CN105973007A CN201610471764.8A CN201610471764A CN105973007A CN 105973007 A CN105973007 A CN 105973007A CN 201610471764 A CN201610471764 A CN 201610471764A CN 105973007 A CN105973007 A CN 105973007A
Authority
CN
China
Prior art keywords
tunnel cave
drying kiln
wall
section
centrifugal blower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610471764.8A
Other languages
Chinese (zh)
Other versions
CN105973007B (en
Inventor
姚飞
王琮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changde Xiamen Building Materials Co Ltd
Original Assignee
Changde Xiamen Building Materials Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changde Xiamen Building Materials Co Ltd filed Critical Changde Xiamen Building Materials Co Ltd
Priority to CN201610471764.8A priority Critical patent/CN105973007B/en
Publication of CN105973007A publication Critical patent/CN105973007A/en
Application granted granted Critical
Publication of CN105973007B publication Critical patent/CN105973007B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27BFURNACES, KILNS, OVENS, OR RETORTS IN GENERAL; OPEN SINTERING OR LIKE APPARATUS
    • F27B19/00Combinations of furnaces of kinds not covered by a single preceding main group
    • F27B19/04Combinations of furnaces of kinds not covered by a single preceding main group arranged for associated working
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F26DRYING
    • F26BDRYING SOLID MATERIALS OR OBJECTS BY REMOVING LIQUID THEREFROM
    • F26B21/00Arrangements or duct systems, e.g. in combination with pallet boxes, for supplying and controlling air or gases for drying solid materials or objects
    • F26B21/14Arrangements or duct systems, e.g. in combination with pallet boxes, for supplying and controlling air or gases for drying solid materials or objects using gases or vapours other than air or steam, e.g. inert gases
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D17/00Arrangements for using waste heat; Arrangements for using, or disposing of, waste gases
    • F27D17/004Systems for reclaiming waste heat
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F26DRYING
    • F26BDRYING SOLID MATERIALS OR OBJECTS BY REMOVING LIQUID THEREFROM
    • F26B2210/00Drying processes and machines for solid objects characterised by the specific requirements of the drying good
    • F26B2210/02Ceramic articles or ceramic semi-finished articles
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27MINDEXING SCHEME RELATING TO ASPECTS OF THE CHARGES OR FURNACES, KILNS, OVENS OR RETORTS
    • F27M2001/00Composition, conformation or state of the charge
    • F27M2001/03Charges containing minerals
    • F27M2001/035China

Abstract

The invention provides a furnace device and a method utilizing the furnace device to manufacture sintered bricks. The furnace device comprises drying kilns, tunnel kilns, ventilation channels and centrifugal fans, wherein the drying kilns communicate with the tunnel kilns through the ventilation channels; and the centrifugal fans are connected with the ventilation channels, and are used for enabling hot air in the tunnel kilns to enter the drying kilns through the ventilation channels. According to the furnace device and the method, the centrifugal fans can extract hot air in the tunnel kilns and feed the hot air into the drying kilns to dry green bricks, so that the energy consumption during the brick manufacturing process is greatly reduced; when the device is utilized to manufacture the sintered bricks, the temperature of the tunnel kilns is increased to 700 to 1000 DEG C, the green bricks are fed into the drying kilns from inlets of the drying kilns to outlets of the drying kilns, and then enter the tunnel kilns from inlet of the tunnel kilns to outlets of the tunnel kilns, and the sintered bricks are obtained; the method fully utilizes the structural characteristics of the furnace device, only the tunnel kilns require to be heated, and the drying kilns do not require to be heated, so that the energy consumption is low, and the method is simple and quick; and besides, the strength of the manufactured sintered bricks is high.

Description

A kind of furnace equipment and the method utilizing its making fired brick
Technical field
The present invention relates to brick equipment field, in particular to a kind of furnace equipment and profit The method making fired brick with it.
Background technology
Fired brick is a kind of construction material being widely used at present, particularly in China rural area, Along with expanding economy, the raising of living standards of the people, fired brick becomes for main building a house Material.
Existing burning process, natural air drying after general brickmaking base, then use coal equal energy source Fire in firing kiln, need the substantial amounts of energy and air-dry time.And, existing burning Kiln energy consumption processed is high, production efficiency is low, and the energy and waste of raw materials are serious.
In view of this, the special proposition present invention.
Summary of the invention
The first object of the present invention is to provide a kind of furnace equipment in order to brickmaking, for existing There is the problem that furnace equipment energy consumption is big, in the furnace equipment that the present invention provides, utilize centrifugal wind Machine, detaches the steam that tunnel cave produces in sintering procedure to drying kiln, enters adobe Sector-style is done, and greatly reduces the consumption of the energy during brickmaking.
The second object of the present invention is to provide one to utilize described furnace equipment to make fired brick Method, the method energy consumption is low, simple and fast, and the intensity of prepared fired brick is high.
In order to realize the above-mentioned purpose of the present invention, spy by the following technical solutions:
A kind of furnace equipment for brickmaking, described equipment comprises drying kiln, tunnel cave, leads to Air channel and centrifugal blower;
Described drying kiln is connected by described ventilating duct with described tunnel cave, described centrifugal blower It is connected with described ventilating duct, and for making the hot blast in described tunnel cave by described ventilating duct Enter described drying kiln.
In the furnace equipment that the present invention provides, centrifugal blower can extract tunnel cave at sintering procedure The steam of middle generation, is sent in drying kiln, dries adobe, greatly reduce The consumption of the energy during brickmaking.
Higher, in causing kiln road in view of the adobe water content just entering drying kiln road High humidity, is unfavorable for the drying of adobe.In order to solve this problem, the kiln that the present invention provides Also including air exhauster in furnace apparatus, the air inlet of described air exhauster connects with described drying kiln. By the continuous work of air exhauster, the dampness in kiln road is detached.
In order to prevent containing sulfide in adobe, the dampness that air exhauster detaches is directly discharged to ring Border pollutes environment, the dampness detached can be sent in desulfurizing tower and carry out from drying kiln Desulfurization, alleviates environmental pollution.
The desulfurizing tower comprised specifically includes that tower body, blower fan, spraying mechanism, waste water process Pond, circulating water pool and circulating pump.
Tower body is set to cylindrical uncovered tower, in the middle part of tower body in set disc type outlet pipe, water pipe Hole for water spraying is offered in lower section, and outlet pipe is connected with circulating pump, sprays water downwards;Blower fan is arranged on tower Side, body lower end, needs gas to be processed to send into tower body by blower fan, and gas is formed with water smoke Convection current, thus realize desulfurization;Waste water enters purification tank for liquid waste, in purification tank for liquid waste after discharging Throwing in Caustic soda to process, the water after process flows into circulating water pool, under the effect of circulating pump Travel further into tower body.
In order to ensure desulfurized effect, disc type outlet pipe arranges multilamellar.
In order to ensure the stability of disc type outlet pipe, it is additionally provided with fixed mount, by disc type Outlet pipe is fixing with tower body to be connected.
Disc type outlet pipe, concrete shape is the shape of coiled mosquito-repellent incense, and end is airtight, a ring One ring.
In order to gas is run helter-skelter to plant area, the tower body top of desulfurizing tower is provided with outwardly open limit Angle between edge, and tower body is 30-45 degree.
Preferably, described furnace equipment also includes pressure fan, the outlet air end of described pressure fan with Described tunnel cave connects, and for blowing in described tunnel cave.
The pressure fan arranged carries air in the kiln road of tunnel cave, improves oxygen in kiln road Concentration, thus play combustion-supporting effect.
In the present invention, the power of pressure fan sets according to the baking temperature of tunnel cave, passes through The watt level of regulation pressure fan can regulate the temperature in tunnel cave.
Preferably, it is provided with track in described drying kiln.
In the furnace equipment of the present invention, in drying kiln, it is provided with track ferrum.By to be dried Adobe is put in transport vehicle, walks to dry according to the speed set along track from drying kiln entrance Kiln exports, and the adobe in transport vehicle is dried equably.By this setting, can be uninterrupted Ground transports adobe in drying kiln dries, thus is greatly improved production efficiency.
Preferably, the top of described tunnel cave is provided with burner, and described burner penetrates described tunnel The top of kiln.
In the furnace equipment that the present invention provides, burner has two effects, and one is to open burner Heat radiation, it is to avoid in causing finished bricks because temperature is the highest during adobe is toasted Portion's structure is uneven;Two is when the temperature of tunnel cave is low, by improving tunnel to burner coal The temperature of road kiln.And the setting of upper width it is more than by lower width so that burner cross section Present trapezoidal, heat can be avoided to scatter and disappear in a large number, thus reduce energy consumption.
In order to avoid heat scatters and disappears in a large number, thus reducing energy consumption, the lower width of burner is more than Upper width so that burner cross section presents trapezoidal.The design of this " the big mouth of tripe is little ", can Effectively reduce the lost speed of heat in tunnel cave.
In order in time the temperature of tunnel cave is adjusted, it is ensured that the temperature of tunnel cave It is suitable for adobe baking, it is further preferred that in tunnel cave, set at interval of 1.6-1.8m Putting row's burner, often arrange and set 4-5 side by side, the upper width of burner is 10-15cm.
Preferably, the body of wall of described drying kiln is sandwich wall and solid wall from top to bottom;Described Being provided with air outlet on the medial wall of sandwich wall, the air inlet of described centrifugal blower is logical with described Air channel connects, and air outlet connects with the inner space of described sandwich wall.
By this design, the steam that centrifugal blower comes from tunnel cave extraction initially enters interlayer The inner space of wall, is dissipated in the kiln road of drying kiln by exhaust vent, it is achieved heat the most again Be uniformly distributed, it is to avoid brick blank drying is uneven and causes crackle occur.
It is further preferred that described tunnel cave along entrance to Way out be divided into preheating section, High temperature section and cooling section, the body of wall of described preheating section and described cooling section is hollow from top to bottom Wall and solid wall, described cavity wall is provided with air port, with the air inlet of described centrifugal blower The ventilating duct of connection connects with the inner space of described cavity wall;It is provided with heat in described high temperature section Galvanic couple, described thermocouple is connected with computer control system.
By this setting, the steam in tunnel cave can be by going out in preheating section and cooling section Air holes enters the inner space of sandwich wall, then by being connected with sandwich wall inner space Air channel is extracted in drying kiln by centrifugal blower, owing in tunnel cave, scattering and disappearing of heat is mainly led to Cross outlet and the entrance of tunnel cave, and by the design of the present invention, it is achieved that in tunnel cave The making full use of of after-heat.
Simultaneously as the body of wall of high temperature section is solid wall, it is achieved that the heat height of high temperature section Concentrating, the adobe entering tunnel cave is sufficiently calcined in this part, makes the property of adobe Matter reaches requirement.
And in order to be precisely controlled the temperature of high temperature section, it is to avoid adobe in baking process because of Too high or too low for temperature finished bricks exterior quality and character is caused to decline, furnace equipment of the present invention In be provided with thermocouple, thermocouple and computer control system at the top of the tunnel cave of high temperature section Connect, in real time the baking temperature in monitoring tunnel cave road.
Preferably, described drying kiln include being connected the most side by side arrange the first drying kiln, the Two drying kilns, the 3rd drying kiln and the 4th drying kiln, described first drying kiln and described second The sandwich wall of drying kiln communicates, and the sandwich wall of described 3rd drying kiln and the 4th drying kiln communicates; Described tunnel cave includes being connected side by side and arranges the first tunnel cave and the second tunnel cave;Described centrifugal Blower fan includes that the first centrifugal blower, the second centrifugal blower, the 3rd centrifugal blower and the 4th are centrifugal Blower fan;
The outlet air end of described first centrifugal blower and described second centrifugal blower is all with described first Drying kiln connects with the inner space of the sandwich wall of described second drying kiln, and described first is centrifuged The air intake of blower fan connects with the inner space of the cavity wall of described second tunnel cave preheating section, The air intake of described second centrifugal blower is interior with the cavity wall of described second tunnel cave cooling section Space, portion connects;The outlet air end of described 3rd centrifugal blower and described 4th centrifugal blower all with Described 3rd drying kiln connects with the inner space of the sandwich wall of shown 4th drying kiln, described The air intake of the 3rd centrifugal blower is empty with the inside of the cavity wall of described first tunnel cave preheating section Between connect, the sky of the air intake of described 4th centrifugal blower and described first tunnel cave cooling section The inner space connection of core-wall.
In order to improve production efficiency, the furnace equipment that the present invention provides comprises four drying kilns With two tunnel caves.Wherein, the first drying kiln and the second drying kiln are connected, and the 3rd dries Kiln and the 4th drying kiln are connected, and so, the hot blast from tunnel cave extraction can be two drying Circulate in kiln.And two bakings being connected can be realized by four centrifugal blowers arranged In dry kiln, heat is uniformly distributed.
Preferably, the top of described tunnel cave is provided with fire brick layer, on described fire brick layer It is provided with Margarita rock stratum, on described Margarita rock stratum, lays concrete prefabricated board.
In the furnace equipment of the present invention, owing to tunnel cave at high temperature uses, especially tunnel The high temperature section of road body of wall, in order to ensure that tunnel wall body disclosure satisfy that the requirement of baking, the present invention Furnace equipment in, the top of described tunnel cave is provided with fire brick layer, described fire brick layer it It is provided with Margarita rock stratum, on described Margarita rock stratum, lays concrete prefabricated board.
The furnace equipment that a kind of present invention of utilization provides makes the method for fired brick, including as follows Step: the temperature of tunnel cave is heated to 700-1000 DEG C, sends into adobe in drying kiln, The outlet of described drying kiln is arrived from described drying kiln entrance, in the described tunnel cave of rear entrance, Arrive the outlet of described tunnel cave from described tunnel cave entrance, obtain fired brick.
The method making fired brick that the present invention provides takes full advantage of the structure of this furnace equipment Characteristic, only need to heat tunnel cave, and without drying kiln is heated, it is ensured that The method energy consumption that the present invention provides is low, simple and fast, and the intensity of the fired brick prepared is high.
Preferably, it is divided into preheating section, height when described tunnel cave along entrance to Way out Temperature section and cooling section, the body of wall of described preheating section and described cooling section is cavity wall from top to bottom And solid wall, described cavity wall is provided with air port, connects with the air inlet of described centrifugal blower Logical ventilating duct connects with the inner space of described cavity wall;It is provided with thermoelectricity in described high temperature section Even, when described thermocouple is connected with computer control system, described high temperature section is along described tunnel Kiln entrance to Way out is divided into first paragraph, second segment, the 3rd section and the 4th section, described The temperature of first paragraph is 700-900 DEG C, and the temperature of described second segment is 920-970 DEG C, described The temperature of the 3rd section is 970-920 DEG C, and the temperature of described 4th section is 900-700 DEG C.
The primary structure district that high temperature section sinters as adobe, its temperature affects adobe at sintering During the internal structure that formed, and then affect the intensity of finished bricks.The side that the present invention provides High temperature section is divided into four sections along tunnel cave entrance to Way out by method so that high temperature section The curved arrangement of temperature.By this method, it is ensured that the intensity of finished bricks is high.
Compared with prior art, the invention have the benefit that
(1), in the furnace equipment that the present invention provides, the centrifugal blower being arranged on drying kiln can be taken out Take the steam that tunnel cave produces in sintering procedure, be sent in drying kiln, utilize from tunnel In road kiln, the adobe in drying kiln is air-dried by the steam of extraction, greatly reduces in brickmaking During the consumption of the energy.
(2), in the furnace equipment that the present invention provides, take out by arranging in the porch of drying kiln Blower fan, and one end of air exhauster connects with the kiln road of described drying kiln, by the dampness in kiln road Detach, beneficially the drying of adobe.
(3) in the furnace equipment that the present invention provides, by arranging bottom the kiln road of drying kiln Two-orbit rail, can transport adobe incessantly in drying kiln road and dry, thus greatly Improve greatly production efficiency.
(4), in the furnace equipment that the present invention provides, the body of wall lower floor of described drying kiln is entity Wall, upper strata is sandwich wall, and in sandwich wall, the body of wall near kiln road is provided with exhaust vent, and institute State centrifugal blower to connect with the inner space of sandwich wall.By this design, centrifugal blower from The steam that tunnel cave extraction comes initially enters the inner space of sandwich wall, passes through air-out the most again Hole is dissipated in kiln road, it is achieved being uniformly distributed of heat, it is to avoid brick blank drying is uneven and causes Crackle occurs.
(5) in the furnace equipment that the present invention provides, in order to improve production efficiency, in this equipment Comprise four drying kilns and two tunnel caves.Wherein, four drying kilns are divided into two groups, Often two drying kilns in group are connected to lead to, by the body of wall at the sandwich wall being connected side by side On exhaust vent be set realize the connection of two drying kilns, so, from the hot blast of tunnel cave extraction Can circulate in two drying kilns.And in order to realize the uniform of heat in two drying kilns Distribution, often in group, the position of the centrifugal blower arranged in two drying kilns differs.
(6) in the furnace equipment that the present invention provides, by arranging pressure fan at tunnel cave, and One end of pressure fan and the connection of described tunnel cave, the other end and ft connection, can tunnel cave Kiln road in carry air, improve the concentration of oxygen in kiln road, thus play combustion-supporting effect.
(7), in the furnace equipment that the present invention provides, run through by arranging at the top of tunnel cave The top burner of tunnel cave, and the lower width of described burner is more than upper width, plays two Individual effect: open during high temperature burner heat radiation, it is to avoid during adobe is toasted because of Temperature is the highest and causes finished bricks internal structure uneven;When temperature is low, by adding to burner Coal improves the temperature of tunnel cave.And the setting of upper width it is more than by lower width so that Burner cross section presents trapezoidal, heat can be avoided to scatter and disappear in a large number, thus reduce energy consumption.
(8), in the furnace equipment that the present invention provides, tunnel cave is divided into along Way in Preheating section, high temperature section and cooling section, the wall of the tunnel cave of described preheating section and described cooling section Body lower floor is solid wall, and upper strata is sandwich wall, and in sandwich wall, the body of wall near kiln road is provided with Exhaust vent;The air channel connected with described centrifugal blower connects with the inner space of sandwich wall.Logical Crossing this setting, the steam in tunnel cave can be entered by the exhaust vent in preheating section and cooling section Enter the inner space of sandwich wall, then by the air channel that is connected with sandwich wall inner space by Centrifugal blower is extracted in drying kiln, owing in tunnel cave, scattering and disappearing of heat mainly passes through tunnel The outlet of kiln and entrance, and by the design of the present invention, it is achieved that to the residue in tunnel cave Making full use of of heat.Simultaneously as the body of wall of high temperature section is solid wall, it is achieved that high temperature Section heat high concentration, enter tunnel cave adobe sufficiently calcine in this part, The character making adobe reaches requirement.
(9) in order to be precisely controlled the temperature of high temperature section, it is to avoid adobe is in baking process Causing finished bricks exterior quality and character to decline because of too high or too low for temperature, kiln of the present invention sets In Bei, the top at the tunnel cave of high temperature section is provided with thermocouple, and thermocouple controls system with computer System connects, in real time the baking temperature in monitoring tunnel cave road.
Accompanying drawing explanation
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, with Lower the accompanying drawing used required in embodiment or description of the prior art will be briefly described.
Fig. 1 is the top view of four drying kilns being arranged side by side;
Fig. 2 is the top view of two tunnel caves being arranged side by side;
Fig. 3 is the front view of four drying kilns being arranged side by side;
Fig. 4 is the front view of two tunnel caves being arranged side by side.
Detailed description of the invention
Below in conjunction with embodiment, embodiment of the present invention are described in detail, but this Skilled person is it will be appreciated that the following example is merely to illustrate the present invention, and should not regard For limiting the scope of the present invention.Unreceipted actual conditions person in embodiment, according to normal condition Or the condition of manufacturer's suggestion is carried out.Agents useful for same or instrument unreceipted production firm person, all For the conventional products that can be obtained by commercially available purchase.
In describing the invention, it should be noted that term " " center ", " on ", D score, The orientation of the instruction such as "left", "right", " vertically ", " level ", " interior ", " outward " or position Relation is based on orientation shown in the drawings or position relationship, is for only for ease of the description present invention Describe rather than indicate or imply that the device of indication or element must have specifically with simplifying Orientation, with specific azimuth configuration and operation, be therefore not considered as limiting the invention. Additionally, term " first ", " second ", " the 3rd " are only used for describing purpose, and can not manage Solve as instruction or hint relative importance.
In describing the invention, it should be noted that unless otherwise clear and definite regulation and limit Fixed, term " is installed ", " being connected ", " connection " should be interpreted broadly, for example, it may be Fixing connection, it is also possible to be to removably connect, or be integrally connected;Can be to be mechanically connected, It can also be electrical connection;Can be to be joined directly together, it is also possible to be indirectly connected to by intermediary, It can be the connection of two element internals.For the ordinary skill in the art, may be used Above-mentioned term concrete meaning in the present invention is understood with concrete condition.
As shown in Fig. 1~2, the furnace equipment for brickmaking that the present invention provides, including drying Kiln 101, tunnel cave 201, ventilating duct 301 and centrifugal blower;
Described drying kiln 101 is connected by described ventilating duct 301 with described tunnel cave 201, Described centrifugal blower is connected with described ventilating duct 301, and is used for making in described tunnel cave 201 Hot blast enter described drying kiln 101 by described ventilating duct 301.
Higher, in causing kiln road in view of the adobe water content just entering drying kiln road High humidity, is unfavorable for the drying of adobe.In order to solve this problem, further, this Air exhauster 401, the air inlet of described air exhauster 401 are also provided in the furnace equipment of bright offer Connect with described drying kiln 101.By the continuous work of air exhauster 401, by kiln road Dampness detaches.
Preferably, described air exhauster 401 is provided with 8, closely entering of each drying kiln 101 Mouth end is provided with 2 air exhausters 401, and 8 air exhausters 401 are all connected with desulfurizing tower.
Further, the present invention provide furnace equipment also include pressure fan 501, described in give The outlet air end of blower fan 501 connects with described tunnel cave 201, and for described tunnel cave 201 Interior air-supply.The pressure fan arranged carries air in the kiln road of tunnel cave 201, improves kiln road The concentration of middle oxygen, thus play combustion-supporting effect.
Further, in the furnace equipment that the present invention provides, in described drying kiln, rail is set Road 114.
In the furnace equipment of the present invention, in drying kiln, it is provided with track 114.By to be dried Adobe put in transport vehicle, along track 114 from drying kiln entrance according to set speed row Export to drying kiln, the adobe in transport vehicle is dried equably.By this setting, can In drying kiln, transport adobe incessantly dry, thus be greatly improved production efficiency.
Further, the top of described tunnel cave 201 is provided with burner, and described burner penetrates institute State the top of tunnel cave.
In the furnace equipment that the present invention provides, burner has two effects, and one is to open burner Heat radiation, it is to avoid in causing finished bricks because temperature is the highest during adobe is toasted Portion's structure is uneven;Two is when the temperature of tunnel cave is low, by improving tunnel to burner coal The temperature of road kiln.And the setting of upper width it is more than by lower width so that burner cross section Present trapezoidal, heat can be avoided to scatter and disappear in a large number, thus reduce energy consumption.
In order to avoid heat scatters and disappears in a large number, thus reducing energy consumption, the lower width of burner is more than Upper width so that burner cross section presents trapezoidal.The design of this " the big mouth of tripe is little ", can Effectively reduce the lost speed of heat in tunnel cave.
In order in time the temperature of tunnel cave is adjusted, it is ensured that the temperature of tunnel cave It is suitable for adobe baking, it is further preferred that in tunnel cave, set at interval of 1.6-1.8m Putting row's burner, often arrange and set 4-5 side by side, the upper width of burner is 10-15cm.
As it is shown on figure 3, further, the body of wall of described drying kiln 101 is from top to bottom for folder Layer wall 111 and solid wall 112;It is provided with air outlet on the medial wall of described sandwich wall 111 113, the air inlet of described centrifugal blower connects with described ventilating duct 301, and air outlet is with described The inner space connection of sandwich wall.
By this design, the steam that centrifugal blower 601~604 comes from tunnel cave 201 extraction Initially enter the inner space of sandwich wall 111, be dissipated to dry by air outlet 113 the most again In Yao101Yao road, it is achieved being uniformly distributed of heat, it is to avoid brick blank drying is uneven and leads There is crackle in cause.
As in figure 2 it is shown, further, described tunnel cave 201 depends on along entrance to Way out Secondary preheating section 211, high temperature section 212 and the cooling section 213 of being divided into, described preheating section 211 and institute State the body of wall of cooling section 213 from top to bottom for cavity wall 214 and solid wall 215, described sky Air port 216 it is provided with, the ventilation connected with the air inlet of described centrifugal blower on core-wall 214 Road connects with the inner space of described cavity wall 214, and the bottom of described tunnel cave 201 also sets It is equipped with tunnel cave track 210 (see Fig. 4);It is provided with thermocouple, institute in described high temperature section 212 State thermocouple to be connected with computer control system.
The most described high temperature section 212 and described preheating section 211, described high temperature section 212 and institute State arranging between the walls between cooling section 213 and all have partition 223, and described high temperature section 212 It is not provided with air channel and air port in the wall at place.
By this setting, the steam in tunnel cave 201 can be by preheating section 211 and cooling Air port 216 in section 213 enters the inner space of sandwich wall 111, then by with interlayer The air channel that wall 111 inner space is connected is extracted into drying by centrifugal blower 601~604 (Fig. 1) In kiln 101, owing in tunnel cave 201, scattering and disappearing of heat is mainly by tunnel cave 201 Outlet and entrance, and by the design of the present invention, it is achieved that to the residue in tunnel cave 201 Making full use of of heat.
Simultaneously as the body of wall of high temperature section 212 is solid wall, it is achieved that high temperature section 212 Heat high concentration, enter tunnel cave 201 adobe sufficiently calcine in this part, The character making adobe reaches requirement.
And in order to be precisely controlled the temperature of high temperature section 212, it is to avoid adobe is in baking process Middle finished bricks exterior quality and character is caused to decline because of too high or too low for temperature, kiln of the present invention In equipment, the tunnel cave top in high temperature section 212 is provided with thermocouple, thermocouple and computer control System processed connects, in real time the baking temperature in monitoring tunnel cave road.
As it is shown in figure 1, further, described drying kiln 101 includes being connected the most side by side The first drying kiln the 121, second drying kiln the 122, the 3rd drying kiln 123 and the 4th drying put Kiln 124, the sandwich wall of described first drying kiln 121 and described second drying kiln 122 communicates, The sandwich wall of described 3rd drying kiln 123 and the 4th drying kiln 124 communicates;Described tunnel cave 201 include being connected side by side arranges the first tunnel cave 221 and the second tunnel cave 222;Described centrifugal Blower fan includes first centrifugal blower the 601, second centrifugal blower the 602, the 3rd centrifugal blower 603 With the 4th centrifugal blower 604;
The outlet air end of described first centrifugal blower 601, the going out of described second centrifugal blower 602 Wind end all interior with the sandwich wall of described first drying kiln 121 and described second drying kiln 122 Space, portion connects, the air intake of described first centrifugal blower 601 and described second tunnel cave 222 The inner space connection of the cavity wall of preheating section, the air intake of described second centrifugal blower 602 Connect with the inner space of the cavity wall of described second tunnel cave 222 cooling section;Described 3rd The outlet air end of centrifugal blower 603, described 4th centrifugal blower 604 outlet air end all with described 3rd drying kiln 123 connects with the inner space of the sandwich wall of shown 4th drying kiln 124, The air intake of described 3rd centrifugal blower 603 and described first tunnel cave 221 preheating section 221 Cavity wall inner space connection, the air intake of described 4th centrifugal blower 604 is with described The inner space connection of the cavity wall of the first tunnel cave cooling section 213.
In order to improve production efficiency, the furnace equipment that the present invention provides comprises four drying kilns 101 and two tunnel caves 201.Wherein, the first drying kiln 121 and the second drying kiln 122 Being connected, the 3rd drying kiln 123 is connected with the 4th drying kiln 124, so, from tunnel The hot blast of kiln extraction can circulate in two drying kilns.And be centrifuged by four of setting Blower fan can realize being uniformly distributed of heat in two drying kilns being connected.
Further, the top of described tunnel cave 201 is provided with fire brick layer 217, described resistance to Margarita rock stratum 218, laying mixed on described Margarita rock stratum 218 it is provided with on firebrick layer 217 Solidifying soil precoated plate 219.
In the furnace equipment of the present invention, owing to tunnel cave 201 at high temperature uses, especially It is the high temperature section of tunnel body of wall, in order to ensure that tunnel wall body disclosure satisfy that the requirement of baking, this In the furnace equipment of invention, the top of described tunnel cave 201 is provided with fire brick layer 217, institute State and on fire brick layer 217, be provided with Margarita rock stratum 218, the upper berth of described Margarita rock stratum 218 If concrete prefabricated board 219 (seeing Fig. 4).
Based on same consideration, in tunnel cave 201, the body of wall near kiln road is fire brick layer.
The both sides of tunnel cave 201 body of wall are additionally provided with reinforcing column, pass through between two edge columns Connect cross bar to connect, prevent tunnel cave from firing and deform afterwards.
The present invention provide furnace equipment make fired brick method, comprise the steps: by The temperature of tunnel cave 201 is heated to 700-1000 DEG C, adobe is sent in drying kiln 101, The outlet of described drying kiln 101, the described tunnel of rear entrance is arrived from described drying kiln 101 entrance In road kiln 201, arrive the outlet of described tunnel cave 201 from described tunnel cave 201 entrance, Obtain fired brick.
Said method takes full advantage of the architectural characteristic of this furnace equipment, only need to be to tunnel cave 201 heat, and without drying kiln 101 is heated, it is ensured that the present invention provides Method energy consumption low, simple and fast, and the intensity of the fired brick prepared is high.
Further, it is divided into preheating when described tunnel cave 201 along entrance to Way out Section 211, high temperature section 212 and cooling section 213, described preheating section 211 and described cooling section The body of wall of 213 is cavity wall 214 and solid wall 215 from top to bottom, described cavity wall 214 On be provided with air port 216, the ventilating duct connected with the air inlet of described centrifugal blower is with described Inner space connection (see Fig. 4) of cavity wall 214;It is provided with thermoelectricity in described high temperature section 212 Even, when described thermocouple is connected with computer control system, described high temperature section 212 is along described Tunnel cave 201 entrance to Way out be divided into first paragraph, second segment, the 3rd section and the 4th Section, the temperature of described first paragraph is 700-900 DEG C, and the temperature of described second segment is 920-970 DEG C, the temperature of described 3rd section is 970-920 DEG C, and the temperature of described 4th section is 900-700℃。
The primary structure district that high temperature section 212 sinters as adobe, its temperature affects adobe and exists The internal structure formed in sintering process, and then affect the intensity of finished bricks.The present invention provides Method in high temperature section 212 is divided into four sections along tunnel cave entrance to Way out so that The curved arrangement of temperature of high temperature section.By this method, it is ensured that the intensity of finished bricks is high.
Although illustrate and describing the present invention with specific embodiment, but it will be appreciated that May be made that without departing from the spirit and scope of the present invention many other change and Amendment.It is, therefore, intended that include in the following claims belonging in the scope of the invention All such changes and modifications.

Claims (10)

1. a furnace equipment, it is characterised in that described equipment comprise drying kiln, tunnel cave, Ventilating duct and centrifugal blower;
Described drying kiln is connected by described ventilating duct with described tunnel cave, described centrifugal blower It is connected with described ventilating duct, and for making the hot blast in described tunnel cave by described ventilating duct Enter described drying kiln.
Furnace equipment the most according to claim 1, it is characterised in that described kiln sets For also including that air exhauster, the air inlet of described air exhauster connect with described drying kiln.
Furnace equipment the most according to claim 1, it is characterised in that described kiln sets For also including that pressure fan, the outlet air end of described pressure fan connect with described tunnel cave, and be used for Blow in described tunnel cave.
Furnace equipment the most according to claim 1, it is characterised in that described drying kiln Inside it is provided with track.
Furnace equipment the most according to claim 1, it is characterised in that described tunnel cave Top be provided with burner, described burner penetrates the top of described tunnel cave.
Furnace equipment the most according to claim 1, it is characterised in that described drying kiln Body of wall be sandwich wall and solid wall from top to bottom;It is provided with on the medial wall of described sandwich wall Air outlet;The air intake of described centrifugal blower connects with described ventilating duct, and outlet air end is with described The inner space connection of sandwich wall.
Furnace equipment the most according to claim 6, it is characterised in that described tunnel cave It is divided into preheating section, high temperature section and cooling section, described preheating section along entrance to Way out It is cavity wall and solid wall from top to bottom with the body of wall of described cooling section, described cavity wall sets It is equipped with air port, the ventilating duct connected with the air inlet of described centrifugal blower and described cavity wall Inner space connects;Thermocouple, described thermocouple and computer control it is provided with in described high temperature section System processed connects.
Furnace equipment the most according to claim 7, it is characterised in that described drying kiln Including be connected the most side by side arrange the first drying kiln, the second drying kiln, the 3rd drying kiln and 4th drying kiln, the sandwich wall of described first drying kiln and described second drying kiln communicates, institute The sandwich wall stating the 3rd drying kiln and the 4th drying kiln communicates;Described tunnel cave includes phase side by side It is connected with the first tunnel cave and the second tunnel cave put;Described centrifugal blower includes that first is centrifuged wind Machine, the second centrifugal blower, the 3rd centrifugal blower and the 4th centrifugal blower;
The outlet air end of described first centrifugal blower and described second centrifugal blower is all with described first Drying kiln connects with the inner space of the sandwich wall of described second drying kiln, and described first is centrifuged The air intake of blower fan connects with the inner space of the cavity wall of described second tunnel cave preheating section, The air intake of described second centrifugal blower is interior with the cavity wall of described second tunnel cave cooling section Space, portion connects;The outlet air end of described 3rd centrifugal blower and described 4th centrifugal blower all with Described 3rd drying kiln connects with the inner space of the sandwich wall of shown 4th drying kiln, described The air intake of the 3rd centrifugal blower is empty with the inside of the cavity wall of described first tunnel cave preheating section Between connect, the sky of the air intake of described 4th centrifugal blower and described first tunnel cave cooling section The inner space connection of core-wall.
9. one kind utilizes the side that furnace equipment described in any one of claim 1-8 makes fired brick Method, it is characterised in that comprise the steps: the temperature of tunnel cave is heated to 700-1000 DEG C, Adobe is sent in drying kiln, arrives the outlet of described drying kiln from described drying kiln entrance, In the described tunnel cave of rear entrance, arrive the outlet of described tunnel cave from described tunnel cave entrance, Obtain fired brick.
Method the most according to claim 9, it is characterised in that when described tunnel cave It is divided into preheating section, high temperature section and cooling section, described preheating section along entrance to Way out It is cavity wall and solid wall from top to bottom with the body of wall of described cooling section, described cavity wall sets It is equipped with air port, the ventilating duct connected with the air inlet of described centrifugal blower and described cavity wall Inner space connects;Thermocouple, described thermocouple and computer control it is provided with in described high temperature section When system processed connects, described high temperature section is divided into the along described tunnel cave entrance to Way out One section, second segment, the 3rd section and the 4th section, the temperature of described first paragraph is 700-900 DEG C, The temperature of described second segment is 920-970 DEG C, and the temperature of described 3rd section is 970-920 DEG C, The temperature of described 4th section is 900-700 DEG C.
CN201610471764.8A 2016-06-24 2016-06-24 A kind of furnace equipment and the method using its making fired brick Active CN105973007B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610471764.8A CN105973007B (en) 2016-06-24 2016-06-24 A kind of furnace equipment and the method using its making fired brick

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610471764.8A CN105973007B (en) 2016-06-24 2016-06-24 A kind of furnace equipment and the method using its making fired brick

Publications (2)

Publication Number Publication Date
CN105973007A true CN105973007A (en) 2016-09-28
CN105973007B CN105973007B (en) 2018-07-31

Family

ID=57019098

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610471764.8A Active CN105973007B (en) 2016-06-24 2016-06-24 A kind of furnace equipment and the method using its making fired brick

Country Status (1)

Country Link
CN (1) CN105973007B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108302934A (en) * 2018-03-12 2018-07-20 练其辉 A kind of tunnel oven using Heat Treatment organic waste
CN110356794A (en) * 2019-07-16 2019-10-22 涡阳县沪涡多孔矸石砖有限公司 Track structure is used in a kind of transfer of hollow brick

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4285669A (en) * 1978-11-23 1981-08-25 Ulrico Walchhutter Roller kiln provided with a drying tunnel, particularly for ceramic or refractory materials
CN201583131U (en) * 2009-11-09 2010-09-15 寿阳县明鑫铝矾耐火材料有限公司 Afterheat utilization system of tunnel furnace
CN102748943A (en) * 2012-06-14 2012-10-24 安徽省六安市佳瑞粉末冶金有限公司 Waste heat utilization technology for metallurgical tunnel kiln
CN203203413U (en) * 2013-01-28 2013-09-18 潮州市新凯陶瓷有限公司 Waste heat recycling device of kiln
CN203489719U (en) * 2013-08-22 2014-03-19 郑州世兴特种耐火材料有限公司 Refractory brick drying system
CN204085158U (en) * 2014-07-31 2015-01-07 淄博鹏达环保科技有限公司 The drying integrated system of roasting
CN204214282U (en) * 2014-10-24 2015-03-18 重庆福希建材有限公司 A kind of high hole rate shale hollow building block calcining kiln residual heat using device
CN205228128U (en) * 2015-12-07 2016-05-11 贵州修文坤泰绿色有限公司 Drying system of gangue shale adobe
CN205860771U (en) * 2016-06-24 2017-01-04 常德天厦建材有限公司 Furnace equipment for brickmaking

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4285669A (en) * 1978-11-23 1981-08-25 Ulrico Walchhutter Roller kiln provided with a drying tunnel, particularly for ceramic or refractory materials
CN201583131U (en) * 2009-11-09 2010-09-15 寿阳县明鑫铝矾耐火材料有限公司 Afterheat utilization system of tunnel furnace
CN102748943A (en) * 2012-06-14 2012-10-24 安徽省六安市佳瑞粉末冶金有限公司 Waste heat utilization technology for metallurgical tunnel kiln
CN203203413U (en) * 2013-01-28 2013-09-18 潮州市新凯陶瓷有限公司 Waste heat recycling device of kiln
CN203489719U (en) * 2013-08-22 2014-03-19 郑州世兴特种耐火材料有限公司 Refractory brick drying system
CN204085158U (en) * 2014-07-31 2015-01-07 淄博鹏达环保科技有限公司 The drying integrated system of roasting
CN204214282U (en) * 2014-10-24 2015-03-18 重庆福希建材有限公司 A kind of high hole rate shale hollow building block calcining kiln residual heat using device
CN205228128U (en) * 2015-12-07 2016-05-11 贵州修文坤泰绿色有限公司 Drying system of gangue shale adobe
CN205860771U (en) * 2016-06-24 2017-01-04 常德天厦建材有限公司 Furnace equipment for brickmaking

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108302934A (en) * 2018-03-12 2018-07-20 练其辉 A kind of tunnel oven using Heat Treatment organic waste
CN110356794A (en) * 2019-07-16 2019-10-22 涡阳县沪涡多孔矸石砖有限公司 Track structure is used in a kind of transfer of hollow brick

Also Published As

Publication number Publication date
CN105973007B (en) 2018-07-31

Similar Documents

Publication Publication Date Title
CN102748942B (en) Wide-bodied energy-saving and environment-friendly tunnel kiln
CN105910437B (en) A kind of Beijing enamel electrical kiln for producing bavin and burning atmosphere
CN202869211U (en) Multi-channel direct-firing tunnel kiln and waste heat recycling utilizing system thereof
CN102012152B (en) Hanging basket drying equipment for drying household porcelain
CN210399933U (en) Hollow brick kiln capable of uniformly supporting combustion
CN108558364A (en) Colliery wastes brick multifuel combustion lime stone technique
CN107560401A (en) Circulation tunnel type rapid draing room and drying means in a kind of
CN103836890B (en) Multi-layer roller way type ceramic drying kiln
CN109237939A (en) A kind of flue gas, waste heat are kept completely separate energy conservation and environmental protection and bake bricks tunnel oven
CN105973007A (en) Furnace device and method utilizing furnace device to manufacture sintered bricks
CN103615885A (en) Turnover kiln with air distribution system arranged at bottom
CN104824820B (en) A kind of portable flue-curing device
CN212620048U (en) Energy-saving efficient continuous red brick roasting production kiln
CN205860771U (en) Furnace equipment for brickmaking
CN104457228B (en) Tenon type composite flat-top tunnel kiln
CN102748926A (en) Building ceramic single-layer rapid dryer equipment
CN205747967U (en) A kind of bavin that produces burns the Beijing enamel electrical kiln of atmosphere
CN206897771U (en) A kind of vertical spraying curing oven
CN205258369U (en) Energy -concerving and environment -protective tunnel cave of matter is carried in brown coal dry distillation
CN205262172U (en) Energy -conserving flat top tunnel cave
CN101749950B (en) Air return type energy saving annular kiln for producing shale brick and production method
CN201203349Y (en) Multichannel energy-saving kiln
CN207299907U (en) Uprush refractory material burns till tunnel oven
CN203744660U (en) Energy-saving ceramic paste and plaster model drying box
CN201018908Y (en) Natural draft ventilation intensive tobacco roasting room rebuilt from ordinary natural ventilation tobacco roasting room

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant