CN106049799B - A kind of metope mounting structure - Google Patents

A kind of metope mounting structure Download PDF

Info

Publication number
CN106049799B
CN106049799B CN201610614544.6A CN201610614544A CN106049799B CN 106049799 B CN106049799 B CN 106049799B CN 201610614544 A CN201610614544 A CN 201610614544A CN 106049799 B CN106049799 B CN 106049799B
Authority
CN
China
Prior art keywords
installation
intermediate plate
perpendicular rail
clamping head
shingle nail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610614544.6A
Other languages
Chinese (zh)
Other versions
CN106049799A (en
Inventor
麦志成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Huaye Building Engineering Co ltd
Original Assignee
Guangxi Huaye Building Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Huaye Building Engineering Co Ltd filed Critical Guangxi Huaye Building Engineering Co Ltd
Priority to CN201610614544.6A priority Critical patent/CN106049799B/en
Publication of CN106049799A publication Critical patent/CN106049799A/en
Application granted granted Critical
Publication of CN106049799B publication Critical patent/CN106049799B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0803Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
    • E04F13/081Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and covering elements
    • E04F13/0814Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and covering elements fixed by means of clamping action

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

The present invention provides a kind of metope mounting structure, including installation corner brace, horizontal corner steel, the perpendicular rail of installation, pressure code, intermediate plate and shingle nail;Corner brace is installed to be fixedly mounted by expansion bolt and construction wall, the vertical edge of horizontal corner steel is frontward fixed in corner brace;The perpendicular rail of installation is vertically extending, its front end is equipped with the clamping head axially extended, and that installs perpendicular rail is respectively arranged on the left side and the right side press fitting plane, installs and is linked together between backboard and clamping head by a connector, and connector is equipped with locating slot with clamping head junction;Two pressure code divisions are not pressed in the both sides of the perpendicular rail of installation;Shingle nail is rectangular and four Edge Bends, intermediate plate take the shape of the letter U, and two sides are elastic spring, and the bending edges back side of shingle nail corner is fixed on the base of intermediate plate, and the elastic spring of intermediate plate is clamped in the clamping head of the perpendicular rail of installation, and flange is fastened in locating slot.The present invention realizes the fastening installation of shingle nail.

Description

A kind of metope mounting structure
Technical field
The present invention relates to construction material, is specifically a kind of metope mounting structure.
Background technology
The shingle nail of steel structure type is a kind of nearest common building materials, and surfacing, decoration performance is good, thus is adopted extensively With.
But the mounting structure of metope but there are it is very big the shortcomings that.The steel structure support covered inside shingle nail employs Substantial amounts of welding structure, it is time-consuming and laborious, it is unfavorable for installing.And the connection between shingle nail and steel structure support uses screw more Installation, then screw is covered with strip of paper used for sealing, the installation difficulty of shingle nail is substantially increased, while consume erector significantly When.
Be not difficult to find out, the prior art also there are it is certain the defects of.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of metope mounting structure, realize the fastening installation of shingle nail.
To achieve the above object, the present invention uses following technical scheme:
A kind of metope mounting structure, including installation corner brace, horizontal corner steel, the perpendicular rail of installation, pressure code, intermediate plate and shingle nail; Corner brace is installed to be fixedly mounted by expansion bolt and construction wall, the vertical edge of horizontal corner steel is frontward fixed in corner brace, water The vertical edge of straight angle steel is equipped with least one set of mounting hole of horizontal arrangement;The perpendicular rail of installation is vertically extending, its front end is equipped with edge Axially extending clamping head, the back side for installing perpendicular rail are equipped with the installation backboard that plane is set, and install the left and right sides difference of backboard Equipped with press fitting plane, the outside for being pressed plane is equipped with the crimping tilted forward, installs and passes through a company between backboard and clamping head Junctor links together, and the both sides of clamping head are equipped with locating slot;Code is pressed to be equipped with the matched through hole of mounting hole with horizontal corner steel, One end of pressure code is equipped with the presser feet protruded backward, presses the other end of code to be equipped with the matched pressure head of press fitting plane for erecting rail with installing, Two pressure code divisions are not pressed is pressed respectively against the surface of press fitting plane in the both sides of the perpendicular rail of installation, pressure head, and presser feet is butted on horizontal corner steel Vertical edge surface, the vertical edge for pressing code and horizontal corner steel is press fit together by screw bolt and nut by through hole and mounting hole; Shingle nail is rectangular and four Edge Bends, intermediate plate take the shape of the letter U, and two sides are elastic spring, and the tip of elastic spring is equipped with and locating slot The bending edges back side of shingle nail corner is fixed on the flange to match, the base of intermediate plate, and the elastic spring of intermediate plate is clamped in installation The clamping head of perpendicular rail, and flange is fastened in locating slot.
Preferably, the perpendicular rail of every installation, which is installed at every grade in corner brace, is correspondingly arranged a horizontal corner steel.
Preferably, the front end of the perpendicular rail of the installation is equipped with two clamping heads being set up in parallel in left and right.
Preferably, the front end of the perpendicular rail of the installation is equipped with the single clamping head axially extended.
Preferably, it is equipped with rivet hole in the middle part of the base of the intermediate plate, the bending edges of intermediate plate and shingle nail pass through closing-up Together.
Preferably, it is equipped with notch in the middle part of the two panels elastic spring of the intermediate plate.
A kind of metope mounting structure provided by the invention, makes shingle nail be fastened on the perpendicular rail of installation using intermediate plate, without by means of Other instruments are helped, it is quick and easy for installation.Directly shingle nail is compressed during installation, installation effectiveness greatly improved, reduces work The labor intensity of people.And the mounting means of the perpendicular rail of installation can compensate for construction wall out-of-flatness and produced using pressure code press fitting The alignment tolerance of every grade of horizontal corner steel.
Brief description of the drawings
In order to clearly introduce the technical solution of the embodiment of the present invention, the attached drawing of embodiment will be briefly described below. It should be noted that those skilled in the art can make shape and structure difference according to common knowledge according to Figure of description Its variant designs, as long as the technical characteristic of its variant designs without departing from the present invention claim described in content, still fall within Protection scope of the present invention.The legend of Figure of description is only for reference.
Fig. 1 is a kind of side structure schematic diagram of metope mounting structure provided in this embodiment.
Fig. 2 is a kind of top view of metope mounting structure provided in this embodiment.
Fig. 3 is a kind of stereogram of metope mounting structure provided in this embodiment.
Fig. 4 is the structure diagram of double perpendicular rails of the installation for compressing hair style.
Fig. 5 is the structure diagram of single perpendicular rail of the installation for compressing hair style.
Fig. 6 is the structure diagram of intermediate plate.
Fig. 7 is the structure diagram of pressure code.
Description of reference numerals:
The 1st, corner brace 2, horizontal corner steel are installed
3rd, the perpendicular rail of code 4, installation is pressed
5th, intermediate plate 6, shingle nail
The 7th, backboard 8, press fitting plane are installed
9th, crimping 10, clamping head
11st, connector 12, locating slot
13rd, elastic spring 14, flange
15th, notch 16, pressure head
17th, presser feet
Embodiment
Embodiment
Such as Fig. 1 to Fig. 7, the present invention provides a kind of metope mounting structure, including installation corner brace 1, horizontal corner steel 2, installation Perpendicular rail 4, pressure code 3, intermediate plate 5 and shingle nail 6.
Corner brace 1 is installed to be fixedly mounted by expansion bolt and construction wall, the vertical edge of horizontal corner steel 2 is frontward fixed on In corner brace, the vertical edge of horizontal corner steel 2 is equipped with least one set of mounting hole of horizontal arrangement.
The perpendicular rail 4 of installation is vertically extending, its front end is equipped with the clamping head 10 axially extended, and the back side for installing perpendicular rail 4 is set There is the installation backboard 7 that plane is set, installation backboard 7 is respectively arranged on the left side and the right side press fitting plane 8, and the outside of press fitting plane 8 is set There is the crimping 9 tilted forward, install and linked together between backboard 7 and clamping head 10 by a connector 11, clamping head 10 Both sides be equipped with locating slot 12.Press code 3 to be equipped with the matched through hole of mounting hole with horizontal corner steel 2, set close to the side of through hole There is the presser feet 17 protruded backward, the side away from through hole is equipped with the matched pressure head 16 of press fitting plane 8 with installing perpendicular rail 4, two Pressure code 3 is pressed respectively is pressed respectively against the surface of press fitting plane 8 in the both sides of the perpendicular rail 4 of installation, pressure head 16, and presser feet 17 is butted on horizontal angle The surface of the vertical edge of steel 2, screw bolt and nut will press code 3 and the vertical edge of horizontal corner steel 2 to be fitted in by through hole and mounting hole Together.When rail 4 is erected in installation installation, it is set to produce pretightning force to press fitting plane 8 by tightening pressure code 3, you can be fixed installation Perpendicular rail 4.And the crimping 9 for being pressed the outside of plane 8 is coordinated with pressing the pressure head 16 of code 3, can prevent pressure code 3 and installation erect rail 4 it Between occurred level shift.By the way of pressure code 3 is pressed, it is allowed to installation is perpendicular certain gap between rail 4 and horizontal corner steel 2, Even if horizontal corner steel 2 since construction wall is uneven or the reason such as artificial location tolerance, is caused between multi gear horizontal corner steel 2 no longer Same perpendicular, installing perpendicular rail 4 also can installation fixation as usual.
Shingle nail 6 is rectangular and four Edge Bends, intermediate plate 5 take the shape of the letter U, and two sides are elastic spring 13, the point of elastic spring 13 End is equipped with the flange 14 to match with locating slot 12, and the bending edges back side of 6 four jiaos of shingle nail, intermediate plate 5 are fixed in the base of intermediate plate 5 Elastic spring 13 be clamped in the clamping head 10 of the perpendicular rail 4 of installation, and flange 14 is fastened in locating slot 12.When shingle nail 6 is installed, 6 surface of shingle nail is directly pressed, the elastic spring 13 of intermediate plate 5 elastic can open, and then promptly install the clamping head of perpendicular rail 4 10, and positioned by flange 14 and locating slot 12.
Horizontal corner steel 2 has two kinds of plans of establishment.The first preferred solution is that the perpendicular rail 4 of every installation installs corner brace 1 at every grade On be correspondingly arranged a horizontal corner steel 2;Second of preferred solution is traversed from left to right using a complete horizontal corner steel 2 Whole metope, the horizontal corner steel 2 as one grade of height.What the first scheme can save horizontal corner steel 2 uses material;Second scheme Integraty is stronger, it is not necessary to excessive adjustment.
Such as Fig. 4, it is preferred that the front end of the perpendicular rail 4 of installation is equipped with two clamping heads 10 being set up in parallel in left and right.This side Under case, the perpendicular rail 4 of an installation can be connected with two row intermediate plates 5 side by side, suitable for the metope of plane formula, adjacent two pieces of shingle nails 6 can be connected with two clamping heads 10 respectively.Such as Fig. 5, or the preferred solution as another kind, the front end of the perpendicular rail 4 of installation is set There is the single clamping head 10 axially extended.Edge or corner of the design of this first 10 formula of single clamping suitable for metope, Only need to be connected with one piece of shingle nail 6, therefore two clamping heads 10 are not required.
Preferably, rivet hole is equipped with the middle part of the base of the intermediate plate 5, intermediate plate 5 and the bending edges of shingle nail 6 pass through rivet riveting It is combined, easy to the combination connection between intermediate plate 5 and shingle nail 6.And it is used as further preferred, the two panels of the intermediate plate 5 The middle part of elastic spring 13 is equipped with notch 15, so that a cavity is formed at the middle part closing-up of intermediate plate 5, easy to riveting tool Operation.
A kind of metope mounting structure provided by the present invention, makes shingle nail 6 be fastened on the perpendicular rail 4 of installation, nothing using intermediate plate 5 Must be quick and easy for installation by other instruments.Directly shingle nail 6 is compressed during installation, installation effectiveness greatly improved, is dropped The labor intensity of low worker.And the mounting means of the perpendicular rail 4 of installation is pressed using pressure code 3, can compensate for construction wall out-of-flatness and The alignment tolerance of the every grade of horizontal corner steel 2 produced.
It should be noted that the protection domain of patent of the present invention should be subject to claim.Even if change is made to the present invention Shape and improvement, on the premise of general plotting is without departing from the present invention, still fall within protection scope of the present invention.

Claims (4)

  1. A kind of 1. metope mounting structure, it is characterised in that:Including installation corner brace, horizontal corner steel, the perpendicular rail of installation, pressure code, intermediate plate with And shingle nail;Corner brace is installed to be fixedly mounted by expansion bolt and construction wall, the vertical edge of horizontal corner steel is frontward fixed on In corner brace, the vertical edge of horizontal corner steel is equipped with least one set of mounting hole of horizontal arrangement;The perpendicular rail of installation is vertically extending, before it End is equipped with the clamping head axially extended, and the back side for installing perpendicular rail is equipped with the installation backboard that plane is set, and installs the left and right of backboard Both sides are respectively equipped with press fitting plane, and the outside for being pressed plane is equipped with the crimping tilted forward, install and lead between backboard and clamping head Cross a connector to link together, the both sides of clamping head are equipped with locating slot;The front end of the perpendicular rail of installation is equipped with left and right two side by side The clamping head of setting or equipped with the single clamping head axially extended;Code is pressed to be equipped with matched logical with the mounting hole of horizontal corner steel Hole, presses one end of code to be equipped with the presser feet protruded backward, presses the other end of code to be equipped with the matched pressure of press fitting plane for erecting rail with installing Head, two pressure code divisions are not pressed is pressed respectively against the surface of press fitting plane in the both sides of the perpendicular rail of installation, pressure head, and presser feet is butted on horizontal angle The vertical edge for pressing code and horizontal corner steel is fitted in one by the surface of the vertical edge of steel, screw bolt and nut by through hole and mounting hole Rise;Shingle nail is rectangular and four Edge Bends, intermediate plate take the shape of the letter U, and two sides are elastic spring, and the tip of elastic spring is equipped with and positioning The bending edges back side of shingle nail corner is fixed on the flange that groove matches, the base of intermediate plate, and the elastic spring of intermediate plate is clamped in peace The clamping head of the perpendicular rail of dress, and flange is fastened in locating slot.
  2. 2. metope mounting structure according to claim 1, it is characterised in that:The perpendicular rail of every installation is in every grade of established angle A horizontal corner steel is correspondingly arranged on code.
  3. 3. metope mounting structure according to claim 1, it is characterised in that:Rivet is equipped with the middle part of the base of the intermediate plate Hole, intermediate plate and the bending edges of shingle nail by closing-up together with.
  4. 4. metope mounting structure according to claim 3, it is characterised in that:Set in the middle part of the two panels elastic spring of the intermediate plate It is jagged.
CN201610614544.6A 2016-07-29 2016-07-29 A kind of metope mounting structure Active CN106049799B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610614544.6A CN106049799B (en) 2016-07-29 2016-07-29 A kind of metope mounting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610614544.6A CN106049799B (en) 2016-07-29 2016-07-29 A kind of metope mounting structure

Publications (2)

Publication Number Publication Date
CN106049799A CN106049799A (en) 2016-10-26
CN106049799B true CN106049799B (en) 2018-05-01

Family

ID=57195926

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610614544.6A Active CN106049799B (en) 2016-07-29 2016-07-29 A kind of metope mounting structure

Country Status (1)

Country Link
CN (1) CN106049799B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110295713A (en) * 2018-12-18 2019-10-01 绿城装饰工程集团有限公司 A kind of external corner strip elasticity connected structure and revetment external corner protect structure

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105386557A (en) * 2014-09-03 2016-03-09 上海西蒙幕墙吊顶板有限公司 Novel mounting structure for enameled ceiling
CN204343484U (en) * 2014-12-25 2015-05-20 林佳杰 A kind of wall combined structure for building
CN204703433U (en) * 2015-05-23 2015-10-14 江苏标榜装饰新材料股份有限公司 The mounting structure of middle latch assembly
CN205134861U (en) * 2015-11-30 2016-04-06 浙江亚厦装饰股份有限公司 Wall paper link plate
CN205857602U (en) * 2016-07-29 2017-01-04 麦志成 A kind of metope mounting structure

Also Published As

Publication number Publication date
CN106049799A (en) 2016-10-26

Similar Documents

Publication Publication Date Title
CN106049799B (en) A kind of metope mounting structure
CN205857602U (en) A kind of metope mounting structure
CN205259530U (en) Press mounting type fossil fragments system
CN212000639U (en) Template splicing structure
CN106592878A (en) Photovoltaic panel supporting frame applied to colored steel tile
CN206016144U (en) A kind of carbon steel skeleton metope mounting structure
CN106049800B (en) A kind of carbon steel skeleton metope mounting structure
CN206571000U (en) Link mechanism for screen-separated system
CN205259528U (en) Press mounting type wall system
CN205077803U (en) Single -curved surface honeycomb aluminum board fixed structure
CN213134503U (en) Novel vertical face lining plate of guide ruler of rolling mill
CN211735837U (en) Industrial and civil building expansion joint waterproof construction
CN210562785U (en) Clip type bridge cut-off connecting piece
CN209620597U (en) Wall external angle formwork lock assembly
CN209277526U (en) Aluminum alloy pattern plate for building
CN108666941B (en) Quick mounting bracket applied to wiring of rear supporting trolley of tunnel boring machine
KR20130088463A (en) Field assembly type soundproofing pannel assembly
CN206016143U (en) A kind of pressing type section bar erects rail
JP5457855B2 (en) Solar cell module fixture and mounting structure
CN212176408U (en) Wall panel structure
CN209760678U (en) Plane wall body intergral template connecting fastener and wallboard
CN211923330U (en) Convenient layering structure is assembled to wallboard
CN210562977U (en) Corner girder structure
CN218714467U (en) Photovoltaic roofing installing the system
CN217840688U (en) Oversized metal honeycomb aluminum plate system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20180403

Address after: Fangcheng District of Fangchenggang city the Guangxi Zhuang Autonomous Region 538000 town Fang Qin Lu No. 528

Applicant after: GUANGXI HUAYE BUILDING ENGINEERING Co.,Ltd.

Address before: 510070 Liwan District, Guangzhou, Zhongshan, No. eight road, No. two, ladder 801, 31

Applicant before: Mai Zhicheng

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Wall mounting structure

Effective date of registration: 20211124

Granted publication date: 20180501

Pledgee: China Construction Bank Corporation Fangchenggang branch

Pledgor: GUANGXI HUAYE BUILDING ENGINEERING Co.,Ltd.

Registration number: Y2021450000049

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20230907

Granted publication date: 20180501

Pledgee: China Construction Bank Corporation Fangchenggang branch

Pledgor: GUANGXI HUAYE BUILDING ENGINEERING Co.,Ltd.

Registration number: Y2021450000049

PC01 Cancellation of the registration of the contract for pledge of patent right