CN106014371B - A kind of waterpower Breakdown acidizing technique - Google Patents

A kind of waterpower Breakdown acidizing technique Download PDF

Info

Publication number
CN106014371B
CN106014371B CN201610363055.8A CN201610363055A CN106014371B CN 106014371 B CN106014371 B CN 106014371B CN 201610363055 A CN201610363055 A CN 201610363055A CN 106014371 B CN106014371 B CN 106014371B
Authority
CN
China
Prior art keywords
waterpower
breakdown acidizing
breakdown
acidizing
pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610363055.8A
Other languages
Chinese (zh)
Other versions
CN106014371A (en
Inventor
王俭
满春山
贺国宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DAQING XINZHIHE TECHNOLOGY Co Ltd
Original Assignee
DAQING XINZHIHE TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DAQING XINZHIHE TECHNOLOGY Co Ltd filed Critical DAQING XINZHIHE TECHNOLOGY Co Ltd
Priority to CN201610363055.8A priority Critical patent/CN106014371B/en
Publication of CN106014371A publication Critical patent/CN106014371A/en
Application granted granted Critical
Publication of CN106014371B publication Critical patent/CN106014371B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/25Methods for stimulating production
    • E21B43/26Methods for stimulating production by forming crevices or fractures

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

Waterpower Breakdown acidizing technique.Technique includes the following steps:(1), well head is torn open;(2), former well casing column is played;(3), lower waterpower Breakdown acidizing tubing string;(4), magnetic orientation;(5), high-pressure hydraulic Breakdown acidizing;(6), ground pressure testing:Ground pressure testing 55Mpa, 10min, which are not pierced, does not leak pressure testing qualification;(7), 1 layer of waterpower Breakdown acidizing;(8), pitching, which is skidded, covers;(9), 2 layers of waterpower Breakdown acidizing;(10), pitching, which is skidded, covers;(11), 3 layers of waterpower Breakdown acidizing;(12), closing well returns drain after reacting 12 hours;(13), Breakdown acidizing tubing string is played;(14), thorn, which is washed, measures;(15), lower completion tubular column:Lower leaf water-distributing tool, antisepsis oil pipe apply stop-leak compound;Seat well head, ending.The abundant Applied Physics method of this application improves the effective penetration range of acid solution in the earth formation, improves stratum permeability energy in wide range, to achieve the purpose that volume increase, augmented injection.

Description

A kind of waterpower Breakdown acidizing technique
Technical field:
The present invention relates to oilfield oil well block releasing technique fields, belong to a kind of waterpower Breakdown acidizing technique.
Background technology:
During oil extraction, oil-water well near wellbore zone stratum has been contaminated clogging, and water injection pressure is high, Injection allocation requirement is not achieved in some water filling layers, influences water injection rate and crude output, in actual operation the low block of in-place permeability Conventional acidulation de-plugging does not have effect, and implementation fracture acidizing de-plugging process complexity is of high cost, and Organic Material Blocking is also easy to produce to stratum.
Invention content:
Insufficient present in background technology in order to overcome, the present invention provides a kind of waterpower Breakdown acidizing technique, and this application is filled Divide Applied Physics method to improve the effective penetration range of acid solution in the earth formation, improves stratum permeability energy in wide range, from And achieve the purpose that consumption reduction volume increase, augmented injection.
The technical solution adopted by the present invention to solve the technical problems is:The waterpower Breakdown acidizing technique includes following step Suddenly:
(1), well head is torn open:It tears well head open, fills well head controller, no overflow;
(2), former well casing column is played;
(3), lower waterpower Breakdown acidizing tubing string:Lower silk plug, 5 grades of packer, band sand blower of sliding sleeve, sanding machine, hydraulic anchor, peace Full connector, external upset tubing;
(4), magnetic orientation:Cooperation test team surveys magnetic orientation, and tool depth is qualified;
(5), high-pressure hydraulic Breakdown acidizing prepares:Extemporaneous preparation acid solution, standby 3, acid solution tank car, water-tank lorry 4, connection are high Press pump vehicle is acidified pump truck, makees the preparation of waterpower Breakdown acidizing;
(6), ground pressure testing:Ground pressure testing 55Mpa, 10min, which are not pierced, does not leak pressure testing qualification:
(7), 1 layer of waterpower Breakdown acidizing:With 30~80m of clear water containing expansion-resisting agent3, improve pump pressure and splash pressure Discharge capacity dynamic, increasing discharge capacity makes crack extend forward after confirmation presses off crack, will contain expansion-resisting agent using ground high pressure pumping-in equipment Clear water, the discharge capacity to substantially exceed formation absorption ability inject pit shaft, high pressure have been suppressed near perforation oil reservoir, when bottom pressure is super After crossing the neighbouring stratum minimum principal stress of the borehole wall and the tensile strength of rock, crack is formed in the earth formation and is extended forward.It takes and replaces Pressure break process, former fracturing fluid carry proppant, not only complex procedures but also pollute stratum, high energy consumption is of high cost.With 1 after water filling Platform is acidified 18~28m of pump truck acid filling liquid3, acid solution decomposes the dilution of contamination and plugging object and flows to shaft bottom, outside discharge well.For crowded liquid clear water 4.0m3, it is that the acid solution in oil pipe is squeezed into stratum for crowded clear water, prevents acid solution to tube corrosion.Complete 1 layer of waterpower de-plugging acid Change construction;Contain expansion-resisting agent in clear water, the mass concentration of expansion-resisting agent is 1%;Electrostatic Absorption is relied in expansion-resisting agent reservoir reconstruction Inhibit small bits of clay migration and hydration swelling, has good inhibiting effect to clay swell, dispersion and migration.
(8), pitching, which is skidded, covers:Steel ball is put into oil pipe, is skidded and is covered with pump truck, blocks 1 layer;
(9), 2 layers of waterpower Breakdown acidizing:With 30~80m of clear water containing 1% expansion-resisting agent3, carry out waterpower de-plugging and improve pump Pressure injection anticipates observed pressure discharge capacity dynamically, and increasing discharge capacity makes crack extend forward after confirmation presses off crack, with acidification pump truck after de-plugging 18~28m of acid filling liquid3, for liquid clear water 4.0m is squeezed3, complete 2 layers of waterpower Breakdown acidizing construction;
(10), pitching, which is skidded, covers:Steel ball is put into oil pipe, is skidded and is covered with pump truck, blocks 2 layers;
(11), 3 layers of waterpower Breakdown acidizing:With 30~80m of clear water containing 1% expansion-resisting agent3, carry out waterpower de-plugging raising Pump pressure splashs pressure discharge capacity dynamic, and increasing discharge capacity makes crack extend forward after confirmation presses off crack, and acidizing pump is used after de-plugging 18~28m of vehicle acid filling liquid3, for liquid clear water 4.0m is squeezed3, complete 3 layers of waterpower Breakdown acidizing construction;Closing well reacts 12h;
(12), drain is returned:Drain is returned, well head is without overflow after drain;
(13), Breakdown acidizing tubing string is played:Act external upset tubing, safety joint, hydraulic anchor, band sand blower of sliding sleeve, repacking Sanding machine, 5 grades of packer and silk plug;
(14), thorn, which is washed, measures:Thorn, which is washed, measures oil pipe, assembles completion tubular column;
(15), lower completion tubular column:Lower box cupling, antisepsis oil pipe apply stop-leak compound;Seat well head, ending.
Acid solution in said program is made of following reagent, and each component is by weight ratio:Acid solution amount 18m3, wherein hydrochloric acid 7300 parts, 820 parts of hydrofluoric acid, 230 parts of demulsifier, 650 parts of surfactant, 2300 parts of corrosion inhibiter, ferrous stability 230 5070 parts of part, 1400 parts of expansion-resisting agent and water.Expansion-resisting agent is potassium chloride or ammonium chloride.
The present invention's has an advantageous effect in that:The waterpower Breakdown acidizing technique of the application, is with containing the clear of expansion-resisting agent Water and high concentration Compound-acid are working solution, will contain expansion-resisting agent clear water using ground high pressure pumping-in equipment, to substantially exceed stratum suction The discharge capacity of receipts ability injects pit shaft, and high pressure has been suppressed near perforation oil reservoir, when bottom pressure is more than stratum minimum master near the borehole wall After the tensile strength of stress and rock, crack is formed in the earth formation and is extended forward.Then, by prepared high concentration Compound-acid It injects in crack, acid solution decomposes the dilution of contamination and plugging object and flows to shaft bottom, is discharged outside well.It is formd in the earth formation with a fixed length The high water conservancy diversion crack of degree, width.The seepage flow mode and seepage flow condition for improving fluid near stratum, expand seepage area, subtract Small filtrational resistance simultaneously relieves the pollution near the borehole wall, to achieve the purpose that volume increase, augmented injection.
Description of the drawings:
Fig. 1 is first layer Fracturing Monitoring curve graph in embodiment 1.
Fig. 2 is second layer Fracturing Monitoring curve graph in embodiment 1.
Fig. 3 is third layer Fracturing Monitoring curve graph in embodiment 1.
Fig. 4 is first layer Fracturing Monitoring curve graph in embodiment 2.
Fig. 5 is second layer Fracturing Monitoring curve graph in embodiment 2.
Specific implementation mode
Below in conjunction with embodiment, the present invention is further illustrated:
Embodiment 1,
(1), it tears well head open, fills well head controller, no overflow.(2), former well casing column is played, acts Φ 62mm antisepsis oil pipes 116 Root, 2 grades of Y341-114YF*0.4/0.6 packers, bridge-type * 1m eccentric injection mandrels 2,50.8/47*0.3 ball seats 1 check: It is serious to act former well tubing wax.(3), it measures oil pipe and assembles waterpower Breakdown acidizing tubing string.(4), lower waterpower Breakdown acidizing tubing string Lower Φ 62mm silk plugs 1,5 grades of Y344-114 packers, band sand blower of sliding sleeve 2 reequip sanding machine 1, Φ 114mm hydraulic anchors 1, Φ 110mm safety joints 1, Φ 62mm external upset tubings 114 complete depth 1101.05m.(5), magnetic orientation is matched It closes test team and surveys magnetic orientation, tool depth is qualified.(5), high-pressure hydraulic Breakdown acidizing prepares, extemporaneous preparation acid solution 44m3, standby acid Tank truck 3, water-tank lorry 4, expansion-resisting agent mass concentration are 1% clear water 102m3, high pressure pump truck is connected, pump truck is acidified, makees water Power Breakdown acidizing prepares.(6), ground pressure testing, ground pressure testing 55Mpa, 10min, which are not pierced, does not leak pressure testing qualification.(6), waterpower de-plugging 1 layer of acidification:It is 1% clear water 30m with expansion-resisting agent mass concentration3, carry out waterpower de-plugging pump pressure and 18Mpa dropped to by 25Mpa, arrange Amount is by 1.5m3/ min rises to 2.0m3/ min, 20min, termination of pumping pressure 11Mpa when sharing, with 1 acidification pump truck acid filling liquid 18m3, for liquid 4.0m is squeezed3, it is pumped 12.1Mpa and does not drop, discharge capacity 0.5m3/ min is acidified used time 40min, completes 1 layer of waterpower de-plugging Acidizing treatment.It is as shown in Figure 1 that monitoring curve is split in 1 lamination.(7), pitching, which is skidded, covers, and Φ 38mm steel balls is put into oil pipe, with pump Vehicle, which skids, to be covered, and blocks 1 layer.(8), 2 layers of waterpower Breakdown acidizing are 1% clear water 30m with expansion-resisting agent mass concentration3, carry out waterpower De-plugging pump pressure drops to 22Mpa by 25.63Mpa, and discharge capacity is by 1.2m3/ min rises to 1.6m3/ min, 25min when sharing, termination of pumping Pressure 14Mpa, with 1 acidification pump truck acid filling liquid 18m3, for liquid 4.0m is squeezed3, it is pumped 14Mpa and does not drop, discharge capacity 0.5m3/ min, acid Change used time 40min, completes 2 layers of waterpower Breakdown acidizing construction.It is as shown in Figure 2 that monitoring curve is split in 2 laminations..(9), pitching, which is skidded, covers Φ 43mm steel balls are put into oil pipe, is skidded and is covered with pump truck.Block 2 layers.(10), 3 layers of waterpower Breakdown acidizing, with expansion-resisting agent matter Measure a concentration of 1% clear water 30m3, carry out waterpower de-plugging pump pressure and 24Mpa dropped to by 29Mpa, discharge capacity is by 1.2m3/ min rises to 1.6m3/ min, 25min when sharing;Termination of pumping pressure 13Mpa, with 1 acidification pump truck acid filling liquid 8.0m3, for liquid 4.0m is squeezed3, pump pressure 13Mpa does not drop, discharge capacity 0.5m3/ min is acidified used time 25min, completes 3 layers of position waterpower Breakdown acidizing construction.3 layers of Fracturing Monitoring song Line is as shown in Figure 3.Closing well reacts 12h.(11), drain is returned, drain 8m is returned3, well head is without overflow.(12), Breakdown acidizing tubing string is played, Act Φ 62mm external upset tubings 114, Φ 110mm safety joints 1, Φ 114mm hydraulic anchors 1, band sand blower of sliding sleeve 2 Part reequips sanding machine 1,5 grades of Y344-114 packers, Φ 62mm silk plugs 1.(13), thorn, which is washed, measures, and thorn, which is washed, measures oil pipe. (9), completion tubular column is assembled.(the underground commingled water injection tubing string), lower Φ 62mm box cuplings 1, Φ 62mm antisepsis oil pipes 116 are complete At depth 1098.40m.Lower completion tubular column base well head ending.This well uses the technique effect reached after this technique to be shown in Table 1.
Embodiment 2,
(1), it tears well head open, fills well head controller, no overflow.(2), former well casing column is played:Act Φ 62mm antisepsis oil pipes 117 Root, 2 grades of Y341-114XM packers, 665-2 eccentric injection mandrels 2, Φ 62mm are extremely 1 stifled, check:It is complete to act former well oil pipe It is good.(3), it measures oil pipe and assembles waterpower Breakdown acidizing tubing string.(4), lower waterpower Breakdown acidizing tubing string, lower Φ 62mm silk plugs 1, 3 grades of Y344-114 packers, band sand blower of sliding sleeve 1 reequip sanding machine 1, Φ 114mm hydraulic anchors 1, Φ 110mm safety Connector 1, Φ 62mm external upset tubings 113 complete depth 1085.38m.(4), magnetic orientation, cooperation test team survey magnetic orientation, Tool depth is qualified.(5), high-pressure hydraulic Breakdown acidizing prepares, extemporaneous preparation acid solution 46m3, standby 3, acid solution tank car, water-tank lorry 4 Platform, mass concentration containing expansion-resisting agent are 1% clear water 170m3, high pressure pump truck is connected, pump truck is acidified, makees the preparation of waterpower Breakdown acidizing. (6), ground pressure testing, ground pressure testing 55Mpa, 10min, which are not pierced, does not leak pressure testing qualification.(7), waterpower Breakdown acidizing F21 layers, with containing Expansion-resisting agent mass concentration is 1% clear water 80m3, carry out waterpower de-plugging, pump pressure drops to 29.0Mpa by 37.0Mpa, discharge capacity by 2.0m3/ min rises to 2.4m3/ min, 50min, termination of pumping pressure 17.3Mpa, acid filling liquid 18.0m when sharing3, for liquid 4.0m is squeezed3, It is pumped 29.0Mpa, is not dropped, discharge capacity 2.0m3/ min is acidified used time 12min, completes F21 layers of waterpower Breakdown acidizing construction.F21 layers Fracturing Monitoring curve is as shown in Figure 4.(8), pitching, which is skidded, covers, and Φ 38mm steel balls are put into oil pipe, is skidded and is covered with pump truck, are blocked F21 layers.(9), waterpower Breakdown acidizing F171 layers, be 1% clear water 80m with mass concentration containing expansion-resisting agent3, carry out waterpower de-plugging pump Pressure drops to 28.0Mpa by 33.0Mpa, and discharge capacity is by 2.0m3/ min rises to 2.4m3/ min, 50min when sharing, termination of pumping pressure 16.0Mpa, acid filling liquid 28.0m3, for liquid 4.0m is squeezed3, it is pumped 28.0Mpa and does not drop, discharge capacity 2.0m3/ min is acidified used time 28min, Complete F171 layers of waterpower Breakdown acidizing construction.It is as shown in Figure 5 that monitoring curve is split in F171 laminations.Closing well reacts 12h.(10), the row of returning Liquid returns drain 3.6m3, well head is without overflow.(11), Breakdown acidizing tubing string is played, acts Φ 62mm external upset tubings 113, Φ 110mm safety joints 1, Φ 114mm hydraulic anchors 1, band sand blower of sliding sleeve 1 reequip sanding machine 1, Y344-114 envelopes Every 3 grades of device, Φ 62mm silk plugs 1.(12), thorn, which is washed, measures, and thorn, which is washed, measures oil pipe, assembles completion tubular column.(13), lower completion tubular Column, lower Φ 50.8*47 balls and seat 1,2 sets of bridge type eccentric injection mandrel, 2 grades of Y341-114-X-JH packers, Φ 62mm anti-corrosions 117, oil pipe, Φ 62mm tubing nipple 5.0m complete depth 1096.38m.(14), oil pipe Φ 59mm inside callipers of going into the well is logical It crosses, applies stop-leak compound.(15), seat well head, tear well head controller open.(15), seat well head surveys magnetic orientation, and cooperation test team surveys magnetic orientation, Tool depth of going into the well is qualified.Release just suppresses 19.3Mpa with pump truck, and voltage stabilizing 15min pressure does not drop, and release is qualified, ending.This well It is shown in Table 1 using the technique effect reached after this technique.
Acid solution in said program is made of following reagent:Hydrochloric acid 7300Kg, 820 Kg of hydrofluoric acid, demulsifier 230Kg, table Face activating agent 650Kg, corrosion inhibiter 2300Kg, ferrous stability 230Kg, expansion-resisting agent 1400Kg and water 5070Kg.Expansion-resisting agent is Potassium chloride or ammonium chloride.
Well waterpower Breakdown acidizing effect statistical form table 1
The application can reach following purpose:1, abundant Applied Physics method improve acid solution in bottom effectively penetrate away from From the improvement stratum permeability energy in wide range.2, it can be layered Breakdown acidizing, de-plugging and acidification very are determined to oil reservoir data Liquid measure.3, compared with conventional acidulation de-plugging, plug removal radius is big, forms the channel of a plurality of Thief zone ability, has to contamination and plugging object Stronger decomposition and dilution capacity.4, instead of pressure break, formation contaminant, volume increase consumption reduction are reduced.
The application scope of application:1, suitable for the straight well inclined shaft within 2500 meters of well depth;2, old well regulating multi-zone production rate injection allocation, it is real Existing oil reservoir remaining oil is taped the latent power;3, it is suitable for peripheral hyposmosis, low abundance, the oil-extracting well water injection well of low yield block;4, gather and drive The blocking of oil-water well near wellbore zone.
Layering Breakdown acidizing technique refers to utilizing well in the case of fixed tubular column for the larger reservoir of interlayer span The mode of lower machine tool layering is implemented targetedly successively to construct respectively.
This technique also is implemented to other wells, the results are shown in Table 2:
Well waterpower Breakdown acidizing effect statistical form table 2

Claims (1)

1. waterpower Breakdown acidizing technique, includes the following steps:
(1), well head is torn open:It tears well head open, fills well head controller, no overflow;
(2), former well casing column is played;
(3), lower waterpower Breakdown acidizing tubing string:Lower silk plug, 5 grades of packer, band sand blower of sliding sleeve, repacking sanding machine, hydraulic anchor, peace Full connector, external upset tubing;
(4), magnetic orientation:Cooperation test team surveys magnetic orientation, and tool depth is qualified;
(5), high-pressure hydraulic Breakdown acidizing prepares:Extemporaneous preparation acid solution, standby 3, acid solution tank car, water-tank lorry 4 connect high-pressure pump Vehicle is acidified pump truck, makees the preparation of waterpower Breakdown acidizing;
(6), ground pressure testing:Ground pressure testing 55Mpa, 10min, which are not pierced, does not leak pressure testing qualification:
(7), 1 layer of waterpower Breakdown acidizing:With 30~80m of clear water containing 1% expansion-resisting agent3, carry out waterpower de-plugging and improve pump pressure attention Observed pressure discharge capacity dynamic, increasing discharge capacity makes crack extend forward after confirmation presses off crack, with acidification pump truck acid filling liquid after de-plugging 18~28m3, for liquid clear water 4.0m is squeezed3, complete 1 layer of waterpower Breakdown acidizing construction;
(8), pitching, which is skidded, covers:Steel ball is put into oil pipe, is skidded and is covered with pump truck, blocks 1 layer;
(9), 2 layers of waterpower Breakdown acidizing:With 30~80m of clear water containing 1% expansion-resisting agent3, carry out waterpower de-plugging and improve pump pressure attention Observed pressure discharge capacity dynamic, increasing discharge capacity makes crack extend forward after confirmation presses off crack, with acidification pump truck acid filling liquid after de-plugging 18~28m3, for liquid clear water 4.0m is squeezed3, complete 2 layers of waterpower Breakdown acidizing construction;
(10), pitching, which is skidded, covers:Steel ball is put into oil pipe, is skidded and is covered with pump truck, blocks 2 layers;
(11), 3 layers of waterpower Breakdown acidizing:With 30~80m of clear water containing 1% expansion-resisting agent3, improve pump pressure and splash pressure row Amount dynamic, increasing discharge capacity makes crack extend forward after confirmation presses off crack, with 18~28m of acidification pump truck acid filling liquid after de-plugging3, replace Squeeze liquid clear water 4.0m3, complete 3 layers of waterpower Breakdown acidizing construction;Closing well reacts 12h;
(12), drain is returned:Drain is returned, well head is without overflow after drain;
(13), Breakdown acidizing tubing string is played:Act external upset tubing, safety joint, hydraulic anchor, band sand blower of sliding sleeve, repacking sandblasting Device, 5 grades of packer and silk plug;
(14), thorn, which is washed, measures:Thorn, which is washed, measures oil pipe, assembles completion tubular column;
(15), lower completion tubular column:Lower box cupling, antisepsis oil pipe apply stop-leak compound;Seat well head, ending;
Acid solution used in said program is made of following reagent, and each component is by weight ratio:Acid solution amount 18m3, wherein hydrochloric acid 7300 parts, 820 parts of hydrofluoric acid, 230 parts of demulsifier, 650 parts of surfactant, 2300 parts of corrosion inhibiter, ferrous stability 230 Part, expansion-resisting agent are 1400 parts of potassium chloride or ammonium chloride and 5070 parts of clear water.
CN201610363055.8A 2016-05-27 2016-05-27 A kind of waterpower Breakdown acidizing technique Active CN106014371B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610363055.8A CN106014371B (en) 2016-05-27 2016-05-27 A kind of waterpower Breakdown acidizing technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610363055.8A CN106014371B (en) 2016-05-27 2016-05-27 A kind of waterpower Breakdown acidizing technique

Publications (2)

Publication Number Publication Date
CN106014371A CN106014371A (en) 2016-10-12
CN106014371B true CN106014371B (en) 2018-10-02

Family

ID=57094874

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610363055.8A Active CN106014371B (en) 2016-05-27 2016-05-27 A kind of waterpower Breakdown acidizing technique

Country Status (1)

Country Link
CN (1) CN106014371B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113494271A (en) * 2020-03-18 2021-10-12 中国石油天然气股份有限公司 Shaft blockage removing method and device for high-pressure gas well

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101126314A (en) * 2007-09-12 2008-02-20 中国石油大学(华东) Foam plug flow diverting acidification technique
CN103075139A (en) * 2011-10-26 2013-05-01 中国石油天然气股份有限公司 Immovable pipe column hydraulic jet process for fracture acidizing and pipe column thereof
CN102418507A (en) * 2011-10-27 2012-04-18 中国石油天然气股份有限公司 Low-cost deep blockage removing method for water injection well
CN102979497A (en) * 2012-11-20 2013-03-20 中国石油大学(北京) Device and method for immovable-string type packer-free sliding-sleeve hydraulic-jet pulsed acid fracturing
CN103061684B (en) * 2013-01-21 2015-09-09 中国石油集团渤海钻探工程有限公司 Open-hole horizontal well segmentation many bunches of homogeneous acidification tubing strings and acidization tool thereof
CN104653164B (en) * 2013-11-22 2018-07-13 中国石油天然气股份有限公司 Water-control blockage-removing production-increasing method for low-pressure bottom water reservoir oil well

Also Published As

Publication number Publication date
CN106014371A (en) 2016-10-12

Similar Documents

Publication Publication Date Title
US20220127942A1 (en) Volumetric fracturing method of temporarily plugging and diverting through functional slick water with oil displacement agent injected simultaneously
CN104695927B (en) Coiled tubing and production tubing combined string fracturing and well completion integrated method
CN103967470B (en) A kind of horizontal well mud stone wears lamination cracking method
CN104213895B (en) Hydraulic sand-blasting perforation fracturing and sand-filling combined process method
CN106593389B (en) Fracturing method for realizing high-angle natural fracture oil reservoir by adopting permanent plugging agent
CN103590801A (en) Coal bed methane horizontal well nitrogen foam fracturing mining technology
CN110439521A (en) Advanced energy storage fracturing method
CN106837274A (en) Method for injecting oil displacement agent into oil layer by fracturing to improve recovery ratio
CN106639971A (en) High pressure-bearing blocking method for perforation shot hole
CN105239984A (en) Method for controlling coal mine underground fracturing crack propagation
CN105756650A (en) Method for realizing staged fracturing of horizontal well by adopting mixed temporary plugging agent to block tubular channeling
CN108756806A (en) Pipe leakage administering method is altered outside a kind of production of hydrocarbons well casing
CN104806219B (en) Oil and gas reservoir increased permeation and blocking removal device and increased permeation and blocking removal method thereof
CN103306645B (en) Horizontal well the pressure of the drill splits completion tubular column and technique thereof
CN104696006A (en) Method for extracting residual coal bed gas in multiple layers of goafs by drilling well from ground and penetrating through residual coal pillars
CN111927423A (en) Shale sand fracturing pump-stopping fracturing steering method
CN105178910A (en) Horizontal well water plugging process pipe column and method
CN107461182B (en) Layered fracturing sand prevention method
CN106761548A (en) Method for injecting plugging agent into thick oil layer to plug strong water washing strip by fracturing
CN106014371B (en) A kind of waterpower Breakdown acidizing technique
CN104121000B (en) Water plugging method for low-permeability fractured reservoir casing completion horizontal well
CN110469320B (en) Lost-return lost circulation equivalent density calculation method
CN113530511B (en) Method for developing natural gas reservoir
CN110439528B (en) Carbon dioxide acid fracturing method for low-permeability heterogeneous carbonate rock gas reservoir
CN107246257A (en) Heterogeneous reservoir is acidified remodeling method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant