CN106026119B - Over long distances, the reactive-load compensation method of more load bus wire electric power systems - Google Patents

Over long distances, the reactive-load compensation method of more load bus wire electric power systems Download PDF

Info

Publication number
CN106026119B
CN106026119B CN201610366684.6A CN201610366684A CN106026119B CN 106026119 B CN106026119 B CN 106026119B CN 201610366684 A CN201610366684 A CN 201610366684A CN 106026119 B CN106026119 B CN 106026119B
Authority
CN
China
Prior art keywords
switch station
station
load
compensation
reactive
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610366684.6A
Other languages
Chinese (zh)
Other versions
CN106026119A (en
Inventor
闫新
闫观清
孙国强
杨纲举
闫鹏
崔浩朋
秦卫贞
胡会永
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yellow River Engineering Consulting Co Ltd
Original Assignee
Yellow River Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yellow River Engineering Consulting Co Ltd filed Critical Yellow River Engineering Consulting Co Ltd
Priority to CN201610366684.6A priority Critical patent/CN106026119B/en
Publication of CN106026119A publication Critical patent/CN106026119A/en
Application granted granted Critical
Publication of CN106026119B publication Critical patent/CN106026119B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/30Reactive power compensation

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Control Of Electrical Variables (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses the reactive-load compensation method of a kind of distance, more load bus wire electric power systems, one, design over long distances, more load bus wire electric power systems when, rationally definite center switch station, the position at interconnection switch station;Interconnection switch station is disposed in adjacent two center switch station centre position;2nd, overhead transmission line length, the cable run length between each center switch station and adjacent interconnection switch station are calculated, and calculates the electrical centre position of line-to-ground capacity current, fuser station is set in electrical centre position;3rd, according to centralized compensation reactive power compensation is carried out with the principle that dispersion compensation is combined.The phenomenon that power factor is relatively low, remarkable in economical benefits are greatly improved the invention has the advantages that realizing.

Description

Over long distances, the reactive-load compensation method of more load bus wire electric power systems
Technical field
The present invention relates to electric power system reactive-load compensation method, more particularly, to long range, more load bus wire power supply system The reactive-load compensation method of system.
Background technology
Over long distances, more load bus wire electric power systems are widely used in long range large water transportation water delivery engineering, at a high speed public affairs In the engineerings such as road, high ferro, urban subway tunnel.Its main feature is that along the line(Along supply line)Load bus is more.Now with big over long distances Exemplified by type water transfer water delivery trunk canal, bleeder gate, control gate, water-break gate, emergency repair gate and other buildings along the line There are many object, load bus mostly so that used in number of cables also increase therewith, and electric power system is linear additionally arranges, therefore causes Electric power system power factor is too low, causes the waste of electric energy, and the power tune expense that grid company is imposed is consequently increased, and adds power supply The operating cost of system.Center switch station power factor is advanced and far below standard value, causes the folding of disjunction equipment difficult, works as hair During raw singlephase earth fault, earthing capacitance current will also greatly increase, and electric arc is not easy to extinguish, and causes failure propagation, exists simultaneously Harmonic pollution power supply environmental problem.
The content of the invention
Present invention aims at the reactive-load compensation methods for providing a kind of long range, more load bus wire electric power systems.
To achieve the above object, the present invention takes following technical proposals:
Long range of the present invention, the reactive-load compensation method of more load bus wire electric power systems, as steps described below into Row:
The first step, when designing the long range, more load bus wire electric power systems, according to the load of more load buses Distribution rationally determines center switch station, the position at interconnection switch station;Center switch station position considers drawing for power supply point It connects, supply load scope, supply load size, power supply distance factor;The interconnection switch station is disposed in adjacent two center Switchyard centre position;Over long distances, more load bus wire electric power systems are arranged as required to multiple center switch stations and contact Switchyard, the interconnection switch at interconnection switch station is off during normal operation, and each center switch station radius of electricity supply is two-phase The half of distance between adjacent center switch station;
Overhead transmission line length, cable run between second step, each center switch station of calculating and adjacent interconnection switch station Length, and the electrical centre position of the line-to-ground capacity current is calculated, in the electrical centre position, fuser station is set, The fuser station provides equipment position for the reactive-load compensation of electric power system;
3rd step, the principle being combined according to centralized compensation with dispersion compensation;
The centralized compensation is:It is idle to adjacent interconnection switch station line-to-ground capacity current to calculate each center switch station Power capacity, the bus bar side at each center switch station implement lagging reactive power compensation, perception by dynamic reactive compensation device Reactive power capacity is in the 30% of the center switch station to the adjacent interconnection switch station transmission line of electricity capacity current capacity of bilateral and this Heart switchyard is the sum of to power system transformer substation transmission line of electricity capacity current capacity;
The center switch station, interconnection switch station, fuser station belong to load bus, exist including other load buses Interior, each load bus all there are electrical equipment, also influences center when the method for operation of equipment changes, in a certain range and opens The power factor of station busbar is closed, therefore the bus bar side at center switch station sets dynamic reactive compensation device, realizes centralized compensation.
The dispersion compensation is:Calculate each center switch station to adjacent interconnection switch station transmission line of electricity capacity current over the ground Reactive power capacity implements lagging reactive power compensation, perceptual nothing in respective fuser station bus bar side by constant reactance device Work(power capacity is the center switch station to the 70% of adjacent interconnection switch station transmission line of electricity capacity current.
The phenomenon that power factor is relatively low, remarkable in economical benefits are greatly improved the invention has the advantages that realizing;Using concentrate with The ratio of the shared compensation demand capacity of the reactive-load compensation that dispersed phase combines, reasonable distribution centralized compensation capacity and dispersion compensation capacity Example, the lagging reactive power of constant reactance device output offset the capacitive charging reactive power that line cord generates, reduce capacitive Caused by reactive power the problem of overtension, good action is played to the operational safety of electric power supply system equipment;Each center switch It stands and implements dynamic passive compensation realization perception, the bidirectional compensating of capacitive reactive power, dynamic tracks real-time compensation, reaches automatic tune Section compensation, the function of filtering, it is therefore prevented that harmonic pollution power supply environment meets demand of the electric power system to harmonic wave control, reduces Energy loss in electric power system.
Description of the drawings
Fig. 1 is the structure diagram that the present invention implements design.
Specific embodiment
As shown in Figure 1, long range of the present invention, the reactive-load compensation method of more load bus wire electric power systems, now with It is described between two center switch stations 1,2 for Typical Representative:
First, second center switch station 1,2 is each responsible for respective power supply area, first, second center switch station 1,2 Leading-out terminal respectively constitutes respective wire electric power system, and wire electric power system is opened by the contact at interconnection switch station 3,3.1,3.2 4,4.1,4.2 connections are closed, interconnection switch station 3 is disposed in the interposition of distance between first, second center switch station 1,2 It puts;The interconnection switch 4 at interconnection switch station 3 is off during wire electric power system normal operation, wire electric power system according to Design requirement is respectively provided with multiple load buses 1.1,2.1 etc., the end of incoming cables at first, second center switch station 1,2 respectively with 35kV electric system connects.
It is each aerial between bilateral interconnection switch station 3,3.1,3.2 that first, second center switch station 1,2 is calculated respectively Then line length and cable run length calculate overhead transmission line described in respective bilateral and cable run capacity current over the ground Electrical centre position sets fuser station 1.2,1.22,2.2,2.22 in respective bilateral electrical centre position;It is of the present invention Load bus centered on all step-down substations in switchyard, interconnection switch station, fuser station and electric power system;When the electricity Gas center is located at some load bus position(Or close to some load bus)When, fuser station may be provided in load bus Locate, the let-down stations at the load bus become selected fuser station, have so not only been convenient for management but also have saved fuser station Construction cost.
The principle being combined according to centralized compensation with dispersion compensation:
The centralized compensation is:(1), calculate the first center switch station 1 to two sections of lines between bilateral interconnection switch station 3 and 3.1 The reactive power capacity of road capacity current over the ground;(2), calculate the second center switch station 2 between bilateral interconnection switch station 3 and 3.2 The reactive power capacity of twolink capacity current over the ground;(3), respectively calculate first, second center switch station 1,2 to corresponding The reactive power capacity of transmission line of electricity between electric system capacity current over the ground;(4), respectively in first, second center switch Stand 1,2 bus bar side set dynamic reactive compensation device 1.3,2.3 implement lagging reactive power compensation.Dynamic reactive compensation device 1.3 lagging reactive power capacity are the center switch station 1 to two sections of power transmission line appearances of a street between the adjacent interconnection switch station 3 and 3.1 of bilateral Property current capacity 30% with the center switch station 1 the sum of to 35kV power system transformer substation transmission line of electricity capacity current capacity;It is dynamic 2.3 lagging reactive power capacity of state reactive power compensator is the center switch station 2 between the adjacent interconnection switch station 3 and 3.2 of bilateral The 30% of two sections of transmission line of electricity capacity current capacity and the center switch station 2 to 35kV power system transformer substation transmission line of electricity capacitives The sum of current capacity.
The dispersion compensation is:Calculate respectively first, second center switch station 1,2 to bilateral interconnection switch station 3,3.1, The reactive power capacity of 3.2 transmission lines of electricity capacity current over the ground, it is then female in respective fuser station 1.2,1.22,2.2,2.22 Line side sets constant reactance device 1.4,1.44,2.4,2.44 to implement lagging reactive power compensation;1.4 inductive reactive power of constant reactance device Switchyard 1 is to the 70% of 3 transmission line of electricity capacity current reactive power capacity of interconnection switch station centered on power capacity;Constant reactance Switchyard 2 is to 3 transmission line of electricity capacity current reactive power capacity of interconnection switch station centered on 2.4 lagging reactive power capacity of device 70%;Switchyard 1 is electric to 3.1 transmission line of electricity capacitive of interconnection switch station centered on 1.44 lagging reactive power capacity of constant reactance device Flow the 70% of reactive power capacity;Switchyard 2 is to interconnection switch station centered on 2.44 lagging reactive power capacity of constant reactance device The 70% of 3.2 transmission line of electricity capacity current reactive power capacity.

Claims (1)

1. a kind of reactive-load compensation method of long range, more load bus wire electric power systems, it is characterised in that:As steps described below It carries out:
The first step, when designing the long range, more load bus wire electric power systems, according to the load of more load buses point Cloth rationally determines center switch station, the position at interconnection switch station;Center switch station position considers drawing for power supply point It connects, supply load scope, supply load size, power supply distance factor;The interconnection switch station is disposed in adjacent two center Switchyard centre position;Over long distances, more load bus wire electric power systems according to design requirement set multiple center switch stations and Interconnection switch station, the interconnection switch at interconnection switch station is off during normal operation, and each center switch station radius of electricity supply is The half of distance between two adjacent center switch stations;
Overhead transmission line length, cable run length between second step, each center switch station of calculating and adjacent interconnection switch station, And the electrical centre position of the overhead transmission line, cable run capacity current over the ground is calculated, it is set in the electrical centre position Fuser station, the fuser station provide equipment position for the reactive-load compensation of electric power system;
The principle that 3rd step, reactive-load compensation are combined according to centralized compensation with dispersion compensation;
The centralized compensation is:Calculate the idle of each center switch station to adjacent interconnection switch station transmission line of electricity capacity current over the ground Power capacity, the bus bar side at each center switch station implement lagging reactive power compensation, perception by dynamic reactive compensation device Reactive power capacity is in the 30% of the center switch station to the adjacent interconnection switch station transmission line of electricity capacity current capacity of bilateral and this Heart switchyard is the sum of to power system transformer substation transmission line of electricity capacity current capacity;
The center switch station, interconnection switch station, fuser station belong to load bus, including other load buses, respectively Load bus all there are electrical equipment, when the method for operation of equipment changes, also influences center switch station in a certain range The power factor of busbar, therefore the bus bar side at center switch station sets dynamic reactive compensation device, realizes centralized compensation;
The dispersion compensation is:Calculate the idle of each center switch station to adjacent interconnection switch station transmission line of electricity capacity current over the ground Power capacity implements lagging reactive power compensation, inductive reactive power work(in respective fuser station bus bar side by constant reactance device Rate capacity is the center switch station to the 70% of adjacent interconnection switch station transmission line of electricity capacity current reactive power capacity.
CN201610366684.6A 2016-05-30 2016-05-30 Over long distances, the reactive-load compensation method of more load bus wire electric power systems Active CN106026119B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610366684.6A CN106026119B (en) 2016-05-30 2016-05-30 Over long distances, the reactive-load compensation method of more load bus wire electric power systems

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610366684.6A CN106026119B (en) 2016-05-30 2016-05-30 Over long distances, the reactive-load compensation method of more load bus wire electric power systems

Publications (2)

Publication Number Publication Date
CN106026119A CN106026119A (en) 2016-10-12
CN106026119B true CN106026119B (en) 2018-05-22

Family

ID=57091937

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610366684.6A Active CN106026119B (en) 2016-05-30 2016-05-30 Over long distances, the reactive-load compensation method of more load bus wire electric power systems

Country Status (1)

Country Link
CN (1) CN106026119B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2813005C1 (en) * 2023-08-18 2024-02-06 федеральное государственное бюджетное образовательное учреждение высшего образования "Национальный исследовательский университет "МЭИ" (ФГБОУ ВО "НИУ "МЭИ") METHOD OF POWER SUPPLY TO CONSUMERS IN CASE OF DAMAGE TO PHASE OF 110 kV ELECTRICAL NETWORK

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107181265B (en) * 2017-07-11 2019-06-18 刘儒水 Distribution line one-point or multi-point reactive-load compensation method and device
CN110289617A (en) * 2019-07-03 2019-09-27 厦门理工学院 A kind of building harmonic compensation method, terminal device and storage medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101872969A (en) * 2010-07-14 2010-10-27 吉林省电力有限公司电力科学研究院 Capacitive grounding current distributed compensation method and device for medium-voltage power supply system
CN202503293U (en) * 2012-03-12 2012-10-24 青海电力科学试验研究院 Dynamic reactive power compensation device for long-distance transmission line of power grid
CN103078329A (en) * 2013-02-05 2013-05-01 江苏科能电力工程咨询有限公司 Output reactive compensation analysis method for long-distance 200kV submarine cable of offshore wind plant
CN104767210A (en) * 2015-04-08 2015-07-08 广西诺思贝电气股份有限公司 Reactive collaborative compensation system and method of power distribution network low voltage circuit

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE510197C2 (en) * 1997-02-06 1999-04-26 Asea Brown Boveri Method and apparatus for controlling a capacitor device for a shunt-coupled static compensator unit with unblocking signals to indicate non-current state of input valves

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101872969A (en) * 2010-07-14 2010-10-27 吉林省电力有限公司电力科学研究院 Capacitive grounding current distributed compensation method and device for medium-voltage power supply system
CN202503293U (en) * 2012-03-12 2012-10-24 青海电力科学试验研究院 Dynamic reactive power compensation device for long-distance transmission line of power grid
CN103078329A (en) * 2013-02-05 2013-05-01 江苏科能电力工程咨询有限公司 Output reactive compensation analysis method for long-distance 200kV submarine cable of offshore wind plant
CN104767210A (en) * 2015-04-08 2015-07-08 广西诺思贝电气股份有限公司 Reactive collaborative compensation system and method of power distribution network low voltage circuit

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2813005C1 (en) * 2023-08-18 2024-02-06 федеральное государственное бюджетное образовательное учреждение высшего образования "Национальный исследовательский университет "МЭИ" (ФГБОУ ВО "НИУ "МЭИ") METHOD OF POWER SUPPLY TO CONSUMERS IN CASE OF DAMAGE TO PHASE OF 110 kV ELECTRICAL NETWORK

Also Published As

Publication number Publication date
CN106026119A (en) 2016-10-12

Similar Documents

Publication Publication Date Title
Van Hertem et al. Multi-terminal VSC HVDC for the European supergrid: Obstacles
CN103078315B (en) Single-phase and three-phase combined in-phase power supply and transformation device
CN103895534B (en) Double-current system traction power supply system based on modularized multi-level current converter
Kaipia et al. Field test environment for LVDC distribution-implementation experiences
CN106374463B (en) A kind of A+ classes power supply area power distribution network powering mode configuration method
CN104734134B (en) A kind of inverter earthed system
CN106099917B (en) A kind of method that substation's load transfer scheme quickly determines
CN105610158A (en) Distributed power flow controller and control method therefor
CN103839116A (en) Transformer substation capacity allocation method based on different power supply areas
CN103078329B (en) Output reactive compensation analysis method for long-distance 200kV submarine cable of offshore wind plant
Gaigowal et al. Distributed power flow controller using single phase DSSC to realize active power flow control through transmission line
CN208796792U (en) A kind of traction-compensator transformer
CN106026119B (en) Over long distances, the reactive-load compensation method of more load bus wire electric power systems
CN109215977A (en) A kind of traction-compensator transformer
CN104767191B (en) A kind of inverter earthed system
CN109065338A (en) A kind of homo-phase traction transformer
CN110588449B (en) Traction substation power supply structure and control method thereof
CN209343923U (en) A kind of homo-phase traction transformer
CN205646836U (en) Long distance, many load bus threadiness power supply reactive compensation system
CN207896531U (en) Extra-high voltage alternating current transformer substation
CN208673836U (en) A kind of compensator transformer
Yang et al. Installation, system-level control strategy and commissioning of the Nanjing UPFC project
CN201846015U (en) GIS (global information system) power distribution unit adopting one and half breaker connection
CN208781621U (en) Weak capacity current type medium-pressure power cable
CN202145572U (en) Turn adjusting controllable reactor

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 450003 Zhengzhou Jinshui Road, Henan, No. 109

Patentee after: Yellow River Survey Planning and Design Research Institute Co., Ltd.

Address before: 450003 Zhengzhou Jinshui Road, Henan, No. 109

Patentee before: Yellow River Engineering Consulting Co., Ltd.

CP01 Change in the name or title of a patent holder