CN106049354A - Quickly-assembled flood control dam - Google Patents

Quickly-assembled flood control dam Download PDF

Info

Publication number
CN106049354A
CN106049354A CN201610563863.9A CN201610563863A CN106049354A CN 106049354 A CN106049354 A CN 106049354A CN 201610563863 A CN201610563863 A CN 201610563863A CN 106049354 A CN106049354 A CN 106049354A
Authority
CN
China
Prior art keywords
king pile
barrier
dams
fixing device
waterproof cloth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610563863.9A
Other languages
Chinese (zh)
Inventor
黄运新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610563863.9A priority Critical patent/CN106049354A/en
Publication of CN106049354A publication Critical patent/CN106049354A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • E02B3/106Temporary dykes

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

A quickly-assembled flood control dam mainly comprises main piles, net barrier fixing devices, main pile connecting devices, connecting rods, auxiliary piles, auxiliary pile connecting devices, pin shafts, a net barrier and high-strength waterproof cloth, wherein the main piles are planted against flood; one auxiliary pile is planted behind each main pipe and in a foundation; the main piles are connected and fixed to the auxiliary piles through extension rods; the net barrier is fixed on the main pipes through the net barrier fixing devices; and the high-strength waterproof cloth is arranged on the net barrier. The quickly-assembled flood control dam has the advantages of high flood control labor intensity, high flood control efficiency, good flood control effect and low flood control cost.

Description

Fast assembling gear flood dykes and dams
Technical field
The present invention relates to a kind of fast assembling gear flood dykes and dams, belong to water conservancy or flood protection device technical field.
Background technology
China is that country is easily sent out in a flood, and the generation of flood not only can cause the damage of corresponding lives and properties Lose, also natural environment can be caused serious harm!When flood is estimated to occur or the process of generation, it is possible to fast and effectively Flood is stopped, is the key winning flood control triumph, and the method for existing stop flood typically uses sandbag to stop flood Water, this method not only labor intensity height, inefficiency, flood control results is poor, it is relatively costly to control flood, simultaneously because efficiency is relatively Low, cause lose opportunity, make flood damage still occur.
Summary of the invention
It is an object of the invention to: for the backward situation existing for existing flood control field, the present invention provides a kind of quick Assembled gear flood dykes and dams.
The present invention realizes above-mentioned purpose and be the technical scheme is that described a kind of fast assembling gear flood dykes and dams, It specifically includes that king pile, barrier fixing device, king pile attachment means, connecting rod, auxiliary stake, auxiliary stake attachment means, bearing pin, resistance Block, high-strength waterproof cloth, some described king piles (1) assign into flood to head-on direction, described king pile (1) can To be regular length or can be assigned on the back ground of each king pile (1) with spreading by thread mechanism at length direction A piece auxiliary stake (8), the upper position at king pile (1) is fixedly disposed a king pile attachment means, described king pile attachment means Including two identical connecting plate first (4), the plane of described connecting plate (4) is shaped with the chute first (6) of opening upwards, two Connecting plate (4) is fixed on the upper position of king pile (1) symmetrically, is provided with auxiliary stake attachment means in auxiliary stake (8), and described is auxiliary Stake attachment means includes: sliding seat second (9), fixing device second (10), two identical connecting plate second (11), two connecting plate second (11) being shaped with the chute second (12) of opening upwards in plane, two connecting plate second (12) are fixed on sliding seat second (9) symmetrically On, described sliding seat second (9) can regulate in the short transverse of auxiliary stake (8), and fixing device second (10) can be by sliding seat second (9) it is fixed in auxiliary stake (8), a bearing pin (5), the bearing pin at extension bar (7) two ends are respectively set at the two ends of bracing piece (7) (5) it is connected to chute first (6) respectively be connected with auxiliary stake (8) by king pile (1) with in chute second (12), at king pile (1) if above arranging Dry barrier fixing device, described barrier fixing device includes: sliding seat first (2), fixing device first (3), barb (15), described sliding seat first (2) can regulate in the short transverse of king pile (1), fixing device first (3) can be by sliding seat first (2) being fixed on king pile (1), be fixed with barb (15) in sliding seat first (2), barb (15) stops through position, place Being fixed on king pile (1) by steel mesh (13) behind hole on net (13), described barrier is in metal material or non-metallic material Any one, before barrier (13), be coated with high-strength waterproof cloth (14), described high-strength waterproof cloth (14) is Any one or two kinds or two kinds in the coating of canvas, synthetic leather, nylon cloth, rubber slab, rubber, plastic-coated, oxford with On combination, along the upper position of high-strength waterproof cloth (14), be provided with several equidistant clear opening buttons (19), rope (18) inside and outside alternatively through clear opening button (19), by the top of high-strength waterproof cloth (14) by rope (18) and king pile (1) Top fix, be fixedly installed elastic hook (20) in the bottom of high-strength waterproof cloth (14) with equidistant interval, Free state, elastic hook (20) struts the bottom of high-strength waterproof cloth (14) and forms flared arc groove (16), by Add weight block (17) in arc groove (16) to be fixed the bottom of high-strength waterproof cloth (14), in order to make high-strength waterproof cloth (14) Bottom quickly sinks, and has densely covered leaking hole (28) on the bottom and bottom outwardly direction of arc groove (16).
Further: described barrier fixing device also includes: U-shaped clip (21), nut (22), pressing plate (23), pad Plate first (24), opens a grade position and arranges a backing plate (24), the two of some U-shaped clips (21) in the bottom of some U-shaped clips (21) Limit is through the hole of barrier (13), and a grade position of opening for U-shaped clip (21) is socketed on king pile (1), on the both sides of U-shaped clip (21) One pressing plate (23) of upper socket, will compress between pressing plate (23) and king pile (1) with nut (22), reaches to make barrier (13) with main The purpose that stake (1) is fixing, the installation of high-strength waterproof cloth (14) is with the most identical.
Further: described barrier fixing device also includes: several screws (25) of being produced on king pile (1), Bolt (26) and backing plate second (27), after bolt (26) sequentially passes through the hole in backing plate second (27) and the hole on barrier (13) Being fixed in screw (25), the installation of high-strength waterproof cloth (14) is with the most identical.
Beneficial effect: due to the fact that the component being made up of king pile, auxiliary stake, bracing piece is prone to in-site installation, and intensity And stability is preferable, it is high that barrier has intensity, and low cost is prone to the advantage of deposit, and high-strength waterproof cloth has by force equally Spend height, low cost, be prone to deposit, easy-to-install advantage, so, the present invention can reduce flood control labor intensity height, improve and prevent Flood inefficiency, flood control results are preferable, lower-cost advantage of controlling flood.
Accompanying drawing explanation
Fig. 1 is the front view of the present invention;
Fig. 2 is the front view of high-strength waterproof cloth in the present invention;
Fig. 3 is the A direction view of Fig. 2;
Fig. 4 is the B direction view of Fig. 1;
The C direction view of Fig. 5 Fig. 1;
Fig. 6 is the Local map of embodiment in the present invention;
Fig. 7 is the D-D sectional view of Fig. 6;
Fig. 8 is the Local map of another embodiment in the present invention.
Shown in figure: 1 is king pile;2 is sliding seat first;3 is fixing device first;4 is connecting plate first;5 is bearing pin;6 is sliding Groove first;7 is bracing piece;8 is auxiliary stake;9 is sliding seat second;10 is fixing device second;11 is connecting plate second;12 is chute second;13 It it is barrier;14 is high-strength waterproof cloth;15 is barb;16 is arc groove;17 is weight block;18 is rope;19 is clear opening button; 20 is elastic hook;21 is U-shaped clip;22 is nut;23 is pressing plate;24 is backing plate first;25 is screw;26 is bolt;27 are Backing plate second;28 is leaking hole.
Detailed description of the invention
Embodiment 1:
In conjunction with Fig. 1 to Fig. 5, the detailed description of the invention of the present invention is: described a kind of fast assembling gear flood dykes and dams, it is main Including: king pile, barrier fixing device, king pile attachment means, connecting rod, auxiliary stake, auxiliary stake attachment means, bearing pin, barrier, height Intensity waterproof cloth, some described king piles (1) assign into flood to head-on direction, described king pile (1) can be solid Measured length or length direction by thread mechanism can with spreading, the back ground of each king pile (1) is assigned one auxiliary Stake (8), the upper position at king pile (1) is fixedly disposed a king pile attachment means, and described king pile attachment means includes two Individual identical connecting plate first (4), the plane of described connecting plate (4) is shaped with the chute first (6) of opening upwards, two connecting plates (4) being fixed on the upper position of king pile (1) symmetrically, be provided with auxiliary stake attachment means in auxiliary stake (8), described auxiliary stake connects Device includes: sliding seat second (9), fixing device second (10), two identical connecting plate second (11), two connecting plate second (11) Being shaped with the chute second (12) of opening upwards in plane, two connecting plate second (12) are fixed in sliding seat second (9) symmetrically, described Sliding seat second (9) can regulate in the short transverse of auxiliary stake (8), fixing device second (10) can be by sliding seat second (9) auxiliary Being fixed in stake (8), respectively arrange a bearing pin (5) at the two ends of bracing piece (7), the bearing pin (5) at extension bar (7) two ends is respectively It is connected to chute first (6) be connected with auxiliary stake (8) by king pile (1) with in chute second (12), king pile (1) arranges several and stops Net fixing device, described barrier fixing device includes: sliding seat first (2), fixing device first (3), barb (15), described Sliding seat first (2) can regulate in the short transverse of king pile (1), and fixing device first (3) can be by sliding seat first (2) at king pile (1) being fixed on, be fixed with barb (15) in sliding seat first (2), barb (15) passes on position, place barrier (13) Hole after steel mesh (13) is fixed on king pile (1), described barrier is any one in metal material or non-metallic material Kind, before barrier (13), it being coated with high-strength waterproof cloth (14), described high-strength waterproof cloth (14) is canvas, synthesis Any one or two or more combination in the coating of leather, nylon cloth, rubber slab, rubber, plastic-coated, oxford, Along the upper position of high-strength waterproof cloth (14), being provided with several equidistant clear opening buttons (19), rope (18) is inside and outside Alternatively through clear opening button (19), the top of high-strength waterproof cloth (14) is solid with the top of king pile (1) by rope (18) Fixed, it is fixedly installed elastic hook (20) in the bottom of high-strength waterproof cloth (14) with equidistant interval, in free state, Elastic hook (20) struts the bottom of high-strength waterproof cloth (14) and forms flared arc groove (16), by arc groove (16) Add weight block (17) to be fixed the bottom of high-strength waterproof cloth (14), under making the bottom of high-strength waterproof cloth (14) quickly Heavy, the bottom and bottom outwardly direction of arc groove (16) have densely covered leaking hole (28).
Embodiment 2:
In conjunction with Fig. 6 to Fig. 7, the detailed description of the invention of the present invention is: described barrier fixing device also includes: U-shaped clip (21), nut (22), pressing plate (23), backing plate first (24), open a grade position in the bottom of some U-shaped clips (21) and one backing plate be set (24), the both sides of some U-shaped clips (21) are through the hole of barrier (13), and a grade position of opening for U-shaped clip (21) is socketed in king pile (1), on, the both sides of U-shaped clip (21) are socketed a pressing plate (23), with nut (22) by between pressing plate (23) and king pile (1) Compressing, reach the purpose making barrier (13) fixing with king pile (1), other is same as in Example 1.
Embodiment 3:
In conjunction with Fig. 8, the detailed description of the invention of the present invention is: described barrier fixing device also includes: be produced on king pile (1) Several screws (25), bolt (26) and backing plate second (27), bolt (26) sequentially pass through the hole in backing plate second (27) and Being fixed on behind hole on barrier (13) in screw (25), other embodiment is same as in Example 1.

Claims (11)

1. fast assembling gear flood dykes and dams, it is characterised in that: it includes: king pile (1), barrier fixing device, king pile Attachment means, connecting rod (7), auxiliary stake (8), auxiliary stake attachment means, bearing pin (5), barrier (13), high-strength waterproof cloth (14).
2. according to claim 1, described a kind of fast assembling gear flood dykes and dams, it is characterised in that: some king pile (1) peaces Be inserted in flood to head-on direction, the back ground of each king pile (1) is assigned an auxiliary stake (8), at king pile (1) Upper position is fixedly disposed a king pile attachment means, is provided with auxiliary stake attachment means, in bracing piece (7) in auxiliary stake (8) Two ends one bearing pin (5) is respectively set, the bearing pin (5) at extension bar (7) two ends is connected to chute first (6) and chute second (12) respectively Interior being connected with auxiliary stake (8) by king pile (1), arrange several barrier fixing devices on king pile (1), barrier (13) is by resistance Block fixing device is fixed on king pile (1), by rope (18) on barrier (13), and clear opening button (19) and weight block (17) high-strength waterproof cloth (13) it is fixed with.
3. according to any one claim 1 or claim 2, described a kind of fast assembling gear flood dykes and dams, its feature Be: king pile (1) can be regular length or length direction by thread mechanism can be with spreading.
4. according to any one claim 1 or claim 2, described a kind of fast assembling gear flood dykes and dams, its feature Be: king pile attachment means includes two identical connecting plate first (4), the plane of described connecting plate (4) is shaped with opening to On chute first (6), two connecting plates (4) are fixed on the upper position of king pile (1) symmetrically.
5. according to any one claim 1 or claim 2, described a kind of fast assembling gear flood dykes and dams, its feature Be: auxiliary stake attachment means includes: sliding seat second (9), fixing device second (10), two identical connecting plate second (11), at two Being shaped with the chute second (12) of opening upwards in the plane of connecting plate second (11), two connecting plate second (12) are fixed on activity to this place On seat second (9), described sliding seat second (9) can regulate in the short transverse of auxiliary stake (8), and fixing device second (10) can be by work Dynamic seat second (9) is fixed in auxiliary stake (8).
6. according to any one claim 1 or claim 2, described a kind of fast assembling gear flood dykes and dams, its feature It is: described barrier fixing device includes: sliding seat first (2), fixing device first (3), barb (15), described sliding seat First (2) can regulate in the short transverse of king pile (1), and fixing device first (3) can be enterprising at king pile (1) by sliding seat first (2) Row is fixing, is fixed with barb (15) in sliding seat first (2).
7. according to any one claim 1 or claim 2, described a kind of fast assembling gear flood dykes and dams, its feature It is: described barrier fixing device also includes: U-shaped clip (21), nut (22), pressing plate (23), backing plate first (24), if The bottom of dry U-shaped clip (21) is opened a grade position and is arranged a backing plate (24), and the both sides of some U-shaped clips (21) pass barrier (13) hole, a grade position of opening for U-shaped clip (21) is socketed on king pile (1), is socketed a pressure on the both sides of U-shaped clip (21) Plate (23), will compress between pressing plate (23) and king pile (1) with nut (22), reach to make barrier (13) and king pile (1) fix Purpose.
8. according to any one claim 1 or claim 2, described a kind of fast assembling gear flood dykes and dams, its feature Be: described barrier fixing device also includes: several screws (25) of being produced on king pile (1), bolt (26) and Backing plate second (27), bolt (26) is fixed on screw after sequentially passing through the hole in backing plate second (27) and the hole on barrier (13) (25) in.
9. according to any one claim 1 or claim 2, described a kind of fast assembling gear flood dykes and dams, its feature It is: described barrier is any one in metal material or non-metallic material.
10. according to any one claim 1 or claim 2, described a kind of fast assembling gear flood dykes and dams, its feature It is: along the upper position of high-strength waterproof cloth (14), is provided with several equidistant clear opening buttons (19), rope (18) Inside and outside alternatively through clear opening button (19), by upper by rope (18) and king pile (1) of the top of high-strength waterproof cloth (14) Portion is fixed, and is fixedly installed elastic hook (20) in the bottom of high-strength waterproof cloth (14) with equidistant interval, in freedom State, elastic hook (20) struts the bottom of high-strength waterproof cloth (14) and forms flared arc groove (16), crosses at arc groove (16) add weight block (17) in be fixed the bottom of high-strength waterproof cloth (14), outside in the bottom of arc groove (16) and bottom Densely covered leaking hole (28) is had on direction.
11. according to claim 10, described a kind of fast assembling gear flood dykes and dams, it is characterised in that: described high intensity Waterproof cloth (14) be in canvas, synthetic leather, nylon cloth, rubber slab, rubber coating, plastic-coated, oxford any one or Two or more combination.
CN201610563863.9A 2016-07-18 2016-07-18 Quickly-assembled flood control dam Pending CN106049354A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610563863.9A CN106049354A (en) 2016-07-18 2016-07-18 Quickly-assembled flood control dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610563863.9A CN106049354A (en) 2016-07-18 2016-07-18 Quickly-assembled flood control dam

Publications (1)

Publication Number Publication Date
CN106049354A true CN106049354A (en) 2016-10-26

Family

ID=57188477

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610563863.9A Pending CN106049354A (en) 2016-07-18 2016-07-18 Quickly-assembled flood control dam

Country Status (1)

Country Link
CN (1) CN106049354A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107268525A (en) * 2017-08-16 2017-10-20 董兰田 Fast-assembling combined emergency flood control water filling dykes and dams
CN107396867A (en) * 2017-09-04 2017-11-28 宜宾县普安镇揽胜种养殖专业合作社 A kind of rice field aquatic products breeding fence easy for installation
CN108457245A (en) * 2018-04-23 2018-08-28 苏州百搭王者物流技术有限公司 One kind is built a dam anchor
CN108797515A (en) * 2017-09-19 2018-11-13 临沂搏水利工程科技有限公司 A kind of moveable floatage-type membrane structure checkdam and its application process
CN110080165A (en) * 2019-03-29 2019-08-02 张谦 A kind of arch thin-wall construction checkdam and its application method that can quickly construct

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1232110A (en) * 1999-04-23 1999-10-20 吴登峰 Emergency flood-control screen for combatting flood
CN1558039A (en) * 2004-01-19 2004-12-29 戎新国 Water retaining dam wall quick assembled by levee crown cement pile for flood fighting
CN201254711Y (en) * 2008-07-26 2009-06-10 沈彦廷 Soilless flood control sub-bank laying machine

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1232110A (en) * 1999-04-23 1999-10-20 吴登峰 Emergency flood-control screen for combatting flood
CN1558039A (en) * 2004-01-19 2004-12-29 戎新国 Water retaining dam wall quick assembled by levee crown cement pile for flood fighting
CN201254711Y (en) * 2008-07-26 2009-06-10 沈彦廷 Soilless flood control sub-bank laying machine

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107268525A (en) * 2017-08-16 2017-10-20 董兰田 Fast-assembling combined emergency flood control water filling dykes and dams
CN107396867A (en) * 2017-09-04 2017-11-28 宜宾县普安镇揽胜种养殖专业合作社 A kind of rice field aquatic products breeding fence easy for installation
CN108797515A (en) * 2017-09-19 2018-11-13 临沂搏水利工程科技有限公司 A kind of moveable floatage-type membrane structure checkdam and its application process
CN108797515B (en) * 2017-09-19 2021-08-17 山东一搏水利工程科技有限公司 Movable buoyancy type membrane structure water retaining dam and application method thereof
CN108457245A (en) * 2018-04-23 2018-08-28 苏州百搭王者物流技术有限公司 One kind is built a dam anchor
CN110080165A (en) * 2019-03-29 2019-08-02 张谦 A kind of arch thin-wall construction checkdam and its application method that can quickly construct
CN110080165B (en) * 2019-03-29 2022-09-27 张谦 Arch thin-wall structure retaining dam capable of being constructed rapidly and application method thereof

Similar Documents

Publication Publication Date Title
CN106049354A (en) Quickly-assembled flood control dam
DE112016002341B4 (en) Arrangement of several tubular piles arranged next to one another with a heat transfer pipe arrangement embedded in at least one prefabricated tubular pile and a pump unit
CN106315451A (en) Integral automatic synchronous control system for steel strand group anchors
CN106988352A (en) A kind of method of testing for considering soil body preconsolidation and the horizontal bearing capacity of single pile under cyclic load
CN106315450A (en) Integral automatic synchronous pre-tightening device for steel strand group anchor inhaul cables
DE102015121371A1 (en) Offshore wind farm
CN108914998B (en) Reinforced soil retaining wall damage mechanism experimental device and working method
CN203414351U (en) Prestrain reinforced experimental device
CN108130883B (en) Water level fluctuation device for simulating tidal load
CN106869194B (en) With the detection method of heavy dynamic penetration test method evaluation pile grouting effect
CN205134391U (en) Tensile detection device of precast pile
CN204940273U (en) A kind of Prestressed anchor rope with pressure dispersing construction equipment
CN205475088U (en) Dykes and dams bank protection structure for hydraulic engineering
CN204126038U (en) A kind of Water-logged draining device
CN206188304U (en) Integral automatic synchronization preloading device of steel strand wires crowd anchor rope
CN203569534U (en) Hydraulic support dam
CN208857812U (en) A kind of civil engineering built pile
CN109252490B (en) Hydraulic energy dissipation device for small channel and construction method
CN202369966U (en) Assembly type height-adjustable bearable flood control sub embankment
CN201024416Y (en) Large area soft foundation soil bag field reinforced structure
CN201686997U (en) Drainage device
CN201447712U (en) Embedded-linked type waterproof coiled material
CN211257063U (en) Water conservancy retaining wall convenient to installation
CN109695222A (en) A kind of slope protection and spats for water conservancy road and water and soil conservation
Hofinger et al. Geothermal energy systems for major projects–design and construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161026