CN105970919B - 一种取土压灌混凝土桩的施工方法 - Google Patents
一种取土压灌混凝土桩的施工方法 Download PDFInfo
- Publication number
- CN105970919B CN105970919B CN201610342296.4A CN201610342296A CN105970919B CN 105970919 B CN105970919 B CN 105970919B CN 201610342296 A CN201610342296 A CN 201610342296A CN 105970919 B CN105970919 B CN 105970919B
- Authority
- CN
- China
- Prior art keywords
- soil
- drawing out
- pile body
- casing
- cast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 32
- 239000004567 concrete Substances 0.000 title claims abstract description 21
- 239000002689 soil Substances 0.000 claims abstract description 78
- 239000000203 mixture Substances 0.000 claims abstract description 16
- 238000000034 method Methods 0.000 claims abstract description 15
- 230000010412 perfusion Effects 0.000 claims abstract description 14
- 239000004568 cement Substances 0.000 claims abstract description 13
- 238000005086 pumping Methods 0.000 claims abstract description 5
- 230000003068 static effect Effects 0.000 claims abstract description 3
- 229910000831 Steel Inorganic materials 0.000 claims description 19
- 239000010959 steel Substances 0.000 claims description 19
- 239000000463 material Substances 0.000 claims description 16
- 230000002787 reinforcement Effects 0.000 claims description 10
- 239000000945 filler Substances 0.000 claims description 9
- 230000003028 elevating effect Effects 0.000 claims description 5
- 239000004576 sand Substances 0.000 claims description 4
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 4
- 230000035515 penetration Effects 0.000 claims description 3
- 239000011178 precast concrete Substances 0.000 claims description 3
- 239000010881 fly ash Substances 0.000 claims description 2
- 230000003014 reinforcing effect Effects 0.000 claims description 2
- 238000003756 stirring Methods 0.000 claims description 2
- 230000015572 biosynthetic process Effects 0.000 claims 1
- -1 rubble Substances 0.000 claims 1
- 239000002131 composite material Substances 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 5
- 230000000694 effects Effects 0.000 description 4
- 238000000605 extraction Methods 0.000 description 3
- 238000005266 casting Methods 0.000 description 2
- 238000005056 compaction Methods 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 201000010099 disease Diseases 0.000 description 1
- 208000037265 diseases, disorders, signs and symptoms Diseases 0.000 description 1
- 235000013399 edible fruits Nutrition 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D13/00—Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
- E02D13/08—Removing obstacles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/04—Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610342296.4A CN105970919B (zh) | 2016-05-23 | 2016-05-23 | 一种取土压灌混凝土桩的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610342296.4A CN105970919B (zh) | 2016-05-23 | 2016-05-23 | 一种取土压灌混凝土桩的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105970919A CN105970919A (zh) | 2016-09-28 |
CN105970919B true CN105970919B (zh) | 2018-05-29 |
Family
ID=56955505
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610342296.4A Active CN105970919B (zh) | 2016-05-23 | 2016-05-23 | 一种取土压灌混凝土桩的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105970919B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106759300B (zh) * | 2016-11-25 | 2018-11-27 | 淮阴工学院 | 利用根式灌注桩的根键施工装置的根键施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103184734A (zh) * | 2013-03-19 | 2013-07-03 | 浙江天润建设有限公司 | 一种植入注浆组合桩及施工方法 |
JP2014025255A (ja) * | 2012-07-26 | 2014-02-06 | Kensho Co Ltd | 基礎杭施工方法、基礎杭、地盤補強材施工方法及び杭状地盤補強材 |
CN103993598A (zh) * | 2014-05-19 | 2014-08-20 | 杭州江润科技有限公司 | 一种引孔植入布袋碎石注浆桩及施工方法 |
CN205135406U (zh) * | 2015-12-09 | 2016-04-06 | 何刚 | 能冲填注浆的钻机 |
-
2016
- 2016-05-23 CN CN201610342296.4A patent/CN105970919B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014025255A (ja) * | 2012-07-26 | 2014-02-06 | Kensho Co Ltd | 基礎杭施工方法、基礎杭、地盤補強材施工方法及び杭状地盤補強材 |
CN103184734A (zh) * | 2013-03-19 | 2013-07-03 | 浙江天润建设有限公司 | 一种植入注浆组合桩及施工方法 |
CN103993598A (zh) * | 2014-05-19 | 2014-08-20 | 杭州江润科技有限公司 | 一种引孔植入布袋碎石注浆桩及施工方法 |
CN205135406U (zh) * | 2015-12-09 | 2016-04-06 | 何刚 | 能冲填注浆的钻机 |
Also Published As
Publication number | Publication date |
---|---|
CN105970919A (zh) | 2016-09-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2017133372A1 (zh) | 一种复合地基及其施工方法 | |
CN102733376B (zh) | 复合桩及其施工方法 | |
CN100497842C (zh) | 一种底部撞击式钢管混凝土桩及其施工方法 | |
CN102733378B (zh) | 混凝土桩的施工方法 | |
CN104074186B (zh) | 一种建筑地基中成孔的护筒装置及其施工方法 | |
CN104294818B (zh) | 混凝土桩的施工方法 | |
CN103821139B (zh) | 一种夯扩载体劲芯多元复合桩及软土地基加固施工方法 | |
CN105040692B (zh) | 一种预制混凝土桩身载体桩的施工方法 | |
CN101200893A (zh) | 载体桩的施工方法 | |
KR100762991B1 (ko) | 고강도 몰탈을 충진하는 기성말뚝 매입공법 | |
CN104314078A (zh) | 混凝土桩的施工设备及其施工方法 | |
CN100375820C (zh) | 混凝土桩的施工方法 | |
CN104099925A (zh) | 混凝土桩的施工装置及其施工方法 | |
CN101575852A (zh) | 护壁式扩底沉管灌注桩施工方法 | |
CN102808407B (zh) | 软土地基钢筋混凝土灌注桩施工方法 | |
CN104790395A (zh) | 一种载体桩的施工设备及其施工方法 | |
CN104929125A (zh) | 一种载体桩的施工设备及其施工方法 | |
CN102635110B (zh) | 混凝土桩的施工方法 | |
CN104404956A (zh) | 一种扩底桩的施工方法 | |
CN104988913B (zh) | 一种大直径长桩的载体桩的施工方法 | |
CN105970919B (zh) | 一种取土压灌混凝土桩的施工方法 | |
CN105064332A (zh) | 一种方形桩身载体桩的施工方法 | |
CN106013093B (zh) | 一种桩施工方法 | |
CN105926621A (zh) | 一种静压载体桩的施工方法 | |
CN106088085B (zh) | 桩施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information |
Inventor after: Wang Jizhong Inventor after: Wang Feng Inventor before: Wang Jizhong |
|
CB03 | Change of inventor or designer information | ||
TR01 | Transfer of patent right |
Effective date of registration: 20200812 Address after: 102218, Beijing, Changping District East small town Taiping homes, building 31 Patentee after: BEIJING PUISSANT GEOTECHNICAL ENGINEERING Co.,Ltd. Address before: 102218 Beijing city Changping District East Town Taiping home building No. 31 Beijing possente Geotechnical Engineering Co. Ltd. Patentee before: Wang Jizhong |
|
TR01 | Transfer of patent right |