CN106049282A - Method for tensioning and releasing hollow slab steel strands prefabricated through pre-tensioning method - Google Patents

Method for tensioning and releasing hollow slab steel strands prefabricated through pre-tensioning method Download PDF

Info

Publication number
CN106049282A
CN106049282A CN201610391392.8A CN201610391392A CN106049282A CN 106049282 A CN106049282 A CN 106049282A CN 201610391392 A CN201610391392 A CN 201610391392A CN 106049282 A CN106049282 A CN 106049282A
Authority
CN
China
Prior art keywords
crossbeam
sandbox
stretch
steel strand
tension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610391392.8A
Other languages
Chinese (zh)
Inventor
翟全磊
刘大勇
侯兆隆
应世明
张何
吴小冬
吴建英
葛纪平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, China Communications Road and Bridge North China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN201610391392.8A priority Critical patent/CN106049282A/en
Publication of CN106049282A publication Critical patent/CN106049282A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

The invention relates to a method for tensioning and releasing hollow slab steel strands prefabricated through a pre-tensioning method. A movable anchoring crossbeam is arranged at one ends of prefabrication pedestals, one end of each prestressed steel strand is anchored, and releasing sand boxes are arranged between the movable anchoring crossbeam and the prefabrication pedestals; and a tensioning crossbeam is arranged at the other ends of the prefabrication pedestals, a tension frame inner crossbeam is arranged on the inner side of the tensioning crossbeam and anchored to the other ends of the prestressed steel strands, a tension frame outer crossbeam is arranged on the outer side of the tensioning crossbeam, the tension frame inner crossbeam and the tension frame outer crossbeam are connected through screws penetrating the tensioning crossbeam, and tensioning jacks are arranged between the tensioning crossbeam and the tension frame outer crossbeam. In the tensioning process, the jacks are operated to jack the tension frame outer crossbeam to move to the outer side, the tension frame inner crossbeam is driven to move, and the steel strands are tensioned; and in the releasing process, sand in the releasing sand boxes is evenly discharged, pistons of the releasing sand boxes retract into steel sleeves, and therefore the steel strands are released.

Description

A kind of pre-tensioned concrete hollow plate steel strand tension and put Zhang Fangfa
Technical field
The present invention relates to concrete core slab prefabricating technique field, be specifically related to a kind of pre-tensioned concrete hollow plate Steel strand tension and put Zhang Fangfa.
Background technology
Pre-tensioned concrete hollow plate because its deadweight is little, convenient transportation, the suitability be strong, assemblingization degree high, extensively Apply in bridges in highway engineering construction.The stretch-draw of prestress wire and put the important ring of Zhang Zuowei precast hollow slab construction Joint, is also the cored slab key factor that has relatively high bearing capacity.The entitled " stretch-draw of pretensioned prestressing steel strand wires and putting " document of (Chinese periodical " harbor work's technology ", in June, 2002, No.2) discloses a kind of stretch-draw and put Zhang Fangfa, such as Fig. 1 institute Show, set fixed anchorage beam in precast pedestal 1 one end, for one end of anchoring prestress steel strand wires, the precast pedestal other end If stretch-drawing beam, inside stretch-drawing beam, it is provided with crossbeam in tension frame, anchors with the prestress wire other end, outside stretch-drawing beam If the outer crossbeam of tension frame, being connected by running through the screw rod of stretch-drawing beam in tension frame between crossbeam crossbeam outer with tension frame, screw rod exists One section between stretch-drawing beam and the outer crossbeam of tension frame is provided with nut, sets stretch-draw very heavy between the outer crossbeam of stretch-drawing beam and tension frame Top, during stretch-draw, realizes prestress wire stretch-draw by the jack piston outer cross beam movement of elongation pushing tow tension frame, and stretch-draw puts in place After, the nut on screw rod is tightened to stretch-drawing beam, makes prestress steel twist line position fix;When putting, first by jack piston Extending LAP again, in order to unclamped by nut, bounce back jack piston the most again, it is achieved puts and opens.Said method, jack is put Also to extend LAP again due to piston when opening, easily cause super of steel strand wires and rupture, cause safe thing Therefore and beam body damage.
Summary of the invention
A problem that present invention aims to exist when prestress wire stretch-draw in prior art is put, it is provided that one Plant and overpull can be avoided to put the pre-tensioned concrete hollow plate stretch-draw opened and put Zhang Fangfa.
Technical scheme is as follows:
A kind of pre-tensioned concrete hollow plate steel strand tension and put Zhang Fangfa, it is characterised in that:
(1) portable anchorage beam is set in precast pedestal one end, one end of anchoring prestress steel strand wires, and at portable anchor Gu arrange between crossbeam and precast pedestal and put a sandbox, described in put to be full of in a sandbox and put Zhang Sha;Put a sandbox include steel bushing and The piston reciprocatingly slided along steel bushing inwall, the steel bushing one end putting a sandbox acts against on precast pedestal, puts the work of a sandbox Plug one end acts against on portable anchorage beam;
(2) set stretch-drawing beam at the precast pedestal other end, inside stretch-drawing beam, set crossbeam in tension frame, with prestress steel twist The line other end anchors, and sets the outer crossbeam of tension frame outside stretch-drawing beam, by running through between crossbeam and the outer crossbeam of tension frame in tension frame The screw rod of stretch-drawing beam connects, and screw rod sets nut between the outer crossbeam of stretch-drawing beam and tension frame one section, stretch-drawing beam with Stretch-draw jack is set between the outer crossbeam of tension frame;
(3), during stretch-draw, handle the outer crossbeam of jack pushing tow tension frame and move laterally, drive cross beam movement in tension frame, To steel strand tension;Steel strand wires drive portable anchorage beam to move to precast pedestal direction simultaneously, make to put a sandbox stress quilt Extruding;Steel strand tension, to after predetermined value, stops jack pushing tow, and is tightened to stretch-drawing beam by the nut on screw rod, make steel Twisted wire positions;
(4) when putting, husky in a sandbox will be put uniformly release, put the piston of a sandbox to steel bushing contract, make to put Extruding force suffered by sandbox is unloaded, and puts so that realizing steel strand wires.
The present invention uses sandbox to put, efficiently avoid when jack is put and easily occurs that super of steel strand wires occurs Fracture, it is to avoid generation security incident and beam body are damaged.The present invention is safe and reliable, easy construction, and the making of sandbox is simple, Put and to draw materials conveniently with the former material such as husky, low cost, there is preferable economic benefit.
Accompanying drawing explanation
Fig. 1 is that a structural representation is put in the stretch-draw of the present invention;
Fig. 2 is the structural representation putting a sandbox that the present invention uses.
Detailed description of the invention
Fig. 1 show pre-tensioned concrete hollow plate steel strand tension of the present invention and puts a structural representation.
It is the structural representation putting a sandbox that uses of the present invention shown in Fig. 2, puts a sandbox 10 and include steel bushing 11 and live Plug 12, piston 12 can reciprocatingly slide in steel bushing 11.Steel bushing 11 top is provided with sand inlet 13 and sand inlet valve 14, steel bushing It is provided with sand outlet 15 and sand outlet valve 16 bottom cylinder 11.
The present invention uses said structure carry out stretch-draw and put and specifically include following steps:
(1) set portable anchorage beam 2, one end of anchoring prestress steel strand wires 3 in precast pedestal 1 one end, and moving Arrange between formula anchorage beam 2 and precast pedestal 1 and put a sandbox 10, described in put to be full of in a sandbox 10 and put a sand 17;Put a sandbox Including steel bushing and the piston that reciprocatingly slides along steel bushing inwall, steel bushing 11 one end putting a sandbox 10 acts against precast pedestal On 1, piston 12 one end putting a sandbox acts against on portable anchorage beam 2;
(2)) set stretch-drawing beam 4 at precast pedestal 1 other end, inside stretch-drawing beam 4, set crossbeam 5 in tension frame, answer with pre- Power steel strand wires 3 other end anchors, and sets the outer crossbeam 6 of tension frame outside stretch-drawing beam 4, crossbeam 5 crossbeam outer with tension frame in tension frame Connecting by running through the screw rod 7 of stretch-drawing beam 4 between 6, screw rod 7 sets nut between the outer crossbeam of stretch-drawing beam and tension frame one section 8, between the outer crossbeam 6 of stretch-drawing beam 4 and tension frame, set stretch-draw jack 9;
(3) during stretch-draw, handling the outer crossbeam 6 of jack 9 pushing tow tension frame and move laterally, in driving tension frame, crossbeam 5 moves Dynamic, it is achieved to steel strand wires 3 stretch-draw;Steel strand wires 3 drive portable anchorage beam 2 to move to precast pedestal 1 direction simultaneously, make to put and open Sandbox 10 stress is extruded;Steel strand wires 3 stretch-draw to after predetermined value, stops jack 9 pushing tow, and by the nut 8 on screw rod 7 to Draw crossbeam 4 to tighten, make steel strand wires position;
(4), when putting, put a sand 17 in a sandbox 10 will be put and uniformly release, put the piston 12 of a sandbox 10 to steel bushing 11 Contract, makes to put the extruding force suffered by a sandbox and is unloaded, and puts so that realizing steel strand wires.
When the present invention is embodied as, the material putting the piston of a sandbox and steel bushing uses seamless steel pipe to make, piston and The spacing of steel bushing barrel is 0.5mm, and rubbing surface to carry out bright and clean process, the effective travel distance at least 180mm of sandbox piston, Meet the loose requirement of steel strand wires.Sand inlet diameter is set to 250mm, and sand outlet diameter is set to 16mm.
Before tension steel strand, sandbox piston is pulled out 180-200mm, by sand inlet, steel bushing filled sand and smash Real, sand inlet valve is tightened.
Putting and put Zhang Sha used by a sandbox, its fineness is the sand by No. 50 and No. 30 standard screens, makes by the grating of 6:4 With, the most both can guarantee that putting Zhang Sha is difficult to crush and causes the phenomenon that can not flow, and can reduce again the voidage putting Zhang Sha, thus reduce The compressed value of Zhang Sha is put during use.

Claims (5)

1. a pre-tensioned concrete hollow plate steel strand tension and put Zhang Fangfa, it is characterised in that:
(1) portable anchorage beam is set in precast pedestal one end, one end of anchoring prestress steel strand wires, and at movable type anchoring horizontal stroke Arrange between beam and precast pedestal and put a sandbox, described in put to be full of in a sandbox and put Zhang Sha;Put a sandbox and include steel bushing and along steel The piston that sleeve lining reciprocatingly slides, the steel bushing one end putting a sandbox acts against on precast pedestal, puts the piston one of a sandbox End acts against on portable anchorage beam;
(2) set stretch-drawing beam at the precast pedestal other end, inside stretch-drawing beam, set crossbeam in tension frame, another with prestress wire One end anchors, and sets the outer crossbeam of tension frame outside stretch-drawing beam, by running through stretch-draw between crossbeam and the outer crossbeam of tension frame in tension frame The screw rod of crossbeam connects, and screw rod sets nut, at stretch-drawing beam and pulling force between the outer crossbeam of stretch-drawing beam and tension frame one section Stretch-draw jack is set between the outer crossbeam of frame;
(3), during stretch-draw, handle the outer crossbeam of jack pushing tow tension frame and move laterally, drive cross beam movement in tension frame, to steel Twisted wire stretch-draw;Steel strand wires drive portable anchorage beam to move to precast pedestal direction simultaneously, make to put a sandbox stress and are extruded; Steel strand tension, to after predetermined value, stops jack pushing tow, and is tightened to stretch-drawing beam by the nut on screw rod, makes steel strand wires fixed Position;
(4) when putting, husky in a sandbox will be put uniformly release, put the piston of a sandbox to steel bushing contract, make to put a sandbox Suffered extruding force is unloaded, and puts so that realizing steel strand wires.
Pre-tensioned concrete hollow plate steel strand tension the most according to claim 1 and put Zhang Fangfa, it is characterised in that: described The steel bushing top putting a sandbox is provided with sand inlet and sand inlet valve, and bottom is provided with sand outlet and sand outlet valve.
Pre-tensioned concrete hollow plate steel strand tension the most according to claim 2 and put Zhang Fangfa, it is characterised in that: described The a diameter of 250mm of sand inlet, a diameter of 16mm of sand outlet.
Pre-tensioned concrete hollow plate steel strand tension the most according to claim 1 and put Zhang Fangfa, it is characterised in that: described The spacing putting a sandbox piston and steel bushing inwall is 0.5mm, the effective travel distance at least 180mm of sandbox piston.
Pre-tensioned concrete hollow plate steel strand tension the most according to claim 1 and put Zhang Fangfa, it is characterised in that: described Putting and put Zhang Sha in a sandbox, its fineness is the sand by No. 50 and No. 30 standard screens, uses by the grating of 6:4.
CN201610391392.8A 2016-06-05 2016-06-05 Method for tensioning and releasing hollow slab steel strands prefabricated through pre-tensioning method Pending CN106049282A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610391392.8A CN106049282A (en) 2016-06-05 2016-06-05 Method for tensioning and releasing hollow slab steel strands prefabricated through pre-tensioning method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610391392.8A CN106049282A (en) 2016-06-05 2016-06-05 Method for tensioning and releasing hollow slab steel strands prefabricated through pre-tensioning method

Publications (1)

Publication Number Publication Date
CN106049282A true CN106049282A (en) 2016-10-26

Family

ID=57170187

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610391392.8A Pending CN106049282A (en) 2016-06-05 2016-06-05 Method for tensioning and releasing hollow slab steel strands prefabricated through pre-tensioning method

Country Status (1)

Country Link
CN (1) CN106049282A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108660907A (en) * 2018-06-14 2018-10-16 中铁贵州旅游文化发展有限公司 A kind of super open of stay cable force puts a structure
CN113215988A (en) * 2021-01-20 2021-08-06 邓莉红 Prestressed steel strand anchoring process for bridge construction
CN115816642A (en) * 2022-11-21 2023-03-21 内蒙古交科路桥建设有限公司 Sheet placing device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2388267Y (en) * 1999-10-08 2000-07-19 许国才 Pretensioning prestressed reinforcement releasing device
CN2823436Y (en) * 2005-09-09 2006-10-04 中国海洋石油总公司 Pretensioning method prestressed tensioned bed device
CN201239993Y (en) * 2008-05-29 2009-05-20 山东省公路建设(集团)有限公司 Integral tension and relaxation system for pre-tensioned prestressing tension process
KR101336518B1 (en) * 2012-10-09 2013-12-03 김삼순 Pre-tensioning method for manufacturing prestressed concrete products

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2388267Y (en) * 1999-10-08 2000-07-19 许国才 Pretensioning prestressed reinforcement releasing device
CN2823436Y (en) * 2005-09-09 2006-10-04 中国海洋石油总公司 Pretensioning method prestressed tensioned bed device
CN201239993Y (en) * 2008-05-29 2009-05-20 山东省公路建设(集团)有限公司 Integral tension and relaxation system for pre-tensioned prestressing tension process
KR101336518B1 (en) * 2012-10-09 2013-12-03 김삼순 Pre-tensioning method for manufacturing prestressed concrete products

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
孙奎增: "浅谈先张法预应力空心板的施工技术与质量控制", 《东北公路》 *
孙忠文等: "砂箱放张在先张法预应力空心板施工中的应用", 《东北公路》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108660907A (en) * 2018-06-14 2018-10-16 中铁贵州旅游文化发展有限公司 A kind of super open of stay cable force puts a structure
CN108660907B (en) * 2018-06-14 2024-02-23 中铁贵州旅游文化发展有限公司 Stay cable force overstretching structure
CN113215988A (en) * 2021-01-20 2021-08-06 邓莉红 Prestressed steel strand anchoring process for bridge construction
CN113215988B (en) * 2021-01-20 2022-09-09 安徽通利预应力科技有限公司 Prestressed steel strand anchoring process for bridge construction
CN115816642A (en) * 2022-11-21 2023-03-21 内蒙古交科路桥建设有限公司 Sheet placing device
CN115816642B (en) * 2022-11-21 2024-01-02 内蒙古交科路桥建设有限公司 Put and open device

Similar Documents

Publication Publication Date Title
US3089215A (en) Apparatus for prestressed concrete construction
CN103726447B (en) Two times tensioning low retraction anchoring system vertical prestressing steel strand wires method and system thereof
CN102251684A (en) Construction method for circumferential pretensioning steel strand reinforcement circular structure or construction member
CN111395336A (en) Prestressed unbonded anchor rod reinforcing steel bar, anchor rod and construction method
CN106049282A (en) Method for tensioning and releasing hollow slab steel strands prefabricated through pre-tensioning method
CN110130234B (en) Novel bridge reinforcing system and construction method thereof
US20060117683A1 (en) Anchor wedge configuration tendon anchors
CN111395335A (en) Tubular column for prestressed anchor rod, anchor rod and construction method
AU2012243430B2 (en) Method and system for forming a support structure
CN203065973U (en) Stretch-draw device for monofilament epoxy coating steel strands
CN102345291A (en) Partially prestressed supporting cantilever pile
CN202925767U (en) Low-retraction pre-stressed anchorage device
CN208857720U (en) A kind of prestressing force metal composite muscle reinforcement bridge structure
CN102345292A (en) Composite prestressed uplift pile with expansion heads
CN205735486U (en) A kind of pre-tensioned concrete hollow plate steel strand tension and put a structure
CN110524675B (en) Pre-tensioning prefabricated I-beam and construction method thereof
KR20100101898A (en) Method for removing the tention member of temporary anchor
CN201377183Y (en) Quick and portable hook
CN102912987A (en) Stress applying method and tool thereof for low retraction pre-stress concrete member
CN204940273U (en) A kind of Prestressed anchor rope with pressure dispersing construction equipment
CN206071086U (en) The system of prestress rope integrative consolidation slab column
CN1206420C (en) High-grade prestressed bolt cable of compact rope for geotechnical engineering
CN108868822A (en) The intelligent slip casting aperture apparatus of tunnel lining trolley
CN213417550U (en) External prestress tie rod system of steel pipe concrete arch bridge
CN201459718U (en) Flexible pull rod for construction bearing platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161026

WD01 Invention patent application deemed withdrawn after publication