CN106033496A - 蒸汽发生器设计裕度计算方法 - Google Patents

蒸汽发生器设计裕度计算方法 Download PDF

Info

Publication number
CN106033496A
CN106033496A CN201510124153.1A CN201510124153A CN106033496A CN 106033496 A CN106033496 A CN 106033496A CN 201510124153 A CN201510124153 A CN 201510124153A CN 106033496 A CN106033496 A CN 106033496A
Authority
CN
China
Prior art keywords
steam generator
primary ioops
steam
transfer capability
design
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510124153.1A
Other languages
English (en)
Other versions
CN106033496B (zh
Inventor
李振振
蔡光明
鲁忆迅
冯杰
程宏亚
郑东佳
孟凡锋
兰蛟龙
张鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CNNC Fujian Nuclear Power Co Ltd
Original Assignee
CNNC Fujian Nuclear Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CNNC Fujian Nuclear Power Co Ltd filed Critical CNNC Fujian Nuclear Power Co Ltd
Priority to CN201510124153.1A priority Critical patent/CN106033496B/zh
Publication of CN106033496A publication Critical patent/CN106033496A/zh
Application granted granted Critical
Publication of CN106033496B publication Critical patent/CN106033496B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Monitoring And Testing Of Nuclear Reactors (AREA)

Abstract

本发明涉及核电厂蒸汽发生器传热能力的评估技术领域,具体涉及一种蒸汽发生器设计裕度计算方法,为后续蒸汽发生器堵管提供参考。该方法主要步骤包括:待核电厂一二回路满功率稳定运行后,关闭蒸汽发生器排污;进行一二回路热平衡测量,获得试验数据及结果;根据试验数据及结果进行数据处理,确认蒸汽发生器传热能力。本发明不需要进行反应堆一回路工况改变,减小了试验过程的风险;增加了蒸汽发生器裕度的准确性。

Description

蒸汽发生器设计裕度计算方法
技术领域
本发明涉及核电厂蒸汽发生器传热能力的评估技术领域,具体涉及一种蒸汽发生器设计裕度计算方法,为后续蒸汽发生器堵管提供参考。
背景技术
核电厂的蒸汽发生器设计过程中通常需考虑10%的裕度来应对后续电厂运行过程中由于传热管破损等原因的堵管造成传热面积减小,及传热管污垢产生造成的传热性能降低导致的蒸汽发生器传热量降低,使核电厂运行在设计的工况下。实际蒸汽发生器制造过程中由于材料实际性能与设计的不完全相符性,及制造厂家不具备相应的条件进行试验,因此蒸汽发生器制造完成后无法确认其真实裕度即其传热能力。目前确认蒸汽发生器设计裕度方法通常是降低一回路运行工况来模拟蒸发器堵管。但该方法主要针对二回路汽轮机的适应能力测试而非进行蒸汽发生器裕度测试。
发明内容
本发明的目的在于提供一种具体可行的蒸汽发生器设计裕度计算方法。
为达到上述目的,本发明所采取的技术方案为:
一种蒸汽发生器设计裕度计算方法,包括以下步骤:
步骤一:确认蒸汽发生器设计参数,包括蒸汽压力P、饱和蒸汽温度ts、蒸汽发生器热功率W、一回路侧进口温度th、一回路侧出口温度tc、一回路流量Q;根据及W=hAΔT计算不同设计流量下的蒸汽发生器设计传热能力hA;
步骤二:待核电厂一二回路满功率稳定运行后,关闭蒸汽发生器排污,待机组稳定后进行步骤三;
步骤三:进行一二回路热平衡测量,获得试验数据及结果,获取的数据包括蒸汽压力P、蒸汽发生器热功率W、一回路侧进口温度th、一回路侧出口温度tc、一回路压力P’、主泵功率Pw;
步骤四:根据试验数据及结果进行数据处理,确认蒸汽发生器传热能力。
所述的步骤四计算方法如下:
(1)根据蒸汽发生器热功率W,一回路压力P’、一回路侧进出口温度tc计算通过蒸汽发生器流量Q:首先通过一回路压力P’、一回路侧进出口温度tc查物性参数表,确定进口段密度ρ、出口段焓Hh、进口段焓Hc
Q = W - Pw ρ ( H h - H c ) * 3600
(2)将计算所得流量Q与设计流量插值,计算Q下蒸汽发生器设计传热能力h’A’;
(3)根据及W=hAΔT计算Q流量下的蒸汽发生器实际传热能力hA;
(4)将实际传热能力hA与蒸汽发生器设计传热能力h’A’比较,确认是否满足设计。
本发明所取得的有益效果为:本发明不需要进行反应堆一回路工况改变,减小了试验过程的风险;增加了蒸汽发生器裕度的准确性。
具体实施方式
下面结合具体实施例对本发明进行详细说明。
待反应堆达到满功率稳态运行后,确认蒸汽发生器的实际运行工况及热功率,确认蒸汽发生器传热能力,与设计值对比进而确认蒸发器的裕度。本发明将传热的计算公式W=hAΔT中hA作为统一的传热能力表现形式,不单独进行传热系数和传热面积计算。
本发明所述蒸汽发生器设计裕度计算方法主要步骤包括:待核电厂一二回路满功率稳定运行后,关闭蒸汽发生器排污;进行一二回路热平衡测量,获得试验数据及结果;根据试验数据及结果进行数据处理,确认蒸汽发生器传热能力。
本发明所述蒸汽发生器设计裕度计算方法具体包括以下步骤:
步骤一:确认蒸汽发生器设计参数,通常为不同流量下的参数,与一回路流量Q设计值匹配,如表1所示;
表1
根据及W=hAΔT计算不同设计流量下的蒸汽发生器传热能力hA,如表2所示;
表2
步骤二:待核电厂一二回路满功率稳定运行后,关闭蒸汽发生器排污,待机组稳定后进行步骤三;
步骤三:进行一二回路热平衡测量,获得试验数据及结果,主要获取数据如表3所示;
表3
步骤四:根据试验数据及结果进行数据处理,确认蒸汽发生器传热能力。计算方法如下:
(1)根据蒸汽发生器热功率W,一回路压力P’、一回路侧进出口温度tc计算通过蒸汽发生器流量Q(m3/h):首先通过一回路压力P’、一回路侧进出口温度tc查物性参数表,确定进口段密度ρ、出口段焓Hh、进口段焓Hc、主泵功率Pw:
Q = W - Pw ρ ( H h - H c ) * 3600
(2)将计算所得流量Q与设计流量插值,计算Q下蒸汽发生器设计传热能力h’A’。
(3)根据及W=hAΔT计算Q流量下的蒸汽发生器实际传热能力hA。
(4)将实际传热能力hA与蒸汽发生器设计传热能力h’A’,比较确认是否满足设计。
上表中计算数据如表4所示;
表4

Claims (2)

1.一种蒸汽发生器设计裕度计算方法,其特征在于:包括以下步骤:
步骤一:确认蒸汽发生器设计参数,包括蒸汽压力P、饱和蒸汽温度ts、蒸汽发生器热功率W、一回路侧进口温度th、一回路侧出口温度tc、一回路流量Q;根据及W=hAΔT计算不同设计流量下的蒸汽发生器设计传热能力hA;
步骤二:待核电厂一二回路满功率稳定运行后,关闭蒸汽发生器排污,待机组稳定后进行步骤三;
步骤三:进行一二回路热平衡测量,获得试验数据及结果,获取的数据包括蒸汽压力P、蒸汽发生器热功率W、一回路侧进口温度th、一回路侧出口温度tc、一回路压力P’、主泵功率Pw;
步骤四:根据试验数据及结果进行数据处理,确认蒸汽发生器传热能力。
2.根据权利要求1所述的蒸汽发生器设计裕度计算方法,其特征在于:所述的步骤四计算方法如下:
(1)根据蒸汽发生器热功率W,一回路压力P’、一回路侧进出口温度tc计算通过蒸汽发生器流量Q:首先通过一回路压力P’、一回路侧进出口温度tc查物性参数表,确定进口段密度ρ、出口段焓Hh、进口段焓Hc
Q = W - Pw ρ ( H h - H c ) * 3600
(2)将计算所得流量Q与设计流量插值,计算Q下蒸汽发生器设计传热能力h’A’;
(3)根据及W=hAΔT计算Q流量下的蒸汽发生器实际传热能力hA;
(4)将实际传热能力hA与蒸汽发生器设计传热能力h’A’比较,确认是否满足设计。
CN201510124153.1A 2015-03-20 2015-03-20 蒸汽发生器设计裕度计算方法 Active CN106033496B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510124153.1A CN106033496B (zh) 2015-03-20 2015-03-20 蒸汽发生器设计裕度计算方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510124153.1A CN106033496B (zh) 2015-03-20 2015-03-20 蒸汽发生器设计裕度计算方法

Publications (2)

Publication Number Publication Date
CN106033496A true CN106033496A (zh) 2016-10-19
CN106033496B CN106033496B (zh) 2019-05-17

Family

ID=57148810

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510124153.1A Active CN106033496B (zh) 2015-03-20 2015-03-20 蒸汽发生器设计裕度计算方法

Country Status (1)

Country Link
CN (1) CN106033496B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109443964A (zh) * 2018-10-23 2019-03-08 岭东核电有限公司 蒸汽发生器管束磨损评估方法
CN111680257A (zh) * 2020-06-16 2020-09-18 三门核电有限公司 一种核电厂热试期间蒸汽发生器泄漏率的计算方法
CN113124387A (zh) * 2021-03-26 2021-07-16 华能山东石岛湾核电有限公司 螺旋盘管式蒸汽发生器的防护装置及防护方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050007938A (ko) * 2003-07-12 2005-01-21 두산중공업 주식회사 원자력 발전소 구조물의 열해석 방법
JP2006300404A (ja) * 2005-04-20 2006-11-02 Mitsubishi Heavy Ind Ltd スケールの除去方法
CN102279901A (zh) * 2011-05-17 2011-12-14 湖北省电力公司电力试验研究院 一种针对第三代压水堆核电机组的建模方法
CN102568625A (zh) * 2011-12-08 2012-07-11 中广核工程有限公司 一种核电站数字化测试系统
CN104200061A (zh) * 2014-07-31 2014-12-10 北京广利核系统工程有限公司 一种第三代核电站压水堆堆芯功率计算方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050007938A (ko) * 2003-07-12 2005-01-21 두산중공업 주식회사 원자력 발전소 구조물의 열해석 방법
JP2006300404A (ja) * 2005-04-20 2006-11-02 Mitsubishi Heavy Ind Ltd スケールの除去方法
CN102279901A (zh) * 2011-05-17 2011-12-14 湖北省电力公司电力试验研究院 一种针对第三代压水堆核电机组的建模方法
CN102568625A (zh) * 2011-12-08 2012-07-11 中广核工程有限公司 一种核电站数字化测试系统
CN104200061A (zh) * 2014-07-31 2014-12-10 北京广利核系统工程有限公司 一种第三代核电站压水堆堆芯功率计算方法

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
叶奇蓁 等: "《中国电气工程大典》", 31 July 2009 *
姚彦贵 等: "核电蒸汽发生器热工水力静态特性计算分析研究", 《能源技术》 *
姚彦贵: "核电蒸汽发生器热工水力稳态特性计算分析研究", 《中国优秀博硕士学位论文全文数据库(硕士) 工程科技Ⅱ辑》 *
孙月多: "《秦山核电二期工程建设经验汇编 调试卷Ⅱ》", 30 June 2004 *
宋京凯 等: "蒸汽发生器堵管对装置功率影响研究", 《哈尔滨工程大学学报》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109443964A (zh) * 2018-10-23 2019-03-08 岭东核电有限公司 蒸汽发生器管束磨损评估方法
CN109443964B (zh) * 2018-10-23 2021-03-02 岭东核电有限公司 蒸汽发生器管束磨损评估方法
CN111680257A (zh) * 2020-06-16 2020-09-18 三门核电有限公司 一种核电厂热试期间蒸汽发生器泄漏率的计算方法
CN111680257B (zh) * 2020-06-16 2023-09-08 三门核电有限公司 一种核电厂热试期间蒸汽发生器泄漏率的计算方法
CN113124387A (zh) * 2021-03-26 2021-07-16 华能山东石岛湾核电有限公司 螺旋盘管式蒸汽发生器的防护装置及防护方法
CN113124387B (zh) * 2021-03-26 2022-10-04 华能山东石岛湾核电有限公司 螺旋盘管式蒸汽发生器的防护装置及防护方法

Also Published As

Publication number Publication date
CN106033496B (zh) 2019-05-17

Similar Documents

Publication Publication Date Title
CN108090663B (zh) 供热机组深度调峰最低出力的评估方法及系统
Taler et al. Monitoring of thermal stresses in pressure components based on the wall temperature measurement
Yang et al. Experimental study of the flow and heat transfer performance of a PCHE with rhombic fin channels
Zhao et al. Fatigue lifetime assessment on a high-pressure heater in supercritical coal-fired power plants during transient processes of operational flexibility regulation
CN105910843B (zh) 一种热工综合试验装置的热损失测试方法
Qi et al. Numerical simulation of the heat transfer of superheater tubes in power plants considering oxide scale
CN103726887A (zh) 一种燃煤机组汽轮机性能在线监测方法
CN103776502B (zh) 火电机组中低压缸入口热再热蒸汽质量流量实时计量方法
CN103674333A (zh) 一种燃煤电站入炉煤低位发热量的实时辨识方法
CN106033496A (zh) 蒸汽发生器设计裕度计算方法
Álvarez-Fernández et al. Thermal analysis of closed feedwater heaters in nuclear power plants
Vinod et al. Experimental evaluation of the heat transfer performance of sodium heated once through steam generator
Xu et al. Research on varying condition characteristic of feedwater heater considering liquid level
CN109002741A (zh) 一种压水堆核电机组一、二回路系统传递功率模拟方法及系统
CN108595723A (zh) 一种锅炉暖风器回热量计算方法及装置
Kang et al. Coupled system model analysis for a small modular reactor cogeneration (combined heat and power) application
CN104896457A (zh) 锅炉各级受热面烟气温度确定方法及装置
Madejski et al. Analysis of fouling degree of individual heating surfaces in a pulverized coal fired boiler
Preda et al. Development of a heat transfer correlation for supercritical CO2 based on multiple data sets
CN103728055B (zh) 一种火电机组锅炉炉膛出口烟气能量的实时估计方法
CN103697958B (zh) 燃煤机组汽包出口饱和蒸汽质量流量的实时计量方法
Liu et al. Experimental study on heat transfer characteristics of a condenser in the presence of air
Ibrahim et al. A parametric study of the impact of the cooling water site specific conditions on the efficiency of a pressurized water reactor nuclear power plant
Galindo-García et al. CFD simulations of heat recovery steam generators including tube banks
Kim et al. Design Features of the Separate Effect Test Facility for a Forced-Draft Sodium-to-Air Heat Exchanger (FHX) with Helical Finned Tubes

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant