CN106123602B - Refractory material pours into a mould safely production system - Google Patents

Refractory material pours into a mould safely production system Download PDF

Info

Publication number
CN106123602B
CN106123602B CN201610689762.6A CN201610689762A CN106123602B CN 106123602 B CN106123602 B CN 106123602B CN 201610689762 A CN201610689762 A CN 201610689762A CN 106123602 B CN106123602 B CN 106123602B
Authority
CN
China
Prior art keywords
cast
water
pipeline
tank
electric arc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610689762.6A
Other languages
Chinese (zh)
Other versions
CN106123602A (en
Inventor
魏晓敏
赵新成
谢建雄
王小东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHENGZHOU DONGFANG ANCAI REFRACTORY CO Ltd
Original Assignee
ZHENGZHOU DONGFANG ANCAI REFRACTORY CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHENGZHOU DONGFANG ANCAI REFRACTORY CO Ltd filed Critical ZHENGZHOU DONGFANG ANCAI REFRACTORY CO Ltd
Priority to CN201610689762.6A priority Critical patent/CN106123602B/en
Publication of CN106123602A publication Critical patent/CN106123602A/en
Application granted granted Critical
Publication of CN106123602B publication Critical patent/CN106123602B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D1/00Casings; Linings; Walls; Roofs
    • F27D1/12Casings; Linings; Walls; Roofs incorporating cooling arrangements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/14Producing shaped prefabricated articles from the material by simple casting, the material being neither forcibly fed nor positively compacted

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Furnace Housings, Linings, Walls, And Ceilings (AREA)
  • Vertical, Hearth, Or Arc Furnaces (AREA)

Abstract

The invention discloses a kind of refractory material cast production system, including electric arc furnaces, heat exchanger, tank, cooling tower, elevated tank, the water supply tank of closed setting, small pump and refractory material rotary casting device safely;Refractory material rotary casting device includes cast base, cast supporting plate and cast rotation loading plate, electric arc furnaces and is provided with water leg;Water leg connects water supply tank, water supply tank connection elevated tank, elevated tank connection small pump.The present invention can avoid electric arc furnaces from outwards discharging high temperature thermal pollution, steam in production process is avoided to permeate into the situation of on-site, cooling water is avoided outwards to discharge steam contamination, and water resource can be recycled, effectively cooling electric arc furnaces, rotary casting is realized in process of production, is greatlyd save the time required to changing cast case, is improved production efficiency;The present invention also can ensure that the job safety of electric arc furnaces in accidental power failure.

Description

Refractory material pours into a mould safely production system
Technical field
The present invention relates to technical field of fire resistant material production, more particularly to a kind of refractory material casting system.
Background technology
In the production process of fusion-cast refractory, electric arc furnaces is conventional equipment.In the process of running, electric arc furnaces by its The interior melting sources of resistance to material, it is therefore desirable to persistently maintain the condition of high temperature in process of production.Too high temperature, which can reduce equipment, to be made With the life-span, and make staff can not normal work in workshop.Therefore, it is necessary to be cooled down to the furnace wall of electric arc furnaces, tieing up While holding furnace high-temperature, by high-temperature area control in electric arc furnaces, prevent furnace heat from largely passing to environment, reduce equipment Service life simultaneously makes to be unsuitable for manual work in workshop.
Existing cooling structure is to use water cooling, and water leg is set at electric arc furnaces furnace wall, and cooling water constantly flows through water Chuck, so as to cool down the furnace wall of electric arc furnaces.The shortcomings that this cooling structure is:Cooling water is higher by electric arc furnaces temperature after heating, Even there is boiling phenomenon when flow is less;Steam diffuses during cooling-water drain, produces pollution to plant area, makes plant area's wall because of length Phase is moist and is damaged.The cooling water of discharge can not reuse, and water resource waste is more serious.
In addition, existing cooling structure also has potential safety hazard:If accidental power failure occurs in production process, water pump stops Only run, cooling water no longer flows;And now the high temperature feed liquid in electric arc furnaces will not then cool down rapidly because of power failure, but can tie up Hold the high temperature of long duration.Water so in electric arc furnaces water leg can be heated to boiling, if system sealing has well The danger blown;If system is open system, substantial amounts of steam can be brought, personnel is cannot be introduced into producing region.At present, The electric arc furnaces production system of this potential safety hazard is not can solve the problem that also.
Fusion-cast refractory substantially uses the method for box production at present, and electric arc furnaces will carry out some case productions per stove liquation The cast of product, i.e., the feed liquid in electric arc furnaces is poured into cast case;This requires to reduce the casting process time as far as possible, improved Efficiency is poured into a mould, reduces energy expenditure.What current domestic fusion-cast refractory manufacturing enterprise was substantially lifted by crane using driving or fork truck Method is poured into a mould, and is that driving and fork truck will have a process for operation after each cast the shortcomings that this pouring procedure maximum, between belonging to Formula of having a rest produces, and even has every stove to be cast with the possibility more than six casees according to brick shape is different so that the duration of pouring at 30 minutes or so, This result in pour into a mould efficiency it is very low, during which electric furnace also otherwise stop heating the feed liquid in electric arc furnaces, so as to cause power consumption Increase.How to go to improve cast efficiency by the improvement of equipment, seeming to fusion-cast refractory enterprise extremely has practical significance.
The content of the invention
It is an object of the invention to provide one kind can avoid steam contamination plant area, recycling water resource, and can prevent The refractory material that safety problem only occurs during accidental power failure pours into a mould safely production system, can realize rotation in process of production Cast, improve production efficiency.
To achieve the above object, cast production system includes electric arc furnaces, heat exchanger, water storage to refractory material of the invention safely Pond, cooling tower, elevated tank, the water supply tank of closed setting, small pump and refractory material rotary casting device;
Refractory material rotary casting device includes cast base, cast supporting plate and cast rotation loading plate, cast support The horizontal cross-section of plate and cast rotation loading plate is size identical regular hexagon;
Cast support post, cast stepper motor are fixedly connected with cast base and is connected with cast stepper motor Pour into a mould decelerator,
Cast support post is respectively equipped with two in the left and right ends portion of cast base, the top of two cast support posts It is fixedly connected with the cast supporting plate;The cast support plate upper surface is provided with the cast low groove of annular, the cast Rotation loading plate is correspondingly arranged with the cast supporting plate, and the lower surface of cast rotation loading plate is relative with the cast low groove The cast upper groove of annular should be provided with, cast low groove and the section for pouring into a mould upper groove are curved, pour into a mould low groove and cast Some cast are provided between upper groove and support ball, the bottom of cast support ball, which rolls, to be connected in cast low groove, cast The top of support ball, which rolls, to be connected in cast upper groove and supports the cast rotation loading plate;The cast supporting plate is set There is cast centre bore, the output shaft of the cast decelerator is upward through the cast centre bore and its top is held with cast rotation The center of support plate is fixedly connected;It is provided between the hole wall of the output shaft of the cast decelerator and the cast centre bore between annular Gap;
The cast rotation loading plate pours case groove provided with 6 sizes with cast with what case was adapted, respectively pours case Circumference of the groove along cast rotation loading plate is uniformly arranged and corresponds respectively to a line line of cast rotation loading plate, respectively pours Case groove is provided with opening in the middle part of the sideline of corresponding cast rotation loading plate;
The refractory material rotary casting device is provided with cast location structure, and cast location structure is included located at cast base On cast positioning hydraulic cylinders and located at cast rotation loading plate on cast positioning hole, cast positioning hole cast rotation carrying Corresponded on plate with the case groove that pours provided with 6;The bottom of positioning hole is poured into a mould in lower upper small tubaeform greatly;
The piston rod for pouring into a mould positioning hydraulic cylinders is adapted with the positioning hole of pouring into a mould, pour into a mould the piston rods of positioning hydraulic cylinders to On slide through it is described cast supporting plate and its upper end with it is described pour into a mould positioning hole it is corresponding;Pour into a mould the piston rod of positioning hydraulic cylinders The cast positioning hole is penetrated at the top of it under stretching state, pours into a mould the piston rods of positioning hydraulic cylinders under retracted state at the top of it Less than the cast rotation loading plate;
Electric arc furnaces has drain pipe, and the distal opening of drain pipe is located at a surface for pouring case groove;On electric arc furnaces Provided with the water leg for cooling down electric arc furnaces;
Heat exchanger includes heat exchange box, and the length direction of heat exchange box interior edge heat exchange box is provided with inner tube, between inner tube outer surface is uniform Every provided with some heat exchange discs;The water inlet end of inner tube is connected with the first pipeline, the top of the water leg of the first pipeline connection electric arc furnaces Portion;The water side of inner tube is connected with the second pipeline, and the second pipeline is passed through a side bottom of tank;Heat exchange box is in inner tube water inlet end Place is connected with the 3rd pipeline, and the distal opening of the 3rd pipeline is in the surface of cooling tower;Heat exchange box connects at inner tube water side There is the 4th pipeline, the 4th pipeline connects the bottom of the cooling tower;4th pipeline, which is provided with, to be used for the water in cooling tower It is sent into the first circulation pump of heat exchange box;
Tank bottom is connected with the 5th pipeline in the opposite side of the second pipeline, and the 5th pipeline connects the water leg of electric arc furnaces Bottom;5th pipeline is provided with the second circulation pump for being used for that the water in tank to be sent into the water leg of electric arc furnaces;
The top of the water leg by the 6th pipeline with being connected at the top of the water supply tank, the bottom of the water supply tank By the 7th pipeline with being connected in the middle part of water leg;6th pipeline is provided with the first valve, and the 7th pipeline is provided with the second valve Door;The bottom of the water supply tank is higher than the top of the water leg;The sidewall bottom of the water supply tank is connected with the first transparent pipe, The upper end of first transparent pipe at the top of water supply tank with being connected;Diffusion valve is connected with the top of water supply tank;Water leg side wall is connected with Thermometer;
The bottom of the elevated tank is higher than the top of water supply tank;The bottom of elevated tank passes through described in the connection of the 8th pipeline The top of water supply tank, the 8th pipeline are provided with the 3rd valve;The water inlet pipe of the small pump connects external water source, small pump Outlet pipe connects the top of elevated tank;The sidewall bottom of the elevated tank is connected with second transparent for show water level Pipe, the top of the second transparent pipe is higher than elevated tank top and its open top;It is inclined upwardly at the top of second transparent pipe Support bar is connected with, support bar top is connected with concave surface arc top cover directed downwardly, and arc top cover is located at the top of the second transparent pipe;
The water leg side wall is provided with the first pressure table for being used for showing pressure in water leg, and the water supply tank side wall is provided with For showing the second pressure gauge of pressure in water supply tank;
Multiple heat exchanging holes are evenly distributed with the heat exchange disc;
The cooling tower includes cooler bin, and the bottom wall central of cooler bin is fixedly connected with montant upwards, and montant top is located at At the top of cooler bin;From top to bottom uniform intervals are connected with some seal cups on montant, and the diameter of seal cup from top to bottom increases successively Greatly;The distal opening of 3rd pipeline is in the surface of the superiors' seal cup;Cooling tower bottom is connected with evacuated tube, is set in evacuated tube There is exhaust-valve.
The seal cup includes trying to get to the heart of a matter, and periphery of trying to get to the heart of a matter connects up the disk edge being obliquely installed.
The upper portion side wall of the cooler bin is provided with blower fan, and the air outlet of blower fan is towards seal cup.
Be provided with spiral plate in the water leg, spiral plate and water leg surround helical flow path, and helical flow path upper end connects the One pipeline and the 5th pipeline of lower end connection.
The refractory material rotary casting device is provided with electromagnetic balance mechanism;Electromagnetic balance mechanism include 6 electromagnet and 6 piece of magnetic material of cast rotation loading plate bottom surface are embedded at, each piece of magnetic material pours case groove positioned at one respectively Underface;6 electromagnet are fixedly connected on cast support plate top surface, the position of 6 electromagnet and 6 magnetic materials Expect that block corresponds.
In general, the present invention can avoid electric arc furnaces from outwards discharging high temperature thermal pollution, avoid in production process steam more The situation of on-site is scattered to, avoids cooling water from outwards discharging steam contamination, and water resource can be recycled, effectively cooling electricity Arc stove, realizes rotary casting in process of production, greatlys save the time required to changing cast case, improves production effect Rate;The present invention also can ensure that the job safety of electric arc furnaces in accidental power failure.
Production system is poured into a mould safely using the refractory material of the present invention, can pass through direct cooling water in normal work Circulation and the furnace wall of the circulation of indirect cooling water effectively cooling electric arc furnaces, are avoided a large amount of to Environment release in electric arc furnaces production process Thermal pollution, also improves the service life of relevant device, and prevents cooling water to be produced steam contamination after electric arc stove heat The problem of.
When having a power failure, pouring into a mould production system safely using the refractory material of the present invention can ensure in electric arc furnaces water leg Water is not heated to boiling, the danger for avoiding hypertonia from bringing, and it also avoid the loss of equipment, while can be filled when having a power failure Divide and utilize the water in water supply tank and elevated tank to absorb the ability of heat energy, and prevent from causing the pressure in water leg because of vaporization phenomenon The problem of water after power rise in water supply tank can not flow downwardly into water leg.
During pouring practice, one pours the lower section that case groove is located at electric arc furnaces drain pipe, and cast is placed on into the present invention with case In 6 pour in case groove, it is possible to start pouring practice.
Next cast can be delivered at electric arc furnaces drain pipe rapidly, greatlyd save by rotation by the present invention with case The time required to changing cast case, production efficiency is improved.After production efficiency improves, also shortening feed liquid in electric arc furnaces needs to protect The time of temperature, so as to greatly save energy consumption.
By type selecting and regulation, conveniently by cast stepper motor cast can be controlled to rotate the anglec of rotation of loading plate Degree, makes it rotate 60 degree every time.Cast case can be positioned exactly by pouring case groove, and cast is limited in case to pour case recessed Groove, be advantageous to pipeline system production, avoid the problem of cast case position is uncertain to bring.
Cast rotation loading plate in refractory material rotary casting device is by pouring into a mould support ball, cast low groove and pouring Upper groove rolling support is noted in cast supporting plate, this structure makes cast rotation loading plate to be held while can rotate By larger weight.
Cast location structure can prevent that cast rotation loading plate rotates during cast, ensures the steady of production Qualitative and reliability.Electromagnetic balance mechanism makes the stress of rotation loading plate 5 more balanced(The suction equalization of the electromagnet weight of feed liquid Power), unstability and structural stress that unbalance loading is brought are avoided, improves the degree of stability of work, while reduces structural stress.
Using the present invention, steam in production process can be avoided to permeate into the situation of on-site completely, and from can circulating Using water resource, electric arc furnaces is effectively cooled down, there is good production application value and the value of environmental protection.
The setting of heat exchanging holes, both reduce heat exchange disc to the resistance of water, be advantageous to flowing of the water in heat exchange box, again plus Fast heat transfer rate between water and heat exchange disc.
Seal cup includes trying to get to the heart of a matter, and periphery of trying to get to the heart of a matter connects up the disk edge being obliquely installed.Such setting, when upper strata overflow When the water of disk overflows to lower floor's seal cup, it would not directly pass through the direct overflow in edge of lower floor's seal cup to more next layer Seal cup, but only just may proceed to underflow stream after this layer of seal cup fills with water.So, every layer of seal cup be all at work Water has been filled with, therefore has considerably increased the area of water and air contact, the heat in water is more quickly taken away by air.
The air outlet of blower fan is towards seal cup.The heat exchange efficiency of water and air so can be further improved, reduces water temperature.
If the second pipeline is not passed through the bottom of tank, but is open in tank ullage, then from second Pipeline still can flow out a small amount of steam, and a small amount of steam contamination is caused to environment;Second pipeline is not passed through the bottom of tank, then The phenomenon that steam can be avoided to permeate into air completely.
Brief description of the drawings
Fig. 1 is to remove structural representation of the invention after refractory material rotary casting device;
Fig. 2 is the enlarged drawing at A in Fig. 1;
Fig. 3 is Fig. 1 A-A direction views;
Fig. 4 is the structural representation of seal cup;
Fig. 5 is Fig. 3 top view;
Fig. 6 is the structural representation that electric arc furnaces is engaged with refractory material rotary casting device;
Fig. 7 is the structural representation of refractory material rotary casting device;
Fig. 8 is the enlarged drawing at A in Fig. 7.
Embodiment
Direction shown in arrow is the flow direction of fluid at this in Fig. 1.
As shown in Figures 1 to 8, cast production system includes electric arc furnaces 1, heat exchanger, storage to refractory material of the invention safely Pond 2, cooling tower, elevated tank 21, the water supply tank 22 of closed setting, small pump 23 and refractory material rotary casting device 91;
Refractory material rotary casting device 91 includes cast base 43, cast supporting plate 44 and cast rotation loading plate 45, The horizontal cross-section for pouring into a mould supporting plate 44 and cast rotation loading plate 45 is size identical regular hexagon;
Cast support post 46, cast stepper motor 47 are fixedly connected with cast base 43 and with pouring into a mould stepper motor 47 The cast decelerator 48 being connected,
Cast support post 46 is respectively equipped with two in the left and right ends portion of cast base 43, two cast support posts 46 Top with it is described cast supporting plate 44 be fixedly connected;Cast supporting plate 44 upper surface is provided with the cast low groove of annular 49, it is described cast rotation loading plate 45 with it is described cast supporting plate 44 be correspondingly arranged, cast rotation loading plate 45 lower surface and The corresponding cast upper groove 50 for being provided with annular of cast low groove 49, cast low groove 49 and the section for pouring into a mould upper groove 50 It is curved, pour into a mould and some cast support balls 51 are provided between low groove 49 and cast upper groove 50, cast support ball 51 Bottom roll be connected to cast low groove 49 in, cast support ball 51 top roll is connected to cast upper groove 50 in simultaneously Support the cast rotation loading plate 45;The cast supporting plate 44 is provided with cast centre bore 53, the cast decelerator 48 Output shaft 52 is upward through the cast centre bore 53 and its top is fixedly connected with the center of cast rotation loading plate 45;It is described Pour into a mould and be provided with annular gap between the output shaft 52 of decelerator 48 and the hole wall of the cast centre bore 53;
The cast rotation loading plate 45 pours case groove 54 provided with 6 sizes with cast with what case was adapted, respectively pours Circumference of the case groove 54 along cast rotation loading plate 45 is built to be uniformly arranged and correspond respectively to one of cast rotation loading plate 45 Sideline, respectively pour case groove 54 and be provided with opening in the middle part of the sideline of corresponding cast rotation loading plate 45;
Electric arc furnaces 1 has drain pipe 90, and the distal opening of drain pipe 90 is located at a surface for pouring case groove 54;
The present invention is provided with cast location structure, and cast location structure includes the cast positioning hydraulic pressure on cast base 43 Cylinder 111 and the cast positioning hole 112 on cast rotation loading plate 45, cast positioning hole 112 rotate loading plate 45 in cast It is upper to be corresponded with the case groove 54 that pours provided with 6;The bottom of positioning hole 112 is poured into a mould in lower upper small tubaeform greatly;
The piston rod for pouring into a mould positioning hydraulic cylinders 111 is adapted with the cast positioning hole 112, pours into a mould positioning hydraulic cylinders 111 Piston rod upward sliding through it is described cast supporting plate 44 and its upper end with it is described pour into a mould positioning hole 112 it is corresponding;Pour and be doomed The piston rod of position hydraulic cylinder 111 penetrates the cast positioning hole 112 under stretching state at the top of it, pour into a mould positioning hydraulic cylinders 111 Piston rod under retracted state at the top of it less than it is described cast rotate loading plate 45.So, a cast is being carried out with case During cast, the piston rod of cast positioning hydraulic cylinders 111 can be made to extend upwardly into cast positioning hole 112, so as to pour into a mould During avoid cast rotation loading plate 45 rotate, strengthen the stability of pouring practice.
The present invention is provided with electromagnetic balance mechanism;Electromagnetic balance mechanism includes 6 electromagnet 114 and held with cast rotation is embedded at 6 piece of magnetic material 113 of the bottom surface of support plate 45, each piece of magnetic material 113 respectively positioned at one pour case groove 54 just under Side;6 electromagnet 114 are fixedly connected on the top surface of cast supporting plate 44, the position of 6 electromagnet 114 and 6 magnetic Property material block 113 corresponds.
Electric arc furnaces 1 is provided with the water leg 24 for being used for cooling down electric arc furnaces 1;Electric arc furnaces 1 and its water leg 24 are this area Routine techniques, concrete structure are no longer described in detail.
Heat exchanger includes heat exchange box 3, and the length direction of the interior edge heat exchange box 3 of heat exchange box 3 is provided with inner tube 4, and the outer surface of inner tube 4 is equal It is even to be interval with some heat exchange discs 5;The water inlet end of inner tube 4 is connected with the first pipeline 6, and the first pipeline 6 connects the water of electric arc furnaces 1 The top of chuck 24;The water side of inner tube 4 is connected with the second pipeline 7, and the second pipeline 7 is passed through a side bottom of tank 2;Heat exchange Case 3 is connected with the 3rd pipeline 8 at the water inlet end of inner tube 4, and the distal opening of the 3rd pipeline 8 is in the surface of cooling tower;Heat exchange box 3 The 4th pipeline 9 is connected with the water side of inner tube 4, the 4th pipeline 9 connects the bottom of the cooling tower;On 4th pipeline 9 Provided with the first circulation pump 10 for the water in cooling tower to be sent into heat exchange box 3;
The bottom of tank 2 is connected with the 5th pipeline 11, the 5th pipeline 11 connection electric arc furnaces 1 in the opposite side of the second pipeline 7 Water leg 24 bottom;5th pipeline 11, which is provided with, to be used to the water in tank 2 being sent into the water leg 24 of electric arc furnaces 1 Second circulation pump 19;
The top of the water leg 24 is connected by the 6th pipeline 25 with the top of the water supply tank 22, the water supply tank 22 bottom is connected by the 7th pipeline 26 with the middle part of water leg 24;6th pipeline 25 is provided with the first valve 27, and the 7th Pipeline 26 is provided with the second valve 28;The bottom of the water supply tank 22 is higher than the top of the water leg 24;The water supply tank 22 Sidewall bottom be connected with the first transparent pipe 29, the upper end of the first transparent pipe 29 is connected with the top of water supply tank 22;Water supply tank 22 tops are connected with diffusion valve 30;The side wall of water leg 24 is connected with thermometer 31;
The bottom of the elevated tank 21 is higher than the top of water supply tank 22;The bottom of elevated tank 21 passes through the 8th pipeline 32 The top of the water supply tank 22 is connected, the 8th pipeline 32 is provided with the 3rd valve 33;The water inlet pipe connection of the small pump 23 is outer The water source put(Not shown water source), the top of the outlet pipe connection elevated tank 21 of small pump 23;The side of the elevated tank 21 Wall bottom is connected with the second transparent pipe 34 for showing water level, the top of the second transparent pipe 34 higher than the top of elevated tank 21 and Its open top;Principle based on linker, the second transparent pipe 34 can show the water level in elevated tank 21.Described second is saturating The top of bright pipe 34, which is inclined upwardly, is connected with support bar 35, and the top of support bar 35 is connected with concave surface arc top cover 36 directed downwardly, arc Shape top cover 36 is located at the top of the second transparent pipe 34;The setting of arc top cover 36, it can avoid in the mistake deposited or used for a long time Foreign matter falls into the second transparent pipe 34 in journey.
The side wall of water leg 24 is provided with the first pressure table 37 for being used for showing pressure in water leg 24, the water supply tank 22 Side wall is provided with the second pressure gauge 38 for being used for showing pressure in water supply tank 22;
Multiple heat exchanging holes 12 are evenly distributed with the heat exchange disc 5;The setting of heat exchanging holes 12, heat exchange disc was both reduced The resistance of 5 pairs of water, be advantageous to flowing of the water in heat exchange box 3, the heat transfer rate for accelerating water again between the disc 5 that exchanges heat.
The cooling tower includes cooler bin 13, and the bottom wall central of cooler bin 13 is fixedly connected with montant 14, montant 14 upwards Top is located at the top of cooler bin 13;From top to bottom uniform intervals are connected with some seal cups 17 on montant 14, seal cup 17 it is straight Footpath from top to bottom increases successively;The distal opening of 3rd pipeline 8 is in the surface of the superiors' seal cup 17;Cool down tower bottom connection There is evacuated tube 39, evacuated tube 39 is provided with exhaust-valve 40, the water in cooling tower is emptied when being easy to safeguard, overhauling.
The seal cup 17 includes trying to get to the heart of a matter 15, and 15 peripheries of trying to get to the heart of a matter connect up the disk that is obliquely installed along 16.It is such to set Put, when the water of upper strata seal cup 17 overflows to lower floor's seal cup 17, would not directly pass through the side of lower floor's seal cup 17 The direct overflow of edge only just may proceed to underflow stream to more next layer of seal cup 17 after this layer of seal cup 17 fills with water. So, every layer of seal cup 17 has all filled with water at work, therefore considerably increases the area of water and air contact, makes in water Heat more quickly can be taken away by air.
The upper portion side wall of the cooler bin 13 is provided with blower fan 18, and the air outlet of blower fan 18 is towards seal cup 17.So can be with The heat exchange efficiency of water and air is further improved, reduces water temperature.
Spiral plate is provided with the water leg 24(It is not shown), spiral plate and water leg 24 surround helical flow path, spiral flow Road upper end connects the first pipeline 6 and lower end connects the 5th pipeline 11.Such setting, direct cooling water is set to pass through the 5th pipeline After 11 reach water leg 24, it is necessary to longer distance is flowed along helical flow path, could be flowed out through the first pipeline 6, so as to prolong significantly Flow path has been grown, has improved the heat exchange efficiency between direct cooling water and electric arc furnaces 1.
Pour into a mould the refractory material of electric-arc furnace cooling rotary casting production safely of production system safely using above-mentioned refractory material Method is carried out according to the following steps:
Water in tank 2 is direct cooling water, and the water in cooling tower is indirect cooling water;
First step is to start second circulation pump 19 and first circulation pump 10, second circulation pump 19 to store up direct cooling water Pond 2, the water leg 24 of electric arc furnaces 1, heat exchange box 3 inner tube 4 between circulate, first circulation pump 10 makes indirect cooling water exist Circulated between cooling tower and heat exchange box 3;What direct cooling water was walked in heat exchange box 3 is tube side, and indirect cooling water is exchanging heat What is walked in case 3 is shell side.
Direct cooling water is heated when by water leg 24, then when by the inner tube 4 of heat exchange box 3 by inner tube 4 outside The indirect cooling water in portion is cooled down;Indirect cooling water is heated when by heat exchange box 3, is then cooled in cooling tower;
Among the operation of first step, the first valve 27, the second valve 28, the 3rd valve 33 and diffusion valve 30 are in Closed mode, staff is by observing the water level in the first transparent pipe 29 determination water supply tank 22, such as the water level in water supply tank 22 Less than the 2/3 of the height of water supply tank 22, then open the valve 33 of diffusion valve 30 and the 3rd, make elevated tank 21 by the 8th pipeline 32 to Moisturizing is filled it up with until water supply tank 22 in water supply tank 22, turns off the valve 33 of diffusion valve 30 and the 3rd;If in elevated tank 21 Water level be less than the height of elevated tank 21 2/3, then open small pump 23, to the moisturizing of elevated tank 21 until the quilt of elevated tank 21 Fill it up with, turn off small pump 23;By observing the water level in the second transparent pipe 34 determination elevated tank 21;Operated more than true Protect among the running of first step, water supply tank 22 and elevated tank 21 are in the sufficient state of water;
Refractory material rotary casting device 91 is located at by electric arc furnaces 1, and one of them pours case groove 54 and gone out positioned at electric arc furnaces Below the end of liquid pipe 90, after the refractory material in electric arc melts well, 6 that cast is put in the present invention with case pour In case groove 54, it is possible to start pouring practice.After a cast is poured with case to be poured in, the cast band of stepper motor 47 can be started Dynamic cast rotation loading plate 45 and cast thereon rotate 60 degree with case, carry the next of cast case and pour case groove 54 Continue pouring practice after reaching pouring position, compared to the cast stand-by period is greatlyd save in the past, improve production efficiency, save Cast waiting time(Next cast case is waited to reach the time for pouring case groove 54)Feed temperature in pilot arc stove 1 Required energy.When electric arc furnaces 1 produces, the condition of high temperature inside maintaining on the one hand is needed, other direction externally maintains again Relatively low temperature(Water leg cooled furnace wall is set), therefore electric arc furnaces 1 is traditional energy consumption rich and influential family, is often saved needed for one section of production The time wanted, big energy can be saved.
In first step is running, when there is power failure phenomenon, second circulation pump 19 and first circulation pump 10 stop Only, second step is now carried out;
Second step is after power failure, and staff observes thermometer 31, first pressure table 37 and second pressure gauge 38;When When thermometer 31 shows that the temperature of water leg 24 is higher than 75 degree, existing part water is vaporized in water leg 24;Now open the 3rd Valve 33, the water vapour in water leg 24 are passed through water supply tank 22 by the 6th pipeline 25, made between water supply tank 22 and water leg 24 In identical pressure;Staff by first pressure table 37 and second pressure gauge 38 confirm water supply tank 22 and water leg 24 it Between be in identical pressure after open the second valve 28, the water in water supply tank 22 flows into water leg 24, and the water in water supply tank 22 In the presence of pressure, the heated water in water leg 24 flows to heat exchange box 3 by the first pipeline 6, finally flows into tank 2;
If first not opening the 3rd valve 33 and directly opening the second valve 28, the water in water leg 24 may be caused because of pressure Power raises(The water being in contact with electric arc furnaces 1 can vaporize because not flowing, and cause pressure rise)And flow backwards to water supply tank 22, so The water in water supply tank 22 will be caused can not to flow downwardly into water leg 24, until the water in water leg 24 dryouies, steam pressure is low In the hydraulic pressure of water supply tank 22, so as to cause safety problem and steam contamination problem in the process.
Among the progress of second step, staff persistently carries out following two operations:
1. observing thermometer 31, after thermometer 31 shows that the water temperature of water leg 24 is less than 50 degree, the second valve 28 is closed; Water temperature in water leg 24 is gone up to after more than 75 degree, reopens the second valve 28;This operation can prevent water supply tank 22 Interior water is too fast to flow into water leg 24, so that the heat energy not fully absorbed in electric arc furnaces 1 is just spilt out by the first pipeline 6. The meaning of this operation is to make full use of the ability of water absorption heat energy in water supply tank 22 when having a power failure.
2. the liquid level in water supply tank 22 is observed by the first transparent pipe 29, when liquid level is high less than water supply tank 22 in water supply tank 22 Degree 1/3 when, open the 3rd valve 33 and diffusion valve 30, the water in elevated tank 21 is passed through the 8th pipeline 32 and inject water supply tank 22, when the water that water supply tank 22 fills in water or the elevated tank 21 of water supply tank 22 is used up, close the 3rd valve 33 and diffusion valve 30.
In first step, while second circulation pump 19 and first circulation pump 10 is started, start blower fan 18 so as to accelerate The radiating of indirect cooling water.
During normal work(Do not have a power failure), the carrying out practically situation of first step is:Start first circulation pump 10 and second to follow Ring pump 19, the water in tank 2 is sent into the water leg 24 of electric arc furnaces 1 by second circulation pump 19, for cooling down electric arc furnaces 1;From The coolant-temperature gage of outflow is higher in water leg 24, and such as directly discharge will produce substantial amounts of steam, pollutes working environment, makes plant area's wall It is damaged because long-term moist.In the present invention, heat exchange box 3 is sent into from the water of the interior outflow of water leg 24, passes through the inner tube 4 of heat exchange box 3 When, heat exchange occurs with the cooling water outside pipe.The setting of heat exchange disc 5 can greatly improve heat exchange efficiency, and because heat exchange The presence in hole 12 is without the excessive flowing for influenceing cooling water.After heat exchange, from the temperature of the water of the water leg 24 of electric arc furnaces 1 outflow It is greatly reduced, the bottom of tank 2 is injected finally by the second pipeline 7.If the second pipeline 7 is not passed through the bottom of tank 2 Portion, but be open in the ullage of tank 2, then a small amount of steam still can be flowed out from the second pipeline 7, environment is caused on a small quantity Steam contamination;Second pipeline 7 is not passed through the bottom of tank 2, then the phenomenon that steam can be avoided to permeate into air completely. Second circulation pump 19 makes this part water be circulated between the water leg 24 of electric arc furnaces 1, heat exchange box 3 and tank 2, constantly cold But electric arc furnaces 1.
First circulation pump 10 will cool down tower bottom water be sent into heat exchange box 3, this flow direction of part water in heat exchange box 3 with it is interior The reclaimed water of pipe 4 flows to contrast, forms countercurrent flow, and the efficiency for cooling down the reclaimed water of inner tube 4 is higher.This part water is through the 3rd pipeline 88 outflows, the top of cooling tower is flow in the presence of hydraulic pressure, flows to first layer seal cup 17, and step by step to underflow stream.Overflowing During stream, blower fan 18 is dried, and accelerates the heat exchange of water and air.Behind water overflow to the bottom of cooler bin 13 of cooling tower, quilt First circulation pump 10 is extracted out again, carries out next round recuperated cycle.
Above example is only to illustrative and not limiting technical scheme, although with reference to above-described embodiment to this hair It is bright to be described in detail, it will be understood by those within the art that:Still the present invention can be modified or be waited With replacing, any modification or partial replacement without departing from the spirit and scope of the present invention, it all should cover the power in the present invention Among sharp claimed range.

Claims (5)

1. refractory material pours into a mould safely production system, it is characterised in that:Including electric arc furnaces, heat exchanger, tank, cooling tower, height Position water tank, the water supply tank of closed setting, small pump and refractory material rotary casting device;
Refractory material rotary casting device include cast base, cast supporting plate and cast rotation loading plate, cast supporting plate and The horizontal cross-section of cast rotation loading plate is size identical regular hexagon;
Cast support post, cast stepper motor and the cast being connected with cast stepper motor are fixedly connected with cast base Decelerator,
Cast support post is respectively equipped with two in the left and right ends portion of cast base, the tops of two cast support posts with The cast supporting plate is fixedly connected;The cast support plate upper surface is provided with the cast low groove of annular, the cast rotation Loading plate is correspondingly arranged with the cast supporting plate, and the lower surface of cast rotation loading plate pours into a mould that low groove is corresponding sets with described There is the cast upper groove of annular, cast low groove and the section for pouring into a mould upper groove are curved, cast low groove and cast fovea superior Some cast are provided between groove and support ball, the bottom of cast support ball, which rolls, to be connected in cast low groove, cast support The top of ball, which rolls, to be connected in cast upper groove and supports the cast rotation loading plate;The cast supporting plate, which is provided with, to be poured Centre bore is noted, the output shaft of the cast decelerator is upward through the cast centre bore and its top and cast rotation loading plate Center be fixedly connected;Annular gap is provided between the hole wall of the output shaft of the cast decelerator and the cast centre bore;
The cast rotation loading plate pours case groove provided with 6 sizes with cast with what case was adapted, respectively pours case groove It is uniformly arranged along the circumference of cast rotation loading plate and corresponds respectively to a line line of cast rotation loading plate, it is recessed respectively pours case Groove is provided with opening in the middle part of the sideline of corresponding cast rotation loading plate;
The refractory material rotary casting device is provided with cast location structure, and cast location structure is included on cast base Positioning hydraulic cylinders and the cast positioning hole on cast rotation loading plate are poured into a mould, cast positioning hole is on cast rotation loading plate Corresponded with the case groove that pours provided with 6;The bottom of positioning hole is poured into a mould in lower upper small tubaeform greatly;
The piston rod for pouring into a mould positioning hydraulic cylinders is adapted with the cast positioning hole, and the piston rod for pouring into a mould positioning hydraulic cylinders slides up It is dynamic through the cast supporting plate and its upper end with described to pour into a mould positioning hole corresponding;The piston rod of cast positioning hydraulic cylinders is being stretched Do well down its top penetrate the cast positioning hole, the piston rod for pouring into a mould positioning hydraulic cylinders is less than under retracted state at the top of it The cast rotation loading plate;
Electric arc furnaces has drain pipe, and the distal opening of drain pipe is located at a surface for pouring case groove;Electric arc furnaces is provided with For cooling down the water leg of electric arc furnaces;
Heat exchanger includes heat exchange box, and the length direction of heat exchange box interior edge heat exchange box is provided with inner tube, and inner tube outer surface uniform intervals are set There are some heat exchange discs;The water inlet end of inner tube is connected with the first pipeline, the top of the water leg of the first pipeline connection electric arc furnaces;It is interior The water side of pipe is connected with the second pipeline, and the second pipeline is passed through a side bottom of tank;Heat exchange box connects at inner tube water inlet end The 3rd pipeline is connected to, the distal opening of the 3rd pipeline is in the surface of cooling tower;Heat exchange box is connected with inner tube water side Four pipelines, the 4th pipeline connect the bottom of the cooling tower;4th pipeline, which is provided with, to be used to the water in cooling tower being sent into The first circulation pump of heat exchange box;
Tank bottom is connected with the 5th pipeline, the bottom of the water leg of the 5th pipeline connection electric arc furnaces in the opposite side of the second pipeline Portion;5th pipeline is provided with the second circulation pump for being used for that the water in tank to be sent into the water leg of electric arc furnaces;
By the 6th pipeline with being connected at the top of the water supply tank, the bottom of the water supply tank passes through at the top of the water leg 7th pipeline in the middle part of water leg with being connected;6th pipeline is provided with the first valve, and the 7th pipeline is provided with the second valve;Institute The bottom for stating water supply tank is higher than the top of the water leg;The sidewall bottom of the water supply tank is connected with the first transparent pipe, and first The upper end of transparent pipe at the top of water supply tank with being connected;Diffusion valve is connected with the top of water supply tank;Water leg side wall is connected with temperature Table;
The bottom of the elevated tank is higher than the top of water supply tank;The bottom of elevated tank connects the moisturizing by the 8th pipeline The top of case, the 8th pipeline are provided with the 3rd valve;The water inlet pipe of the small pump connects external water source, the water outlet of small pump Pipe connects the top of elevated tank;The sidewall bottom of the elevated tank is connected with the second transparent pipe for showing water level, the The top of two transparent pipes is higher than elevated tank top and its open top;It is inclined upwardly and is connected with the top of second transparent pipe Support bar, support bar top are connected with concave surface arc top cover directed downwardly, and arc top cover is located at the top of the second transparent pipe;
The water leg side wall is provided with the first pressure table for being used for showing pressure in water leg, and the water supply tank side wall, which is provided with, to be used for Show the second pressure gauge of pressure in water supply tank;
Multiple heat exchanging holes are evenly distributed with the heat exchange disc;
The cooling tower includes cooler bin, and the bottom wall central of cooler bin is fixedly connected with montant upwards, and montant top is positioned at cooling Box top;From top to bottom uniform intervals are connected with some seal cups on montant, and the diameter of seal cup from top to bottom increases successively;The The distal opening of three pipelines is in the surface of the superiors' seal cup;Cooling tower bottom is connected with evacuated tube, and evacuated tube is provided with row Empty valve.
2. refractory material according to claim 1 pours into a mould safely production system, it is characterised in that:The seal cup includes disk Bottom, periphery of trying to get to the heart of a matter connect up the disk edge being obliquely installed.
3. refractory material according to claim 1 or 2 pours into a mould safely production system, it is characterised in that:The cooler bin Upper portion side wall is provided with blower fan, and the air outlet of blower fan is towards seal cup.
4. refractory material according to claim 3 pours into a mould safely production system, it is characterised in that:It is provided with the water leg Spiral plate, spiral plate surround helical flow path with water leg, and helical flow path upper end connects the first pipeline and lower end connects the 5th pipeline.
5. refractory material according to claim 4 pours into a mould safely production system, it is characterised in that:The refractory material rotation Apparatus for pouring is provided with electromagnetic balance mechanism;Electromagnetic balance mechanism includes 6 electromagnet and is embedded at cast rotation loading plate bottom surface 6 piece of magnetic material, each piece of magnetic material is located at a underface for pouring case groove respectively;6 electromagnet are consolidated Surely cast support plate top surface is connected to, the position of 6 electromagnet corresponds with 6 piece of magnetic material.
CN201610689762.6A 2016-08-19 2016-08-19 Refractory material pours into a mould safely production system Active CN106123602B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610689762.6A CN106123602B (en) 2016-08-19 2016-08-19 Refractory material pours into a mould safely production system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610689762.6A CN106123602B (en) 2016-08-19 2016-08-19 Refractory material pours into a mould safely production system

Publications (2)

Publication Number Publication Date
CN106123602A CN106123602A (en) 2016-11-16
CN106123602B true CN106123602B (en) 2018-02-27

Family

ID=57280247

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610689762.6A Active CN106123602B (en) 2016-08-19 2016-08-19 Refractory material pours into a mould safely production system

Country Status (1)

Country Link
CN (1) CN106123602B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2003246149A1 (en) * 2002-06-28 2004-01-19 Taiko Refractories Co., Ltd. Powder composition for castable refractory and premixed material comprising the same, method for applying premixed material and refractory hardened product therefrom
CN101579733A (en) * 2009-06-11 2009-11-18 内蒙古第一机械制造(集团)有限公司 Nozzle structure at bottom of refining furnace and nozzle filling method
CN101658916B (en) * 2009-09-22 2011-05-04 西安建筑科技大学 Preparation method of prefabricated framework reinforcement compound grinding disc
JP2013040721A (en) * 2011-08-17 2013-02-28 Nippon Steel & Sumitomo Metal Corp Drying method of lining
CN102492440B (en) * 2011-12-16 2013-11-13 宁波钢铁有限公司 Protection method for weld on inner wall of water seal seat used on mouth of coke dry quenching furnace
CN206019338U (en) * 2016-08-19 2017-03-15 郑州东方安彩耐火材料有限公司 Production system poured into a mould safely by refractory material

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2003246149A1 (en) * 2002-06-28 2004-01-19 Taiko Refractories Co., Ltd. Powder composition for castable refractory and premixed material comprising the same, method for applying premixed material and refractory hardened product therefrom
CN101579733A (en) * 2009-06-11 2009-11-18 内蒙古第一机械制造(集团)有限公司 Nozzle structure at bottom of refining furnace and nozzle filling method
CN101658916B (en) * 2009-09-22 2011-05-04 西安建筑科技大学 Preparation method of prefabricated framework reinforcement compound grinding disc
JP2013040721A (en) * 2011-08-17 2013-02-28 Nippon Steel & Sumitomo Metal Corp Drying method of lining
CN102492440B (en) * 2011-12-16 2013-11-13 宁波钢铁有限公司 Protection method for weld on inner wall of water seal seat used on mouth of coke dry quenching furnace
CN206019338U (en) * 2016-08-19 2017-03-15 郑州东方安彩耐火材料有限公司 Production system poured into a mould safely by refractory material

Also Published As

Publication number Publication date
CN106123602A (en) 2016-11-16

Similar Documents

Publication Publication Date Title
CN206019338U (en) Production system poured into a mould safely by refractory material
CN106197034B (en) Produce the safe cooling system of electric arc furnaces used for refractory material
CN105458164A (en) Energy-saving stuffing cooling type casting sand rapid roasting regeneration system
CN106123602B (en) Refractory material pours into a mould safely production system
CN107764046A (en) Refractory material of electric-arc furnace cools down safely production method
CN102618732A (en) Continuous multistage refining and degassing keeping furnace for molten aluminum
CN206019353U (en) Produce the safe cooling system of electric arc furnaces used for refractory material
CN105127406B (en) Tundish roaster
WO2004080904A1 (en) A cooling method for prolonging service life of glass tank furnace and decreasing glass defect
CN206019282U (en) Water-cooled electric arc furnaces environmental protection cooling body
CN215090651U (en) Multi-head movable ladle baking device
CN101890245A (en) Method and device for quickly dehydrating investment casting mould materials
CN105195690B (en) Automatic bismuth ingot casting machine
CN108180763A (en) A kind of calcium carbide device for recycling heat and application method
US7828004B2 (en) Method and device for storing chemical products in a container
CN209558903U (en) A kind of novel carbon calcining furnace removal device
CN201908109U (en) Cooling and control system for quenching agent in production line of mesh belt furnace
CN208406999U (en) A kind of material device for liquid sodium silicate production
CN209386782U (en) A kind of mold firing kiln
CN105115307B (en) Quickly cooling mechanism and its control method
CN206011353U (en) Refractory material rotary casting device
CN105728684B (en) Fluid-flywheel clutch all-metal mould mould pre-heating mean and application
CN204867369U (en) Multi -functional casting fluffing of moulding sand stove
CN105798254B (en) Fluid-flywheel clutch workpiece and production method
CN206391886U (en) A kind of energy-efficient knot screen of rosin

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant