Summary of the invention
It is an object of the invention to solve problems of the prior art, and a kind of mountain highway buried garden pipe culvert is provided
The construction method of control critical eigenvalue, to reduce the actual loading of pipe culvert, prevents cracking.
The technical solution adopted in the present invention is as follows:
A kind of construction method of mountain highway buried garden pipe culvert control critical eigenvalue, step is as follows:
1) filling roadbed to garden pipe culvert top design height;
2) excavation roadbed and ground are to garden pipe culvert substrate designed elevation;
3) pour garden pipe culvert substrate, and carry out maintenance;
4) installing prefabricated garden pipe culvert, and arrange half moon-shaped soil arch guiding bed course at pipe culvert top, described soil arch draws
Lead bed course and use elastic-plastic material, and its two ends extend respectively to the two ends of the horizontal external diameter of pipe culvert;Half moon-shaped soil arch guides
Bed course patch pipe culvert outer wall is arranged;
5) layering Bu Tian garden pipe culvert periphery roadbed, and hand compaction;
6) soil layer more than pipe culvert top is carried out layered rolling, filling roadbed to designed elevation.
The theoretical foundation of the present invention is as follows:
From mechanical concept, existing buried garden pipe culvert job specfication does not illustrates how buried garden pipe culvert avoids cracking risk to ask
Topic.How applicant creatively directly avoids cracking risk with mechanics methods analyst buried garden pipe culvert, and find buried garden to manage
The control cracking method contained.
The first step is directly with mechanics methods analyst buried garden pipe culvert Cracks:
From Fig. 1 (a), buried garden pipe culvert design load PDesign=H × D (1.1)
Owing to garden pipe culvert rigidity is less than garden pipe culvert actual loading more than subgrade stiffness, the garden rectangular distribution of pipe culvert design load
Being distributed in similar inverted trapezoidal, shallow embedding garden pipe culvert exceeds the quata stress within safety range;The pipe culvert stress that exceeds the quata in buried garden can cause garden
Pipe culvert ftractures, and the weak part of the most buried garden pipe culvert or link are garden pipe culvert crackings, it should prevent from inducing detrimental effect power
With the transfer of energy Dou Xiang garden pipe culvert structure or concentration effect.The most buried garden pipe culvert actual loading
PActual=H × (D+Hsin α) (1.2)
Wherein H is the above height of embankment in pipe culvert top, garden;D is garden pipe culvert diameter;α is actual loading extended corner;PDesignFor deeply
Bury garden pipe culvert design load;PActualFor buried garden pipe culvert actual loading.
Obviously PActual> PDesign (1.3)
If PActualExceeding buried garden pipe culvert allowable stress, buried garden pipe culvert will necessarily produce crack.
Second step is directly by mechanics method searching buried garden pipe culvert minimizing load method:
From Fig. 1 (b), Fig. 2, formula (1.4), formation soil arch is set at pipe culvert top, buried garden roadbed and guides bed course,
The elastic-plastic materials such as the foam of such as thick D/6~D/4, then carry out embankment construction, on bed course, roadbed block or granule have sinking to become
Gesture but run into bed course and hinder, periphery roadbed can produce top roadbed block or the holding power of granule, and self-assembling formation soil encircles, soil
Arch upper load is transferred to neighbouring roadbed and undertakes, and the equation of equilibrium of pipe culvert top, the most buried garden roadbed is as follows:
P1cosα1+P2cosα2+ T=W (1.4)
In formula (1.4), mutual holding power between P1, P2 roadbed block or granule;W roadbed gravity;T garden
Pipe culvert top roadbed pressure (pressure T is the least for roadbed).
Therefore, the garden rectangular distribution of pipe culvert design load is similar to the distribution of slump body, its top more than garden pipe culvert actual loading
Load transfer undertakes to neighbouring roadbed, and so no matter shallow embedding or buried garden pipe culvert stress are all within safety range, and garden pipe culvert is not
Can ftracture.The most buried garden pipe culvert actual loading
PActual=D/2 × D (1.5)
Wherein H approximates D/2, much smaller than the above height of embankment in pipe culvert top, garden;
Obviously PActual< PDesign (1.6)
So part embankment load transfer undertakes to neighbouring roadbed, and buried garden pipe culvert will not produce crack naturally.
It addition, soil arch guides the two ends of bed course to extend respectively to the two ends of pipe culvert horizontal direction external diameter, the most half moon-shaped
Two acute angles lay respectively at the point of intersection of pipe culvert outer wall and the horizontal plane through the center of circle.Applicant finds under study for action, if native
Arch guides the two ends of bed course not extend to the two ends of pipe culvert horizontal direction external diameter, and the actual loading formed can be greatly increased.
Still being acted on by trapezoidal load on the section tubular wall of bed course because guiding for overburden soil arch, may be led under part extreme case
Cause actual loading still more than design load, cause pipe culvert to ftracture.
As preferably, described soil arch guides thickness thickness is garden pipe culvert internal diameter the 1/6~1/4 of bed course.
As preferably, described soil arch guides the elastic properties of materials of bed course need to meet following condition: buried garden pipe culvert designs lotus
When loading capacity acts on meniscus elastoplasticity subgrade soils arch guiding bed course, the soil arch caused guides bed course compression little
In 20%.
Above-mentioned soil arch guides the thickness of bed course and aeroelastic requirements to be all that applicant is obtained through lot of experiments, buried garden
The thickness of pipe culvert and compression all can affect the actual loading transfer amount that it is above-mentioned.Actual loading to be made is formed such as Fig. 1 (b)
Load mode, when design load weight acts on meniscus elastoplasticity subgrade soils arch guiding bed course, the compression caused
Must be not more than 20%, otherwise, bed course compression is excessive, and bed course cannot preferably encircle by self-assembling formation soil, therefore its transfer road
The effect of base upper design load is the most poor, still may can produce the load mode of similar Fig. 1 (a) so that actual lotus
Load is likely larger than design load, is likely to result in buried garden pipe culvert cracking.Elastic-plastic material can use foam, it is possible to uses other to have
The current material of flexible deformation nature.
As preferably, described step 1) before need, according to measuring roadbed scope, to clear up foundation surface foreign material.
As preferably, described soil arch guides bed course to be bilateral symmetry.Can keep under symmetrical state as far as possible
Pipe culvert accept uniformity, prevent its long-term pressurized irregular cause cracking.
As preferably, described step 1) in, the roadbed thickness that every layer is filled is 50cm.
As preferably, described step 6) in, the roadbed thickness that every layer is rolled is 50cm.
The present invention guides bed course by arranging half moon-shaped soil arch on pipe culvert so that carry out embankment construction, bed course again
Upper roadbed block or granule have sinking tendency but run into bed course and hinder, and periphery roadbed can produce top roadbed block or granule
Holding power, self-assembling formation soil encircles, and soil arch upper load is transferred to neighbouring roadbed and undertakes.The garden rectangular distribution of pipe culvert design load
Being similar to the distribution of slump body more than garden pipe culvert actual loading, its upper load is transferred to neighbouring roadbed and undertakes, it is ensured that garden pipe culvert stress
Less than design load and within being in safety range, prevent cracking.
Detailed description of the invention
With detailed description of the invention the present invention it is further elaborated below in conjunction with the accompanying drawings and illustrates.In the present invention, each is implemented
The technical characteristic of mode, on the premise of not colliding with each other, all can carry out respective combination.
A kind of construction method of mountain highway buried garden pipe culvert control critical eigenvalue, step is as follows:
(1) cleaning foundation surface foreign material;
According to measuring roadbed scope, clearing up foundation surface foreign material, such as table soil, vegetation etc., prepare for filling roadbed.
(2) placement in layers roadbed is to garden pipe culvert overhead height;
According to roadbed code requirement every 50cm thickness layered rolling, filling roadbed to garden pipe culvert top design height.
(3) garden pipe culvert scope excavation roadbed and ground are to garden pipe culvert substrate designed elevation;
(4) pour garden pipe culvert substrate by design requirement, and carry out maintenance by specification;
(5) by design requirement, prefabricated garden pipe culvert, layering Bu Tian garden pipe culvert periphery roadbed, and hand compaction are installed.
(6) according to formula (1.4), by the form of Fig. 2, at pipe culvert top, buried garden, patch outer wall arranges symmetrical in newly
The soil arch of month shape guides bed course.Soil arch guide bed course use thickness thickness be the foam of D/6~D/4 as elastic-plastic material,
Process the crescent consistent with pipe culvert external diameter in internal diameter, thus can be covered in pipe culvert top.The concrete thickness of bed course regards top
Depending on portion's overlying soil, basic demand is that design load weight acts on meniscus elastoplasticity subgrade soils arch guiding bed course
Time, the compression caused must be not more than 20%.Half moon-shaped soil arch guides the two ends of bed course to extend to outside pipe culvert level
The two ends in footpath, in order to form the symmetrical actual loading soil arch shown in Fig. 1 (b), be otherwise likely to occur the unbalance loading shown in Fig. 1 (a) existing
As, it is likely to result in pipe culvert cracking.
(7) according to roadbed code requirement every 50cm thickness layered rolling, filling roadbed to designed elevation;Due to pipe culvert top, garden
Roadbed arranges formation soil arch and guides bed course, and its upper load is transferred to neighbouring roadbed and undertakes, rectangular point of garden pipe culvert design load
Cloth is similar to the distribution of slump body more than garden pipe culvert actual loading, so regardless of shallow embedding or buried garden pipe culvert stress all safety range it
In, garden pipe culvert will not ftracture.
Above-mentioned construction method is applied in the construction of certain railway division, the pipe culvert top, buried garden in this section is provided with
After above-mentioned soil arch guides bed course, within the use time of nearly 20 years, the most there is not crack in garden pipe culvert.Thus may certify that, this
Bright arranges the actual loading that soil arch guides the method for bed course can effectively reduce pipe culvert top, thus reduces its cracking wind
Danger.
Embodiment described above is the one preferably scheme of the present invention, and so it is not intended to limiting the invention.Have
Close the those of ordinary skill of technical field, without departing from the spirit and scope of the present invention, it is also possible to make various change
Change and modification.The technical scheme that the most all modes taking equivalent or equivalent transformation are obtained, all falls within the guarantor of the present invention
In the range of protecting.