CN106087973B - Lattice diaphram wall arrangement - Google Patents

Lattice diaphram wall arrangement Download PDF

Info

Publication number
CN106087973B
CN106087973B CN201610606298.XA CN201610606298A CN106087973B CN 106087973 B CN106087973 B CN 106087973B CN 201610606298 A CN201610606298 A CN 201610606298A CN 106087973 B CN106087973 B CN 106087973B
Authority
CN
China
Prior art keywords
wall
shaped connector
longitudinal direction
longitudinal
steel reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610606298.XA
Other languages
Chinese (zh)
Other versions
CN106087973A (en
Inventor
孔科
王小波
汤雷
雷运华
相昆山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201610606298.XA priority Critical patent/CN106087973B/en
Publication of CN106087973A publication Critical patent/CN106087973A/en
Application granted granted Critical
Publication of CN106087973B publication Critical patent/CN106087973B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/185Bulkheads or similar walls made solely of concrete in situ with flexible joint members between sections
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0046Foams

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

The present invention relates to a kind of lattice diaphram wall arrangement.The present invention includes longitudinal wall and horizontal wall, the axis of longitudinal wall is perpendicular to primary load direction, the axis of horizontal wall is identical with primary load direction, longitudinal wall includes inner side longitudinal direction wall, outside longitudinal direction wall, the longitudinal wall in one end connection inner side, the longitudinal wall in other end connection outside of horizontal wall, inner side longitudinal direction wall is being provided with u shaped connector towards the side of outside longitudinal direction wall, u shaped connector insertion inner side longitudinal direction is within the walls, and the steel reinforcement cage with inner side longitudinal direction within the walls is fixedly connected, in the cell body of the end insertion u shaped connector of horizontal wall, and laterally steel reinforcement cage within the walls is fixedly connected with u shaped connector;Outside longitudinal direction wall is being provided with the second u shaped connector towards the side of inner side longitudinal direction wall, second u shaped connector insertion outside longitudinal direction is within the walls, and the steel reinforcement cage with outside longitudinal direction within the walls is fixedly connected, the end of horizontal wall is embedded in the cell body of the second u shaped connector, and laterally steel reinforcement cage within the walls is fixedly connected with the second u shaped connector.

Description

Lattice diaphram wall arrangement
Technical field
The present invention relates to a kind of lattice diaphram wall arrangement, belong to Hydraulic and Hydro-Power Engineering and building engineering construction Field.
Background technology
Diaphram wall has that geological conditions strong adaptability, barrier performance are good, work efficiency is high, short time limit, reliable in quality, economy High efficiency, environment influence the advantages that small, are widely used at present in hydroelectric project as leakage preventing structure, in work China Democratic National Construction Association and bridge tunnel work Mainly as foundation pit safeguard structure in journey.In Hydraulic and Hydro-Power Engineering, open caisson is widely used as load-bearing and anti-washing structure, but its is steady The problems such as qualitative, economy and difficulty of construction, protrudes, using open caisson handle deep alluvion foundation the defects of clearly.In view of The unique advantage of diaphram wall and the good three-dismensional effect of lattice diaphram wall, lattice diaphram wall is increasingly It is used as Anti-scouring structure and bearing structure more.Existing construction technology is limited by, in length and breadth the structural type of wall boundary position Formula and form of construction work are always to perplex the problem of engineering circles.The structural shape of existing lattice diaphram wall mainly includes " piling wall " pattern and conventional type.Piling wall pattern be in the larger pile body of one section of wall boundary location arrangements in length and breadth, according to The surrounding in pile body is needed to arrange shaped-steel joint, pile body of first constructing, then " one " font wall section for surrounding of constructing;This structure is lattice Structure formula continuous underground wall structure is discrete to be embedded in pile body and forms good integrity for pile body with " one " font wall, " one " font wall Gridiron structure, trenching construction is convenient, and the reinforcing bar cage hoisting of each wall section is convenient, and avoids and occur in vertical wall and cross wall boundary position The turning for the coating projection easily caved in;The shortcomings that structural shape is the engineering in order to which pile body diameter is more much bigger than thickness of wall body Investment is higher.Conventional type is that lattice diaphram wall is discrete for " ten " font groove section, " T " font groove section, " L " type groove section " one " font groove section, it is each section of wall section equal thickness the advantages of this structural shape, quantities is relatively small, construction investment It is relatively low;Shortcoming is that have the raised turning of the coating easily to cave in, and lattice diaphram wall with cross wall boundary position in vertical wall The steel bar meter difficulty for four kinds of groove sections being discretely formed is big, and reinforcing bar cage hoisting difficulty is big.
The content of the invention
The technical problems to be solved by the invention are:A kind of lattice diaphram wall arrangement is provided, its structure is whole Body performance is good, easy for construction, while can save construction investment.
It is to solve above-mentioned technical problem the technical solution adopted in the present invention:Lattice diaphram wall arrangement, Including longitudinal wall and horizontal wall, perpendicular to primary load direction, the axis of horizontal wall is identical with primary load direction for the axis of longitudinal wall, Longitudinal wall includes inner side longitudinal direction wall, outside longitudinal direction wall, the longitudinal wall in one end connection inner side of horizontal wall, other end connection outside longitudinal direction Wall, inner side longitudinal direction wall are provided with u shaped connector in the side towards outside longitudinal direction wall, and u shaped connector insertion inner side is longitudinal within the walls, and with The steel reinforcement cage of inner side longitudinal direction within the walls is fixedly connected, in the cell body of the end insertion u shaped connector of horizontal wall, and laterally reinforcing bar within the walls Cage is fixedly connected with u shaped connector;Outside longitudinal direction wall is being provided with the second u shaped connector towards the side of inner side longitudinal direction wall, and second is U-shaped Joint insertion outside longitudinal direction within the walls, and is fixedly connected with the longitudinal steel reinforcement cage within the walls in outside, and the end insertion second of horizontal wall is U-shaped In the cell body of joint, and laterally steel reinforcement cage within the walls is fixedly connected with the second u shaped connector.
It is further:Longitudinal wall also includes the longitudinal wall in centre between inner side longitudinal direction wall, outside longitudinal direction wall, laterally The side of wall is provided with the 3rd u shaped connector for being used for connecting middle longitudinal wall, the insertion of the 3rd u shaped connector laterally within the walls, and with transverse direction Steel reinforcement cage within the walls is fixedly connected, the end of middle longitudinal wall is embedded in the cell body of the 3rd u shaped connector, and middle longitudinal direction is within the walls Steel reinforcement cage is fixedly connected with the 3rd u shaped connector.
It is further:Before horizontal wall is connected, it is equipped with the cell body of u shaped connector, in the cell body of the second u shaped connector Detachable froth bed, froth bed fill the cell body of full u shaped connector and the cell body of the second u shaped connector respectively;Indulged between in this connection To before wall, detachable froth bed, the cell body of full 3rd u shaped connector of froth bed filling are provided with the cell body of the 3rd u shaped connector.
It is further:Connecting between u shaped connector and inner side longitudinal direction steel reinforcement cage within the walls, steel reinforcement cage laterally within the walls with Connecting between the steel reinforcement cage of connection, the second u shaped connector between u shaped connector and outside longitudinal direction within the walls, reinforcing bar laterally within the walls Connecting between connection, the 3rd u shaped connector between cage and the second u shaped connector and laterally steel reinforcement cage within the walls, middle longitudinal wall Connection between interior steel reinforcement cage and the 3rd u shaped connector is welding.
The beneficial effects of the invention are as follows:According to the loading characteristic of lattice diaphram wall, armored concrete is made full use of The characteristics of wall load performance is strong, u shaped connector is introduced in longitudinal wall and horizontal wall, lattice diaphram wall it is discrete for etc. " one " font groove section of thickness, and the froth bed easily removed can be filled in u shaped connector in advance, to ensure later stage groove section wall Body is sufficiently close embedded in groove wall in advance, forms more complete stress system.This integrality performance of the structure is good, easy for construction, The reinforcing bar cage hoisting at each position is convenient, avoids turning for the coating projection that occurs easily caving in cross wall boundary position in vertical wall Angle, reduce construction risk;Each section of thickness of wall body is identical, and quantities is smaller, reduces construction investment;The use of u shaped connector, without again Individually processing profiled drill bit construction longitudinal wall and longitudinal wall joint area, and more can guarantee that construction quality, in length and breadth wall Connection can more be closely linked.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the structural representation of construction procedure one of u shaped connector;
Fig. 3 is the structural representation of construction procedure two of u shaped connector;
Marked in figure:1- longitudinal directions wall, longitudinal wall on the inside of 11-, longitudinal wall on the outside of 12-, longitudinal wall among 13-, 2- transverse directions wall, 3-U type joints, the u shaped connectors of 4- second, the u shaped connectors of 5- the 3rd, 6- froth beds.
Embodiment
The invention will be further described below in conjunction with the accompanying drawings, and direction shown in arrow is primary load direction in figure.
As shown in figure 1, the present invention includes longitudinal wall 1 and horizontal wall 2, the axis of longitudinal wall 1 is horizontal perpendicular to primary load direction It is identical with primary load direction to the axis of wall 2, longitudinal wall 1 include inner side longitudinal direction wall 11, outside longitudinal direction wall 12, the one of horizontal wall 2 The longitudinal wall 11 in end connection inner side, the longitudinal wall 12 in other end connection outside, inner side longitudinal direction wall 11 is towards the one of outside longitudinal direction wall 12 Side is provided with u shaped connector 3, and u shaped connector 3 is embedded in the longitudinal wall 11 in inner side, and is fixed and connected with the steel reinforcement cage in inner side longitudinal direction wall 11 Connect, in the cell body of the end insertion u shaped connector 3 of horizontal wall 2, and the steel reinforcement cage in horizontal wall 2 is fixedly connected with u shaped connector 3;Outside Side longitudinal direction wall 12 is provided with the second u shaped connector 4, the second u shaped connector 4 insertion outside longitudinal direction in the side towards inner side longitudinal direction wall 11 In wall 12, and it is fixedly connected with the steel reinforcement cage in outside longitudinal direction wall 12, the end of horizontal wall 2 is embedded in the cell body of the second u shaped connector 4 It is interior, and the steel reinforcement cage in horizontal wall 2 is fixedly connected with the second u shaped connector 4.Wherein, u shaped connector 3, the second u shaped connector 4, the 3rd U Type joint 5 is preferably made using steel plate;The depth that u shaped connector 3, the second u shaped connector 4, the 3rd u shaped connector 5 are embedded in wall can Selected according to the thickness of corresponding wall, it is proposed that select 1/6 thickness of wall body;Each phase groove section division of lattice diaphram wall It can be selected according to the length and construction ability of wall.
If longitudinal wall 1 also includes the longitudinal wall 13 in centre between inner side longitudinal direction wall 11, outside longitudinal direction wall 12, its is preferred Arrangement is:The side of horizontal wall 2 is provided with the 3rd u shaped connector 5 for being used for connecting middle longitudinal wall 13, and the 3rd u shaped connector 5 is embedding Enter in horizontal wall 2, and be fixedly connected with the steel reinforcement cage in horizontal wall 2, the end of middle longitudinal wall 13 is embedded in the 3rd u shaped connector 5 Cell body in, and the steel reinforcement cage in middle longitudinal wall 13 is fixedly connected with the 3rd u shaped connector 5.Wherein, the number of middle longitudinal wall 13 Amount can be one or multi-channel.
As shown in Figure 2 and Figure 3, before horizontal wall 2 is connected, detachable froth bed 6 is provided with the cell body of u shaped connector 3, The cell body of the full u shaped connector 3 of the filling of froth bed 6.During construction, the steel reinforcement cage of the longitudinal wall 11 in installation inner side first, then by u shaped connector 3 It is secured to connect, the full froth bed 6 of filling in the cell body of u shaped connector 3, pours the section concrete of the longitudinal wall 11 in inner side, construction After the completion of remove froth bed 6, then the steel reinforcement cage for connecting horizontal wall 2 is installed, and it is fixedly connected with u shaped connector 3, pours transverse direction The section concrete of wall 2, completes the construction of the linkage section.Froth bed 6 is set to avoid connecing during diaphram wall concreting Head cavity builds reality by concrete, to ensure later stage groove section wall sufficiently close embedded groove wall in advance so that structural integrity Can be more preferable.
Similarly, before horizontal wall 2 is connected, detachable froth bed 6, froth bed are provided with the cell body of the second u shaped connector 4 The cell body of full second u shaped connector 4 of 6 fillings;It is provided between in this connection before longitudinal wall 13, in the cell body of the 3rd u shaped connector 5 removable The froth bed 6 removed, the cell body of full 3rd u shaped connector 5 of the filling of froth bed 6.Its form of construction work is identical with u shaped connector 3.
Preferably, connecting between the steel reinforcement cage in u shaped connector 3 and inner side longitudinal direction wall 11, the steel reinforcement cage in horizontal wall 2 with Connecting, in horizontal wall 2 between the steel reinforcement cage in connection, the second u shaped connector 4 and outside longitudinal direction wall 12 between u shaped connector 3 Connecting, be middle between the steel reinforcement cage in connection, the 3rd u shaped connector 5 and horizontal wall 2 between steel reinforcement cage and the second u shaped connector 4 The connection between steel reinforcement cage and the 3rd u shaped connector 5 in longitudinal wall 13 is welding.It is easy for construction by the way of welding, and Structure bulk strength can be ensured.

Claims (4)

1. lattice diaphram wall arrangement, including longitudinal wall (1) and horizontal wall (2), the axis of longitudinal wall (1) perpendicular to Primary load direction, the axis of horizontal wall (2) is identical with primary load direction, and longitudinal wall (1) includes inner side longitudinal direction wall (11), outside is indulged To wall (12), the longitudinal wall (11) in one end connection inner side, the longitudinal wall (12) in other end connection outside of horizontal wall (2), its feature exist In:Inner side longitudinal direction wall (11) is provided with u shaped connector (3) in the side towards outside longitudinal direction wall (12), in u shaped connector (3) is embedded In side longitudinal direction wall (11), and it is fixedly connected with the steel reinforcement cage in inner side longitudinal direction wall (11), the end insertion of horizontal wall (2) is U-shaped to be connect In the cell body of head (3), and the steel reinforcement cage in horizontal wall (2) is fixedly connected with u shaped connector (3);Outside longitudinal direction wall (12) is in direction The side of inner side longitudinal direction wall (11) is provided with the second u shaped connector (4), and the embedded longitudinal wall (12) in outside of the second u shaped connector (4) is interior, And be fixedly connected with the steel reinforcement cage in outside longitudinal direction wall (12), the end of horizontal wall (2) is embedded in the cell body of the second u shaped connector (4) It is interior, and the steel reinforcement cage in horizontal wall (2) is fixedly connected with the second u shaped connector (4).
2. lattice diaphram wall arrangement as claimed in claim 1, it is characterised in that:Longitudinal wall (1) also includes position The longitudinal wall in centre (13) between inner side longitudinal direction wall (11), outside longitudinal direction wall (12), the side of horizontal wall (2), which is provided with, to be used to connect Connect the 3rd u shaped connector (5) of middle longitudinal wall (13), in the embedded horizontal wall (2) of the 3rd u shaped connector (5), and with horizontal wall (2) Interior steel reinforcement cage is fixedly connected, and the end of middle longitudinal wall (13) is embedded in the cell body of the 3rd u shaped connector (5), and middle longitudinal direction Steel reinforcement cage in wall (13) is fixedly connected with the 3rd u shaped connector (5).
3. lattice diaphram wall arrangement as claimed in claim 1 or 2, it is characterised in that:Connecting horizontal wall (2) Before, detachable froth bed (6), froth bed are equipped with the cell body of u shaped connector (3), in the cell body of the second u shaped connector (4) (6) cell body of full u shaped connector (3) and the cell body of the second u shaped connector (4) are filled respectively;Between in this connection before longitudinal wall (13), Detachable froth bed (6), the groove of full 3rd u shaped connector (5) of froth bed (6) filling are provided with the cell body of 3rd u shaped connector (5) Body.
4. lattice diaphram wall arrangement as claimed in claim 1 or 2, it is characterised in that:U shaped connector (3) with it is interior Connecting between the steel reinforcement cage in side longitudinal direction wall (11), the steel reinforcement cage in horizontal wall (2) and the connection between u shaped connector (3), Connecting between the steel reinforcement cage in two u shaped connectors (4) and outside longitudinal direction wall (12), the steel reinforcement cage in horizontal wall (2) and second are U-shaped Connecting between the steel reinforcement cage in connection, the 3rd u shaped connector (5) and horizontal wall (2) between joint (4), middle longitudinal wall (13) connection between steel reinforcement cage and the 3rd u shaped connector (5) in is welding.
CN201610606298.XA 2016-07-28 2016-07-28 Lattice diaphram wall arrangement Active CN106087973B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610606298.XA CN106087973B (en) 2016-07-28 2016-07-28 Lattice diaphram wall arrangement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610606298.XA CN106087973B (en) 2016-07-28 2016-07-28 Lattice diaphram wall arrangement

Publications (2)

Publication Number Publication Date
CN106087973A CN106087973A (en) 2016-11-09
CN106087973B true CN106087973B (en) 2017-12-12

Family

ID=57478612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610606298.XA Active CN106087973B (en) 2016-07-28 2016-07-28 Lattice diaphram wall arrangement

Country Status (1)

Country Link
CN (1) CN106087973B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113605368B (en) * 2021-07-27 2023-03-24 广西交通设计集团有限公司 Large-span arch bridge lattice type underground continuous wall for thick-covering-layer area and construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63125721A (en) * 1986-11-17 1988-05-28 Shimizu Constr Co Ltd Construction of underground continuous wall and element coupler therefor
JP4043621B2 (en) * 1998-11-20 2008-02-06 株式会社竹中工務店 Formation method of crossing wall by continuous mixing method
CN203905064U (en) * 2014-06-03 2014-10-29 金陵科技学院 Underground diaphragm wall tooth-shaped connector
CN105239607B (en) * 2015-10-19 2018-03-09 苏州大学 Diaphram wall and concrete structure bottom plate whole anti-uplift structure and its construction method
CN205917686U (en) * 2016-07-28 2017-02-01 中国电建集团成都勘测设计研究院有限公司 Lattice formula underground continuous wall arrangement structure

Also Published As

Publication number Publication date
CN106087973A (en) 2016-11-09

Similar Documents

Publication Publication Date Title
CN110017144B (en) Loess tunnel three-step construction method considering substrate reinforcement treatment
CN103233459B (en) A kind of construction method of two-in-one double steel plate Combined concrete diaphragm wall
CN106988750B (en) Implementation mode of ultra-short-distance underpass of existing station of large-span interval tunnel
CN203476347U (en) Preliminary bracing device for collapsible loess tunnel
CN103898900A (en) Concrete-filled steel tube composite structure underground diaphragm wall with pull rods and construction method of underground diaphragm wall
CN104895093B (en) A kind of half coercion underground continuous wall and its construction method
CN102134853A (en) CT sealed steel pipe pile foundation pit water stop supporting device and construction method thereof
CN102011410A (en) Prefabricated prestressed underground continuous wall and construction method thereof
CN103924581B (en) Prefabricated concrete-filled steel tube combining structure diaphragm wall and construction method thereof
CN102363955A (en) Prefabricated transverse H-shaped underground continuous wall joint section structure
CN201502060U (en) Bored pile double pile casing system
CN101793027B (en) Core-grouted static pressure anchor rod pile
CN106087973B (en) Lattice diaphram wall arrangement
CN201943077U (en) Waterproof curtain of CT-type fore shaft steel pipe pile
CN203429665U (en) Immersed tunnel axis dry dock opening structure
CN110359471B (en) Anti-seepage damage structure of strong water-permeable sandy soil layer of underwater tunnel and construction method
CN210177527U (en) On-spot prefabricated construction of small-size independent cushion cap basis
CN209228377U (en) A kind of multistage set arch structure and pipe canopy set arch structure for tunnel portal supporting
CN205917686U (en) Lattice formula underground continuous wall arrangement structure
CN217028931U (en) Steel pipe concrete support assembly
CN216276371U (en) Double-sleeve grouting connection full-assembly type reinforced concrete floor
CN212375896U (en) Line tower type-returning pile-anchor composite foundation suitable for karst region
CN210216391U (en) Enclosed type diaphragm wall surrounding well structure extending into bedrock
CN105200984B (en) A kind of novel sea engineering pile foundation reducing pile body displacement and preparation method thereof
CN210887256U (en) Straight combined sheet pile-ground wall-connecting type frame of water retaining cofferdam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant