CN106087987A - A kind of expansion steel reinforcement cage - Google Patents

A kind of expansion steel reinforcement cage Download PDF

Info

Publication number
CN106087987A
CN106087987A CN201610657077.5A CN201610657077A CN106087987A CN 106087987 A CN106087987 A CN 106087987A CN 201610657077 A CN201610657077 A CN 201610657077A CN 106087987 A CN106087987 A CN 106087987A
Authority
CN
China
Prior art keywords
steel reinforcement
reinforcement cage
muscle
stretching
extension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610657077.5A
Other languages
Chinese (zh)
Inventor
胡勇
李云安
周春华
王博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Geosciences
Original Assignee
China University of Geosciences
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Geosciences filed Critical China University of Geosciences
Priority to CN201610657077.5A priority Critical patent/CN106087987A/en
Publication of CN106087987A publication Critical patent/CN106087987A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

The present invention relates to building field, it is specifically related to a kind of expansion steel reinforcement cage, including main muscle and stirrup, described stirrup being hinged with stretching, extension muscle, described stretching, extension muscle includes, extension section and linkage section, described linkage section is arranged on the root stretching muscle, and described extension section stretches to the outside of described steel reinforcement cage cage body, and described stretching, extension muscle is hinged on stirrup by linkage section, it is provided with fake in described extension section, is provided with in fake to tie up the rope stretching muscle.

Description

A kind of expansion steel reinforcement cage
Technical field
The present invention relates to building field, be specifically related to a kind of expansion steel reinforcement cage.
Background technology
Pilework is base structure commonly used in the buildings such as house, highway, bridge and harbour.Wherein, friction pile is The frictional resistance relying on stake side supports the stake of vertical load, and from the point of view of the principle of friction pile, pile side friction removes the character with soil, executes Outside the Pass work technique, material of body of a pile etc. have, also directly related with the concaveconvex shape of stake cross-sectional circumference girth and stake side surface.And it is conventional The cross sectional shape of reinforced concrete pile is along being longitudinally constant, and cross sectional shape is also the most square or circular, so, and conventional steel If reinforced concrete friction pile to obtain higher vertical bearing capacity, only by increasing, stake is long improves side friction.But, Stake long can not arbitrarily increase, because construction costs is not only significantly increased, and stake is long is limited by slenderness ratio in relevant design specification System.Such as, disclosed in CN104179174A, a kind of multiple holes grouting pipe shaped pile, arranges injected hole at pile tube sidewall, by concrete Overflow formation Seed harvest from injected hole and improve the coefficient of friction of sidewall, thus improve frictional resistance, but, this Seed harvest does not contains Having reinforcing bar, Seed harvest is more crisp, is susceptible to fracture, thus affects the load performance of stake under high intensity pressure.
Summary of the invention
The purpose of the present invention, is the problem in order to solve in background technology, it is provided that a kind of expansion steel reinforcement cage.
The above-mentioned technical purpose of the present invention has the technical scheme that
A kind of expansion steel reinforcement cage, including main muscle and stirrup, described stirrup is hinged with stretching, extension muscle, and described stretching, extension muscle includes, outward The section of prolonging and linkage section, described linkage section is arranged on the root stretching muscle, and described extension section stretches to the outside of described steel reinforcement cage cage body, Described stretching, extension muscle is hinged on stirrup by linkage section, described extension section is provided with fake, is provided with to tie up in fake Stretch the rope of muscle.
As preferably, described stretching, extension muscle forms multiple stretching, extension muscle group along the circumferential array of steel reinforcement cage, and described stretching, extension muscle group exists If steel reinforcement cage be axially arranged in dried layer.
As preferably, one end of described rope is provided with stopper, and described stopper is provided with draw-string, described rope The other end sequentially passes through every layer of fake stretched in muscle group.
As preferably, described linkage section includes arch steel and the part lengths of rebar of described stretching, extension muscle root, described arc Two end points of reinforcing bar are separately fixed at the two ends of described lengths of rebar so that linkage section forms the annular region of Guan Bi.
As preferably, described linkage section is a split ring.
As preferably, described linkage section is spiral type.
As preferably, described in be provided with described stretching, extension muscle root and be provided with the positioning section stretched into inside steel reinforcement cage cage body, institute It is provided with positioning bar in stating steel reinforcement cage.
As preferably, described positioning bar is fixed in steel reinforcement cage cage body by stirrup.
As preferably, described positioning bar is fixed on main muscle, arranges between described positioning bar and corresponding stretching, extension muscle group There is range difference.
Use the construction method of the bored concrete pile of above-mentioned steel reinforcement cage, comprised the following steps:
1, preparing steel reinforcement cage, design calculates steel reinforcement cage size, is produced by size steel reinforcement cage, and the top indicator at steel reinforcement cage stretches muscle Position, take out guy tightening, make stretching, extension muscle be adjacent to steel reinforcement cage outer surface;
2, pile hole, bores stake holes with drill bit, makes the stake holes diameter external diameter slightly larger than steel reinforcement cage;
3, open side opening, use broaching equipment, the sidewall of stake holes is offered multiple side opening, and at stake holes top indicator side opening Position and set up the absolute altitude of side opening;
4, hang steel reinforcement cage, steel reinforcement cage is hung in stake holes, rotate the position adjusting steel reinforcement cage during handling so that reinforcing bar The labelling of labelling and stake holes top side opening that muscle is stretched at the top of cage aligns, and steel reinforcement cage is hung onto by the absolute altitude of corresponding side opening Specified altitude assignment, it is ensured that the expanded position stretching muscle is consistent with side opening direction, unclamps rope, makes stretching, extension muscle be deployed in side opening;
5, casting concrete.
In sum, beneficial effects of the present invention:
A kind of expansion steel reinforcement cage the most of the present invention, arranges stretching, extension muscle at side surface, adds the friction of pile body sidewall Power, such that it is able to reduce driving depth, reduces piling construction cost.
A kind of expansion steel reinforcement cage the most of the present invention, stretches the movable property of muscle, it is not necessary to extra increase stake holes is straight Footpath, adds sidewall stress performance simultaneously.
Accompanying drawing explanation
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the use schematic diagram of the present invention;
Fig. 3 is the structure chart stretching muscle in the present invention;
Fig. 4 is the structure chart stretching muscle in the embodiment of the present invention 2;
Fig. 5 is the structure chart stretching muscle in the embodiment of the present invention 3;
Fig. 6 is the structural representation of the embodiment of the present invention 4.
Detailed description of the invention
Specific examples below is only explanation of the invention, and it is not limitation of the present invention, art technology The present embodiment can be made after reading this specification by personnel as required does not has the amendment of creative contribution, but as long as All protected by Patent Law in scope of the presently claimed invention.
With embodiment, the present invention is described in detail below in conjunction with the accompanying drawings.
Embodiment 1:
According to Fig. 1, Fig. 2, Fig. 3, a kind of expansion steel reinforcement cage, including main muscle 1 and stirrup 2, stirrup 2 is hinged with stretching, extension muscle 3, stretch muscle 3 and include, extension section 31 and linkage section 32, linkage section 32 is arranged on the root stretching muscle 3, and extension section 31 stretches to reinforcing bar The outside of cage cage body, is stretched muscle 3 and is hinged on stirrup 2 by linkage section 32, extension section 31 is provided with fake 311, fake 311 Inside it is provided with to tie up the rope 5 stretching muscle 3.
Stretching, extension muscle 3 forms multiple stretching, extension muscle group along the circumferential array of steel reinforcement cage, stretches the axial arrangement at steel reinforcement cage of the muscle group If becoming dried layer, one end of rope 5 is provided with stopper 51, and stopper 51 is provided with draw-string 52, and the other end of rope 5 is worn successively Cross every layer of fake 311 stretched in muscle group.
According to Fig. 3, linkage section 32 includes arch steel and stretches the lengths of rebar in the middle part of muscle 3, two of arch steel End points is separately fixed at the two ends of lengths of rebar so that linkage section 32 forms the annular region of Guan Bi.Stretch the preparation method of muscle 3 For: 1. by a bar bending camber;2. two end points of the arch steel after bending are welded in a straight steel bar; 3. fake 311 is welded in the one end away from linkage section 32.
Use the construction method of the bored concrete pile of above-mentioned steel reinforcement cage, comprised the following steps:
1, preparing steel reinforcement cage, design calculates steel reinforcement cage size, is produced by size steel reinforcement cage, and the manufacture method of steel reinforcement cage is: 1. make Make some stretching, extension muscle 3 stand-by;2. long reinforcing bar is placed on moulding bed location, makes main muscle 1;3. bar dowel is enclosed in main muscle 1 Outward, simultaneously by stretching the linkage section 32 of muscle 3 through on bar dowel, then being welded with main muscle 1 by bar dowel, formation stirrup 2, at steel The top indicator of muscle cage stretches the position of muscle 3, takes out guy tightening 5, makes stretching, extension muscle 3 be adjacent to steel reinforcement cage outer surface;
2, pile hole, bores stake holes with drill bit, makes the stake holes diameter external diameter slightly larger than steel reinforcement cage;
3, open side opening, use broaching equipment, the sidewall of stake holes is offered multiple side opening, and at stake holes top indicator side opening Position and set up the absolute altitude of side opening;
4, hang steel reinforcement cage, steel reinforcement cage is hung in stake holes, rotate the position adjusting steel reinforcement cage during handling so that reinforcing bar The labelling of labelling and stake holes top side opening that muscle 3 is stretched at the top of cage aligns, and steel reinforcement cage is hung by the absolute altitude of corresponding side opening To specified altitude assignment, it is ensured that the expanded position stretching muscle 3 is consistent with side opening direction, unclamps rope 5, makes stretching, extension muscle 3 be deployed into side In hole;
5, casting concrete.
Embodiment 2:
As preferably, according to Fig. 4, linkage section 32 is a split ring, the two ends of split ring respectively with extension section 31 and fixed Position section 33 is connected.The preparation method stretching muscle 3 is: take a straight steel bar, and one end therein bends to a split ring knot Structure, welds fake 311 at the other end.
Embodiment 3:
As preferably, according to Fig. 5, linkage section 32 is spiral type.The preparation method stretching muscle 3 is: take a straight steel bar, Its one end carries out twisted, and sweep forms linkage section 32, welds fake 311 at its other end.
Embodiment 4:
Supports different from above-described embodiment 1 are, according to Fig. 6, are provided with stretching, extension muscle 3 root and are provided with and stretch into steel reinforcement cage cage The positioning section 33 of internal side, is provided with positioning bar 4 in steel reinforcement cage, positioning bar 4 is fixed in steel reinforcement cage cage body by stirrup 2, fixed Position muscle 4 is fixed on main muscle 1, is provided with range difference between positioning bar 4 and corresponding stretching, extension muscle group.Controlled by positioning bar 4 System stretches the rotational angle of muscle.

Claims (9)

1. an expansion steel reinforcement cage, including main muscle (1) and stirrup (2), it is characterised in that is hinged with on described stirrup (2) and stretches Exhibition muscle (3), described stretching, extension muscle (3) includes, extension section (31) and linkage section (32), and described linkage section (32) is arranged on stretching, extension muscle (3) root, described extension section (31) stretches to the outside of described steel reinforcement cage cage body, and described stretching, extension muscle (3) passes through linkage section (32) Being hinged on stirrup (2), described extension section (31) is provided with fake (311), fake is provided with to tie up stretching, extension in (311) The rope (5) of muscle (3).
A kind of expansion steel reinforcement cage the most according to claim 2, it is characterised in that described stretching, extension muscle (3) is along steel reinforcement cage Circumferential array forms multiple stretching, extension muscle group, if described stretching, extension muscle group is axially arranged in dried layer at steel reinforcement cage.
A kind of expansion steel reinforcement cage the most according to claim 3, it is characterised in that one end of described rope (5) is provided with Stopper (51), described stopper (51) is provided with draw-string (52), and the other end of described rope (5) sequentially passes through every layer of stretching, extension Fake (311) in muscle group.
A kind of expansion steel reinforcement cage the most according to claim 3, it is characterised in that described linkage section (32) includes arc-shaped steel Muscle and the part lengths of rebar of described stretching, extension muscle (3) root, two end points of described arch steel are separately fixed at described lengths of rebar Two ends so that linkage section (32) formed Guan Bi annular region.
A kind of expansion steel reinforcement cage the most according to claim 3, it is characterised in that described linkage section (32) is an opening Ring.
A kind of expansion steel reinforcement cage the most according to claim 3, it is characterised in that described linkage section (32) is spiral type.
7. according to a kind of expansion steel reinforcement cage described in claim 4 or 5 or 6, it is characterised in that described in be provided with described stretching, extension Muscle (3) root is provided with the positioning section (33) stretched into inside steel reinforcement cage cage body, is provided with positioning bar (4) in described steel reinforcement cage.
A kind of expansion steel reinforcement cage the most according to claim 7, it is characterised in that described positioning bar (4) passes through stirrup (2) It is fixed in steel reinforcement cage cage body.
A kind of expansion steel reinforcement cage the most according to claim 7, it is characterised in that described positioning bar (4) is fixed on main muscle (1), on, between described positioning bar (4) and corresponding stretching, extension muscle group, it is provided with range difference.
CN201610657077.5A 2016-08-12 2016-08-12 A kind of expansion steel reinforcement cage Pending CN106087987A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610657077.5A CN106087987A (en) 2016-08-12 2016-08-12 A kind of expansion steel reinforcement cage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610657077.5A CN106087987A (en) 2016-08-12 2016-08-12 A kind of expansion steel reinforcement cage

Publications (1)

Publication Number Publication Date
CN106087987A true CN106087987A (en) 2016-11-09

Family

ID=57457065

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610657077.5A Pending CN106087987A (en) 2016-08-12 2016-08-12 A kind of expansion steel reinforcement cage

Country Status (1)

Country Link
CN (1) CN106087987A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108049400A (en) * 2018-01-19 2018-05-18 中水北方勘测设计研究有限责任公司 For increasing the spiral shape reinforcing body of mixing pile intensity
CN108411904A (en) * 2018-05-09 2018-08-17 山东建筑大学 Large-scale karst strata partial stowage armored concrete cloth bag pilework and technique
CN110904952A (en) * 2019-12-04 2020-03-24 大成科创基础建设股份有限公司 Horizontal bearing reinforcement for soft soil foundation filling pile

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201598633U (en) * 2010-03-03 2010-10-06 东南大学 Drilling cast-in-place pile
CN102061699A (en) * 2010-12-02 2011-05-18 上海城建(集团)公司 Reinforcing bar of bottom-reamed bored pile and construction method thereof
CN202081419U (en) * 2011-05-26 2011-12-21 中国建筑第七工程局有限公司 Squeezed branch pile
CN103161154A (en) * 2013-04-15 2013-06-19 合肥建工集团有限公司 Distribution and application of pile foundation well squeezed bearing disk steel bars
CN104674791A (en) * 2013-11-28 2015-06-03 上海尧华科技发展有限公司 Collapse prevention steel reinforcement cage
CN205990617U (en) * 2016-08-12 2017-03-01 中国地质大学(武汉) A kind of expansion steel reinforcement cage

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201598633U (en) * 2010-03-03 2010-10-06 东南大学 Drilling cast-in-place pile
CN102061699A (en) * 2010-12-02 2011-05-18 上海城建(集团)公司 Reinforcing bar of bottom-reamed bored pile and construction method thereof
CN202081419U (en) * 2011-05-26 2011-12-21 中国建筑第七工程局有限公司 Squeezed branch pile
CN103161154A (en) * 2013-04-15 2013-06-19 合肥建工集团有限公司 Distribution and application of pile foundation well squeezed bearing disk steel bars
CN104674791A (en) * 2013-11-28 2015-06-03 上海尧华科技发展有限公司 Collapse prevention steel reinforcement cage
CN205990617U (en) * 2016-08-12 2017-03-01 中国地质大学(武汉) A kind of expansion steel reinforcement cage

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108049400A (en) * 2018-01-19 2018-05-18 中水北方勘测设计研究有限责任公司 For increasing the spiral shape reinforcing body of mixing pile intensity
CN108411904A (en) * 2018-05-09 2018-08-17 山东建筑大学 Large-scale karst strata partial stowage armored concrete cloth bag pilework and technique
CN108411904B (en) * 2018-05-09 2023-10-17 中铁十四局集团建筑工程有限公司 Reinforced concrete cloth bag pile structure for local filling of large karst stratum and process
CN110904952A (en) * 2019-12-04 2020-03-24 大成科创基础建设股份有限公司 Horizontal bearing reinforcement for soft soil foundation filling pile

Similar Documents

Publication Publication Date Title
WO2020238501A1 (en) Full-assembly pressure-bearing type variable-diameter steel cage expansion head anchor rod pile system
US9739027B2 (en) Perimeter pile anchor foundation
CN106760219A (en) A kind of reducing steel reinforcement cage and its enlarging anchor rod or pile foundation
CN106400787B (en) The construction method of bored concrete pile is made of extended position double steel bar cage
CN103882798B (en) The reinforced concrete arch bridge of the powerful skeleton of a kind of concrete filled steel tube and construction method thereof
CN106400783B (en) The construction method of bored concrete pile is made of expansion steel reinforcement cage
CN206736901U (en) A kind of anchor pole or pile foundation variable diameters steel reinforcement cage
WO2018205702A1 (en) Variable-diameter reinforcing cage for anchor rod or pile foundation
CN106087987A (en) A kind of expansion steel reinforcement cage
CN106400784B (en) The construction method of bored concrete pile is made of filling pile cage of reinforcement
CN103233464A (en) Manual hole digging pile and construction method thereof
CN205223839U (en) Bridge prefabrication stand and prefabricated bent cap slot -in type connection structure
CN107489144B (en) Reinforcing tubular pile
CN107916664B (en) The construction method of bored concrete pile is made of rotation expansion formula steel reinforcement cage
CN206521873U (en) A kind of reducing steel reinforcement cage and its enlarging anchor rod or pile foundation
CN105178324B (en) Construction device for umbrella tray type special-shaped pile
CN104563103A (en) Composite-reinforcement partially-prestressed concrete solid square pile and production method thereof
CN205990617U (en) A kind of expansion steel reinforcement cage
CN205954615U (en) Extension formula double -layer steel muscle cage
CN204401627U (en) To pull-type prestressed pipe pile pit supporting construction
CN106087986A (en) A kind of filling pile cage of reinforcement
CN208701693U (en) The concrete-steel strand cage of deep basal pit pre-stressing force cantilever support pile
RU176898U1 (en) Hollow screw pile
CN207228108U (en) A kind of novel enhanced pile pile
CN104532852A (en) Opposite-pull type prestressed pipe pile foundation pit supporting structure and mounting method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161109

RJ01 Rejection of invention patent application after publication