CN106121250A CN201610738288.1A CN201610738288A CN106121250A CN 106121250 A CN106121250 A CN 106121250A CN 201610738288 A CN201610738288 A CN 201610738288A CN 106121250 A CN106121250 A CN 106121250A
Authority
CN
China
Prior art keywords
cement mortar
toilet
mounting process
casing pressure
marble
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610738288.1A
Other languages
Chinese (zh)
Inventor
林武臣
蒋希
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Shang Yunyi Home Furnishing Engineering Co Ltd
Original Assignee
Fujian Shang Yunyi Home Furnishing Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Shang Yunyi Home Furnishing Engineering Co Ltd filed Critical Fujian Shang Yunyi Home Furnishing Engineering Co Ltd
Priority to CN201610738288.1A priority Critical patent/CN106121250A/en
Publication of CN106121250A publication Critical patent/CN106121250A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Floor Finish (AREA)

Abstract

The present invention relates to a kind of toilet casing pressure stone mounting process, comprise the following steps: the first step, set cement mortar on the upper berth, threshold position of toilet, and take marble, smear cement mortar in bottom, then marble is layed in cement mortar;Second step, on the floor of toilet, position and the cement mortar of cement mortar lay waterproof layer on the one side of toilet respectively in succession;3rd step, is positioned on waterproof layer above the floor of toilet and lays the second cement mortar, and lays floor tile in the second cement mortar, and the upper surface of described second cement mortar is less than marmorean upper surface less than the upper surface of cement mortar, the upper surface of floor tile.

Description

A kind of toilet casing pressure stone mounting process
Technical field
The present invention relates to a kind of toilet casing pressure stone mounting process.
Background technology
China Patent No.: CN201420764992.0 discloses a kind of casing pressure stone structure, it is characterised in that tie at room door It is provided with the casing pressure stone being above the ground level at structure installing port, door pocket is installed on described casing pressure stone.The beneficial effect of this utility model It is: this structure can be prevented effectively from door pocket and rotten problem occurs, and improves the quality of decorations.But, if door pocket uses Wood materials, and if this door pocket be provided on bathroom door, then be still easy to make moist.
Summary of the invention
Therefore, for above-mentioned problem, the present invention proposes that a kind of water resistance is good, construction is simple, marble is not easily stripped Sanitary towel's casing pressure stone mounting process.
For achieving the above object, present invention employs techniques below scheme: a kind of toilet casing pressure stone mounting process, including Following steps:
The first step, sets cement mortar on the upper berth, threshold position of toilet, and takes marble, smear cement mortar in bottom, Then marble is layed in cement mortar;
Second step, on the floor of toilet in succession the position of cement mortar and cement mortar near the one side of toilet Upper lay waterproof layer respectively;
3rd step, is positioned on waterproof layer above the floor of toilet and lays the second cement mortar, and at the second cement bonded sand Laying floor tile on slurry, the upper surface of described second cement mortar is less than the upper surface of cement mortar, and the upper surface of floor tile is less than big The upper surface of Gypsum Fibrosum.
Further, described marmorean length is equal to the length at threshold position.
Further, in the 3rd step, floor tile first smears cement mortar on the bottom surface of floor tile when laying, stand 0.5~ 2min, is then layed in the second cement mortar.
Further, in the first step, after smearing cement mortar bottom marble, stand 0.5~2min, then spread If.
Further, the width of described cement mortar is equal to marmorean width.
By using preceding solution, the invention has the beneficial effects as follows: this toilet casing pressure stone mounting process is by big The change of the paving mode of Gypsum Fibrosum can be effectively improved water resistance, improves the steadiness that marble is installed, and marble is not Easy to fall off;Further, marmorean length, equal to the length at threshold position, can be effectively improved the goodness of fit of installation;Enter one Step, floor tile first smears cement mortar on the bottom surface of floor tile when laying, and stands 0.5~2min, is then layed in the second cement On mortar, by the way of standing, allow cement mortar be in leather hard, but so cement can have certain aridity, from And the floor tile after laying can tightly be held ground, will not produce hollow, warp, the defective mode such as infiltration;Further, After smearing cement mortar bottom marble, stand 0.5~2min, then lay, allow cement mortar be in leather hard, but So cement can have certain aridity, the ground so that the marble after Pu Sheing can tightly be held, and will not produce sky The heart, warp, the defective mode such as infiltration.
Accompanying drawing explanation
Fig. 1 is the structural representation of the present invention.
Detailed description of the invention
In conjunction with the drawings and specific embodiments, the present invention is further described.
With reference to Fig. 1, the present embodiment provides a kind of toilet casing pressure stone mounting process, comprises the following steps:
The first step, sets cement mortar 1 on the upper berth, threshold position of toilet, and takes marble 2, smear cement in bottom Slurry, after smearing cement mortar, stands 1min, is then layed in cement mortar 1 by marble 2, described Dali bottom marble The length of stone 2 is equal to the length at threshold position, and the width of described cement mortar 1 is equal to the width of marble 2;
Second step, on the floor of toilet in succession the position of cement mortar 1 and cement mortar 1 near the side of toilet Waterproof layer 3 is laid respectively on face;
3rd step, is positioned on waterproof layer 3 above the floor of toilet and lays the second cement mortar 4, and at the second cement Laying floor tile 5 on mortar 4, floor tile 5 first smears cement mortar on the bottom surface of floor tile 5 when laying, and stands 1min, is then layed in In second cement mortar 4, the upper surface of described second cement mortar 4 is less than the upper surface of cement mortar 1, the upper surface 5 of floor tile Upper surface less than marble 2.
After smearing cement mortar bottom marble or floor tile, time of repose can be 0.5min or 2min or 0.5~2min Between any value.
This toilet casing pressure stone mounting process can be effectively improved water resistance by the change of marmorean paving mode, The steadiness that raising marble is installed, and marble difficult drop-off;Further, marmorean length is equal to threshold position Length, can be effectively improved the goodness of fit of installation;Further, floor tile first smears cement when laying on the bottom surface of floor tile Slurry, stands 0.5~2min, is then layed in the second cement mortar, by the way of standing, allows cement mortar be in leather hard State, but so cement can have certain aridity, the ground so that the floor tile after Pu Sheing can tightly be held, and will not produce Raw hollow, warp, the defective mode such as infiltration;Further, after smearing cement mortar bottom marble, standing 0.5~2min, and After lay, allow cement mortar be in leather hard, but so cement can have certain aridity, so that after Pu Sheing Marble can tightly hold ground, will not produce hollow, warp, the defective mode such as infiltration.
Although specifically showing and describe the present invention in conjunction with preferred embodiment, but those skilled in the art should be bright In vain, in the spirit and scope of the present invention limited without departing from appended claims, in the form and details can be right The present invention makes a variety of changes, and is protection scope of the present invention.

Claims (5)

1. a toilet casing pressure stone mounting process, it is characterised in that comprise the following steps:
The first step, sets cement mortar on the upper berth, threshold position of toilet, and takes marble, smear cement mortar in bottom, then Marble is layed in cement mortar;
Second step, on the floor of toilet, position and the cement mortar of cement mortar are divided on the one side of toilet in succession Do not lay waterproof layer;
3rd step, is positioned on waterproof layer above the floor of toilet and lays the second cement mortar, and in the second cement mortar Laying floor tile, the upper surface of described second cement mortar is less than marble less than the upper surface of cement mortar, the upper surface of floor tile Upper surface.
A kind of toilet casing pressure stone mounting process the most according to claim 1, it is characterised in that: described marmorean length Length equal to threshold position.
A kind of toilet casing pressure stone mounting process the most according to claim 1, it is characterised in that: in the 3rd step, floor tile exists On the bottom surface of floor tile, first smear cement mortar during laying, stand 0.5~2min, be then layed in the second cement mortar.
A kind of toilet casing pressure stone mounting process the most according to claim 1, it is characterised in that: in the first step, in Dali After smearing cement mortar bottom stone, stand 0.5~2min, then lay.
A kind of toilet casing pressure stone mounting process the most according to claim 1, it is characterised in that: the width of described cement mortar Degree is equal to marmorean width.
CN201610738288.1A 2016-08-26 2016-08-26 A kind of toilet casing pressure stone mounting process Pending CN106121250A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610738288.1A CN106121250A (en) 2016-08-26 2016-08-26 A kind of toilet casing pressure stone mounting process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610738288.1A CN106121250A (en) 2016-08-26 2016-08-26 A kind of toilet casing pressure stone mounting process

Publications (1)

Publication Number Publication Date
CN106121250A true CN106121250A (en) 2016-11-16

Family

ID=57275428

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610738288.1A Pending CN106121250A (en) 2016-08-26 2016-08-26 A kind of toilet casing pressure stone mounting process

Country Status (1)

Country Link
CN (1) CN106121250A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10280662A (en) * 1997-03-31 1998-10-20 Nippon Sogo Jiyuuseikatsu Kk Floor material and execution method therefor
JP2007197921A (en) * 2006-01-24 2007-08-09 Yuka Sansho Kenzai Kk Floor structure
CN203347182U (en) * 2013-07-18 2013-12-18 北京丽贝亚建筑装饰工程有限公司 Water-impermeable structural layer for toilet
CN104653036A (en) * 2014-12-23 2015-05-27 上海聚通装饰集团有限公司 Moisture-proof and mildew-proof installation method for door pocket line and doorsill stone
CN205153852U (en) * 2015-10-30 2016-04-13 洛阳师范学院 Type of preventing stumbling is dampproofing structure for bathroom threshold

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10280662A (en) * 1997-03-31 1998-10-20 Nippon Sogo Jiyuuseikatsu Kk Floor material and execution method therefor
JP2007197921A (en) * 2006-01-24 2007-08-09 Yuka Sansho Kenzai Kk Floor structure
CN203347182U (en) * 2013-07-18 2013-12-18 北京丽贝亚建筑装饰工程有限公司 Water-impermeable structural layer for toilet
CN104653036A (en) * 2014-12-23 2015-05-27 上海聚通装饰集团有限公司 Moisture-proof and mildew-proof installation method for door pocket line and doorsill stone
CN205153852U (en) * 2015-10-30 2016-04-13 洛阳师范学院 Type of preventing stumbling is dampproofing structure for bathroom threshold

Similar Documents

Publication Publication Date Title
CN104234362B (en) Outdoor tile construction method
CN104653036B (en) A kind of door sleeve and door stone are moistureproof, the mounting method of mildew-resistant
CN106121250A (en) A kind of toilet casing pressure stone mounting process
CN207796262U (en) A kind of water pipe finishing waterproof assembling structure
CN204754074U (en) Laminate flooring brick with moisture resistance function of preventing fires
CN204370762U (en) A kind of anti-skidding marble tile of easy processing
CN208473229U (en) A kind of overhead type decorative ground
CN103806664A (en) Construction technology of external thermal insulation mortar
CN206158102U (en) Balcony construction site layout structure
CN202194324U (en) Novel specially shaped ceramic brick
CN202577809U (en) Precast stair structure
CN205224451U (en) Roofing parapet flashing protective layer structure
CN205421842U (en) Threshold prevention of seepage control structure between residential sanitation
CN205153392U (en) Install ceramic tile structure of floor drain fast
CN204609214U (en) Composite floor board
CN204738498U (en) Floor tile can seep water
CN202936687U (en) Cement foamed concrete floor
CN205348655U (en) External wall insulation decorates production board's mounting structure
CN210508240U (en) Vibration-damping lateral-movement-preventing structure of stone ground at elevator room
CN103790245A (en) Construction process for interior thermal insulation mortar
CN210622230U (en) Wall brick and ground internal corner line edge
CN205276825U (en) Connecting piece of connecting ceramic tile and wall brick
CN203905234U (en) Integrated decorative heat-insulation board for curtain wall dry hanging
CN202899562U (en) Paving structure of thin-type floor decorative materials
CN103216073A (en) Antiskid waterproof ceramic tile for toilet

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161116