CN106088603A - A kind of construction method of cast-in-place concrete building structure - Google Patents

A kind of construction method of cast-in-place concrete building structure Download PDF

Info

Publication number
CN106088603A
CN106088603A CN201610596509.6A CN201610596509A CN106088603A CN 106088603 A CN106088603 A CN 106088603A CN 201610596509 A CN201610596509 A CN 201610596509A CN 106088603 A CN106088603 A CN 106088603A
Authority
CN
China
Prior art keywords
post
enclosure wall
wall
concrete
shear wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610596509.6A
Other languages
Chinese (zh)
Inventor
张晶廷
张喜臣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610596509.6A priority Critical patent/CN106088603A/en
Publication of CN106088603A publication Critical patent/CN106088603A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The invention discloses the construction method of a kind of cast-in-place concrete building structure, belong to field of house buildings, method includes: A, installation stress shear wall/post and the template of enclosure wall, assembling reinforcement;B, stress shear wall/post fills dividing plate with the connection part of templates of enclosure wall;C, the connection reinforcing bar of stress shear wall/post and enclosure wall is set;D, first pour enclosure wall with lightweight concrete, then pour stress shear wall/post with normal concrete, or pour simultaneously, wherein, bottom the casting position of lightweight concrete and structure beam body between leave the headspace of plastic foamboard;In E, headspace, paving is for the reinforcing bar of the plastic foamboard of structure sediment, stitch structure beam body and stress shear wall/intercolumniation;F, pouring structure beam body;G, form removal.The present invention first pours into a mould the concrete of enclosure wall, then pours into a mould the concrete of stress shear wall/post, or pours into a mould simultaneously, it is achieved that construction industrialization, improves the overall performance in house, add anti-seismic performance, reduces construction costs, shortens the duration.

Description

A kind of construction method of cast-in-place concrete building structure
Technical field
The invention belongs to building construction technology field, relate to the construction method of a kind of building structure, specifically one The construction method of cast-in-place concrete building structure.
Background technology
Concrete frame structure engineering at present, is all first construction stress shear wall or frame part, form removal during construction After fill enclosure wall part, complex procedures, labor intensive with light block or lightweight template die again, extend the duration, these blocks resist Shake ability, after some employing frameworks complete, secondary formwork pours into a mould enclosure wall, causes claim for eot and main body to connect the feelings such as bad Condition.
Summary of the invention
The present invention, in order to overcome existing technological deficiency, devises the construction method of a kind of cast-in-place concrete building structure, This method first pours into a mould the concrete of enclosure wall, then pours into a mould the concrete of stress shear wall, or two kinds of concrete are poured into a mould simultaneously, change Become original first construction stress shear wall, the method building enclosure wall after form removal again by laying bricks or stones, it is achieved that construction industrialization, improve The overall performance in house, add anti-seismic performance, reduce construction costs, shorten the duration.
The concrete technical scheme that the present invention is taked is: the construction method of a kind of cast-in-place concrete building structure, this method Including stress shear wall/post and the construction of enclosure wall, it is important to: this method be with prefabricated simultaneously support stress shear wall/post and The template of enclosure wall, based on the dividing plate operation of precast stressed shear wall/between post and enclosure wall, on this basis, we Method step includes:
A, stress shear wall/post and the template of enclosure wall are installed, and assembling reinforcement is fixed;
B, dividing plate is installed at the connection part of templates of stress shear wall/post and enclosure wall and fixes;
C, the connection reinforcing bar of stress shear wall/post and enclosure wall is set;
D, the first lightweight concrete pouring enclosure wall in the template of enclosure wall, then pour stress shear wall/post, or, Pour enclosure wall and the concrete of stress shear wall/post simultaneously;
Reinforcing bar between E, binding structure beam body and stress shear wall/post;
F, pouring structure beam body;
G, form removal.
Can install in plastic foamboard, i.e. step D for the beam that deflection is bigger, pouring of the lightweight concrete of enclosure wall Position is-25~-15mm place bottom distance structure beam body, lays plastic foamboard in this space of-25~-15mm.
Preferably, in step D, the casting position of the lightweight concrete of enclosure wall is-20mm place bottom distance structure beam body, Correspondingly, in the space of-20mm, plastic foamboard is laid.
In step D, lightweight concrete is the lightweight aggregate concrete less than 800 kilograms/cube or foamed concrete.
The longitudinal direction height of described plastic foamboard is 20mm, and density is no less than 18kg/m3
The width of described plastic foamboard is less than the width of enclosure wall, and is reserved with Concrete Filled away from enclosure wall both sides Space.
The thickness in described Concrete Filled space is 20mm.
The invention has the beneficial effects as follows: 1, the present invention changes traditional building structure order, and will be traditional first pour is subject to The concrete of power shear wall is built enclosure wall again by laying bricks or stones or waters the construction process of lightweight concrete again, is changed to first pour the mixed of enclosure wall The building new method that solidifying soil pours the concrete of stress shear wall again or both concrete pour simultaneously, this construction method realizes Construction industrialization, improves the overall performance in house, reduces construction costs, shorten the duration;2, by stress in the present invention Shear wall part separates with enclosure wall body of wall dividing plate, is difficult to the stress shear wall occurring causing because of stress shear wall sedimentation and deformation Problem with the gaping of joints of enclosure wall;3, plastic foamboard absorbing structure deflection, and foam plastics is inside body of wall, becomes Shape is difficult to discover, and plastic foamboard, than enclosure wall both sides narrow 20mm respectively, this space fill concrete, deforms in body of wall large scale Time broken, prevent the problem that stress shear wall directly contacts the enclosure wall damage caused with enclosure wall;4, entirety after house builds up Property is good, and the enclosure wall of the building block pile before comparing, this method lower stress shear wall, enclosure wall planarization are good, in fitment process Need not plaster leveling, only need to scrape DABAI, save decoration cost, it is achieved that the industrialization in integral cast-in-situ house.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of step A in the present invention;
Fig. 2 is the schematic diagram of step B in the present invention;
Fig. 3 is the schematic diagram of step C in the present invention;
Fig. 4 is the schematic diagram of step D in the present invention;
Fig. 5 is the schematic diagram of step E in the present invention;
Fig. 6 is the schematic diagram of step F in the present invention;
In accompanying drawing, 1 is stress shear wall/post, and 2 is enclosure wall, and 3 is dividing plate, and 4 is plastic foamboard, and 5 is structure beam body.
Detailed description of the invention
Below in conjunction with the accompanying drawings the present invention is elaborated:
Embodiment 1, pours explanation as a example by the concrete of stress shear wall again by the concrete first pouring enclosure wall.
Seeing accompanying drawing 1-6, this method includes stress shear wall/post 1 and the construction of enclosure wall 2, and this method is with prefabricated same Time support stress shear wall/post 1 and the template of enclosure wall 2, the dividing plate 3 of precast stressed shear wall/between post and enclosure wall, in advance Based on the operation of plastic foamboard 4 processed, on this basis, this method step includes:
A, stress shear wall/post 1 and the template of enclosure wall 2 are installed, and assembling reinforcement is fixed, and specifically can be found in Fig. 1;
B, dividing plate 3 it is installed at the connection part of templates of stress shear wall/post and enclosure wall and fixes, seeing Fig. 2;
C, stress shear wall/post 1 connection reinforcing bar with enclosure wall 2 is set, sees Fig. 3;
D, first pour in the template of enclosure wall with lightweight aggregate concrete or the foamed concrete less than 800 kilograms/cube Enclosure wall 2, bottom the casting position of concrete and structure beam body 5 between leave-25~-15mm, the foam plastic of preferably-20mm The headspace of flitch 4, sees Fig. 4;
E, in headspace, lay 15~25mm high density no less than 18kg/m3Plastic foamboard 4, accordingly, Plastic foamboard 4 high for preferably 20mm the reinforcing bar of binding structure beam body, see Fig. 5, wherein, and described plastic foamboard 4 Length is less than the length of enclosure wall 2, and is reserved with Concrete Filled space away from enclosure wall 2 both sides;
F, pour stress shear wall/post 1 and structure beam body 5, see Fig. 6;
G, form removal.
Embodiment 2: explanation as a example by the concrete of the concrete simultaneously pouring enclosure wall and stress shear wall.
A kind of construction method of cast-in-place concrete building structure, it is important to: this method is prefabricated support stress shearing simultaneously Wall/post 1 and the template of enclosure wall 2, the dividing plate 3 of precast stressed shear wall/between post 1 and enclosure wall 2, preformed foam plastic plate 4 Operation based on, on this basis, this method step includes:
A, stress shear wall/post 1 and the template of enclosure wall 2 are installed, and assembling reinforcement is fixed;
B, dividing plate 3 is installed at the connection part of templates of stress shear wall/post 1 and enclosure wall 2 and fixes;
C, stress shear wall/post 1 connection reinforcing bar with enclosure wall 2 is set;
D, first pour in the template of enclosure wall 2 with lightweight aggregate concrete or the foamed concrete less than 800 kilograms/cube While enclosure wall 2, pour stress shear wall/post 1, wherein, bottom the casting position of concrete and structure beam body 5 between stay Having-25~-15mm, the headspace of the plastic foamboard 4 of preferably-20mm, if the less beam of deflection can be not provided with The headspace of this plastic foamboard 4;
E, in headspace, lay 15~25mm high density no less than 18kg/m3Plastic foamboard 4, accordingly, Plastic foamboard 4 high for preferably 20mm the reinforcing bar between binding structure beam body and stress shear wall/post 1, see Fig. 5, its In, the length of described plastic foamboard 4 is less than the width of enclosure wall 2, and be reserved with Concrete Filled away from enclosure wall 2 both sides empty Between, and casting concrete in this Concrete Filled space, if this foam plastics can not be installed for the beam that deflection is less Plate;
F, pouring structure beam body 5;
G, form removal.
The present invention first pours into a mould the lightweight concrete of enclosure wall 2, then pours into a mould the concrete of stress shear wall/post 1, or simultaneously Cast, changes original first construction stress shear wall/post 1, the method building enclosure wall 2 after form removal again by laying bricks or stones, it is achieved that construction Industrialization, improve the overall performance in house, add anti-seismic performance, reduce construction costs, shorten the duration.

Claims (7)

1. a construction method for cast-in-place concrete building structure, this method includes stress shear wall/post (1) and enclosure wall (2) Construction, it is characterised in that: this method is with prefabricated stress shear wall/post (1) and the template of enclosure wall (2) of supporting simultaneously, in advance Based on dividing plate (3) operation of stress shear wall processed/between post and enclosure wall, on this basis, this method step includes:
A, stress shear wall/post (1) and the template of enclosure wall (2) are installed, and assembling reinforcement is fixed;
B, dividing plate (3) is installed at the connection part of templates of stress shear wall/post and enclosure wall and fixes;
C, the connection reinforcing bar of stress shear wall/post and enclosure wall is set;
D, the first lightweight concrete (2) pouring enclosure wall in the template of enclosure wall, then pour stress shear wall/post (1), or Person, pours enclosure wall (2) and the concrete of stress shear wall/post (1) simultaneously;
Reinforcing bar between E, binding structure beam body (5) and stress shear wall/post (1);
F, pouring structure beam body (5);
G, form removal.
The construction method of a kind of cast-in-place concrete building structure the most according to claim 1, it is characterised in that: in step D, The casting position of the lightweight concrete of enclosure wall be distance structure beam body (5) bottom-25~-15mm place, this-25~-15mm Space in lay plastic foamboard.
The construction method of a kind of cast-in-place concrete building structure the most according to claim 2, it is characterised in that: in step D, The casting position of the lightweight concrete of enclosure wall is-20mm place, distance structure beam body (5) bottom, correspondingly, in the space of-20mm Interior laying plastic foamboard.
The construction method of a kind of cast-in-place concrete building structure the most according to claim 1, it is characterised in that: in step D, Lightweight concrete is the lightweight aggregate concrete less than 800 kilograms/cube or foamed concrete.
The construction method of a kind of cast-in-place concrete building structure the most according to claim 3, it is characterised in that: described foam The longitudinal direction height of plastic plate (4) is 20mm, and density is no less than 18kg/m3
The construction method of a kind of cast-in-place concrete building structure the most according to claim 1, it is characterised in that: described bubble The width of foam plastic plate (4) is less than the width of enclosure wall, and is reserved with Concrete Filled space away from enclosure wall (2) both sides.
The construction method of a kind of cast-in-place concrete building structure the most according to claim 6, it is characterised in that: described is mixed The thickness of solidifying soil packing space is 20mm.
CN201610596509.6A 2016-07-27 2016-07-27 A kind of construction method of cast-in-place concrete building structure Pending CN106088603A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610596509.6A CN106088603A (en) 2016-07-27 2016-07-27 A kind of construction method of cast-in-place concrete building structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610596509.6A CN106088603A (en) 2016-07-27 2016-07-27 A kind of construction method of cast-in-place concrete building structure

Publications (1)

Publication Number Publication Date
CN106088603A true CN106088603A (en) 2016-11-09

Family

ID=57448802

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610596509.6A Pending CN106088603A (en) 2016-07-27 2016-07-27 A kind of construction method of cast-in-place concrete building structure

Country Status (1)

Country Link
CN (1) CN106088603A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107587630A (en) * 2017-09-05 2018-01-16 山东绿昱建筑科技有限公司 A kind of lightweight aggregate partition wall and its with main body simultaneously construction technology
CN111335490A (en) * 2020-03-13 2020-06-26 山西四建集团有限公司 Crack-resistant structure at joint of filler wall and shear wall under full-concrete outer wall window and construction method of crack-resistant structure
CN114352017A (en) * 2022-02-17 2022-04-15 合肥建工集团有限公司 Full cast-in-place outer wall construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1994006976A1 (en) * 1992-09-11 1994-03-31 Woolhouse International Limited Method and apparatus for improving sound insulation
EP0625617A1 (en) * 1993-05-19 1994-11-23 C.A.E.C. HOWARD (HOLDINGS) Ltd. Insulating strip and method
CN101476360A (en) * 2009-01-20 2009-07-08 北京交通大学 Novel energy-consumption shock-absorbing filling wall board used for frame structure
CN101812882A (en) * 2009-06-15 2010-08-25 黑龙江宇辉新型建筑材料有限公司 Concrete shear wall with once-molded filling wall and manufacturing method thereof
CN103243837A (en) * 2013-05-23 2013-08-14 石家庄晶达建筑体系有限公司 Construction and construction method exclusively used in composite shear wall structure filler wall
CN103469939A (en) * 2013-09-24 2013-12-25 中国建筑第二工程局有限公司 Flexible connection anti-seismic structure for masonry infilled wall and main body, and construction method for flexible connection anti-seismic structure
CN104831829A (en) * 2015-05-11 2015-08-12 孟凡林 Integrated prefabrication method for connecting concrete shear wall and filler wall

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1994006976A1 (en) * 1992-09-11 1994-03-31 Woolhouse International Limited Method and apparatus for improving sound insulation
EP0625617A1 (en) * 1993-05-19 1994-11-23 C.A.E.C. HOWARD (HOLDINGS) Ltd. Insulating strip and method
CN101476360A (en) * 2009-01-20 2009-07-08 北京交通大学 Novel energy-consumption shock-absorbing filling wall board used for frame structure
CN101812882A (en) * 2009-06-15 2010-08-25 黑龙江宇辉新型建筑材料有限公司 Concrete shear wall with once-molded filling wall and manufacturing method thereof
CN103243837A (en) * 2013-05-23 2013-08-14 石家庄晶达建筑体系有限公司 Construction and construction method exclusively used in composite shear wall structure filler wall
CN103469939A (en) * 2013-09-24 2013-12-25 中国建筑第二工程局有限公司 Flexible connection anti-seismic structure for masonry infilled wall and main body, and construction method for flexible connection anti-seismic structure
CN104831829A (en) * 2015-05-11 2015-08-12 孟凡林 Integrated prefabrication method for connecting concrete shear wall and filler wall

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107587630A (en) * 2017-09-05 2018-01-16 山东绿昱建筑科技有限公司 A kind of lightweight aggregate partition wall and its with main body simultaneously construction technology
CN111335490A (en) * 2020-03-13 2020-06-26 山西四建集团有限公司 Crack-resistant structure at joint of filler wall and shear wall under full-concrete outer wall window and construction method of crack-resistant structure
CN114352017A (en) * 2022-02-17 2022-04-15 合肥建工集团有限公司 Full cast-in-place outer wall construction method
CN114352017B (en) * 2022-02-17 2024-02-09 合肥建工集团有限公司 Full cast-in-situ exterior wall construction method

Similar Documents

Publication Publication Date Title
CN105926803B (en) A kind of 3D printing reinforced masonry shear wall structure with concave convex texture
CN207616844U (en) Foundation platform precast concrete side form and molding machine
CN106193292A (en) A kind of steel frame assembled integral reinforced concrete shear wall structure system
CN104631677A (en) Construction technology for hollow super-thick concrete terrace
CN106088603A (en) A kind of construction method of cast-in-place concrete building structure
CN102619330B (en) Hollow building roof system GBF pipe anti-floating positioning construction method
CN104295003A (en) Structural column construction method
CN102400513B (en) Fireproof cast-in-place hollow floor system
CN207110214U (en) A kind of prefabricated interior fill concrete wallboard
CN105756377B (en) A kind of swimming pool and its construction method
CN107237448B (en) The prefabricated interior fill concrete wallboard of one kind and its manufacturing method
JP2004232328A (en) Structure of half precast type arch culvert and its construction method
CN215106098U (en) Prefabricated post connection structure
CN106930391B (en) Cast-in-place drainage channel structure of top plate for formwork-free construction and construction method
CN105064500A (en) Balcony beam slab inner side filling wall body and main body structure integral casting construction method
JP7232714B2 (en) how to build a foundation
CN102400510B (en) Hollow floor system made of steel bar and foam combined filled member
CN205637707U (en) Swimming pool
CN108193706A (en) A kind of downward construction concrete pouring procedure of part contrary sequence method vertical structure
CN104234432B (en) Shed deckhead construction method
CN107288028B (en) Large volume concrete structural and its construction method
JP6986803B1 (en) Retaining wall structure and how to build a retaining wall
CN110748221A (en) Prefabricated assembled pond guide wall
CN110076877A (en) Building site enclosing prefabricated foundation and its construction method
JPH0657768A (en) Retaining wall structure and working method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161109