CN106087774A - A kind of utilize 900 tons of beam shifting machines to bridge floor beam car dress beam Summarized Account of Bridge Erection Construction method - Google Patents

A kind of utilize 900 tons of beam shifting machines to bridge floor beam car dress beam Summarized Account of Bridge Erection Construction method Download PDF

Info

Publication number
CN106087774A
CN106087774A CN201610432466.8A CN201610432466A CN106087774A CN 106087774 A CN106087774 A CN 106087774A CN 201610432466 A CN201610432466 A CN 201610432466A CN 106087774 A CN106087774 A CN 106087774A
Authority
CN
China
Prior art keywords
bridge
tons
car
shifting
erection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610432466.8A
Other languages
Chinese (zh)
Other versions
CN106087774B (en
Inventor
乐锋
孙修德
曹会芹
魏文柱
张生全
张孝儒
閤鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Priority to CN201610432466.8A priority Critical patent/CN106087774B/en
Publication of CN106087774A publication Critical patent/CN106087774A/en
Application granted granted Critical
Publication of CN106087774B publication Critical patent/CN106087774B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections

Abstract

The invention discloses a kind of utilize 900 tons of beam shifting machines to bridge floor beam car dress beam Summarized Account of Bridge Erection Construction method, relate to high-speed railway bridge erection technique field.The present invention comprises the following steps according to bridge pier height, installs and increase joint on the supporting leg of 900 tons of beam shifting machines;Bridge Erector, beam car put in place in bridge floor assembly;Reserve 2 holes in one end of bridge not set up, sequentially advance bridge formation from this end to the other end of bridge;900 tons of beam shifting machine bale handles and travel to bridge floor circuit overlapping positions, then turn to 90 degree, bridge face walk at beam car fill beam position, beam is filled on beam car;900 tons of beam shifting machine dress beam backed off after randoms, beam car starts to transport beam, pushes ahead bridge formation.The present invention utilizes existing 900 tons of beam shifting machines, beam is filled on the beam car on bridge floor, save the infrastructure such as two 450 tons of attached tracks of lifting beam machine and ground of set, achieve the abundant flexible utilization of resource, reduce equipment investment cost, alleviating Company capital pressure, the erection for bridge simultaneously provides the mode of another kind of solution.

Description

A kind of utilize 900 tons of beam shifting machines to bridge floor beam car dress beam Summarized Account of Bridge Erection Construction method
Technical field
The present invention relates to high-speed railway bridge erection technique field, particularly one utilizes 900 tons of beam shifting machines to transport to bridge floor The Summarized Account of Bridge Erection Construction method of beam car dress beam.
Background technology
Along with the development that China's capital construction is quick, sane, Chinese Railway has been enter into the great-leap-forward development stage, wherein due to Landform and geographical position and bridge, the erection of grand bridge that must build the most gradually increase, and are also faced with perhaps in work progress Many problems, it is high that the specification of existing engineering mechanical device is not suitable for such as construction cost.
In terms of railway construction construction, it is necessary first to of solution key challenge is how with relatively low construction cost, Higher efficiency of construction, high-quality completes construction object, meets growing demand.At present, constructed in railway construction Cheng Zhong, in order to be not take up soil, guarantee the safety of railway operation, the proportion shared by overhead portion on railway is increasing, and In elevated line, large-sized concrete box beam becomes the vitals on overhead route as weight support, and due to this The weight planting large-sized concrete box beam is big, extremely difficult when transport and construction overhead railway.At present, this box beam is generally adopted Form of construction work: being first to use beam car to realize the transport of box beam, then supporting with it Bridge Erector is directly from beam car On take beam and build bridge at the construction field (site).
At present in high-speed railway bridge formation process of construction, a set of 900 tons of beam shifting machines during fortune beam, are needed to move beam and 450 tons of two sets On lifting beam machine bale handle, bridge fills beam to beam car, if owing to each construction enterprises assort the various construction equipments of needs, can cause big The waste of amount resource, accounts for pressure fund, improves the operating cost of company, the most rationally, flexibly, integrate and use existing resource, the blindest Mesh procuring equipment, Shi Ge construction enterprises need the practical problem considered.The present invention is directed to job site and there is no the feelings of 450 lifting beam machines Under condition, a kind of approach of the solution problem of proposition.
Summary of the invention
The technical problem to be solved be to provide a kind of utilize 900 tons of beam shifting machines to bridge floor beam car dress beam frame Bridge construction method, utilizes the Summarized Account of Bridge Erection Construction method of the present invention, saves the bases such as two 450 tons of attached tracks of lifting beam machine and ground of set and sets Execute;The present invention is by using existing equipments resources, it is achieved that the abundant flexible utilization of resource, reduces equipment investment cost, it is to avoid Enterprise's blind investment, causes the occupation of capital, alleviates Company capital pressure;Erection for bridge, grand bridge provides another kind of solution Mode certainly.
For solving above-mentioned technical problem, the technical solution used in the present invention is:
A kind of utilize 900 tons of beam shifting machines to bridge floor beam car dress beam Summarized Account of Bridge Erection Construction method, comprise the following steps:
1) according to bridge pier height, the supporting leg of 900 tons of beam shifting machines is installed and increases joint;
2) Bridge Erector, beam car put in place in bridge floor assembly;
3) one end at bridge is reserved 2 holes and is not set up, it is simple to 900 tons of beam shifting machine bale handles pass through, from this end to the other end of bridge sequentially Advance and build bridge;
4) 900 tons of beam shifting machine bale handles and travel to bridge floor circuit overlapping positions, then wheels turn to 90 degree, bridge face walk to fortune Liang Chechu fills beam position, is filled on beam car by beam;
5) 900 tons of beam shifting machine dress beam backed off after randoms, beam car starts to transport beam, pushes ahead bridge formation;
6) if only built bridge to the other end from one end, after this end-rack is complete, after-frame holes;If only from middle to two end-rack Bridge, after an end-rack is complete, then by Bridge Erector, beam car lifting or dismounting to the bridge of bridge another side, after another end-rack is complete, After-frame holes;
The erection method of last holes is: beam is placed on bridge floor by 900 tons of beam shifting machine elder generation bale handles through 2 preformed holes, then carries additionally The roof beam structure being placed on bridge floor, on bridge pier, is then set to last hole by the erection in one hole, after having set up, and 900 tons of shiftings Beam machine bridge is dismantled.
Wherein, being built bridge as odd number hole or even hole, the quantity of bridge opening is more than or equal to 3.
Use and have the beneficial effects that produced by technique scheme: existing 900 tons of beam shifting machines only need to be entered by the present invention Row increases improvement, can save the infrastructure such as 450 tons of attached tracks of lifting beam machine and ground of two sets;Utilize Summarized Account of Bridge Erection Construction side of the present invention Method, only need to increase place hardening region at bridge pier when beam fabricating yard construction, i.e. may utilize 900 tons of beam shifting machines and be filled on bridge floor by beam Beam car on;The present invention is by using existing equipments resources, it is achieved that the abundant flexible utilization of resource, reduces equipment investment and becomes This, it is to avoid enterprise's blind investment, causes the occupation of capital, alleviates Company capital pressure;Erection for bridge, grand bridge provides separately A kind of mode of solution.
Accompanying drawing explanation
Fig. 1 be in the present invention beam shifting machine bale handle parallel to location drawing when longitudinally overlapping with bridge pier;
Fig. 2 is the dress beam location drawing that in the present invention, beam shifting machine turns to when walking to beam car;
Fig. 3 is the side view of Fig. 2;
Fig. 4 be beam shifting machine exit rear beam car fortune beam time structure chart;
In figure: 1, increase joint;2, beam car;3,900 tons of box beams of frame are treated;4, bridge pier;5,900 tons of beam shifting machines.
Detailed description of the invention
The present invention is further detailed explanation with detailed description of the invention below in conjunction with the accompanying drawings.
In high-speed railway bridge formation process of construction, Dang Liangchang is positioned at bridge side, needs a set of 900 tons of beam shifting machines to move beam during fortune beam And two bridge on 450 tons of lifting beam machine bale handles of set fill beam to beam car, but in the case of there is no 450 lifting beam machines at the construction field (site), utilize This Summarized Account of Bridge Erection Construction method, utilizes the existing 900 tons of beam shifting machines in beam field convenient and strength-saving can fill beam to bridge floor beam car.Due to existing The insufficient height of the 900 tons of beam shifting machines having, therefore the method first has to, according to bridge floor height, transform 900 tons of beam shifting machines, I.e. setting up on beam shifting machine supporting leg and increase joint, increasing joint increases at the top of supporting leg, increases joint upper end with girder by flange spiral shell Bolt pair connects, and increases joint lower end and is connected by flange bolt pair with supporting leg.
The present invention comprises the following steps:
1) according to bridge pier 4 height, the supporting leg of 900 tons of beam shifting machines 5 is installed and increases joint 1;
2) Bridge Erector, beam car 2 put in place in bridge floor assembly;
3) one end at bridge is reserved 2 holes and is not set up, it is simple to 900 tons of beam shifting machine 5 bale handles pass through, from this end to the other end of bridge sequentially Advance and build bridge;
4) 900 tons of beam shifting machine 5 bale handles and travel to bridge floor circuit overlapping positions as it is shown in figure 1, the most only wheels turn to 90 degree As in figure 2 it is shown, and the support body entirety that whole wheels support above does not turns to, then bridge face walk at beam car 2 fill beam position, Beam is filled on beam car 2 as shown in Figure 3;
5) 900 tons of beam shifting machines 5 fill beam backed off after random, and beam car 2 starts to transport forward beam as shown in Figure 4, pushes ahead bridge formation;
6) if only built bridge to the other end from one end, after this end-rack is complete, after-frame holes;If only from middle to two end-rack Bridge, after an end-rack is complete, then lifts or dismounts on the bridge of bridge another side by Bridge Erector, beam car 2, after another end-rack is complete, After-frame holes;
The erection method of last holes is: beam is placed on bridge floor by 900 tons of beam shifting machine elder generation bale handles through 2 preformed holes, then carries additionally The erection in one hole, on bridge pier, then sets up last hole, after having set up, and 900 tons of beam shifting machine bridges dismountings.
Wherein, the supporting leg of 900 tons of beam shifting machines 5 is installed after increasing joint 1, first should set up adjacent continuous on bridge pier and set up Two pieces of beams, provide for assembled beam car and support.
Wherein, being built bridge can be that odd number hole can also be for even hole, and the quantity of bridge opening is more than or equal to 3.
As a example by 8 hole box beams, setting up 6 hole box beams with 900 tons of beam shifting machines bale handle in the middle part of beam field, 2 hole beam not framves are stayed in centre If both sides respectively set up 3 holes, Bridge Erector, beam car are assembled at bridge floor, 900 tons of beam shifting machines travels at the bridge pier do not set a roof beam in place extremely with Bridge floor circuit overlapping positions, by longitudinal driving, is placed into beam on the beam car of bridge floor, after 900 tons of beam shifting machines exit, transports beam Che Yunliang is to the place that sets a roof beam in place.As Liang Chang is located in the middle part of bridge, then set up to both sides in the middle part of bridge, first to a direction one direction frame If 3 hole box beams, after completing, Bridge Erector is dismantled, and carries out 3 hole box girder bridge faces assembly at other direction, and beam car moves beams by 900 tons Machine integral hoisting, on other direction, uses this method to carry out filling beam, and after both direction has all set up, 900 tons of beam shifting machines carry Beam, by a wherein hole elder generation box girder erection, then bale handle sets up an other hole, after last aperture frame has set, 900 tons of beam shifting machine bridges Dismantle.
The advantage that the present invention highlights is to save the infrastructure such as 450 tons of attached tracks of lifting beam machine and ground of two sets, only Existing 900 tons of beam shifting machines need to be improved, and when beam fabricating yard construction, increase place hardening region at bridge pier, and after improving 900 tons of beam shifting machines not only do not interfere with original range, the most also expand range, cost-effective substantially.

Claims (2)

1. one kind utilizes 900 tons of beam shifting machines to the Summarized Account of Bridge Erection Construction method of bridge floor beam car dress beam, it is characterised in that include following step Rapid:
1) according to bridge pier (4) highly, on the supporting leg of 900 tons of beam shifting machines (5), joint (1) is increased in installation;
2) Bridge Erector, beam car (2) put in place in bridge floor assembly;
3) one end at bridge is reserved 2 holes and is not set up, it is simple to 900 tons of beam shifting machine (5) bale handles pass through, suitable to the other end of bridge from this end Secondary propelling is built bridge;
4) 900 tons of beam shifting machine (5) bale handles and travel to bridge floor circuit overlapping positions, then wheels turn to 90 degree, bridge face row Fill beam position to beam car (2) place, beam is filled on beam car (2);
5) 900 tons of beam shifting machine (5) dress beam backed off after randoms, beam car (2) starts to transport beam, pushes ahead bridge formation;
6) if only built bridge to the other end from one end, after this end-rack is complete, after-frame holes;If only from middle to two end-rack Bridge, after an end-rack is complete, then lifts Bridge Erector, beam car (2) or dismounts on the bridge of bridge another side, treat that another end-rack is complete After, after-frame holes;
The erection method of last holes is: beam is placed on bridge floor by 900 tons of first bale handles of beam shifting machine (5) through 2 preformed holes, then carries another The roof beam structure being placed on bridge floor, on bridge pier, is then set to last hole by the erection in an outer hole, after having set up, and 900 tons Beam shifting machine (5) bridge is dismantled.
The most according to claim 1 a kind of utilize 900 tons of beam shifting machines to bridge floor beam car dress beam Summarized Account of Bridge Erection Construction method, its Being characterised by, being built bridge as odd number hole or even hole, the quantity of bridge opening is more than or equal to 3.
CN201610432466.8A 2016-06-17 2016-06-17 It is a kind of to utilize Summarized Account of Bridge Erection Construction method of 900 tons of beam shifting machines to bridge floor beam car dress beam Active CN106087774B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610432466.8A CN106087774B (en) 2016-06-17 2016-06-17 It is a kind of to utilize Summarized Account of Bridge Erection Construction method of 900 tons of beam shifting machines to bridge floor beam car dress beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610432466.8A CN106087774B (en) 2016-06-17 2016-06-17 It is a kind of to utilize Summarized Account of Bridge Erection Construction method of 900 tons of beam shifting machines to bridge floor beam car dress beam

Publications (2)

Publication Number Publication Date
CN106087774A true CN106087774A (en) 2016-11-09
CN106087774B CN106087774B (en) 2018-02-06

Family

ID=57236793

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610432466.8A Active CN106087774B (en) 2016-06-17 2016-06-17 It is a kind of to utilize Summarized Account of Bridge Erection Construction method of 900 tons of beam shifting machines to bridge floor beam car dress beam

Country Status (1)

Country Link
CN (1) CN106087774B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638315A (en) * 2016-11-10 2017-05-10 秦皇岛天业通联重工科技有限公司 Combined beam transporting vehicle
CN110055894A (en) * 2018-11-21 2019-07-26 中铁十一局集团第六工程有限公司 A kind of flow type bridge erecting machine and its heavy grade erecting beam construction method
WO2020233501A1 (en) * 2019-05-23 2020-11-26 中铁二局集团有限公司 Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder
CN114635360A (en) * 2022-03-11 2022-06-17 中铁第五勘察设计院集团有限公司 Method for erecting bridge body

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080107085A (en) * 2007-06-05 2008-12-10 삼성물산 주식회사 Construction method for girder in bridge and crane for pulling up girder, vehicle for carriage girder, girder used for the same
CN201180066Y (en) * 2008-01-03 2009-01-14 中铁二局股份有限公司 Tyre type large-capacity tonnage carrying implement
CN201932818U (en) * 2010-12-30 2011-08-17 徐州徐工铁路装备有限公司 Hole-girder type box girder crane
CN202688887U (en) * 2012-07-13 2013-01-23 徐州徐工铁路装备有限公司 Anchoring device for girder transporting vehicle
CN103132459A (en) * 2013-03-01 2013-06-05 中铁十七局集团第三工程有限公司 Method for picking beams of beam lifting and carrying machine for railway bridging
JP5649637B2 (en) * 2012-11-27 2015-01-07 三菱重工鉄構エンジニアリング株式会社 Bridge erection device and bridge erection method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080107085A (en) * 2007-06-05 2008-12-10 삼성물산 주식회사 Construction method for girder in bridge and crane for pulling up girder, vehicle for carriage girder, girder used for the same
CN201180066Y (en) * 2008-01-03 2009-01-14 中铁二局股份有限公司 Tyre type large-capacity tonnage carrying implement
CN201932818U (en) * 2010-12-30 2011-08-17 徐州徐工铁路装备有限公司 Hole-girder type box girder crane
CN202688887U (en) * 2012-07-13 2013-01-23 徐州徐工铁路装备有限公司 Anchoring device for girder transporting vehicle
JP5649637B2 (en) * 2012-11-27 2015-01-07 三菱重工鉄構エンジニアリング株式会社 Bridge erection device and bridge erection method
CN103132459A (en) * 2013-03-01 2013-06-05 中铁十七局集团第三工程有限公司 Method for picking beams of beam lifting and carrying machine for railway bridging

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638315A (en) * 2016-11-10 2017-05-10 秦皇岛天业通联重工科技有限公司 Combined beam transporting vehicle
CN106638315B (en) * 2016-11-10 2024-04-09 秦皇岛天业通联重工科技有限公司 Combined beam transporting vehicle
CN110055894A (en) * 2018-11-21 2019-07-26 中铁十一局集团第六工程有限公司 A kind of flow type bridge erecting machine and its heavy grade erecting beam construction method
CN110055894B (en) * 2018-11-21 2024-02-09 中铁十一局集团第六工程有限公司 Mobile bridge girder erection machine and large-gradient girder erection construction method thereof
WO2020233501A1 (en) * 2019-05-23 2020-11-26 中铁二局集团有限公司 Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder
US11391004B1 (en) 2019-05-23 2022-07-19 China Railway No. 2 Engineering Group Co. LTD. Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder
CN114635360A (en) * 2022-03-11 2022-06-17 中铁第五勘察设计院集团有限公司 Method for erecting bridge body

Also Published As

Publication number Publication date
CN106087774B (en) 2018-02-06

Similar Documents

Publication Publication Date Title
CN106760619B (en) A kind of building translation apparatus and its construction method
CN106087774A (en) A kind of utilize 900 tons of beam shifting machines to bridge floor beam car dress beam Summarized Account of Bridge Erection Construction method
CN103215894B (en) Portable interim prestressed stretch-draw anchor block
CN105256713B (en) Half assembled steel concrete combination beam and its method of construction
CN106012878A (en) Construction method for continuous type construction auxiliary girder in jacking of railway box culvert and device for implementing construction method
CN106401592A (en) Construction method for tunnel boring off-contact sending and receiving platform of up-down overlapped tunnel
CN103016029A (en) Grouped second liner construction method for large cross-section tunnel
CN105672353B (en) A kind of cast-in-place diaphram wall and assembled metro station construction integral method
CN102200019B (en) Tunnel boring machine middle-plate stepping reinforcing support mechanism and construction method thereof
CN103075163A (en) Support change process of second liner construction of large-cross-section tunnel
CN110055902A (en) Bridge construction method and its erection method on a kind of large-tonnage box beam normotopia bale handle
CN205638490U (en) A portable platform truck that is used for subway station tread wind channel to pour
CN204716257U (en) Guarantee that shield whole starts and the variable door opening cribbing of station main body synchronous construction
CN202039858U (en) Automatically-folded multifunctional tunnel construction scaffolding
CN109098099A (en) Continuous truss flexible arch bridge rapid constructing method
CN108004929A (en) A kind of H-type road-cum-rail bridge floorings hanging apparatus and hanging method
CN107939074A (en) The Subway Station Platform and its construction method of a kind of precast splice type
CN202273169U (en) Trestle
CN104564101A (en) Single-tube double-layer tunnel simultaneous construction method
CN104018426A (en) Steel truss installation method
CN103321153B (en) A kind of construction method of Mid and minor spans channel girder
CN207498835U (en) Needle beam combined steel plate beam bridge panel cast-in-place construction sliding form frame system
CN105019357A (en) Method for mounting specially-shaped precast bridge decks on open lattice steel beams of arched bridge
CN104947804B (en) A kind of steel bracket and the construction method that beam-column node structure is built using it
CN104929045B (en) Box girder transfer platform and girder feeding and fetching method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant