corresponding screw, opens the pneumatic switch 14 of screw dismantling device, lock-screw, is pulling of 15N.m by moment Hands rotates screw dismantling device and rotates to same direction, repeats above-mentioned installation steps, until being arranged on by 24 new screws Base screwhole position;After installation, remove screw dismantling device with crane, by crane envelope silicon instrument is placed on and installs Directly over the screw of screw, screw crimping tool is inserted in screw and successively each screw is carried out crimping process.
The unloading process of the fuel assembly carried out by the way base under water, it achieves the fast of fuel assembly base Speed is disintegrated and installs, and for the disintegration of damaged fuel assembly with repair and provide precondition, utilizes fuel element for economical rationality, Improve fuel element utilization rate and provide important technical support.
Above-described detailed description of the invention, has been carried out the purpose of the present invention, technical scheme and beneficial effect further Describe in detail, be it should be understood that the detailed description of the invention that the foregoing is only the present invention, be not intended to limit the present invention Protection domain, all within the spirit and principles in the present invention, any modification, equivalent substitution and improvement etc. done, all should comprise Within protection scope of the present invention.

Claims (6)

1. the assembly and disassembly methods of a fuel assembly base under water, it is characterised in that comprise the following steps:
(1) surface of the supreme base of base setting tool in movement, inserts upper base pair by the pin of upper base setting tool In the hole answered, under press the handle of base setting tool, base in locking;
(2) move directly over the supreme base of screw dismantling device, the lower end of screw dismantling device be inserted into base any one In screw hole, turn rotary handle controls cylinder and opens the gripping apparatus of screw dismantling device lower end, and rotary screw dismantling device makes it Can naturally enter in sleeve and firmly grasp this screw, the compression lock pressing screw dismantling device cuts out gripping apparatus, uses torque spanner Rotate screw dismantling device to rotate to same direction, upper base is fixed and after screw screws out, moves screw dismantling device by screw Put in screw storage device, repeat above-mentioned demounting procedure, be all removed and placed in screw storage device to all screws;
(3) remove telescope-srew dismantling device, upper base installation tool is moved the surface of supreme base, upper base erector The pin of expressing of tool inserts in the hole that upper base is corresponding, presses the upper base of pneumatic switch locking of base installation tool, promotes Upper base installation tool, removes upper base from crude fuel assembly;
(4) the upper base dismantled is moved to the surface of fuel assembly to be installed, continuous by upper base installation tool Base position in adjustment, finds the best position of base, and the pneumatic switch pressing base installation tool puts down pipe Seat, then removes base installation tool, screw dismantling device moves to the surface of new screw storage device, tears open with screw The gripping apparatus of a holding tool wherein screw, and this screw is inserted in corresponding screw, open the gas of screw dismantling device Dynamic switch, lock-screw, rotate screw dismantling device with torque spanner and rotate to same direction, repeat above-mentioned installation steps, Until the new screw in all screw holes is all arranged on upper base screwhole position;
(5) after installation, remove screw dismantling device, envelope silicon instrument is placed on and installs directly over the screw of screw, will Screw crimping tool inserts in screw and successively each screw is carried out crimping process.
The assembly and disassembly methods of a kind of fuel assembly base under water the most according to claim 1, it is characterised in that: described upper base Setting tool includes that support bar (4), the bottom of support bar (4) are fixed with bracing frame (5), and bracing frame is provided with brake on (5) (2) and several pins (1), support bar (4) is provided with handle (3), and handle (3) is through support bar (4), handle (3) Axis vertical with the axis of support bar (4).
The assembly and disassembly methods of a kind of fuel assembly base under water the most according to claim 1, it is characterised in that: described screw is torn open Holding tool includes that the dismounting bar (8) of inner hollow, the top of dismounting bar (8) are provided with compression lock (20), the bottom of dismounting bar (8) Being provided with gripping apparatus (9), the outer wall of dismounting bar (8) is sheathed with rotary handle (6) and cylinder (7), and rotary handle (6) is arranged on gas Between cylinder (7) and compression lock (20), cylinder (7) is internal with dismounting bar (8) to be connected.
The assembly and disassembly methods of a kind of fuel assembly base under water the most according to claim 1, it is characterised in that: described upper base Installation tool includes that mounting rod (10), the bottom of mounting rod (10) are fixed with installing rack (11), installing rack (11) is provided with bright Show pin (13) and diagonal angle suspension hook (12), the outer wall of mounting rod (10) is provided with pneumatic switch (14).
The assembly and disassembly methods of a kind of fuel assembly base under water the most according to claim 1, it is characterised in that: described screw pressure Bonding tool includes the crimping bar (17) of inner hollow, is provided with stamping machine (18), stamping machine (18) in the bottom of crimping bar (17) In be provided with weight (19), the top of crimping bar (17) is provided with tightens screw (15), fit on the outer wall of crimping bar (17) There is control cylinder (16), and control cylinder (16) is connected with stamping machine (18).
The assembly and disassembly methods of a kind of fuel assembly base under water the most according to claim 1, it is characterised in that: described moment is pulled The moment of hands is 15N.m.
CN201610519456.8A 2016-07-05 2016-07-05 A kind of assembly and disassembly methods of fuel assembly base under water Active CN106128531B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610519456.8A CN106128531B (en) 2016-07-05 2016-07-05 A kind of assembly and disassembly methods of fuel assembly base under water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610519456.8A CN106128531B (en) 2016-07-05 2016-07-05 A kind of assembly and disassembly methods of fuel assembly base under water

Publications (2)

Publication Number Publication Date
CN106128531A true CN106128531A (en) 2016-11-16
CN106128531B CN106128531B (en) 2017-10-27

Family

ID=57468353

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610519456.8A Active CN106128531B (en) 2016-07-05 2016-07-05 A kind of assembly and disassembly methods of fuel assembly base under water

Country Status (1)

Country Link
CN (1) CN106128531B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106531258A (en) * 2016-12-29 2017-03-22 核动力运行研究所 Removal tool and method for PU cover plate of control rod guide barrel

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4659537A (en) * 1982-11-16 1987-04-21 Framatone Et Cogema Apparatus for maintenance of nuclear fuel assemblies
US20040196949A1 (en) * 2000-04-14 2004-10-07 Kabushiki Kaisha Toshiba Modular submersible repairing system and repairing method
US20050135540A1 (en) * 2003-11-17 2005-06-23 Pabis George S. Fuel assembly nozzleless handling tool and method
CN202307177U (en) * 2011-10-13 2012-07-04 秦山核电有限公司 Underwater operating device for disassembling and assembling nuts of nuclear fuel assembly framework
CN202373315U (en) * 2011-10-13 2012-08-08 秦山核电有限公司 Underwater operating device for gripping end fittings of nuclear fuel assembly
CN103559923A (en) * 2013-11-06 2014-02-05 国核电站运行服务技术有限公司 Padding block operation tool for repairing nuclear fuel assembly

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4659537A (en) * 1982-11-16 1987-04-21 Framatone Et Cogema Apparatus for maintenance of nuclear fuel assemblies
US20040196949A1 (en) * 2000-04-14 2004-10-07 Kabushiki Kaisha Toshiba Modular submersible repairing system and repairing method
US20050135540A1 (en) * 2003-11-17 2005-06-23 Pabis George S. Fuel assembly nozzleless handling tool and method
CN202307177U (en) * 2011-10-13 2012-07-04 秦山核电有限公司 Underwater operating device for disassembling and assembling nuts of nuclear fuel assembly framework
CN202373315U (en) * 2011-10-13 2012-08-08 秦山核电有限公司 Underwater operating device for gripping end fittings of nuclear fuel assembly
CN103559923A (en) * 2013-11-06 2014-02-05 国核电站运行服务技术有限公司 Padding block operation tool for repairing nuclear fuel assembly

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106531258A (en) * 2016-12-29 2017-03-22 核动力运行研究所 Removal tool and method for PU cover plate of control rod guide barrel

Also Published As

Publication number Publication date
CN106128531B (en) 2017-10-27

Similar Documents

Publication Publication Date Title
CN103029099A (en) Quick dismounting tool for cylinder sleeve of internal combustion engine and realization method thereof
CN106128530B (en) A kind of fuel assembly spike pulling method under water
CN106128531A (en) A kind of assembly and disassembly methods of fuel assembly base under water
CN109968275A (en) A kind of live dismounting process of upper-part in-reactor component control rod guide tubes and bundles
CN201868115U (en) Emergency tripping tool for incident occurring during reactor discharging
CN107351020B (en) A kind of dismounting of reusable expansion bolt and restorative procedure
CN206568077U (en) The specific purpose tool dismounted for high-pressure self-sealing manhole
CN106625389B (en) Specific purpose tool and method for the dismounting of high-pressure self-sealing manhole
CN206645780U (en) A kind of novel electric power well cover opening device
CN206705639U (en) Manhole lifting device
CN206512614U (en) Bridge maintenance system supporting device with steel structure
CN109759836A (en) A kind of installation method of the anodontia grinding machine input and output material end cap of ultra-large type
CN201279764Y (en) Shaft stripping device
CN211444835U (en) Tower body tile holding mounting and dismounting device of tower crane
CN203918942U (en) A kind of specific purpose tool of dismantling grab bucket bearing
CN207259096U (en) A kind of power cable Well cover unlatching tool
CN106711777A (en) Top cover opening and closing device for power cabinet
CN205472228U (en) Simple and easy vertical roller mill roller shell is dismantled and installation device
CN206397153U (en) It is a kind of to remove device for the glue cup that aluminum alloy pattern plate is removed
CN202148542U (en) Safe supporting rod opening/locking mechanism of loading arm of backhoe loader
CN201857249U (en) Cover pulling device
CN216803252U (en) Emergent diesel engine cylinder jacket extracting tool of nuclear power plant
CN111271009B (en) Holding and pulling device and construction method
CN212825134U (en) Major diameter corrugated compensator tears instrument open and trades
CN221589586U (en) Quick pile pulling device based on civil engineering is used

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant