CN106087745A - A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method - Google Patents

A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method Download PDF

Info

Publication number
CN106087745A
CN106087745A CN201610301377.XA CN201610301377A CN106087745A CN 106087745 A CN106087745 A CN 106087745A CN 201610301377 A CN201610301377 A CN 201610301377A CN 106087745 A CN106087745 A CN 106087745A
Authority
CN
China
Prior art keywords
construction
concrete
crossbeam
girder
fulcrum
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610301377.XA
Other languages
Chinese (zh)
Other versions
CN106087745B (en
Inventor
邓青儿
于洋
金德�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201610301377.XA priority Critical patent/CN106087745B/en
Publication of CN106087745A publication Critical patent/CN106087745A/en
Application granted granted Critical
Publication of CN106087745B publication Critical patent/CN106087745B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method, described monolithic construction includes crossbeam, across a girder, it is characterized in that the method comprises the following steps: A, fulcrum both sides arrange across a girder steel construction, described fulcrum includes limit fulcrum and central bearing point;B, pour floorings and concrete beam, at described position of the fulcrum casting concrete crossbeam so that described concrete beam and the concrete slab above a girder are connected as a single entity.The technical characterstic of the present invention and effect be, 1, crossbeam changed into concrete beam by conventional steel structure beam, cost reduces;2, Site Welding workload reduces, and construction method is conventional, easy, reduces difficulty of construction, and construction quality is easily controlled;3, crossbeam and be positioned at same elevation plane across a girder, both form unitary construction, are not take up too many under-clearance, and structure height is less, and Bridge Landscape is good;4, late maintaining workload reduces.

Description

A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method
The present invention is filing date on October 17th, 2012, Application No. 2012103943817, invention entitled " a kind of Multiple-piece composite beam bridge top and the bottom monolithic construction and construction method thereof " the divisional application of patent application.
Technical field
The present invention relates to the civil engineering technical field of bridge, specifically a kind of multiple-piece composite beam bridge top and the bottom are whole Body formula structure and construction method thereof.
Background technology
In conventional bridge, beam bridge accounts for the overwhelming majority, and beam bridge is classified by structural system, typically has system of simple supporting, continuous (firm structure) System.Classify by construction material, typically have concrete beam bridge, steel construction beam bridge, steel-concrete combined structure beam bridge.Steel-coagulation Soil combinative structure is divided into again combined steel plate beam, compound section steel box girder, Corrugated webs steel-concrete composite beam etc. according to section difference. The situation bigger for adapting to bridge width, multiple-piece steel-concrete combined steel plate continuous beam and multiple-piece steel-concrete combination steel The advantages such as case continuous beam is little due to monolithic beam lifting weight, and processing is easy, construction is rapid, span ability is strong increasingly have extensively should Trend.But steel structure beam or concrete bent cap are generally set at pier top position of the fulcrum, thus bring problems.
Use steel structure beam time, as it is shown in figure 1, gooseneck 11 and across a girder 12 in same elevation plane, design For the common force modes of beam in length and breadth.First lift gooseneck during construction, lift across a girder afterwards, then both are welded into entirety.Should The advantage of scheme is to be not take up too many under-clearance, and structure height is little, and corresponding Bridge Landscape is preferable, but rolled steel dosage is more, Cost is higher, and weld seam is intensive near fulcrum, and welding residual stress is big, there is a large amount of building sites weld seam, and welding condition is poor, weld seam Difficult quality guarantee, it addition, the application maintenance of steel structure beam adds later stage expense and workload.
When using concrete bent cap, as shown in Figure 2, although construct the most conventional, easy, late maintaining work is few, but Owing to superstructure 13 is supported on the bent cap 14 of substructure, position of the fulcrum structure height is that superstructure deck-molding adds bottom Structural cover depth of beam, structure height is higher, Bridge Landscape phase strain differential, it is ensured that need during under-clearance to raise floor elevation, from And increase bridge length and improve cost.
Summary of the invention
It is an object of the invention to provide a kind of multiple-piece composite beam bridge top and the bottom monolithic construction, it can adapt to the modern times The structure stress requirement of bridge, it is to avoid the shortcoming of the existing Normal practice of above two, the advantage remaining both, at convenient horizontal stroke While beam construction, reduce structure height, save cost, reduce late maintaining.
To achieve these goals, the technical scheme is that a kind of multiple-piece composite beam bridge top and the bottom monoblock type knot Structure, it mainly includes crossbeam, across a girder and across the connecting structure between girder and crossbeam, it is characterised in that: across a girder Using multiple-piece steel-concrete combined steel plate beam or multiple-piece steel-concrete compound section steel box girder, position of the fulcrum arranges crossbeam, institute Stating crossbeam using concrete as material, be provided with prestressed strand in crossbeam, the steel construction part across a girder arranges connection structure Making, concrete parts and crossbeam across a girder pour integral, and above-mentioned crossbeam is connected as a single entity with described connecting structure. Described connecting structure includes shear connector, and the steel construction part across a girder disconnects at crossbeam and is anchored in horizontal stroke by shear key Beam.Described connecting structure also includes deformed bar, described deformed bar through crossbeam and both sides across a girder steel construction Connect.Described connecting structure is steel construction, and described steel construction is connected across a girder steel construction part with both sides.Described Shear connection Part can use socket cap weldering nail, perforated panel shear key etc..
Another object of the present invention is a kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction methods, and it can be fitted Should the structure stress requirement of modern bridge, it is to avoid the shortcoming of the existing Normal practice of above two, the advantage remaining both, While facilitating construction of beam, reduce structure height, save cost, reduce late maintaining.
To achieve these goals, technical scheme is as follows: a kind of multiple-piece composite beam bridge top and the bottom monoblock type Construction method, described monolithic construction includes crossbeam, across a girder, it is characterised in that the method comprises the following steps: A, Arranging across a girder steel construction in fulcrum both sides, described fulcrum includes limit fulcrum and central bearing point;B, pour floorings and concrete Crossbeam, at described position of the fulcrum casting concrete crossbeam so that described concrete beam and the concrete bridge above a girder Panel is connected as a single entity.
According to one embodiment of present invention, in step B, concretely comprising the following steps of central bearing point casting concrete crossbeam: first water Note is across a concrete slab for girder part, is more together poured into a mould with concrete beam by concrete slab near central bearing point. According to another embodiment of the present invention, in step B, concretely comprising the following steps of central bearing point casting concrete crossbeam: in first cast lower floor Fulcrum concrete beam, then the concrete slab of girder part between casting bay, finally concrete near cast central bearing point crossbeam Floorings.
According to the first embodiment of the present invention, described disconnect near fulcrum across a girder steel construction, across a girder steel Structure end is provided with shear connector, and in step B, casting concrete crossbeam is allowed to be connected as a single entity with described shear connector.According to this The second bright embodiment, described disconnects near fulcrum across a girder steel construction, cuts being provided with across a girder steel construction end Power key, fulcrum both sides between a girder steel construction, be also associated with deformed bar, in step B, casting concrete crossbeam makes Be connected as a single entity with described shear connector and deformed bar.According to the third embodiment of the invention, described position of the fulcrum is also provided with Having steel construction, with being connected across a girder steel construction of both sides, in step B, casting concrete crossbeam is allowed to pass with described The steel construction of fulcrum is connected as a single entity.
The obvious technical characterstic that the present invention is consisted of such scheme feature, 1, crossbeam changes by conventional steel structure beam For concrete beam, cost reduces;2, Site Welding workload reduces, and construction method is conventional, easy, reduces difficulty of construction, Construction quality is easily controlled;3, crossbeam and be positioned at same elevation plane across a girder, both form unitary construction, are not take up too Many under-clearances, structure height is less, and Bridge Landscape is good;4, late maintaining workload reduces.
Accompanying drawing explanation
Fig. 1 is the schematic diagram one of prior art, and wherein Fig. 1 a is elevation, and Fig. 1 b is the A-A profile of Fig. 1 a.
Fig. 2 is the schematic diagram two of prior art, and wherein Fig. 2 a is elevation, and Fig. 2 b is the B-B profile of Fig. 2 a.
Fig. 3 is the structural representation of one embodiment of the invention, and wherein Fig. 3 a is elevation, and Fig. 3 b is the C-C section of Fig. 3 a Figure.
Fig. 4 is the structural representation of further embodiment of this invention, and wherein Fig. 4 a is elevation, and Fig. 4 b is that the D-D of Fig. 4 a cuts open Face figure.
Fig. 5 is the structural representation of another embodiment of the present invention, and wherein Fig. 5 a is elevation, and Fig. 5 b is that the E-E of Fig. 5 a cuts open Face figure.
Fig. 6 is middle cross beam one embodiment sequence of construction schematic diagram of the present invention.
Fig. 7 is middle cross beam of the present invention another embodiment sequence of construction schematic diagram.
Detailed description of the invention
Below in conjunction with the accompanying drawings with embodiment to further description of the present invention.
The present invention is a kind of multiple-piece composite beam bridge top and the bottom monolithic constructions, and it mainly includes crossbeam 1, across a girder 2 And the connecting structure across a girder Yu crossbeam, crossbeam is bridge end face using concrete as material, crossbeam 1 end face, across Girder includes steel construction part and is arranged on the concrete slab of steel construction upper, across the steel construction portion of a girder 2 Dividing and be attached with crossbeam 1 by connecting structure, the concrete parts across a girder 2 is directly linked together with crossbeam 1.That is, Concrete slab above the concrete slab 5 of a girder 2 and the concrete of crossbeam 1 and crossbeam 1 pours integral. In figure, 4 is the prestressed strand of crossbeam itself.
Across a girder 2 generally multiple-piece steel-concrete combined steel plate beam or multiple-piece steel-concrete compound section steel box girder, Can need to use freely-supported or continuous structure system according to stress.
The section of crossbeam 1 is rectangle, inverted trapezoidal or other form.Use concrete as construction material, simultaneously and across Girder (including steel construction and concrete roof i.e. concrete slab) is linked as entirety, can need to use regular reinforcement according to stress Concrete or prestressed reinforced concrete structure.
Connecting structure, when across a structure across footpath difference time, different types of attachment can be used according to force request, to guarantee Structure stress safety.As longitudinally across footpath less (less than 20m), the steel construction part across a girder can be disconnected at crossbeam, Across a girder 2 end, shear connector 3a connecting cross beam 1 is only being set.When across a girder when footpath is between 20 ~ 40m, also need Increase and deformed bar 3b is connected the both sides measure across a girder through crossbeam.When increasing to further across footpath across a girder During more than 60m, near central bearing point, the steel construction part across a girder can not turn off, and continues through crossbeam, and described logical Cross perforate in the steel construction 3c of crossbeam with the prestressed strand 4 of crossbaring itself and regular reinforcement.Wherein, shear connector Socket cap weldering nail, perforated panel shear key etc. can be used.
As across footpath less (less than 20m), shear connector 3a is only set across a girder and is attached with crossbeam, due to disconnected The top part in face along bridge to bearing bigger tension, section lower portion along bridge to bearing relatively huge pressing stress, and whole disconnected The shear key connector in face bears section shearing jointly, and therefore, in the distribution of WELDING STUDS, section upper position should be the closeest Collection, upper position can be the most sparse, and in shear key specification, the shear key that resistance to tension is stronger is preferentially selected in upper position, as The weldering nail shear key etc. that length is longer.
When increasing (between 20 ~ 40m) across footpath, in addition to arranging shear connector, also need to increase to be passed by deformed bar 3b Crossbeam connects the both sides measure across a girder.For prestressing force measure, owing to length is shorter, preferential selection anchor head loss is less Finish rolling screw thread prestressed thick reinforcement and the anchorage of repeatable stretch-draw, on prestressing force is arranged, should focus primarily upon section top Part is to resist tension.Arrange when prestressed thick reinforcement and concentrate, when same section cannot complete anchorage layout, it may be considered that Anchorage point is located at different section to obtain anchoring space.WELDING STUDS requires and the layout when footpath is less and specification requirement phase With.
When increasing further across footpath, the steel construction part across a girder can not turn off, and continues through crossbeam, and In this steel construction, perforate is with the prestressed strand of crossbaring itself and regular reinforcement.Opening diameter should be greater than steel bundle or reinforcing bar Diameter is plus the maximum coarse aggregate diameter of twice, with the anchoring of reinforced steel beam and girder Yu concrete beam, Kong Bianyu steel beam flange plate Distance should be greater than 5cm to ensure the effectiveness that steel beam web plate welds with flange plate.Girder steel top flange plate, bottom wing listrium and web are equal Crossbeam should be continued through.Some shear connectors can be arranged on steel beam web plate, enter with the girder steel ensureing crossbeam with continue to pass through Row effectively connects.Limit crossbeam and less owing to bearing moment of flexure across the connection of a girder, can take above-mentioned little two kinds of companies when footpath Connect mode.
The construction method of bridge still can use routine, ripe prefabrication to combine support casting, i.e. across a girder Steel construction part is prefabricated in the factory.After on-the-spot Bridge Pier Construction completes, set up in column (i.e. fulcrum) both sides support lifting longitudinally across Between the steel construction part of girder, joint connection in site forms entirety, sets up overarm brace, formwork erection, assembling reinforcement at position of the fulcrum, buries underground Crossbeam prestressed strand pipeline, cast floorings and concrete beam, stretch-drawing beam prestressing force, laying is mated formation, and pours into a mould crashproof protecting Hurdle, is finally completed the construction of whole bridge.
Wherein, limit crossbeam can be with once-cast with neighbouring concrete slab, for floorings near solution central bearing point along bridge To the problem that tension is bigger, it is preferable that the floorings above last casting concrete crossbeam.Middle cross beam can use following two Plant arrangement and method for construction: 1, the concrete slab 5 of girder part between first casting bay, near reserved central bearing point, concrete slab is with mixed Solidifying soil crossbeam together pours into a mould (Fig. 6);2, first cast lower floor central bearing point concrete beam 2, the concrete slab portion of reserved crossbeam Divide and do not pour into a mould, then the concrete slab 5 of girder part between casting bay, finally concrete slab near cast central bearing point crossbeam 6(Fig. 7).
When using arrangement and method for construction 2, just can be with stretch-drawing beam prestressing force and remove after crossbeam lower-layer concrete casting complete All bridge lower carriages, this scheme accomplishes during vehicle pass-through requirement to minimize space under bridge impact under having bridge.
According to calculating comparative analysis, a length of central bearing point centrage two that reserved central bearing point concrete slab finally pours Being advisable across footpath in each 0.1 ~ 0.2 times of side, this arrangement and method for construction can reduce into when bridge is open to traffic near central bearing point that drawing of upper limb concrete should Power, is reduced to about 1Mpa by the 2Mpa of conventional once-cast concrete scheme, and owing to concrete is carried out step pouring, Blockage effect can be reduced, reduce shrinkage stress about the 0.5Mpa of concrete under least favorable Load Combination, for optimizing structure Stressed effect is obvious.
With common bridge width 25m, as a example by span setting 3 × 30m steel-concrete combined steel plate continuous beam, section such as Fig. 3, Full-bridge uses steel 236.25t, and floorings use concrete 562.5m3, reinforcing bar 247.5t, crossbeam uses concrete 375m3, steel Bundle 11.25t, reinforcing bar 32t.Compare conventional gooseneck scheme and reduce crossbeam steel about 90t, reduce weld seam about 900m, Qi Zhongshi The field welding about 230m that work difficulty is bigger, reduces the anticorrosive coating area 580m needing maintenance2, this binding beam total price reduces about 95 Ten thousand, being converted into unit price index is 420 yuan/m2, be equivalent to save bridge superstructure cost about 14%.And adopt compared to common By the scheme of concrete bent cap, can reduce deck-molding 1.5m, calculate with headroom current under identical bridge, longitudinal gradient considers according to 3%, whole Individual engineering will reduce bridge area 2500m2, save bridge total cost about 1500W.

Claims (6)

1. a multiple-piece composite beam bridge top and the bottom monolithic construction construction method, described monolithic construction include crossbeam, across Girder, it is characterised in that the method comprises the following steps: A, fulcrum both sides arrange across a girder steel construction, described fulcrum includes Limit fulcrum and central bearing point;B, pour floorings and concrete beam, at described position of the fulcrum casting concrete crossbeam so that described Concrete beam and the concrete slab above a girder are connected as a single entity.
2. the construction method as described in claim 1, it is characterised in that: in step B, central bearing point casting concrete crossbeam concrete Step is: the concrete slab of girder part between first casting bay, then concrete slab near central bearing point is horizontal with concrete Beam is together poured into a mould.
3. the construction method as described in claim 1, it is characterised in that: in step B, central bearing point casting concrete crossbeam concrete Step is: first cast lower floor central bearing point concrete beam, then the concrete slab of girder part between casting bay, finally in cast Concrete slab near fulcrum crossbeam.
4. the construction method as described in claim 1, it is characterised in that: described disconnect near fulcrum across a girder steel construction, A girder steel construction end is being provided with shear connector, and in step B, casting concrete crossbeam is allowed to be linked as one with described shear connector Body.
5. the construction method as described in claim 4, it is characterised in that: described disconnect near fulcrum across a girder steel construction, A girder steel construction end is being provided with shear connector, and connecting between a girder steel construction of fulcrum both sides has prestress steel Muscle, in step B, casting concrete crossbeam is allowed to be connected as a single entity with described shear connector and deformed bar.
6. the construction method as described in claim 1, it is characterised in that: described position of the fulcrum is also equipped with steel construction, with both sides Be connected across a girder steel construction, in step B, casting concrete crossbeam is allowed to be linked as with the described steel construction through fulcrum Integrally.
CN201610301377.XA 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method Active CN106087745B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610301377.XA CN106087745B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201610301377.XA CN106087745B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method
CN201210394381.7A CN103774541B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction and construction method thereof

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201210394381.7A Division CN103774541B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction and construction method thereof

Publications (2)

Publication Number Publication Date
CN106087745A true CN106087745A (en) 2016-11-09
CN106087745B CN106087745B (en) 2017-11-07

Family

ID=50567252

Family Applications (3)

Application Number Title Priority Date Filing Date
CN201610198667.6A Active CN105862597B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method
CN201210394381.7A Active CN103774541B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction and construction method thereof
CN201610301377.XA Active CN106087745B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method

Family Applications Before (2)

Application Number Title Priority Date Filing Date
CN201610198667.6A Active CN105862597B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method
CN201210394381.7A Active CN103774541B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction and construction method thereof

Country Status (1)

Country Link
CN (3) CN105862597B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106930181A (en) * 2017-04-18 2017-07-07 浙江省交通规划设计研究院 A kind of simple-supported thencontinuous steel reinforced concrete combined bridge hogging moment area structure
CN109183615A (en) * 2018-08-17 2019-01-11 中铁大桥勘测设计院集团有限公司 A kind of more girder formula steel reinforced concrete combination continuous beams

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104195950A (en) * 2014-08-15 2014-12-10 中交第二航务工程局有限公司 Steel-concrete composite beam cable-stayed bridge glued joint connecting method
CN105178191B (en) * 2015-08-10 2017-03-22 中交第一公路工程局有限公司 Sand bucket positioning device used for shear pin
CN107044091B (en) * 2017-05-18 2019-03-29 中铁十六局集团铁运工程有限公司 A kind of bridge side bar formwork for placing and its casting method
CN108118610A (en) * 2017-12-26 2018-06-05 上海市政工程设计研究总院(集团)有限公司 A kind of ultra-high performance concrete and regular reinforcement concrete combination beam
CN114592440B (en) * 2022-03-21 2024-03-19 武汉市规划设计有限公司 Upper structure of assembled steel-concrete combined bridge and construction process thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003041516A (en) * 2001-07-27 2003-02-13 Ttk Corp Integral structure of upper and lower parts of continuous girder bridge and method of constructing it
CN201390928Y (en) * 2009-04-16 2010-01-27 中铁二院工程集团有限责任公司 Support rail continuous beam in double track railway
CN102383374A (en) * 2011-11-28 2012-03-21 湖南大学 Fabricated fibrous concrete combined deck structure and construction method thereof
CN102409602A (en) * 2011-12-02 2012-04-11 四川西南交大土木工程设计有限公司 Concrete structure box, plate and joist combined beam
CN102561172A (en) * 2010-12-22 2012-07-11 中交公路规划设计院有限公司 Celled hybrid beam junction with composite connectors
CN102704394A (en) * 2012-06-15 2012-10-03 湖南大学 Steel-fiber concrete combined bridge deck structure with reinforced joints and construction method of steel-fiber concrete combined bridge deck structure

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2928513A1 (en) * 1979-07-14 1981-01-29 Peter Dipl Ing Dr Techn Wagner Demountable steel flyover bridge superstructure - comprises triangular main roadway girder, side border and possibly footpath carriers
CN2816118Y (en) * 2005-06-13 2006-09-13 上海市政工程设计研究院 Prefabricated beam connection structure
CN101570960B (en) * 2009-05-08 2011-06-15 北京市市政专业设计院有限责任公司 Fastening method of T-shaped beam bridge
CN101603288B (en) * 2009-07-03 2012-05-30 中铁大桥局股份有限公司 Three-truss main girder structure of highway and railway bi-purpose cable-stayed bridge and installation method thereof
CN201546165U (en) * 2009-11-18 2010-08-11 上海市城市建设设计研究院 Simple support-continuous box girder structure
CN201648950U (en) * 2010-05-11 2010-11-24 天津市市政工程设计研究院 Novel beam structure of steel-concrete combination section
CN102021885B (en) * 2011-01-04 2012-02-15 上海市城市建设设计研究院 Bridge deck continuous seam structure
CN201924278U (en) * 2011-01-04 2011-08-10 上海市城市建设设计研究院 Continuous seam structure for bridge floor

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003041516A (en) * 2001-07-27 2003-02-13 Ttk Corp Integral structure of upper and lower parts of continuous girder bridge and method of constructing it
CN201390928Y (en) * 2009-04-16 2010-01-27 中铁二院工程集团有限责任公司 Support rail continuous beam in double track railway
CN102561172A (en) * 2010-12-22 2012-07-11 中交公路规划设计院有限公司 Celled hybrid beam junction with composite connectors
CN102383374A (en) * 2011-11-28 2012-03-21 湖南大学 Fabricated fibrous concrete combined deck structure and construction method thereof
CN102409602A (en) * 2011-12-02 2012-04-11 四川西南交大土木工程设计有限公司 Concrete structure box, plate and joist combined beam
CN102704394A (en) * 2012-06-15 2012-10-03 湖南大学 Steel-fiber concrete combined bridge deck structure with reinforced joints and construction method of steel-fiber concrete combined bridge deck structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106930181A (en) * 2017-04-18 2017-07-07 浙江省交通规划设计研究院 A kind of simple-supported thencontinuous steel reinforced concrete combined bridge hogging moment area structure
CN109183615A (en) * 2018-08-17 2019-01-11 中铁大桥勘测设计院集团有限公司 A kind of more girder formula steel reinforced concrete combination continuous beams
CN109183615B (en) * 2018-08-17 2020-05-26 中铁大桥勘测设计院集团有限公司 Multi-main-beam type steel-concrete combined continuous beam

Also Published As

Publication number Publication date
CN105862597B (en) 2017-11-24
CN103774541A (en) 2014-05-07
CN106087745B (en) 2017-11-07
CN103774541B (en) 2016-08-03
CN105862597A (en) 2016-08-17

Similar Documents

Publication Publication Date Title
CN103774541B (en) A kind of multiple-piece composite beam bridge top and the bottom monolithic construction and construction method thereof
CN105839510B (en) A kind of steel and ultra-high performance concrete composite continuous bridge structure and its construction method
CN108677685B (en) Ultra-high-performance concrete-part steel beam combined bent cap and construction method thereof
CN105625572B (en) Distinctiveness uses the precast prestressed concrete frame bean column node of high performance material
CN104988844B (en) Two times tensioning prestressing force assembled Wavelike steel webplate combination beam
CN101613997B (en) Method for widening steel-concrete combination
CN108978434B (en) Bracket-free industrialized construction method of steel-concrete combined continuous box girder bridge
CN108867310A (en) The short rib T beam bridge of pretensioning prestressed concrete and its construction method
CN103046463B (en) Assembly type saddle-shell-shaped bottom plate continuous box girder bridge and construction method thereof
CN101994293A (en) High pier coping construction method
CN109958049A (en) A kind of modularization steel-is mixed to combine small box girder freely-supported continuous bridge and its construction method
CN209144668U (en) A kind of anti-buckling structure of large span box girder with corrugated steel webs
CN106087711B (en) Antinode work beam-steel concrete top plate-external prestressing combines T-shaped simply supported beam
CN107130715A (en) Teeth groove is poured after a kind of to be linked and packed the construction method of formula building roof system
CN208121541U (en) In across the steel reinforced concrete composite beam bridge constructed using no mount approach
CN111254800A (en) Combined beam suitable for urban bridge and construction method thereof
CN106436591A (en) Steel cantilever combined bridge deck slab widening and reconstruction structure and construction method thereof
CN112458877A (en) Assembled steel-concrete combined rigid frame bridge and construction method thereof
CN110644349A (en) Superstructure for wide box girder and short tower cable-stayed bridge and construction method
CN211522899U (en) Long-span steel-concrete composite beam convenient to erect by bridge girder erection machine
CN110331664B (en) Steel-concrete mixed continuous box girder bridge deck joint structure and construction method thereof
CN109137757A (en) A kind of anti-buckling structure of large span box girder with corrugated steel webs and construction method
CN103205930B (en) Structure for continuous transformation of existing simply supported hollow slab girder bridge and construction method of structure
CN205934687U (en) Antinode worker roof beam - steel concrete roof - external prestress combination T type simple beam
CN109972512B (en) Cast-in-place construction method of profiled steel sheet-concrete combined bridge deck slab

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant