- CN105973080B CN105973080B CN201610321951.8A CN201610321951A CN105973080B CN 105973080 B CN105973080 B CN 105973080B CN 201610321951 A CN201610321951 A CN 201610321951A CN 105973080 B CN105973080 B CN 105973080B
- Authority
- CN
- China
- Prior art keywords
- block
- pushing block
- fixture block
- base
- red needle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F42—AMMUNITION; BLASTING
- F42B—EXPLOSIVE CHARGES, e.g. FOR BLASTING, FIREWORKS, AMMUNITION
- F42B33/00—Manufacture of ammunition; Dismantling of ammunition; Apparatus therefor
- F42B33/02—Filling cartridges, missiles, or fuzes; Inserting propellant or explosive charges
- F42B33/0207—Processes for loading or filling propulsive or explosive charges in containers
Abstract
The invention discloses a kind of upper fire in a stove before fuel is added system, including interior goods casket and the interior base provided with curved channel provided with vertical goods groove, passage upper end is smoothly docked with goods groove lower end;The base plate for being provided with punching is fixed in the lower end of base, the red needle just to punching is also inserted with base, red needle is suspended by elastic supporting mechanism, pushing block and fixture block are installed in base, between pushing block and fixture block termination close to each other be provided with breach, crossed strip is also lined between pushing block and base, when crossed strip in the raw when, breach between pushing block and fixture block is smoothly connected with the lower end of curved channel, and pushing block covers punching;Striking gear is connected with fixture block, in the presence of striking gear, fixture block transversely spring centerline direction movement.Said structure makes the fire in a stove before fuel is added to be press-fited be disconnected by the transfer of fixture block and pushing block with passage, efficiently avoid and press-fits fire in a stove before fuel is added burning and ignite a series of fire in a stove before fuel is added, not only reduces potential safety hazard, and be conducive to the control of production cost.
Description
Technical field
The present invention relates to a kind of upper fire in a stove before fuel is added system, specifically, it is mainly used in the fire in a stove before fuel is added being pressed into shell case.
Background technology
At present, it is required to load the fire in a stove before fuel is added in shell case, the fire in a stove before fuel is added, which is also referred to as, excites medicine or ignition charge, with the inflammable spy of collision
Point.The process that the fire in a stove before fuel is added loads shell case is commonly called as " the upper fire in a stove before fuel is added ", existing upper fire in a stove before fuel is added system is horizontal type structure, i.e.,:Shell case is horizontal
Arrangement, goods casket are vertically arranged, and vertical goods groove is provided with goods casket, and the fire in a stove before fuel is added slides into the position just to shell case through goods groove, then
The fire in a stove before fuel is added is pressed into shell case by horizontal red needle.During this, the fire in a stove before fuel is added easily burns when being hit by red needle, due to combustion
The fire in a stove before fuel is added of burning is not kept apart with other fires in a stove before fuel is added in goods groove, is easily caused a series of fire in a stove before fuel is added and is ignited, not only with peace
Full hidden danger, make troubles to production, and the extremely disadvantageous control in production cost.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of upper fire in a stove before fuel is added system, and the fire in a stove before fuel is added is press-fited for completely cutting off, it is to avoid
The a succession of burning of the fire in a stove before fuel is added.
Technical scheme is as follows:A kind of upper fire in a stove before fuel is added system, including vertical goods casket, provided with perpendicular in the goods casket
To goods groove, also include base, the passage of arc be provided with the base, the upper end and goods groove lower end of the passage be smooth
Docking;Base plate is fixed with the lower end of the base, punching is provided with the base plate, is also vertically inserted with just on the base
To the red needle of punching, the red needle is suspended by elastic supporting mechanism, and when red needle is moved downward, the lower end of the red needle passes through
Punching;Pushing block and fixture block are installed in the base, breach is provided between the pushing block and fixture block termination close to each other,
Also be lined with crossed strip between the pushing block and base, when the crossed strip in the raw when, the pushing block and folder
Breach between block is smoothly connected with the lower end of curved channel, and the pushing block covers punching;Connected on the fixture block
There is striking gear, in the presence of striking gear, the centerline direction of fixture block transversely spring is moved back and forth;Also, work as fixture block
When being moved to pushing block direction, the fixture block compresses pushing block, and the breach between fixture block and pushing block is moved to the direction of crossed strip,
Make the breach between fixture block and pushing block just to punching.
Using said structure, the passage docked with goods groove is set to be used to convey the fire in a stove before fuel is added in base, the lower end of passage is with pushing away
Breach docking between block and fixture block, rather than goods groove are directly docked with punching, and the fire in a stove before fuel is added for conveying goods groove and passage, which enters, to be pushed away
Breach between block and fixture block, only when fixture block is being moved in the presence of striking gear to pushing block direction, pushing block and fixture block it
Between breach could make the fire in a stove before fuel is added by fixture block and pushing block gripping to above punching, the fire in a stove before fuel is added for carrying out next step press-fits just to punching;This
Sample one, the fire in a stove before fuel is added to be press-fited is disconnected by the transfer of fixture block and pushing block with passage, be efficiently avoid and is press-fited fire in a stove before fuel is added burning and draw
The a series of fire in a stove before fuel is added is fired, potential safety hazard is not only reduced, and be conducive to the control of production cost.
The striking gear includes the swing rod for inserting fixture block from top to bottom, and the swing rod is installed by mounting seat, the peace
Dress seat is fixed on above base, two parallel vertical interlayers is provided with the mounting seat, in two interbedded dividing plates
On be provided with horizontal bar shaped spacing hole, the top of the swing rod is inserted in one of in interlayer, and middle part and the installation of swing rod
Seat is hinged, and latch is fixed with the upper end of the swing rod;The slide plate of suspension is inserted with another interlayer, is put in slide plate direction
Chute is provided with the plate face of bar side, the corresponding end of the latch passes through spacing hole and is caught in chute;The chute includes smooth
Upper vertical section, tilting section and the lower vertical section of connection;Also suspended jumper bar in the top of the red needle, the jumper bar of suspension and
Slide plate is linked by attachment structure;
Move down when slide plate and jumper bar, when the lower vertical section of latch and chute coordinates, the swing rod is not swung, the punching
Bar is downwards close to red needle;
Move down when slide plate and jumper bar, when the tilting section of latch and chute coordinates, the swing rod lower end is to pushing block direction
Swing, the fixture block is pushed against with pushing block, and the breach between pushing block and fixture block is moved to the direction of crossed strip, until pushing block
Punching of the breach just to base plate between fixture block, the jumper bar continues downwards close to red needle;
Move down when slide plate and jumper bar, when the upper vertical section of latch and chute coordinates, the swing rod is not swung, the punching
Bar is pressed downward red needle, and breach through pushing block and fixture block of the lower end of red needle simultaneously stretches into punching;
Move up when slide plate and jumper bar, when the upper vertical section of latch and chute coordinates, the swing rod is not swung, the punching
Bar is moved up, the red needle upward resilience in the presence of elastic supporting mechanism;
Move up when slide plate and jumper bar, when the tilting section of latch and chute coordinates, the swing rod lower end is to away from pushing block
Direction swing, the fixture block decontrols pushing block, pushing block resilience in the presence of crossed strip, until between fixture block and pushing block
Lower end of the breach just to passage;
Move up when slide plate and jumper bar, when the lower vertical section of latch and chute coordinates, the swing rod is not swung, the cunning
Plate and jumper bar move back up to initial position.
Striking gear is so set, and the slide plate swung with driven fork and the jumper bar being suspended above red needle are linked, is made
With more facilitate.
The base include pedestal, cover plate and side plate, the L-shaped bulk of pedestal, be provided with the pedestal bottom with
The adaptable resigning breach of passage, swing rod, fixture block, pushing block and crossed strip;The cover plate is from bottom to top by resigning breach correspondence
The position masking of passage;The resigning breach and poroid, the institute that the position that crossed strip is adapted is in insertion pedestal respective side wall
Side plate is stated to be fixed on the side wall of pedestal, and side plate inwall be provided with crossed strip adapt to guide hole, the transverse direction
The corresponding end of spring is stretched into the guide hole of side plate.Base it is simple in construction, the installation of fixture block, pushing block and crossed strip is more square
Just.
The elastic supporting mechanism includes being fixed on the support block above base, and the red needle is from top to bottom through support
Block, set is lined between the upper end of red needle and support block, is lined with and traps between the lower end of red needle and support block, the upper set
Fixed with trapping with support block, the block being located in upper set is further fixed in the red needle upper end, be cased with red needle vertical
Spring, upper end and the block of the Vertical Spring are pushed against, the lower end of Vertical Spring and abutting of trapping.The structure of elastic supporting mechanism
Simply, it is easy to assembly.
Beneficial effect:The present invention in base by setting the passage docked with goods groove, lower end and pushing block and the folder of passage
Breach docking between block, rather than directly docked with punching, make the fire in a stove before fuel is added to be press-fited by the transfer of fixture block and pushing block with leading to
Road disconnects, and is ignited a series of fire in a stove before fuel is added so as to efficiently avoid and press-fit fire in a stove before fuel is added burning, not only reduces potential safety hazard, Er Qieyou
Beneficial to the control of production cost.
Brief description of the drawings
Fig. 1 is structural representation of the invention.
Fig. 2 is Fig. 1 left view.
Fig. 3 is Fig. 2 A-A sectional views.
Fig. 4 removes the stereogram of support block for Fig. 1.
Fig. 5 is Fig. 4 explosive view.
Fig. 6 is the mounting structure schematic diagram of pushing block and fixture block.
Fig. 7 is the polycrystalline substance schematic diagram of pedestal.
Fig. 8 is Fig. 7 stereogram.
Marked in figure as follows:Base D, passage D1, base plate 1, punching 1a, side plate 2, pedestal 3, resigning breach 3a, trap 4,
Vertical Spring 5, upper set 6, red needle 7, mounting seat 8, interlayer 8a, slide plate 9, chute 9a, jumper bar 10, goods casket 11, goods groove 11a, swing rod
12nd, support block 13, block 14, fixture block 15, pushing block 16, breach 17, cover plate 18, crossed strip 19 and latch 20.
Embodiment
Embodiments of the invention are described below in detail, described embodiment example is shown in the drawings, wherein from beginning to end
Same or similar label represents same or similar element or the element with same or like function.Below with reference to attached
Figure description embodiment is exemplary, it is intended to explains the present invention, and is not considered as limiting the invention.In retouching for the present invention
In stating, it is necessary to explanation, if any term " " center ", " transverse direction ", " longitudinal direction ", " length ", " width ", " thickness ", " on ",
" under ", "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom ", " interior ", " outer ", " clockwise ", " counterclockwise "
It is, based on orientation shown in the drawings or position relationship, to be for only for ease of the narration present invention and letter Deng indicating position and position relationship
Change description, rather than indicate or imply that the device or element of meaning there must be specific orientation, be constructed and grasped with particular orientation
Make, the specific protection domain that should not be construed as limiting the invention.
In the present invention, except as otherwise clear stipulaties and restriction, if any term " assembling ", " connected ", " connection ", " fixation " etc.
Term should go to understand as broad sense, for example, it may be being fixedly connected or being detachably connected, or be integrally connected;Can be
It is joined directly together or is connected by intermediary, can also be that two element internals are connected;Can be direct fixation,
Can also be relatively fixed indirectly.For those of ordinary skills, it can understand above-mentioned as the case may be
The concrete meaning of term in the present invention.
In invention, unless otherwise prescribed and limit, fisrt feature second feature it " on " or it " under " can include
First and second features are directly contacted, and can also not be direct contact including the first and second features but by between them
Other characterisation contact.Moreover, fisrt feature second feature " on ", " under " and " above " to include fisrt feature special second
Directly over levying and oblique upper, or be only to represent that fisrt feature level height is higher than the height of second feature.Fisrt feature is
Two features " on ", " under " and " following " fisrt feature that includes are immediately below second feature or obliquely downward, or are merely representative of the
One characteristic level is highly less than second feature.
Below in conjunction with the accompanying drawings, it is further described by the embodiment to the present invention, makes the technology of the present invention
Scheme and its advantage are clearer, clear and definite.
As shown in Figure 1, Figure 2, Figure 3 and Figure 4, the present invention includes vertical goods casket 11, provided with vertical in the goods casket 11
Goods groove 11a, these are same as the prior art, will not be described here.Also include base D, arc is provided with the base D
Smoothly docked with goods groove 11a lower ends the passage D1, the passage D1 of shape upper end.Base plate is fixed with the lower end of the base D
1, punching 1a is provided with the base plate 1, the red needle 7 just to punching 1a, the red needle 7 are also vertically inserted with the base D
Suspended by elastic supporting mechanism, when red needle 7 is moved downward, the lower end of the red needle 7 pass through punching 1a.The resilient support
Mechanism includes being fixed on support block 13 above base D, the support block 13 can be directly fixed with base D or
Ground connection is relatively fixed.The red needle 7 runs through support block 13 from top to bottom, is lined between the upper end of red needle 7 and support block 13
Set 6, is lined between the lower end of red needle 7 and support block 13 and traps 4, and the upper set 6 and trapping 4 is fixed with support block 13.
The upper end of red needle 7 is further fixed on the block 14 being located in upper set 6, and Vertical Spring 5, the Vertical Spring 5 are cased with red needle 7
Upper end pushed against with block 14, the lower end of Vertical Spring 5 and trap 4 abuttings.
As shown in Fig. 2, Fig. 3, Fig. 5 and Fig. 6, elongated pushing block 16 and fixture block 15 is installed in the base D,
Line of the pushing block 16 with fixture block 15 along its length is vertical with the plane where passage D1 camber lines.In the pushing block 16 and folder
Breach 17 is provided between the termination close to each other of block 15, crossed strip 19 is also lined between the pushing block 16 and base D, the horizontal stroke
Length direction arrangement to spring 19 along pushing block 16.When the crossed strip 19 in the raw when, the pushing block 16 and folder
Breach 17 between block 15 is smoothly connected with curved channel D1 lower end, and the pushing block 16 covers punching 1a.Described
Striking gear is connected with fixture block 15, in the presence of striking gear, the centerline direction of the transversely spring 19 of fixture block 15 is reciprocal
It is mobile.Also, when fixture block 15 is moved to the direction of pushing block 16, the fixture block 15 compresses pushing block 16, fixture block 15 and pushing block 16 it
Between direction from breach 17 to crossed strip 19 move, make the breach 17 between fixture block 15 and pushing block 16 just to punching 1a.
As shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 4, Fig. 5 and Fig. 6, the striking gear includes the pendulum for inserting fixture block 15 from top to bottom
Bar 12, the swing rod 12 is installed by mounting seat 8, and the mounting seat 8 is fixed on above base D, and the mounting seat 8 can be straight
Connect and be fixed on above base D or be relatively fixed indirectly with base D, the lower end of the present embodiment preferably mounting seat 8
It is relatively fixed by support block 13 with base D.Two parallel vertical interlayer 8a are provided with the mounting seat 8, in two folders
Horizontal bar shaped spacing hole is provided with dividing plate between layer 8a.The top of the swing rod 12 is inserted in one of in interlayer 8a, and
And the middle part of swing rod 12 is hinged with mounting seat 8, latch 20 is fixed with the upper end of the swing rod 12.It is inserted with another interlayer 8a
The slide plate 9 of suspension, in the slide plate 9 towards chute 9a is provided with the plate face of the side of swing rod 12, the corresponding end of the latch 20 is passed through
Spacing hole is simultaneously caught in chute 9a.The chute 9a includes upper vertical section, tilting section and the lower vertical section smoothly connected.Described
The top of red needle 7 has also suspended jumper bar 10, and the jumper bar 10 and slide plate 9 of suspension are linked by attachment structure.The jumper bar 10
Know with the mounting structure of slide plate 9 for those skilled in the art, do not limit herein.
Move down when slide plate 9 and jumper bar 10, when latch 20 and chute 9a lower vertical section coordinates, the dead beat of swing rod 12
Dynamic, the jumper bar 10 is downwards close to red needle 7;
Move down when slide plate 9 and jumper bar 10, when latch 20 and chute 9a tilting section coordinates, the lower end of swing rod 12 to
The direction of pushing block 16 is swung, and the fixture block 15 pushes against with pushing block 16, and the breach 17 between pushing block 16 and fixture block 15 is to horizontal bullet
The direction movement of spring 19, until punching 1a of the breach 17 between pushing block 16 and fixture block 15 just to base plate 1, the jumper bar 10 continues
Downwards close to red needle 7;
Move down when slide plate 9 and jumper bar 10, when latch 20 and chute 9a upper vertical section coordinates, the dead beat of swing rod 12
Dynamic, the jumper bar 10 is pressed downward red needle 7, and breach 17 through pushing block 16 and fixture block 15 of the lower end of red needle 7 simultaneously stretches into punching
1a;
Move up when slide plate 9 and jumper bar 10, when latch 20 and chute 9a upper vertical section coordinates, the dead beat of swing rod 12
Dynamic, the jumper bar 10 is moved up, the red needle 7 upward resilience in the presence of elastic supporting mechanism;
Move up when slide plate 9 and jumper bar 10, when latch 20 and chute 9a tilting section coordinates, the lower end of swing rod 12 to
Direction away from pushing block 16 is swung, the relieving of fixture block 15 pushing block 16, the resilience in the presence of crossed strip 19 of pushing block 16,
Until lower end of the breach 17 just to passage D1 between fixture block 15 and pushing block 16;
Move up when slide plate 9 and jumper bar 10, when latch 20 and chute 9a lower vertical section coordinates, the dead beat of swing rod 12
Dynamic, the slide plate 9 and jumper bar 10 move back up to initial position.
As shown in Figure 1, Figure 2, shown in Fig. 4, Fig. 5, Fig. 7 and Fig. 8, the base D includes pedestal 3, cover plate 18 and side plate 2, described
The L-shaped bulk of pedestal 3.It is provided with and passage D1, swing rod 12, fixture block 15, pushing block 16 and crossed strip 19 in the bottom of pedestal 3
Adaptable resigning breach 3a.The cover plate 18 is in the plate body that circular arc is bent, and cover plate 18 is from bottom to top by 3a pairs of resigning breach
Passage D1 position is answered to cover.The resigning breach 3a is in the respective side wall of insertion pedestal 3 with the position that crossed strip 19 is adapted
It is poroid, the side plate 2 is fixed on the side wall of pedestal 3, and side plate 2 inwall be provided with and crossed strip 19 adapt to
Guide hole, the corresponding end of the crossed strip 19 is stretched into the guide hole of side plate 2.
Claims (4)
1. a kind of upper fire in a stove before fuel is added system, including vertical goods casket, are provided with vertical goods groove in the goods casket, it is characterised in that:Also
Include base, the passage of arc is provided with the base, the upper end of the passage is smoothly docked with goods groove lower end;
Base plate is fixed with the lower end of the base, punching is provided with the base plate, is also vertically inserted with just on the base
To the red needle of punching, the red needle is suspended by elastic supporting mechanism, and when red needle is moved downward, the lower end of the red needle passes through
Punching;
Pushing block and fixture block are installed in the base, being provided between the pushing block and fixture block termination close to each other is used to press from both sides
The breach of the fire in a stove before fuel is added, crossed strip is also lined between the pushing block and base, when the crossed strip in the raw when, institute
The breach stated between pushing block and fixture block is smoothly connected with the lower end of curved channel, and the pushing block covers punching;Described
Striking gear is connected with fixture block, in the presence of striking gear, the centerline direction of fixture block transversely spring is moved back and forth;And
And, when fixture block is moved to pushing block direction, the fixture block compresses pushing block, and the breach between fixture block and pushing block is to crossed strip
Direction is moved, and makes the breach between fixture block and pushing block just to punching.
2. upper fire in a stove before fuel is added system according to claim 1, it is characterised in that:The striking gear includes insertion folder from top to bottom
The swing rod of block, the swing rod is installed by mounting seat, and the mounting seat is fixed on above base, and two are provided with the mounting seat
Individual parallel vertical interlayer, is provided with horizontal bar shaped spacing hole on two interbedded dividing plates, and the top of the swing rod is inserted
Enter in one of interlayer, and the middle part of swing rod is hinged with mounting seat, and latch is fixed with the upper end of the swing rod;Another
The slide plate of suspension is inserted with interlayer, in the slide plate towards chute is provided with the plate face of swing rod side, the corresponding end of the latch is worn
Cross spacing hole and be caught in chute;The chute includes upper vertical section, tilting section and the lower vertical section smoothly connected;In the punching
The top of pin has also suspended jumper bar, and the jumper bar and slide plate of suspension are linked by attachment structure;
Move down when slide plate and jumper bar, when the lower vertical section of latch and chute coordinates, the swing rod is not swung, the jumper bar to
Lower close red needle;
Move down when slide plate and jumper bar, when the tilting section of latch and chute coordinates, the swing rod lower end is swung to pushing block direction,
The fixture block is pushed against with pushing block, and the breach between pushing block and fixture block is moved to the direction of crossed strip, until pushing block and folder
Punching of the breach just to base plate between block, the jumper bar continues downwards close to red needle;
Move down when slide plate and jumper bar, when the upper vertical section of latch and chute coordinates, the swing rod is not swung, the jumper bar to
Push red needle, breach through pushing block and fixture block of the lower end of red needle simultaneously stretches into punching;
Move up when slide plate and jumper bar, when the upper vertical section of latch and chute coordinates, the swing rod is not swung, the jumper bar to
Upper movement, the red needle upward resilience in the presence of elastic supporting mechanism;
Move up when slide plate and jumper bar, when the tilting section of latch and chute coordinates, the swing rod lower end is to the side away from pushing block
To swing, the fixture block decontrols pushing block, pushing block resilience in the presence of crossed strip, until lacking between fixture block and pushing block
Lower end of the mouth just to passage;
Move up when slide plate and jumper bar, when the lower vertical section of latch and chute coordinates, the swing rod is not swung, the slide plate and
Jumper bar moves back up to initial position.
3. upper fire in a stove before fuel is added system according to claim 2, it is characterised in that:The base includes pedestal, cover plate and side plate, institute
The L-shaped bulk of pedestal is stated, is provided with the pedestal bottom and allowing that passage, swing rod, fixture block, pushing block and crossed strip are adapted
Position breach;The cover plate from bottom to top covers the position of resigning breach respective channel;The resigning breach and crossed strip phase
The position of adaptation is poroid in insertion pedestal respective side wall, and the side plate is fixed on the side wall of pedestal, and in side plate
Inwall is provided with the guide hole adapted to crossed strip, and the corresponding end of the crossed strip is stretched into the guide hole of side plate.
4. the upper fire in a stove before fuel is added system according to claim 1 or 2 or 3, it is characterised in that:The elastic supporting mechanism includes fixing
Support block above base, the red needle runs through support block from top to bottom, is lined between the upper end of red needle and support block
Set, is lined between the lower end of red needle and support block and traps, and the upper set and traps and is fixed with support block, in the red needle
End is further fixed on the block being located in upper set, and Vertical Spring is cased with red needle, and upper end and the block of the Vertical Spring are pushed against,
The lower end of Vertical Spring and abutting of trapping.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610321951.8A CN105973080B (en) | 2016-05-16 | 2016-05-16 | Upper fire in a stove before fuel is added system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610321951.8A CN105973080B (en) | 2016-05-16 | 2016-05-16 | Upper fire in a stove before fuel is added system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105973080A CN105973080A (en) | 2016-09-28 |
CN105973080B true CN105973080B (en) | 2017-07-14 |
Family
ID=56955915
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610321951.8A Active CN105973080B (en) | 2016-05-16 | 2016-05-16 | Upper fire in a stove before fuel is added system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105973080B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108458632A (en) * | 2018-04-10 | 2018-08-28 | 东冠科技(上海)有限公司 | The fire in a stove before fuel is added assembles device and fire in a stove before fuel is added assembly method |
CN114018107A (en) * | 2021-11-23 | 2022-02-08 | 上海智能制造功能平台有限公司 | Multipoint primer press-fitting mechanism with self-adaptive capacity |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3128668A (en) * | 1961-09-05 | 1964-04-14 | Howard E Dicken | Shell primer loading apparatus |
US3224318A (en) * | 1964-03-05 | 1965-12-21 | Theodore J Bachhuber | Automatic primer cap feeder for shotgun shell reloaders |
US6397718B2 (en) * | 2000-05-11 | 2002-06-04 | John R. Jamison | Device for reducing the eccentricity and non-uniformities among cartridge cases |
CN101290205A (en) * | 2008-06-25 | 2008-10-22 | 廊坊智通机器人系统有限公司 | Primer automatic screwing device |
CN102128572A (en) * | 2010-12-10 | 2011-07-20 | 天津理工大学 | Machine integrating functions of filling pads and closing-up of shotgun shell case |
CN102645138A (en) * | 2012-04-24 | 2012-08-22 | 中国科学院合肥物质科学研究院 | Double-station automatic pressing machine for primer of hunting shot |
CN104229413A (en) * | 2014-09-04 | 2014-12-24 | 中国科学院合肥物质科学研究院 | Primer double-way automatic conveying interface |
CN104842141A (en) * | 2015-05-29 | 2015-08-19 | 重庆市机电设计研究院 | Multi-station capstan press fitting machine |
-
2016
- 2016-05-16 CN CN201610321951.8A patent/CN105973080B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3128668A (en) * | 1961-09-05 | 1964-04-14 | Howard E Dicken | Shell primer loading apparatus |
US3224318A (en) * | 1964-03-05 | 1965-12-21 | Theodore J Bachhuber | Automatic primer cap feeder for shotgun shell reloaders |
US6397718B2 (en) * | 2000-05-11 | 2002-06-04 | John R. Jamison | Device for reducing the eccentricity and non-uniformities among cartridge cases |
CN101290205A (en) * | 2008-06-25 | 2008-10-22 | 廊坊智通机器人系统有限公司 | Primer automatic screwing device |
CN102128572A (en) * | 2010-12-10 | 2011-07-20 | 天津理工大学 | Machine integrating functions of filling pads and closing-up of shotgun shell case |
CN102645138A (en) * | 2012-04-24 | 2012-08-22 | 中国科学院合肥物质科学研究院 | Double-station automatic pressing machine for primer of hunting shot |
CN104229413A (en) * | 2014-09-04 | 2014-12-24 | 中国科学院合肥物质科学研究院 | Primer double-way automatic conveying interface |
CN104842141A (en) * | 2015-05-29 | 2015-08-19 | 重庆市机电设计研究院 | Multi-station capstan press fitting machine |
Also Published As
Publication number | Publication date |
---|---|
CN105973080A (en) | 2016-09-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105973080B (en) | Upper fire in a stove before fuel is added system | |
CN206342829U (en) | A kind of fire-fighting equipment steel cylinder bracket | |
CN105424868A (en) | Battery burning testing device | |
CN206047579U (en) | Torsion spring presss subgroup is installed | |
CN208333272U (en) | Holdback and deep hole explosive device | |
CN210151171U (en) | Automatic ignition device for heat treatment | |
CN201316723Y (en) | High-pressure washer frame | |
CN204730771U (en) | High temperature resistant big gun span charge constitution | |
CN202993283U (en) | Gas stove | |
CN205665212U (en) | Burning test case | |
CN203980354U (en) | Smokeless fire-banking device | |
CN206929821U (en) | The crash structure of smoke exhaust ventilator drop front and fixed panel | |
CN208184721U (en) | Merogenesis assembly type firing mount | |
CN205433410U (en) | A connection structure that is used for oven furnace body and ignites a barrel staving | |
CN205482398U (en) | Stove is smelted to small -size dissolving of being equipped with gettering cover in ejection of compact department | |
CN202955295U (en) | Explosion-proof device | |
CN214453823U (en) | Leakage-proof device for hazardous chemical transportation | |
CN205375943U (en) | Ware is exploded to omnipotent testing | |
CN209997660U (en) | hanging device for building structure laboratory | |
CN209991517U (en) | Oil receiving device for range hood | |
CN206235249U (en) | One kind is set off firecracker safety device | |
CN208640473U (en) | A kind of furnace body of oven | |
DE1460576U (en) | ||
CN213216029U (en) | Explosion-proof cabinet for test gun | |
CN202614100U (en) | Safe and environment-friendly firecracker burning device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |