CN106087808B CN201610697527.3A CN201610697527A CN106087808B CN 106087808 B CN106087808 B CN 106087808B CN 201610697527 A CN201610697527 A CN 201610697527A CN 106087808 B CN106087808 B CN 106087808B
Authority
CN
China
Prior art keywords
channel steel
chan frame
frame
chan
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610697527.3A
Other languages
Chinese (zh)
Other versions
CN106087808A (en
Inventor
刘云贵
王小颖
李杰荣
蔡彭华
梅林�
朱宁
杨苑瑛
聂红
陈福耀
佘丕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Zhengzhong Design Co., Ltd
Original Assignee
SHENZHEN ASIANTIME INTERNATIONAL CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHENZHEN ASIANTIME INTERNATIONAL CONSTRUCTION Co Ltd filed Critical SHENZHEN ASIANTIME INTERNATIONAL CONSTRUCTION Co Ltd
Priority to CN201610697527.3A priority Critical patent/CN106087808B/en
Publication of CN106087808A publication Critical patent/CN106087808A/en
Priority to PCT/CN2017/079039 priority patent/WO2018032772A1/en
Application granted granted Critical
Publication of CN106087808B publication Critical patent/CN106087808B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F15/00Safety arrangements for slowing, redirecting or stopping errant vehicles, e.g. guard posts or bollards; Arrangements for reducing damage to roadside structures due to vehicular impact
    • E01F15/02Continuous barriers extending along roads or between traffic lanes

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to building decoration guardrail fields, disclose a kind of modular railing and installation method.The modular railing includes the chan frame (1), the toughened rubber-laminated vacuum glass (2) in chan frame and the stone material (3) with adjacent slot beam-to-column connection two-by-two that are connect with ground, and by being welded, stone material is inserted into metalwork (5) one end to the stone material, one end is welded chan frame mode and connect with the chan frame.The present invention provides the novel modular railings of one kind of multiple material adapteds, style, fastening, each part dimension specification, pattern diversification are connected between all parts, various occasions can be widely used in, and due to so that modular railing is more attractive using more material adapteds.

Description

A kind of modular railing and installation method
Technical field
The present invention relates to building decoration guardrail field more particularly to a kind of modular railings and installation method.
Background technology
Railing is seen everywhere as road, a kind of safety devices of building in our life.Previous railing makes With homogenous material and unit is fabricated to, unit is connected into composition guardrail, such as wooden railing, stone railing successively.With society Can development, some new materials, new process modular railing emerge, such as:Glass balustrade, stainless steel railing, peace It loads easily, style shape style is more, and adapts to various occasions.But it also has the following disadvantages:Material adapted is single;Column Bar is fragile;Railing connect insecure etc. with ground.
Invention content
In order to overcome more than the deficiencies in the prior art, the purpose of the present invention is to provide one kind of multiple material adapteds, it is not easy The modular railing of damage and the installation method being connected firmly with ground.
The purpose of the present invention is realized using following technical scheme:
A kind of modular railing including multiple chan frames, multiple is connect in the chan frame and with chan frame Toughened rubber-laminated vacuum glass and multiple stone materials with adjacent slot beam-to-column connection two-by-two;The stone material passes through electricity with the chan frame Metalwork connection is welded, stone material is inserted into described electric welding metalwork one end, and one end is welded with chan frame.
Preferably, the chan frame include upper channel steel, respectively with upper channel steel both ends welding 2 side channel steel parts and With 2 steel plates of 2 side channel steel part other end welding;The chan frame is in inverted U;The upper channel steel of the chan frame is recessed Downward, 2 side channels steel part groove port is opposite for notch.
Preferably, the upper channel steel both ends open face and upper channel steel web surface are in 45 degree, the side channel steel part and upper slot One end open face and the side channel steel part web surface of steel welding in 45 degree, the steel plate open there are four through-hole.
Preferably, which is characterized in that the side channel steel part includes channel steel ontology, the U being welded in channel steel body recess Type card slot, the packing material being filled between channel steel body recess and U-shaped card slot and the rubber pad being pasted onto in U-shaped card slot.
Preferably, which is characterized in that the both ends that the stone material is connect with chan frame are symmetrically equipped with multiple 50mm depths Grooving.
Preferably, which is characterized in that epoxy resin AB glue is coated in the grooving.
Preferably, described electric welding metalwork one end is inserted into grooving, and the electric welding metalwork electric welding metal being inserted into grooving Part surface is coated with epoxy resin AB glue.
A kind of installation method of modular railing, the described method comprises the following steps:
Unwrapping wire is measured by design drawing and code requirement, identifies chan frame steel plate position position line and heeling-in Learn the hole position position line of anchor bolt;
According to chan frame material object verify mark position line, verify it is errorless after according to the hole position position line to ground into Row punching, then by chemical anchor bolts implant holes, then pour into chemical agent in hole, and adjust the flatness of chemical anchor bolts and hang down Straight degree;
The steel plate through-hole on chan frame and the chemical anchor bolts on heeling-in ground are directed at, chan frame is placed on ground, and Chan frame verticality and levelness are adjusted, then tightens the nut on chemical anchor bolts;
Concrete bed course is carried out to the footing steel plate position of chan frame and pours bottom;
Toughened rubber-laminated vacuum glass is mounted in the U-shaped card slot in chan frame;
Epoxy resin AB glue is smeared to stone material grooving and electric welding metalwork, stone material grooving is inserted into electric welding metalwork one end Interior, the other end and chan frame carry out electric welding again with the gap between structure glue filling stone material and chan frame.
Preferably, the footing steel plate position of chan frame is carried out to further include after concrete bed course pours bottom:It is fallen on concrete bed course Expansive concrete in a subtle way, and vibration compacting is carried out, the concrete cushion thickness is 5mm.
Preferably, it is further included later in the U-shaped card slot that toughened rubber-laminated vacuum glass is mounted in chan frame:
The gap between the U-shaped stainless steel card slot in toughened rubber-laminated vacuum glass and chan frame, Ran Houyong are filled with structure glue Packing material clogs in gap between side channel steel groove and U-shaped stainless steel card slot completely, and is compacted, and finally uses silicone sealant Closing in is sealed to the gap of packing material.
Description of the drawings
It in order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the present invention Example, for those of ordinary skill in the art, without having to pay creative labor, can also be according to these attached drawings Obtain other attached drawings.
Fig. 1 is the front view of the modular railing in the embodiment of the present invention;
Fig. 2 is the chan frame front view in the embodiment of the present invention;
Fig. 3 is the chan frame vertical view in the embodiment of the present invention;
Fig. 4 is the side channel steel part structure chart in the embodiment of the present invention;
Fig. 5 is Figure 1B-B diagrammatic cross-sections;
Fig. 6 is Figure 1A-A diagrammatic cross-sections;
Fig. 7 is part A enlarged diagram in Fig. 6;
It is marked in attached drawing:1st, chan frame;2nd, toughened rubber-laminated vacuum glass;3rd, stone material;4th, structure glue;5th, it is welded metalwork;6、 Chemical anchor bolts;11st, upper channel steel;12nd, side channel steel part;13rd, steel plate;121st, channel steel ontology;122nd, U-shaped stainless steel card slot;123、 Rubber pad;124th, packing material;1211st, channel steel web;31st, stone material grooving;32nd, epoxy resin AB glue.
Specific embodiment
In the following, with reference to attached drawing and specific embodiment, the present invention is described further:
As shown in Figure 1, modular railing provided in an embodiment of the present invention, including 2 chan frames 1, mounted on channel steel frame 2 toughened rubber-laminated vacuum glass 2 in frame 1 and the stone material 3 being connect with 2 chan frames 1.Stone material 3 and 2 chan frames 1 It is connected by 4 stainless steel angle steel lacing films 5, stone material 3, one end and 2 chan frames 1 are inserted into 45 one end of electric welding metalwork Electric welding.Certainly in practice, chan frame, toughened rubber-laminated vacuum glass and stone material quantity and size can design according to demand, The embodiment of the present invention does not limit.
As shown in Figure 2 and Figure 3, chan frame 1 includes 1 upper 11,2 side channel steel part 12 of channel steel and 2 steel plates 13. Upper 11 both ends open face of channel steel is in 45 degree, and 2 12 one end open faces of side channel steel part are in 45 degree, are all opened respectively on 2 steel plates 13 There are 4 through-holes.Upper 11 both ends of channel steel are welded together respectively with 2 opening faces of side channel steel parts 12 in 45 degree one end, upper channel steel 11 groove ports are directed downward, and the groove port direction of 2 side channel steel parts 12 is opposite.The other end of 2 side channel steel parts 12 and 2 Steel plate 13 is respectively welded together, and welding position is located at 13 center of steel plate.Chemistry of the chan frame 1 by heeling-in in ground Anchor bolt 6 links together with ground.Certainly in practice, the shape of chan frame can also evolve into other shape accordingly, preferably Ground is inverted U, and the number of openings of steel plate also can be more, such as 6,8 etc., it is therefore preferable to which 4, the embodiment of the present invention does not limit It is fixed.
As shown in figure 4, side channel steel part 12 is by channel steel ontology 121, U-shaped stainless steel card slot 122, rubber pad 123 and fills out Material 124 is filled to be composed.U-shaped 122 groove port of stainless steel card slot is consistent with 121 groove port direction of channel steel ontology, and is welded on 1211 intermediate position of channel steel body recess endosternum.U-shaped 122 height of stainless steel card slot is less than the height of channel steel ontology 121, U-shaped 122 width of stainless steel card slot is more than 2 thickness of toughened rubber-laminated vacuum glass, and U-shaped 122 lower bottom part of stainless steel card slot is sealing;Rubber pad 123 are pasted onto on U-shaped stainless steel card slot 122, and the length of rubber pad 123 is identical with the height of U-shaped stainless steel card slot 122;Filling Material 124 is located in channel steel ontology 121 and U-shaped 122 gap of stainless steel card slot.Certainly in practice, the shape of card slot can also evidence This evolves into other shape, can also use other material, it is therefore preferable to which U-shaped stainless steel, the embodiment of the present invention do not limit.
As shown in figure 5,3 both sides of the face of stone material are respectively provided with the grooving 31 of 2 50mm depths, epoxide resin AB is coated in grooving Glue 32.One end that 5 surface of electric welding metalwork is coated with epoxy resin AB glue 32 is placed in grooving 31, and electric welding metalwork part 5 is in three Angle-style is set.Certainly in practice, the shape of grooving can also evolve into other shape accordingly, and the depth of grooving can also be set It is deeper or slightly shallow, it is therefore preferable to which that rectangle, 50mm, the embodiment of the present invention do not limit.
As shown in Figure 6, Figure 7,2 left and right ends of toughened rubber-laminated vacuum glass are placed in 1 two 12 grooves of side channel steel part of chan frame In U-shaped stainless steel card slot 122 in, closely contacted, and pass through structure glue with pasting rubber pad 123 on U-shaped stainless steel card slot 122 4 with U-shaped stainless steel card slot 122) and rubber pad 123 stickup connect.5 one end of electric welding metalwork, which is arranged in grooving 31, to be passed through Epoxy resin AB glue 32 pastes curing connection with stone material 3, and the other end passes through with the side channel steel part web 1211 in chan frame 1 Electric welding connection.Gap setting structure glue 4 is filled between stone material 3 and chan frame 1, certainly in practice, is welded the shape of metalwork Other shape can also be evolved into accordingly, and the material of pendant can also select other material, it is therefore preferable to stainless steel angle steel, this hair Bright embodiment does not limit.
The beneficial effects of the present invention are:The embodiment of the present invention using chan frame as pillar, toughened rubber-laminated vacuum glass with And stone material collocation, as guardrail, three kinds of materials belong to firm material, are hardly damaged, and toughened rubber-laminated vacuum glass can print on surface Various patterns are made, depiction may be used in stone material, can also use various granites, and toughened rubber-laminated vacuum glass is arranged in pairs or groups with stone material Come, more attractive, toughened rubber-laminated vacuum glass is mounted in chan frame, and stone material is welded on by being welded metal hanger on frame, each It is connected firmly between component.
The embodiment of the present invention additionally provides a kind of installation method of modular railing, the method
Include the following steps:
Step 101 measures unwrapping wire by design drawing and code requirement, identifies chan frame steel plate position position line With the hole position position line of heeling-in chemical anchor bolts.
Specifically, measuring unwrapping wire by design drawing and code requirement, the steel plate position on each chan frame is determined And lead to the hole site on steel plate, the good control line of bullet simultaneously identify heeling-in chemistry at steel plate position line and lead to the hole site on the ground The cross position line of anchor bolt.
Step 102, the position line that mark is verified according to chan frame material object, according to hole position position line after verification is errorless Ground is punched, then by chemical anchor bolts implant holes, is then poured into chemical agent in hole, and adjusts the flat of chemical anchor bolts Whole degree and verticality.
Specifically, verify the position line that lead to the hole site is identified with front on the steel plate position and steel plate of chan frame material object Whether it coincide, ground is punched according to the cross position line of mark after verification is errorless, it is after punching, dust in hole is clear Reason is clean, then by chemical anchor bolts implant holes, and adjusts the flatness and verticality of chemical anchor bolts, by chemical agent after adjusting It pours into hole, after chemical agent curing, chemical anchor bolts check whether firm.
Step 103, the steel plate through-hole on alignment chan frame and the chemical anchor bolts on heeling-in ground, place ground by chan frame On face, and chan frame verticality and levelness are adjusted, then tighten the nut on chemical anchor bolts.
Specifically, in the embodiment of the present invention, after confirming that chemical anchor bolts heeling-in is consolidated and treated, chan frame is holded up by channel steel frame Frame, which is placed on, plants on the ground for burying chemical anchor bolts, needs alignment steel plate through-hole with chemical anchor bolts in placement process and makes the chemistry of heeling-in Anchor bolt completely extends across steel plate through-hole, then adjusts verticality and levelness to chan frame, and after adjusting, set top nut is in chemical anchors On bolt, and tightening nut makes chan frame be fastenedly connected together with ground, and if chemical anchor bolts have exposing nut portion, hand can be used Grinding machine cuts off and applies last layer antirust paint.
Step 104 pours bottom to the footing steel plate position progress concrete bed course of chan frame.
In the step of the embodiment of the present invention, the steel plate top and bottom of chan frame are rinsed with water and are cleaned out, then to channel steel Frame steel plate position carries out pouring bottom concrete bed course 5mm, it is preferred that can pour into C40 microdilatancy concretes to concrete bed course later, and shake Puddling is real, further consolidates the connection on chan frame and ground.
Toughened rubber-laminated vacuum glass is mounted in the U-shaped card slot in chan frame by step 105.
Specifically, first the inclination of toughened rubber-laminated vacuum glass one end is inserted into stainless in a side channel steel part of chan frame In steel U-shaped card slot, then the other end of toughened rubber-laminated vacuum glass is inserted into stainless in another side channel steel part of chan frame In steel U-shaped card slot, toughened rubber-laminated vacuum glass is adjusted, toughened rubber-laminated vacuum glass is made to be centered in stainless steel U-shaped card slot, toughened rubber-laminated vacuum glass Both ends are close to rubber pad, then fill knot using gap of the glue rifle between stainless steel U-shaped card slot and toughened rubber-laminated vacuum glass Structure glue after structure glue is fully cured, is finally clogged gap between side channel steel groove and U-shaped stainless steel card slot with packing material It is full, and be compacted, after compacting closing in is sealed with silicone sealant;
Step 106 smears epoxy resin AB glue to stone material grooving and electric welding metalwork, and electric welding metalwork one end is inserted into stone In material grooving, the other end and chan frame carry out electric welding again with the gap between structure glue filling stone material and chan frame.
Specifically, smearing epoxy resin AB glue in electric welding metalwork end surface and stone material grooving, then metal will be welded Part smear epoxy resin AB glue one end be inserted into stone material grooving in, electric welding metalwork in fall positive triangle, until grooving bottom, then Stone material is fixed vertically, adjusts stone material right position and terrain clearance, after adjusting OK, to electric welding metalwork and chan frame Side channel steel part web outside carries out electric welding, clears up welding slag after having welded, and brushing antirust paint, finally using glue rifle pair Gap interstitital texture glue between stone material and chan frame, the width of glue-line are consistent.
It should be noted that for aforementioned embodiment of the method, in order to be briefly described, therefore it is all expressed as a series of Combination of actions, but those skilled in the art should know, the present invention is not limited by described sequence of movement, because according to According to the present invention, certain steps may be used other sequences or be carried out at the same time.
The beneficial effects of the present invention are:A kind of installation method of modular railing, steel are provided in the embodiment of the present invention Change doubling glass to be placed in chan frame, be connect by structure glue with chan frame, stone material is welded on by being welded metalwork It on frame, is connected firmly between all parts, chan frame passes through chemical anchor bolts and irrigate the fields concrete bed course and ground stable connection.
It will be apparent to those skilled in the art that technical solution that can be as described above and design, make other various Corresponding change and deformation, and all these changes and deformation should all belong to the protection domain of the claims in the present invention Within.

Claims (10)

1. a kind of modular railing, which is characterized in that including multiple chan frames, it is multiple be located at chan frame in and with channel steel frame The toughened rubber-laminated vacuum glass of frame connection and multiple stone materials with adjacent slot beam-to-column connection two-by-two;The stone material and the channel steel frame Frame is connected by being welded metalwork, and stone material is inserted into described electric welding metalwork one end, and one end is welded with chan frame.
2. a kind of modular railing according to claim 1, which is characterized in that the chan frame includes upper channel steel, difference 2 steel plates with 2 side channel steel parts of upper channel steel both ends welding and with 2 side channel steel part other end welding;The slot Steel frame is in inverted U;The upper channel steel groove mouth down of the chan frame, 2 side channels steel part groove port are opposite.
3. a kind of modular railing according to claim 2, which is characterized in that the upper channel steel both ends open face and upper channel steel Web surface is in 45 degree, and the side channel steel part is in 45 degree with the one end open face of upper channel steel welding and side channel steel part web surface, The steel plate is opened there are four through-hole.
4. a kind of modular railing according to claim 2, which is characterized in that the side channel steel part include channel steel ontology, The U-shaped card slot that is welded in channel steel body recess, the packing material being filled between channel steel body recess and U-shaped card slot and viscous The rubber pad being attached in U-shaped card slot.
A kind of 5. modular railing according to claim 1, which is characterized in that the both ends that the stone material is connect with chan frame Symmetrically it is equipped with the grooving of multiple 50mm depths.
6. a kind of modular railing according to claim 5, which is characterized in that epoxy resin AB glue is coated in the grooving.
7. a kind of modular railing according to claim 5, which is characterized in that be inserted into the electric welding metalwork in grooving End surface is coated with epoxy resin AB glue.
8. the installation method of modular railing described in a kind of claim 1, which is characterized in that the described method comprises the following steps:
Unwrapping wire is measured by design drawing and code requirement, identifies chan frame steel plate position position line and heeling-in chemical anchors The hole position position line of bolt;
The position line of mark is verified according to chan frame material object, ground is beaten according to hole position position line after verification is errorless Hole, then by chemical anchor bolts implant holes, then pour into chemical agent in hole, and adjust the flatness of chemical anchor bolts and vertical Degree;
The steel plate through-hole on chan frame and the chemical anchor bolts on heeling-in ground are directed at, chan frame is placed on ground, and is adjusted Then chan frame verticality and levelness tighten the nut on chemical anchor bolts;
Concrete bed course is carried out to the footing steel plate position of chan frame and pours bottom;
Toughened rubber-laminated vacuum glass is mounted in the U-shaped card slot in chan frame;
Epoxy resin AB glue is smeared to stone material grooving and electric welding metalwork, electric welding metalwork one end is inserted into stone material grooving, separately One end and chan frame carry out electric welding again with the gap between structure glue filling stone material and chan frame.
9. a kind of installation method of modular railing according to claim 8, which is characterized in that
The footing steel plate position of chan frame further included after concrete bed course pours bottom:Microdilatancy concrete is poured on concrete bed course, And vibration compacting is carried out, the concrete cushion thickness is 5mm.
10. the installation method of modular railing according to claim 8, which is characterized in that described by toughened rubber-laminated vacuum glass It is further included after in the U-shaped card slot in chan frame:
The gap between the U-shaped stainless steel card slot in toughened rubber-laminated vacuum glass and chan frame is filled with structure glue, then with filling Material clogs in gap between side channel steel groove and U-shaped stainless steel card slot completely, and is compacted, finally with silicone sealant to filling out The gap for filling material is sealed closing in.
CN201610697527.3A 2016-08-19 2016-08-19 A kind of modular railing and installation method Active CN106087808B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201610697527.3A CN106087808B (en) 2016-08-19 2016-08-19 A kind of modular railing and installation method
PCT/CN2017/079039 WO2018032772A1 (en) 2016-08-19 2017-03-31 Combined handrail and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610697527.3A CN106087808B (en) 2016-08-19 2016-08-19 A kind of modular railing and installation method

Publications (2)

Publication Number Publication Date
CN106087808A CN106087808A (en) 2016-11-09
CN106087808B true CN106087808B (en) 2018-06-08

Family

ID=58070002

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610697527.3A Active CN106087808B (en) 2016-08-19 2016-08-19 A kind of modular railing and installation method

Country Status (2)

Country Link
CN (1) CN106087808B (en)
WO (1) WO2018032772A1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106087808B (en) * 2016-08-19 2018-06-08 深圳市亚泰国际建设股份有限公司 A kind of modular railing and installation method
CN108677799A (en) * 2018-05-18 2018-10-19 南京天方电子工程有限公司 A kind of installation method of isolated gate
CN108868315B (en) * 2018-07-26 2020-07-03 温州鹿城第三建筑工程有限公司 Building construction protective fence

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2729250B2 (en) * 1994-12-22 1998-03-18 メトロ電気工業株式会社 Luminous curb
DE29721660U1 (en) * 1997-12-09 1998-02-12 Fa. Hermann Uhl, 77746 Schutterwald Construction system
CN2451652Y (en) * 2000-07-26 2001-10-03 吕明良 Imitation white marble railing
WO2009023310A2 (en) * 2007-05-04 2009-02-19 Defenshield, Inc. Barrier
CN201924652U (en) * 2011-03-24 2011-08-10 招景棉 Assembly type glass rail
CN202577814U (en) * 2012-05-04 2012-12-05 孙玉良 Novel stainless steel glass railing
CN203977332U (en) * 2014-07-11 2014-12-03 郑州三迪建筑科技有限公司 The guardrail of a kind of high-speed railway both sides
CN104164848B (en) * 2014-07-23 2016-03-09 华北水利水电大学 Junked tire highway isolation belt device
CN105672172B (en) * 2016-01-06 2017-09-22 潍坊远大金属表面科技有限公司 A kind of construction method of Dacroment steel highway barrier
CN205369158U (en) * 2016-03-04 2016-07-06 沈文权 View flood control dykes and dams
CN106087808B (en) * 2016-08-19 2018-06-08 深圳市亚泰国际建设股份有限公司 A kind of modular railing and installation method
CN205907636U (en) * 2016-08-19 2017-01-25 深圳市亚泰国际建设股份有限公司 Combined railing

Also Published As

Publication number Publication date
CN106087808A (en) 2016-11-09
WO2018032772A1 (en) 2018-02-22

Similar Documents

Publication Publication Date Title
CN106087808B (en) A kind of modular railing and installation method
US9670668B2 (en) Masonry system
CN109853800B (en) Assembled low-energy-consumption curtain wall system and construction method thereof
CN109457993A (en) A kind of concrete column restoring and fastening method
CN107237257A (en) A kind of precast assembly guardrail construction connection method
CN105507607A (en) Method for repairing crack in ancient building wall
US20090241439A1 (en) Method and Device for Producing Precast Components and Corresponding Precast Component
CN103835303B (en) A kind of cast-type armored concrete shearing resistance method and structure
CN205934852U (en) A top layer combination stagnant water structure for it is removable that concrete structure stitches
CN210395980U (en) Wall brick dry hanging connection structure
CN205907636U (en) Combined railing
CN206571155U (en) A kind of wall vertical construction joint template and wall vertical construction joint structure
CN207131073U (en) A kind of wall construction template
JPS61151328A (en) Installation structure for machinery
CN207582743U (en) Light and thin type prefabricated section
CN208346789U (en) Concrete pressure cell Embedded installation device
CN207775725U (en) A kind of special disposable light filling composite core mould of bridge
JP3042891U (en) Concrete block for simple construction
CN207091864U (en) A kind of road surface baste transmission rod construction auxiliary device
CN207079769U (en) The building template that need not be dismantled
CN107419631A (en) A kind of rapid constructing method on brick structure road surface
CN214460654U (en) Subside advanced stagnant water anti-seepage concrete structure of post-cast strip
JPH03247802A (en) Manufacturing method of mosaic pattern of panel block
CN104088207B (en) There is the constructional method of the highway of shock-absorbing function
CN204098048U (en) A kind of prefabricated assembled view bank protection/bank block

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Liu Yungui

Inventor after: She Pi

Inventor after: Wang Xiaoying

Inventor after: Li Jierong

Inventor after: Cai Penghua

Inventor after: Mei Lin

Inventor after: Zhu Ning

Inventor after: Yang Yuanying

Inventor after: Nie Hong

Inventor after: Chen Fuyao

Inventor before: Lin Zheng

Inventor before: Li Shenglin

Inventor before: Zhu Tong

Inventor before: Hu Weijian

Inventor before: Deng Jiye

Inventor before: Qiu Xiaowei

Inventor before: Cai Penghua

Inventor before: Xie Gaorang

GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 518000 Guangdong city of Shenzhen province Yitian Futian District District Road and Fuhua Road Interchange, 4B02 4B01 excellence Times Square

Patentee after: Shenzhen Zhengzhong Design Co., Ltd

Address before: 518000 Guangdong city of Shenzhen province Yitian Futian District District Road and Fuhua Road Interchange, 4B02 4B01 excellence Times Square

Patentee before: SHENZHEN ASIANTIME INTERNATIONAL CONSTRUCTION Co.,Ltd.