CN106087769A - A kind of steel bowstring arch bridge entirety crane barge erection construction method - Google Patents

A kind of steel bowstring arch bridge entirety crane barge erection construction method Download PDF

Info

Publication number
CN106087769A
CN106087769A CN201610663521.4A CN201610663521A CN106087769A CN 106087769 A CN106087769 A CN 106087769A CN 201610663521 A CN201610663521 A CN 201610663521A CN 106087769 A CN106087769 A CN 106087769A
Authority
CN
China
Prior art keywords
ship
crane barge
earth anchor
bridge
wire rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610663521.4A
Other languages
Chinese (zh)
Other versions
CN106087769B (en
Inventor
王华东
杨基好
欧阳光辉
李海超
彭建刚
陆宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FOURTH ENGINEERING Co Ltd OF CHINA RAIWAY TENTH GROUP
China Railway No 10 Engineering Group Co Ltd
Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
FOURTH ENGINEERING Co Ltd OF CHINA RAIWAY TENTH GROUP
China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FOURTH ENGINEERING Co Ltd OF CHINA RAIWAY TENTH GROUP, China Railway No 10 Engineering Group Co Ltd filed Critical FOURTH ENGINEERING Co Ltd OF CHINA RAIWAY TENTH GROUP
Priority to CN201610663521.4A priority Critical patent/CN106087769B/en
Publication of CN106087769A publication Critical patent/CN106087769A/en
Application granted granted Critical
Publication of CN106087769B publication Critical patent/CN106087769B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

The present invention relates to a kind of steel bowstring arch bridge entirety crane barge erection construction method, belong to technical field of bridge construction.It uses at bank side integral assembling, and later stage integral erection is constructed, and uses two table flotations to hang ship and carries out overall crane barge erection construction, comprises the steps: that the earth anchor of crane barge ship is arranged;The overall examination of crane barge ship is hung;The synchronization of crane barge ship retreats;Crane barge ship synchronous rotary 90 °;Crane barge ship moves in place to bridge location direction;At artificial bridge location, precision adjusts, fall bridge.The present invention is by overall crane barge erection construction, it is achieved that the shortest take the navigation channel time and completes integral erection construction, and its construction safety risk is little, takies the navigation channel time short, substantially increases integral erection efficiency, shortens and takies the navigation channel time.The present invention is best suitable for, across having the erection construction that navigation requires the steel structural form bridge in river course, having the strongest suitability and superiority for China railways, highway, municipal administration etc. across the steel structure bridge engineering construction of navigable river.

Description

A kind of steel bowstring arch bridge entirety crane barge erection construction method
Technical field
The present invention relates to a kind of steel bowstring arch bridge entirety crane barge erection construction method, belong to technical field of bridge construction.
Background technology
Lu east, Danyang City bridge is the bridge block on Jinghang Canal, overall length of bridge 294.77m, the most main bridge total length 110m, uses base-supporting Steel Pipe Concrete Tied-arch Bridge.Main bridge superstructure uses 110m single span concrete-filled steel tube tied arch, for Rigid tie bar rigid arch, calculates across footpath L=107.2m, and arch is second-degree parabola, and ratio of rise to span is 1/5.36, and rise is 20m. In view of Jinghang Canal is navigable river, stop navigation for reducing and hinder ETS estimated time of sailing, being designed with land integral assembling, later stage entirety transportation by driving Erection construction method.Owing to arch bridge span is big, prior art is used to carry out crane barge construction, in the safety of erection construction and account for With the time in navigation channel upper exist many uncertain, therefore, how take the navigation channel time minimum in the case of quickly, safety, Effectively complete the integral erection construction of steel bowstring arch bridge, be technical problem urgently to be resolved hurrily in construction.
Summary of the invention
For drawbacks described above present in prior art, the invention provides a kind of construction safety risk little, take navigation channel Time is short, can complete the construction method of the integral erection construction of steel bowstring arch bridge fast and effectively.
The present invention is achieved by the following technical solution: a kind of steel bowstring arch bridge entirety crane barge erection construction method, Steel bowstring arch bridge uses at bank side integral assembling, and later stage integral erection is constructed, and uses 1# crane barge ship and 2# crane barge ship two table flotation to hang Ship carries out overall crane barge erection construction, it is characterized in that: construction as follows:
(1) earth anchor of crane barge ship is arranged: bury several earth anchors, wherein, at least 1# earth anchor, 2# respectively underground in both sides, riverbank Earth anchor, 3# earth anchor, 4# earth anchor, 5# earth anchor are positioned at same bank side and are sequentially distributed along riverbank, at least 6# earth anchor, 7# earth anchor, 8# Earth anchor, 9# earth anchor, 10# earth anchor are positioned at another bank side and are sequentially distributed along riverbank, and 5# earth anchor and 10# earth anchor are arranged on bridge main Pier position;
(2) examination of crane barge ship entirety is hung: every table flotation is hung and is each provided with two wire rope hoists on ship in its rear and front end, utilizes Wire rope hoist on earth anchor and two crane barge ships is connected formation pull rope by steel wire rope, and by controlling pull rope by two table flotations Hang ship and be fixed on water surface bank side, suspension centre is set on steel bowstring arch bridge simultaneously, two table flotations hang the loop wheel machine of ship respectively with steel tied arch Suspension centre on bridge connects, and then two loop wheel machines lift by crane simultaneously and make steel bowstring arch bridge stop lifting when departing from concrete pedestal 20cm, After stablizing and checking that arch bridge is errorless, it is further continued for being lifted to safe altitude;
(3) crane barge ship synchronizes to retreat: by controlling pull rope and utilizing the self power of crane barge ship to make two table flotations hang ship together Step retreats to certain distance backward, and two table flotations are hung ship is fixed on the water surface by controlling pull rope;
(4) crane barge ship synchronous rotary 90 °: by changing the ground anchor location of steel wire rope and controlling the force of steel wire rope and make two Crane barge ship synchronous rotary 90 ° makes arch bridge towards at bridge location, stablizes two table flotations and hangs the appearance of ship by controlling steel wire rope after being rotated in place State;
(5) crane barge ship moves in place at bridge location: the self power being hung ship by two table flotations is moved horizontally at bridge location, directly To at the bridge location, and two table flotations are hung ship it is fixed on the water surface by controlling pull rope;
(6) at artificial bridge location, precision adjusts, fall bridge: coordinate steel wire rope to carry out direction across bridge in main pier position manually calabash And adjust to the precision of both direction along bridge, after precision has adjusted, crane barge ship release sling cable carries out the bridge work that falls.
Further, described earth anchor is the deep timber of 1.5m.
Further, in step (2), every table flotation hangs two wire rope hoists of forward quarter and two fixing volumes at rear portion Machine of raising forms the cross cable of " X " type respectively by steel wire rope with two earth anchor interconnections of corresponding bank side.
Further, in step (3), two table flotations hang ship by control pull rope synchronize retrogressing be by tightening up crane barge ship after The pull rope of the pull rope in portion simultaneously release crane barge forward quarter realizes.
Further, step (4) is carried out in accordance with the following steps: a: change pull rope: hang ship by connecting two table flotations On the steel wire rope of wire rope hoist release from earth anchor, then will connect two steel of two wire rope hoists in crane barge forward quarter A steel wire rope away from Main Pier of Bridges in cord is changed on 10# earth anchor, by another steel wire in these two steel wire ropes Rope is changed on 5# earth anchor and loosens, by the close bridge in two steel wire ropes connecting two wire rope hoists in crane barge ship rear portion One steel wire rope of main pier is changed on 1# earth anchor, is changed to by another steel wire rope in these two steel wire ropes on 6# earth anchor also Loosen;B: crane barge ship rotates: hang ship applying outside by tightening up the steel wire rope being connected with 10# earth anchor and 1# earth anchor to two table flotations Pull strength draw crane barge ship rotate, wherein with on the steel wire rope being connected with 10# earth anchor on 1# crane barge ship and 2# crane barge ship with 1# The traction power of the steel wire rope that earth anchor connects is main;C: strong fix: hang in two table flotations and stop after ship is rotated in place tightening up and 10# The steel wire rope that earth anchor and 1# earth anchor connect, meanwhile tightens up the steel wire rope being connected with 5# earth anchor and 6# earth anchor, until Stablize crane barge ship attitude.
Further, two table flotations hang fixing on the water surface of ship is by tightening up the pull rope being connected to crane barge ship front and back end Realize.
The invention has the beneficial effects as follows: the construction method strong adaptability of the present invention, applied range, can be according to steel tied arch The weight of the integral hoisting of bridge and field condition select rational crane barge ship tonnage, are suitably adapted for the steel system of different size specification Bar arch bridge entirety crane barge erection construction, its construction safety risk is little, takies the navigation channel time short, is best suitable for across having navigation requirement The erection construction of the steel structural form bridge in river course, it greatly improves integral erection efficiency, shortens the navigation channel time that takies, and Almost without coming into operation of any auxiliary material.For China railways, highway, municipal administration etc. across the steel structure bridge of navigable river Engineering construction has the strongest suitability and superiority.
Accompanying drawing explanation
Fig. 1 be in specific embodiment steel bowstring arch bridge entirety crane barge set up in earth anchor and pull rope layout drawing;
Fig. 2 is to carry out overall examination in specific embodiment in the erection of steel bowstring arch bridge entirety crane barge to hang work layout drawing;
Fig. 3 is that in specific embodiment, in the erection of steel bowstring arch bridge entirety crane barge, crane barge ship synchronizes to retreat layout drawing;
Fig. 4 is that in specific embodiment, in the erection of steel bowstring arch bridge entirety crane barge, crane barge ship starts to synchronize 90 ° of rotation layout drawings;
Fig. 5 is that in specific embodiment, in the erection of steel bowstring arch bridge entirety crane barge, 90 ° of rotations of crane barge ship synchronization complete back plane Layout drawing;
Fig. 6 is that in specific embodiment, in the erection of steel bowstring arch bridge entirety crane barge, crane barge ship moves to bridge location horizontal layout Figure;
Fig. 7 is that in specific embodiment, in the erection of steel bowstring arch bridge entirety crane barge, the artificial precision of direction across bridge adjusts schematic diagram;
Fig. 8 is that forward artificial precision adjusts schematic diagram during in specific embodiment, steel bowstring arch bridge entirety crane barge sets up;
In figure: 1,1# earth anchor;2,2# earth anchor;3,3# earth anchor;4,4# earth anchor;5,5# earth anchor;6,6# earth anchor;7,7# earth anchor; 8,8# earth anchor;9,9# earth anchor;10,10# earth anchor;11,1# pull rope;12,2# pull rope;13,3# pull rope;14,4# pull rope; 15,5# pull rope;16,6# pull rope;17,7# pull rope;18,8# pull rope;19, bearing;20, bracing frame;21, stiffness bone Frame;22, interim middle cross beam;23,1# chain block guide chain;24,2# chain block guide chain;25, carrier setting bolt;26,5-1# pulls Calabash guide chain, 27, steel bowstring arch bridge, 28,1# crane barge ship, 29,2# crane barge ship, 30, the main pier of 4#, 31, the main pier of 5#.
Detailed description of the invention
Below by the embodiment of indefiniteness and combine accompanying drawing the present invention is further illustrated:
As shown in drawings, Lu east bridge is steel bowstring arch bridge, uses bank side integral assembling, later stage integrated stand facility Work, uses two table flotations to hang ship: 1# crane barge ship 28,2# crane barge ship 29 carry out overall crane barge erection construction, overall crane barge erection construction Specifically include that the earth anchor of crane barge ship is arranged;The overall examination of crane barge ship is hung;The synchronization of crane barge ship retreats;Crane barge ship synchronizes clockwise Half-twist;Crane barge ship moves in place to bridge location direction;At artificial bridge location, precision adjusts, fall bridge.
By calculate arch bridge bank assembly pedestal hang away from, hang height and at main pier position hang away from, hang height and select The rationally crane barge ship of hoisting weight.Its Specific construction step is as follows:
1, the earth anchor of crane barge ship is arranged:
Several earth anchors, wherein, at least 1# earth anchor 1,2# earth anchor 2,3# earth anchor 3,4# ground are buried respectively underground in both sides, riverbank Anchor 4,5# earth anchor 5 are positioned at same bank side and are sequentially distributed along riverbank, at least 6# earth anchor 6,7# earth anchor 7,8# earth anchor 8,9# earth anchor 9,10# earth anchor 10 is positioned at another bank side and is sequentially distributed along riverbank, and 5# earth anchor 5 is arranged on the main Dun31Chu of 5#, and 10# earth anchor 10 sets Putting the main Dun30Chu of 4#, 1# earth anchor 1,2# earth anchor 2 are correspondingly arranged at the anterior position of 2# crane barge ship, and 6# earth anchor 6,7# earth anchor 7 correspondence set In the rear position of 2# crane barge ship, 3# earth anchor 3,4# earth anchor 4 are correspondingly arranged at the anterior position of 1# crane barge ship, 8# earth anchor 8,9# earth anchor 9 rear positions being correspondingly arranged at 1# crane barge ship, concrete setting is as shown in Figure 1.
Ground anchor location and quantity are arranged according to the hydrolocation in hoisting process of crane barge ship, are risen by early stage Hang, hoisting process is turned and the later stage lifts position in concrete crane barge ship water in place and determines.
2, the examination of crane barge ship entirety is hung:
As shown in Figure 2, the examination of crane barge ship entirety is hung is to hang ship integral lifting by two table flotations to carry out.At 1# crane barge ship 28 Front and back end is respectively provided with two wire rope hoists, holds and is also respectively provided with two wire rope hoists, utilize steel before and after 2# crane barge ship 29 Wire rope hoist on corresponding earth anchor and two crane barge ships is connected formation pull rope by cord.Wherein, 1# earth anchor 1 and 2# earth anchor 2 are connected with two wire rope hoists of 2# crane barge forward quarter by 1# pull rope 11 and 2# pull rope 12 respectively, 1# pull rope 11 With the cross cable that 2# pull rope 12 intersects to form " X " type, 6# earth anchor 6 and 7# earth anchor 7 is drawn by 5# pull rope 15 and 6# respectively Rope 16 is connected with two wire rope hoists at 2# crane barge ship rear portion, and 5# pull rope 15 and 6# pull rope 16 intersects to form " X " type Cross cable, 3# earth anchor 3 and 4# earth anchor 5 is fixed with two of 1# crane barge forward quarter by 3# pull rope 13 and 4# pull rope 14 respectively Hoist engine connects, and 3# pull rope 13 and 4# pull rope 14 intersects to form the cross cable of " X " type, and 8# earth anchor 8 and 9# earth anchor 9 leads to respectively Crossing 7# pull rope 17 and 8# pull rope 18 to be connected with two wire rope hoists of 1# crane barge forward quarter, 7# pull rope 17 and 8# draws Rope 18 intersects to form the cross cable of " X " type.Arranging two suspension centres on steel bowstring arch bridge 27, two table flotations hang the loop wheel machine of ship by hanging Rope steel wire rope is connected with the suspension centre arranged on steel bowstring arch bridge respectively.Then by tightening up above-mentioned 8 pull rope by two table flotations Hang ship and be fixed on water surface bank side.
After preparation completes, crane barge commander assigns unified instruction, and two table flotations are hung and slowly lifted by crane, when arch bridge departs from concrete During pedestal 20cm, crane barge commander assigns halt instruction, stablizes arch bridge, and check arch bridge comprehensively, observes deformation etc., After all are errorless, continue to be lifted to certain safe altitude (liftoff 2m).During lifting, special messenger should be had to watch steel wire rope at suspension centre Degree of tightness situation, find potential safety hazard should suspend lifting immediately, process.
3, crane barge ship synchronizes to retreat:
The synchronization retrogressing of crane barge ship hangs quarter pull rope by two table flotations and self power is worked in coordination with and carried out, such as accompanying drawing Shown in 3, by tightening up 7# the pull rope 17 and 8# pull rope 18 of 1# crane barge ship 28 afterbody and tightening up 2# crane barge ship 29 afterbody simultaneously 5# pull rope 15 and 6# pull rope 16 provide power carry out synchronize retreat, provided by the power of crane barge ship self simultaneously Retreat thrust.Meanwhile discharge two table flotations and hang the 1# pull rope 11 in fore portion, 2# pull rope 12,3# pull rope 13,4# traction Rope 14, wait retreating to certain distance (20m), stops tightening up 5# pull rope 15,6# pull rope 16,7# pull rope 17,8# traction Rope 18, and brake two table flotations hang ship by fastening 1# pull rope 11,2# pull rope 12,3# pull rope 13,4# pull rope 14, treat 8 pull ropes all fasten after stablizing, and two table flotations are hung ship and are i.e. fixed on the water surface, i.e. complete the construction that crane barge ship synchronizes to retreat Operation.
4, crane barge ship synchronizes to turn clockwise 90 °:
It is to adjust crane barge ship attitude by the ground anchor location of conversion steel wire rope that crane barge ship synchronizes to turn clockwise 90 °.Its Specifically comprise the following steps that
A: change pull rope: the pull rope connecting two table flotations and hanging the wire rope hoist on ship is released, then from earth anchor 2# pull rope 12,4# pull rope 14 are changed on 10# earth anchor 10,5# pull rope 15,7# pull rope 17 are changed to 1# earth anchor 1 On, meanwhile 1# pull rope 1,3# pull rope 3 are changed on 5# earth anchor 5 and loosened, by 6# pull rope 16,8# pull rope 18 Change on 6# earth anchor 6 and loosen.
B: crane barge ship rotate: by tighten up 2# pull rope 12,4# pull rope 14,5# pull rope 15,7# pull rope 17 to Two table flotations are hung the outside pull strength clockwise of ship applying and are rotated clockwise to draw crane barge ship, under the effect of current Crane barge attitude can be adjusted effectively and rapidly, wherein based on 4# pull rope 14, the traction power of 5# pull rope 15, until rotation Turn in place, as shown in Figure 4.
C: strong fix: hang stopping contraction 2# pull rope 12,4# pull rope 14,5# when ship rotates to 90 ° in two table flotations and lead Messenger 15,7# pull rope 17, meanwhile shrink 1# pull rope 1,3# pull rope 3,6# pull rope 16,8# pull rope 18 Tighten up, until stablizing crane barge ship attitude, as shown in Figure 5.
5, crane barge ship moves in place at bridge location:
It is to be travelled at bridge location by crane barge ship self power that crane barge ship moves in place to bridge location direction, until near bridge location Place.Specifically comprise the following steps that
After crane barge ship has turned clockwise, should move horizontally at bridge location direction, move at current and crane barge ship self The lower power forming movement of the effect of power moves at bridge location.After starting crane barge ship self power, crane barge ship is slowly at bridge location Mobile, the most slowly release 5# pull rope 15,6# pull rope 16,7# pull rope 17,8# pull rope 18, and according to speed of advancing Degree shrinks 1# pull rope 11,2# pull rope 12,3# pull rope 13,4# pull rope 14, until crane barge ship following current traveling sets to distance Meter bridge location 10m place stops power and navigates by water, and fixes two table flotations hang the water surface site of ship by tightening up 8 pull ropes.
After crane barge ship is stable, improve the height of arch bridge, until exceeding by shrinking sling cable on crane barge main hook Bridge location designed elevation 1m, by shrinking 1# pull rope 11,2# pull rope 12,3# pull rope 13,4# pull rope 14 after stable There is provided onward impulse, at slow for arch bridge transportation by driving to bridge location.And fix two table flotations hang ship again by tightening up 8 pull ropes Water surface site, actual plane is arranged as shown in Figure 6.6, at artificial bridge location, precision adjusts, fall bridge:
At artificial bridge location, precision adjusts, the bridge that falls is by coordinating steel wire rope to carry out cross-bridges in main pier position manually calabash To and along precision from bridge to both direction adjust, after precision has adjusted, crane barge ship discharge sling cable carry out the bridge work that falls Make.
After crane barge ship is fixing, carry out falling bridge construction, is carried out falling bridge by sling cable on release crane barge main hook, waits To the last 10cm discrepancy in elevation, use and manually on main pier, carry out precision adjustment, adjust in place after can fall bridge.Concrete operations As follows:
(1) direction across bridge accurate adjustment: use chain block to be finely adjusted, two chain block guide chains are set at a bridge location, with As a example by the main pier of 5#, as shown in Figure 7,1# chain block guide chain 23 is fixed on the bearing 19 of 5-1# pier stud by steel wire rope one end At bolt 25, the other end is fixed on the stiff skeleton 21 on 5-2# pier stud by chain block;2# chain block guide chain 24 is led to Crossing at the bolt 25 of the bearing 19 that steel wire rope one end is fixed on 5-2# pier stud, the other end is fixed on 5-1# pier stud by chain block On stiff skeleton 21 on;
If arch bridge offsets to 5-2# pier direction, then led by contraction 1# chain block guide chain 23, release 2# chain block Chain 24 regulates bridge location and moves to 5-1# pier stud direction and carry out accurate adjustment.On the contrary, if arch bridge offsets to 5-1# pier direction, then pass through Shrink 2# chain block guide chain 24, release 1# chain block guide chain 23 regulates bridge location and moves to 5-2# direction and carry out accurate adjustment.Treat After direction across bridge position adjustment is in place, 1#, 2# chain block guide chain should be fastened, it is ensured that main bridge does not shifts at direction across bridge simultaneously.
(2) along bridge to accurate adjustment: the main pier of this bridge is 4#, 5# pier, suitable bridge is also to carry out accurate adjustment by chain block to regulation, tool Body as shown in Figure 8, arranges (26) 5-1# chain block guide chain 26 on the main pier of 5#, and one end is fixed on the bolt 25 of bearing 19 On, the other end is fixed on interim middle cross beam 22;Arranging 4-1# chain block guide chain on the main pier of 4# equally, one end is fixed on props up On seat bolt, the other end is fixed on interim middle cross beam.
If bridge location offsets to 5# main pier side, then accurately adjusted by contraction 4-1# chain block guide chain;If it is main Bridge offsets to 4# main pier side, then accurately adjusted by contraction 5-1# chain block guide chain 26, until along bridge to just adjusting After Wei, answer two ends to fasten chain block, it is ensured that main bridge is not moving along the bridge simultaneously.
Until along bridge after, direction across bridge accurate adjustment completes, crane barge ship should be assigned bridge instruction, crane barge ship release main hook steel immediately Cord, main bridge falls on the support system on bearing, carries out follow-up fixing work subsequently.
Other parts in the present embodiment use known technology, do not repeat them here.

Claims (6)

1. a steel bowstring arch bridge entirety crane barge erection construction method, steel bowstring arch bridge uses at bank side integral assembling, and the later stage is whole Body erection construction, uses 1# crane barge ship (28) and 2# crane barge ship (29) two table flotation to hang ship and carries out overall crane barge erection construction, and it is special Levy and be: construction as follows:
(1) earth anchor of crane barge ship is arranged: bury several earth anchors, wherein, at least 1# earth anchor (1), 2# respectively underground in both sides, riverbank Earth anchor (2), 3# earth anchor (3), 4# earth anchor (4), 5# earth anchor (5) are positioned at same bank side and are sequentially distributed along riverbank, at least 6# ground Anchor (6), 7# earth anchor (7), 8# earth anchor (8), 9# earth anchor (9), 10# earth anchor (10) are positioned at another bank side and are sequentially distributed along riverbank, And 5# earth anchor (5) and 10# earth anchor (10) are arranged on Main Pier of Bridges position;
(2) examination of crane barge ship entirety is hung: every table flotation is hung and is each provided with two wire rope hoists on ship in its rear and front end, utilizes steel wire Restrict to connect the wire rope hoist on earth anchor and two crane barge ships and form pull rope, and by controlling pull rope, two table flotations are hung ship Be fixed on water surface bank side, suspension centre be set on steel bowstring arch bridge simultaneously, two table flotations hang the loop wheel machine of ship respectively with on steel bowstring arch bridge Suspension centre connect, then two loop wheel machines lift by crane simultaneously and make steel bowstring arch bridge stop lifting when departing from concrete pedestal 20cm, stable And after checking that arch bridge is errorless, be further continued for being lifted to safe altitude;
(3) crane barge ship synchronize retreat: by control pull rope and utilize the self power of crane barge ship make two table flotations hang ship synchronize to Retreat to certain distance, and two table flotations are hung ship be fixed on the water surface by controlling pull rope;
(4) crane barge ship synchronous rotary 90 °: by changing the ground anchor location of steel wire rope and controlling the force of steel wire rope and make two table flotations hang Ship synchronous rotary 90 ° makes arch bridge towards at bridge location, stablizes two table flotations and hangs the attitude of ship by controlling steel wire rope after being rotated in place;
(5) crane barge ship moves in place at bridge location: the self power being hung ship by two table flotations is moved horizontally at bridge location, until leaning on At nearly bridge location, and two table flotations are hung ship it is fixed on the water surface by controlling pull rope;
(6) at artificial bridge location, precision adjusts, fall bridge: coordinate steel wire rope to carry out direction across bridge and suitable in main pier position manually calabash Bridge adjusts to the precision of both direction, and after precision has adjusted, crane barge ship release sling cable carries out the bridge work that falls.
Steel bowstring arch bridge entirety crane barge erection construction method the most according to claim 1, is characterized in that: described earth anchor is The deep timber of 1.5m.
Steel bowstring arch bridge entirety crane barge erection construction method the most according to claim 1 and 2, is characterized in that: step (2) In, two wire rope hoists of two wire rope hoists and rear portion that every table flotation hangs forward quarter pass through steel wire rope respectively with corresponding Two earth anchor interconnections of bank side form the cross cable of " X " type.
Steel bowstring arch bridge entirety crane barge erection construction method the most according to claim 1 and 2, is characterized in that: step (3) In, it is by tightening up the pull rope at crane barge ship rear portion and discharging crane barge simultaneously that two table flotations hang ship by control pull rope synchronizing to retreat The pull rope of forward quarter realizes.
Steel bowstring arch bridge entirety crane barge erection construction method the most according to claim 1 and 2, is characterized in that: in step (4) Carry out in accordance with the following steps:
A: change pull rope: is released from earth anchor by the steel wire rope connecting two table flotations and hanging the wire rope hoist on ship, then will company Connect the steel wire rope away from Main Pier of Bridges in two steel wire ropes of two wire rope hoists in crane barge forward quarter and change to 10# ground On anchor (10), another steel wire rope in these two steel wire ropes is changed to 5# earth anchor (5) and above and loosens, after crane barge ship being connected One steel wire rope of the close Main Pier of Bridges in two steel wire ropes of two wire rope hoists in portion is changed on 1# earth anchor (1), will Another steel wire rope in these two steel wire ropes is changed to 6# earth anchor (6) and above and is loosened;
B: crane barge ship rotates: hang ship to two table flotations execute by tightening up the steel wire rope being connected with 10# earth anchor (10) and 1# earth anchor (1) Add external traction force and rotate to draw crane barge ship, wherein float with the steel wire rope being connected with 10# earth anchor (10) on 1# crane barge ship and 2# The traction power hanging the steel wire rope being connected on ship with 1# earth anchor (1) is main;
C: strong fix: hang in two table flotations and stop after ship is rotated in place tightening up the steel being connected with 10# earth anchor (10) and 1# earth anchor (1) Cord, meanwhile tightens up the steel wire rope being connected with 5# earth anchor (5) and 6# earth anchor (6), until stablizing crane barge ship attitude.
Steel bowstring arch bridge entirety crane barge erection construction method the most according to claim 1 and 2, is characterized in that: two table flotations are hung Fixing on the water surface of ship is to realize by tightening up the pull rope being connected to crane barge ship front and back end.
CN201610663521.4A 2016-08-12 2016-08-12 A kind of overall crane barge erection construction method of steel bowstring arch bridge Active CN106087769B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610663521.4A CN106087769B (en) 2016-08-12 2016-08-12 A kind of overall crane barge erection construction method of steel bowstring arch bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610663521.4A CN106087769B (en) 2016-08-12 2016-08-12 A kind of overall crane barge erection construction method of steel bowstring arch bridge

Publications (2)

Publication Number Publication Date
CN106087769A true CN106087769A (en) 2016-11-09
CN106087769B CN106087769B (en) 2017-10-10

Family

ID=57456387

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610663521.4A Active CN106087769B (en) 2016-08-12 2016-08-12 A kind of overall crane barge erection construction method of steel bowstring arch bridge

Country Status (1)

Country Link
CN (1) CN106087769B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107905116A (en) * 2017-12-19 2018-04-13 中机建重工有限公司 Construction method of large-span through type rigid tied steel arch bridge
CN109552563A (en) * 2018-12-18 2019-04-02 中铁广州工程局集团有限公司 A kind of accurate positioning method of barge
CN110747752A (en) * 2019-10-31 2020-02-04 上海东鼎钢结构有限公司 Floating-dragging method installation process for large-span steel structure arch bridge
CN110878531A (en) * 2019-10-18 2020-03-13 安徽省路港工程有限责任公司 Navigation water steel bridge pushing and dragging system and construction method thereof
CN113684760A (en) * 2021-08-03 2021-11-23 中交路桥建设有限公司 Method for hoisting ropeless area beam section of half-through basket arch bridge
CN114319136A (en) * 2022-01-19 2022-04-12 江苏海洋大学 Rapid construction method for pushing steel bridge floating crane in navigation water area

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1811070A (en) * 2005-01-28 2006-08-02 上海市第七建筑有限公司 First-arch-then-beam concrete steel skeleton constructing process for through arch bridge with mooring post of steel pipe concrete
KR101118526B1 (en) * 2011-09-08 2012-03-12 주식회사 한진중공업 Construction method of steel tower of bridge and dismantling method of lifting frame
CN103866693A (en) * 2014-03-13 2014-06-18 中石化胜利建设工程有限公司 Installing method of reinforced concrete bowstring rod arch bridge arch ribs and hanging auxiliary bridge
CN104594197A (en) * 2014-12-01 2015-05-06 中铁二十局集团第一工程有限公司 Construction process of large-span steel tube arch bridge without supports
CN105672134A (en) * 2016-01-26 2016-06-15 河海大学 Through concrete-filled steel tube tied-arch bridge erection construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1811070A (en) * 2005-01-28 2006-08-02 上海市第七建筑有限公司 First-arch-then-beam concrete steel skeleton constructing process for through arch bridge with mooring post of steel pipe concrete
KR101118526B1 (en) * 2011-09-08 2012-03-12 주식회사 한진중공업 Construction method of steel tower of bridge and dismantling method of lifting frame
CN103866693A (en) * 2014-03-13 2014-06-18 中石化胜利建设工程有限公司 Installing method of reinforced concrete bowstring rod arch bridge arch ribs and hanging auxiliary bridge
CN104594197A (en) * 2014-12-01 2015-05-06 中铁二十局集团第一工程有限公司 Construction process of large-span steel tube arch bridge without supports
CN105672134A (en) * 2016-01-26 2016-06-15 河海大学 Through concrete-filled steel tube tied-arch bridge erection construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
尹振君: ""钢管混凝土系杆拱桥无支架施工技术浅析"", 《黑龙江科技信息》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107905116A (en) * 2017-12-19 2018-04-13 中机建重工有限公司 Construction method of large-span through type rigid tied steel arch bridge
CN109552563A (en) * 2018-12-18 2019-04-02 中铁广州工程局集团有限公司 A kind of accurate positioning method of barge
CN109552563B (en) * 2018-12-18 2020-04-28 中铁广州工程局集团有限公司 Precise positioning method for barge
CN110878531A (en) * 2019-10-18 2020-03-13 安徽省路港工程有限责任公司 Navigation water steel bridge pushing and dragging system and construction method thereof
CN110747752A (en) * 2019-10-31 2020-02-04 上海东鼎钢结构有限公司 Floating-dragging method installation process for large-span steel structure arch bridge
CN113684760A (en) * 2021-08-03 2021-11-23 中交路桥建设有限公司 Method for hoisting ropeless area beam section of half-through basket arch bridge
CN114319136A (en) * 2022-01-19 2022-04-12 江苏海洋大学 Rapid construction method for pushing steel bridge floating crane in navigation water area
CN114319136B (en) * 2022-01-19 2023-04-25 江苏海洋大学 Rapid construction method for pushing steel bridge floating crane in navigable water area

Also Published As

Publication number Publication date
CN106087769B (en) 2017-10-10

Similar Documents

Publication Publication Date Title
CN106087769A (en) A kind of steel bowstring arch bridge entirety crane barge erection construction method
CN102251530B (en) Construction process of double-wall steel cofferdam for construction of pier bearing platform in main river water of Yellow River
CN108532465B (en) A kind of construction method of the main bridge of Through Steel case arch bridge
CN104963301B (en) The dilatory translation downward putting device and method removed for pier top beam section and bridge pier
CN103167983B (en) Ship for installing offshore wind turbines, and method for installing offshore wind turbines using same
CN102071644B (en) Lifting installation method of integral bridge arch rib
CN102912730B (en) Hoisting construction method for single-rib closure rope of large-span reinforced concrete arch bridge
CN102561191A (en) Integral lifting system and construction method for arch bridge ribs
CN106087752B (en) Multispan cable-carried arch bridge construction method
CN105839537B (en) Construction method for hoisting stiffening girder of suspension bridge by adopting girdle-carrying traveling of deck erection gantry
CN101117795A (en) Mounting method for steel case basket arch single-frame segment
CN106049293B (en) Stiffening girder of suspension bridge installation method and used shifting system is swung on navigable river
CN104480865B (en) A kind of Large Steel open caisson accurate positioning method
CN102367650A (en) Construction method of steel pipe arch bridge
CN105603881A (en) Integral erecting system for large sea-crossing arch bridge and construction method thereof
CN105484162B (en) Suspension bridge construction stiff girder secondary on the bank swings moving device and method
CN108265628A (en) One kind rides cable-styled erection crane lifting cable-stayed bridge girder steel and bridge floor board construction method
CN107119567A (en) Suspension bridge steel box-girder deck erection gantry and spreading hoist cable swing shifting construction method
CN106192776A (en) A kind of big Span Continuous Flexible arch bridge with steel truss beam free cantilever erection construction technology
CN103882812A (en) Construction method for midspan main beams of cable-stayed bridge
CN104925672A (en) Full-hydraulic self-climbing suspended double-sided tower crane
CN208088097U (en) A kind of three-tower suspension bridge erection of main beam constructing structure
CN108396754A (en) A kind of floating construction method for spelling steel cofferdam and its lower water of suspention
CN105484168A (en) Rotary hoisting equipment for stiffening beam of suspension bridge and erecting method of stiffening beam
CN202380403U (en) Integral hoisting system of arch rib of arch bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant