CN105965738B - A kind of method for filling to special-shaped coils skeleton form - Google Patents

A kind of method for filling to special-shaped coils skeleton form Download PDF

Info

Publication number
CN105965738B
CN105965738B CN201610385200.2A CN201610385200A CN105965738B CN 105965738 B CN105965738 B CN 105965738B CN 201610385200 A CN201610385200 A CN 201610385200A CN 105965738 B CN105965738 B CN 105965738B
Authority
CN
China
Prior art keywords
bonding agent
hole
perfusion
glue
coil rack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610385200.2A
Other languages
Chinese (zh)
Other versions
CN105965738A (en
Inventor
马军伟
郝娟
蔺玲
安平
张锐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xi'an North Electro-Optic Technology Defense Co Ltd
Original Assignee
Xi'an North Electro-Optic Technology Defense Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xi'an North Electro-Optic Technology Defense Co Ltd filed Critical Xi'an North Electro-Optic Technology Defense Co Ltd
Priority to CN201610385200.2A priority Critical patent/CN105965738B/en
Publication of CN105965738A publication Critical patent/CN105965738A/en
Application granted granted Critical
Publication of CN105965738B publication Critical patent/CN105965738B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29CSHAPING OR JOINING OF PLASTICS; SHAPING OF MATERIAL IN A PLASTIC STATE, NOT OTHERWISE PROVIDED FOR; AFTER-TREATMENT OF THE SHAPED PRODUCTS, e.g. REPAIRING
    • B29C39/00Shaping by casting, i.e. introducing the moulding material into a mould or between confining surfaces without significant moulding pressure; Apparatus therefor
    • B29C39/02Shaping by casting, i.e. introducing the moulding material into a mould or between confining surfaces without significant moulding pressure; Apparatus therefor for making articles of definite length, i.e. discrete articles
    • B29C39/10Shaping by casting, i.e. introducing the moulding material into a mould or between confining surfaces without significant moulding pressure; Apparatus therefor for making articles of definite length, i.e. discrete articles incorporating preformed parts or layers, e.g. casting around inserts or for coating articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29BPREPARATION OR PRETREATMENT OF THE MATERIAL TO BE SHAPED; MAKING GRANULES OR PREFORMS; RECOVERY OF PLASTICS OR OTHER CONSTITUENTS OF WASTE MATERIAL CONTAINING PLASTICS
    • B29B13/00Conditioning or physical treatment of the material to be shaped
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29BPREPARATION OR PRETREATMENT OF THE MATERIAL TO BE SHAPED; MAKING GRANULES OR PREFORMS; RECOVERY OF PLASTICS OR OTHER CONSTITUENTS OF WASTE MATERIAL CONTAINING PLASTICS
    • B29B13/00Conditioning or physical treatment of the material to be shaped
    • B29B13/02Conditioning or physical treatment of the material to be shaped by heating
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29BPREPARATION OR PRETREATMENT OF THE MATERIAL TO BE SHAPED; MAKING GRANULES OR PREFORMS; RECOVERY OF PLASTICS OR OTHER CONSTITUENTS OF WASTE MATERIAL CONTAINING PLASTICS
    • B29B7/00Mixing; Kneading
    • B29B7/002Methods
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29CSHAPING OR JOINING OF PLASTICS; SHAPING OF MATERIAL IN A PLASTIC STATE, NOT OTHERWISE PROVIDED FOR; AFTER-TREATMENT OF THE SHAPED PRODUCTS, e.g. REPAIRING
    • B29C39/00Shaping by casting, i.e. introducing the moulding material into a mould or between confining surfaces without significant moulding pressure; Apparatus therefor
    • B29C39/22Component parts, details or accessories; Auxiliary operations

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Materials For Medical Uses (AREA)

Abstract

The present invention relates to a kind of method for filling to special-shaped coils skeleton form, comprise the following steps:Step 1, bonding agent is pre-processed, the mode deaeration processing of pressure drop is stirred to bonding agent, that is, uses and vacuumizes with normal pressure alternately;Step 2, workpiece is installed, coil rack is loaded in forming frock;Step 3, embedding, four faces of coil rack are irrigated simultaneously by four mouthfuls of synchronous frocks that irrigate.Using the frock and its method for filling of the present invention, the Forming Quality of target seeker product line bag perfusion ensure that, it is ensured that properties of product are reliable, improve production efficiency.

Description

A kind of method for filling to special-shaped coils skeleton form
Technical field
The present invention relates to a kind of method for filling, particularly a kind of method for filling to special-shaped coils skeleton form.Category In the assembling process technique field of certain product.
Background technology
Bonding agent is used in the coil rack embedding of some products to the process of abnormity, small space perfusion, main If play a part of making copper coil and external insulation and fixed copper coil position.Coil rack is assemblied in some product tops Spiral shell outer, magnetic field is produced after copper coil electricity thereon and controls some product gyrobearings.The position of copper coil and sealing Its electricity, magnetic property is directly affected, and then influences the temporald eixis performance of some product gyros, reliability of product etc..
The special-shaped component that the copper coil and " emitting shape " housing that current coil rack is molded by four coilings form, " emits Shape " housing is provided with center hole on four faces, on the housing face where " bongrace ", 6 semicircle openings is provided with, for copper The export of matter lead-out wires of coil;Embedding requires fully wrapped around coil, and fills the gap between coil and skeleton.In coil rack In remain for the most wide 9mm of bonding agent passage, most narrow only 3mm, the space available for perfusion is very narrow and small, causes form to be stranded It is difficult.Coil rack perfusion uses special bonding agent, and not only viscosity is big for the bonding agent, poor fluidity, hardening time are short, Er Qie Easily parcel air forms bubble in bonding agent in mixed process.Conventional bonding agent uses to the technique of abnormity, small space perfusion Needle tubing is irrigated model frock single port, one side, due to the influence of the limitation of tool structure, reperfusion mode and bonding agent, coil Occur more leakage after skeleton perfusion to fill, it is necessary to which requirement could be met by carrying out manual operation to the coil firmware after embedding.Make The coil rack that embedding is carried out with original frock and method for filling repairs the serious shadows such as cost height, low yield, poor reliability repeatedly Ring the production of some products.
The content of the invention
The present invention is in order to solve the problems, such as bonding agent to product special-shaped coils skeleton form difficulty, it is proposed that a kind of right The method for filling of special-shaped coils skeleton form.In actual production process, using the frock and its method for filling of the present invention, protect The Forming Quality of target seeker product line bag perfusion is demonstrate,proved, it is ensured that properties of product are reliable, improve production efficiency.
The technical scheme is that:A kind of method for filling to special-shaped coils skeleton form, it is characterized in that:The party Method specifically comprises the following steps:
Step 1, pre-process bonding agent, bonding agent is stirred pressure drop mode deaeration processing, i.e., using vacuumize with Normal pressure is alternately;
Step 2, workpiece is installed, 4 locating modules of forming frock taken out, to all positions that can touch bonding agent A thin layer lubricating grease is applied, and checks that the first glue hole, second excessively of forming frock crosses glue hole and steam vent smoothness;By non-embedding Coil rack is placed at forming frock center, Primary Location after coil rack is wrapped up with 4 locating modules;By pressure ring by 4 Individual locating module compacting, is in close contact;The center hole of coil rack is blocked with 4 rubber plugs;By at the top of coil rack Sealed with lute with the junction of forming frock, and fastened using trim ring and depression bar;With 4 fixing bolts by pressure ring and positioning Module is fixed on base;By process installed above, coil rack is loaded in forming frock;
Step 3, embedding, the bonding agent of insulation is poured into the feed bin of four mouthfuls of synchronous perfusion frocks, piston is installed;Reversely put Four mouthfuls of synchronous perfusion frocks are put, slowly promote piston, until four mouthfuls of synchronous 4 targeted ducts of frock that irrigate have bonding agent a small amount of Untill outflow, then to 4 targeted duct installation perfusion interfaces;By 4 notes of the forming frock of 4 perfusion interface alignment embeddings Glue hole, slowly promotes piston, it is ensured that 3~5min completes the perfusion of a coil rack, and binding agent enters shaping work by hole for injecting glue The first glue hole, second excessively is filled to be filled reperfusion space after crossing glue hole;Air in reperfusion space by steam vent from bottom to top Exclude;Four mouthfuls of synchronous perfusion frocks irrigate four faces of coil rack simultaneously, storage glue groove of the foundation bonding agent in forming frock Spill-out judges whether to irrigate completely, stops perfusion when bonding agent is full of 1/2~3/4 volume of storage glue groove, removes four mouthfuls together Step perfusion frock;Normal temperature dismantles forming frock after standing 20~24 hours, complete embedding.
Described bonding agent is by 50 by first component, component B and the third component:(1-5):(5-8)Mass ratio composition;Institute The first component stated is that molecular weight is 1200-3000 liquid polysulphide rubbers and liquid-state epoxy resin by 1:1 mass ratio mixes; Component B is triethylene tetramine;Third component is the silicon powder of 1200-2000 mesh.
The use of the step 1 vacuumizes alternately to be comprised the concrete steps that with normal pressure:Bonding agent is placed in vacuum tank first Under interior electric blender, stirring rod is set to be placed in the magazine equipped with bonding agent using lifting platform;Normal pressure at the uniform velocity stirs bonding agent 2 ~5min, pressure is then evacuated to 0.05~0.06MPa, keeps 1~4min, be slowly dropped to normal pressure, bubble to be extracted out disappears After continue to vacuumize and with being slowly stirred, be so repeated, deaeration carried out to embedding bonding agent;It will finally be stirred Bonding agent is put into high-temperature cabinet is incubated 10~15min in the case where temperature is 40~70 DEG C, treats embedding.
A thin layer lubricating grease in the step 2 will be smeared uniformly, and thickness is 0.03~0.10mm.
Forming frock in the step 2 includes base, locating module, depression bar, pressure ring, fixing bolt, trim ring and rubber Plug forms, and described base is disc-shaped base, and 4 tops are arranged on 3 locating modules for being uniformly distributed steam vent In the locating groove of base, 4 locating modules form a cylindrical shape;Pressure ring is enclosed on cylindrical exterior, and fixing bolt passes through pressure Locating module is fastened on base by the fixing hole of ring and locating module;Described trim ring is fixed on base center spiral shell by depression bar In pit;Described rubber plug is 4, and rubber plug one end is arranged on the inner surface in the middle part of the locating module of each two contact On groove in, the other end is arranged in the center hole of coil rack;The side of the locating module bottom of each two contact is all Corresponding to be provided with two parallel up and down radial direction half slots, combination is coordinated and parallel first crosses glue hole and second up and down and cross glue hole;Often The locating module side top part of two contacts is all corresponding to be provided with groove, forms storage glue groove, the side below respective groove It is all corresponding on face to be provided with axial half slot, combine to form hole for injecting glue in the top surface of the locating module of each two contact, under hole for injecting glue End connects with the first glue hole and the second glue hole excessively excessively respectively, and hole for injecting glue is located at the central part of storage glue groove.
Four mouthfuls of synchronous perfusion frocks in the step 3 include:Targeted duct, sealing ring, piston and feed bin, described work The bottom shape of plug is consistent with the shape of feed bin, and is arranged in feed bin, and described seal is arranged between piston and feed bin, more Individual targeted duct is uniformly arranged on the bottom of feed bin, and each targeted duct is connected with perfusion interface.
Described seal is 2, up and down arrangement;Targeted duct is 4.
The preparation method of described bonding agent is:
1)By 50:(1-5):(5-8)Mass ratio weigh first component, component B and the third component;
2)After the first component and component B of formula ratio are well mixed, mixed liquor is formed;
3)In step 2)Mixed liquor in add formula ratio the third component, stir.
Advantages of the present invention:
The present invention solves the problems, such as coil rack abnormity, the perfusion of small space.
1st, the mode deaeration processing of pressure drop is stirred to bonding agent, using vacuumizing with normal pressure alternately, while companion With stirring, promote the broken spilling of bubble in bonding agent.The viscosity of bonding agent is reduced by the way of heating, adds flowing Property, be advantageous to the progress of embedding.Confirm(40~70)At a temperature of DEG C, bonding agent mobility is optimal.
2nd, forming frock designs, and bonding agent is proceeded by perfusion by coil rack bottom, bonding agent by external pressure from Coil rack bottom enters reperfusion space, and is filled since coil rack bottom, in the process bonding agent extrusion pressing type intracavitary Air discharged by top steam vent.It is abnormally-structured for coil rack, special the is left to privileged sites design One crosses glue hole.Design multiple steam vents, cross glue hole and storage glue groove, while shape need is met, can timely and effectively arrange The air gone out between filling process center line ring mould and frock, it is ensured that the integrality of form.
3rd, four mouthfuls of synchronous perfusion frocks, are irrigated, the method can effectively control four simultaneously for four faces of coil rack The bonding agent flux of individual perfusing hole, ensure four hand-hole feed pressure uniformity, avoid due to pressure difference and produce perfusion sky The problem of gap.Because perfusion is to carry out from bottom to top, therefore judge whether to fill in the spill-out of storage glue groove according to coil bonding agent Note is complete.With the solidification of glue, glue volume can carry out certain contraction, and the glue in storage glue groove plays supplement embedding simultaneously The effect of material, it is ensured that the pouring quality in four perfusion faces.In storage glue groove during the amount of bonding agent to 3/4ths volume, complete to fill Note.
4th, the coil rack irrigated by process above method and frock, it is conveniently stripped, it is simple and convenient can be once Irrigate 8~10 products;Embedding body surface face is smooth, and moulding property is good, and potting compound parcel coil is intact, and coil rack enriches nothing completely Space;After certain Product Assembly, coil frame electricity, magnetic property are good.The application of the present invention not only ensure that product quality and And greatly improve production efficiency.
Brief description of the drawings
Fig. 1 is the forming frock structural representation of the present invention;
Fig. 2 is Fig. 1 top view;
Fig. 3 is four mouthfuls of synchronous perfusion tool structure schematic diagrames of the present invention.
In figure, 1, base;2nd, locating module;3rd, depression bar;4th, pressure ring;5th, fixing bolt;6th, trim ring;7th, rubber plug;8、 First crosses glue hole;9th, second glue hole is crossed;10th, hole for injecting glue;11st, storage glue groove;12nd, steam vent;13rd, interface is irrigated;14th, positioning pipe Road;15th, sealing ring;16th, piston;17th, feed bin;18th, coil rack.
Below in conjunction with the accompanying drawings and embodiment the present invention is described in more detail, it is but not as a limitation of the invention.
Embodiment
Embodiment 1
A kind of method for filling to special-shaped coils skeleton form, it is characterized in that:This method specifically comprises the following steps:
Step 1, pre-process bonding agent, bonding agent is stirred pressure drop mode deaeration processing, i.e., using vacuumize with Normal pressure is alternately;
Step 2, workpiece is installed, 4 locating modules 2 of forming frock taken out, to all portions that can touch bonding agent Position applies a thin layer lubricating grease, and checks that glue hole 9 and the smoothness of steam vent 12 are crossed in the first glue hole 8, second excessively of forming frock;Will not The coil rack 18 of embedding is placed at forming frock center, Primary Location after coil rack 18 is wrapped up with 4 locating modules 2; 4 locating modules 2 are compacted by pressure ring 4, are in close contact;The center hole of coil rack is blocked with 4 rubber plugs 7; Junction at the top of coil rack with forming frock is sealed with lute, and fastened using trim ring 6 and depression bar 3;With 4 fixations Pressure ring 4 and locating module 2 are fixed on base 1 by bolt 5;By process installed above, coil rack 18 is loaded into shaping work In dress;
Step 3, embedding, the bonding agent of insulation is poured into the feed bin 17 of four mouthfuls of synchronous perfusion frocks, piston 16 is installed;Instead To four mouthfuls of synchronous perfusion frocks are placed, slowly promote piston 16, until four mouthfuls it is synchronous irrigate 4 targeted ducts 14 of frock have it is viscous Untill connecing a small amount of outflow of agent, then to 4 installation perfusion interfaces 13 of targeted ducts 14;4 perfusion interfaces 13 are directed at embedding 4 hole for injecting glue 10 of forming frock, slowly promote piston 16, it is ensured that 3~5min completes the perfusion of a coil rack, binding agent Crossed by hole for injecting glue 10 into forming frock first after glue hole 9 is crossed in glue hole 8, second and reperfusion space is filled;In reperfusion space Air excluded from bottom to top by steam vent 12;Four mouthfuls of synchronous perfusion frocks irrigate four faces of coil rack simultaneously, according to viscous Connect agent and judge whether that perfusion is complete in the spill-out of the storage glue groove 11 of forming frock, when 1/2 of bonding agent full of storage glue groove 11~ Stop perfusion during 3/4 volume, remove four mouthfuls of synchronous perfusion frocks;Normal temperature dismantles forming frock after standing 20~24 hours, completes Embedding.
Embodiment 2
A kind of method for filling to special-shaped coils skeleton form, specifically comprise the following steps:
Step 1, pre-process bonding agent, bonding agent is stirred pressure drop mode deaeration processing, i.e., using vacuumize with Normal pressure is alternately;
The use vacuumizes alternately to be comprised the concrete steps that with normal pressure:Bonding agent is placed in first electronic in vacuum tank Under mixer, stirring rod is set to be placed in the magazine equipped with bonding agent using lifting platform;Normal pressure at the uniform velocity stirs 2~5min of bonding agent, Then pressure is evacuated to 0.05~0.06MPa, keeps 1~4min, be slowly dropped to normal pressure, continue to take out after the bubble extracted out disappears Vacuum and with being slowly stirred, is so repeated, deaeration is carried out to embedding bonding agent;Finally the bonding agent being stirred is put Enter in high-temperature cabinet and be incubated 10~15min in the case where temperature is 40~70 DEG C, treat embedding.The mode that pressure drop is stirred to bonding agent takes off Bubble processing, using vacuumizing with normal pressure alternately, while with stirring, promote the broken spilling of bubble in bonding agent.Using The mode of heating reduces the viscosity of bonding agent, adds mobility, is advantageous to the progress of embedding.
Step 2, workpiece is installed, 4 locating modules 2 of forming frock taken out, to all portions that can touch bonding agent Position applies a thin layer lubricating grease, smears the dismounting that lubricating grease is easy to frock and coil rack after embedding shaping;And check forming frock First cross glue hole 8, second and cross glue hole 9 and the smoothness of steam vent 12;The coil rack 18 of non-embedding is placed in forming frock At the heart, Primary Location after coil rack 18 is wrapped up with 4 locating modules 2;4 locating modules 2 are compacted by pressure ring 4, tightly Contiguity is touched;The center hole of coil rack is blocked with 4 rubber plugs 7, prevents casting glue hydrorrhea from going out;By at the top of coil rack Sealed with lute with the junction of forming frock, and fastened using trim ring 6 and depression bar 3;With 4 fixing bolts 5 by the He of pressure ring 4 Locating module 2 is fixed on base 1;By process installed above, coil rack 18 is loaded in forming frock;
The a thin layer lubricating grease will be smeared uniformly, and thickness is 0.03~0.10mm.
As depicted in figs. 1 and 2, described forming frock includes base 1, locating module 2, depression bar 3, pressure ring 4, fixing bolt 5th, trim ring 6 and rubber plug 7 form, and described base 1 is disc-shaped base, and 4 tops are uniformly distributed steam vent 12 with 3 Locating module 2 be arranged in the locating groove of base 1,4 locating modules 2 form a cylindrical shapes;Pressure ring 4 is enclosed on cylindrical shape Outside, 4 locating modules 2 are compacted by pressure ring 4, be in close contact;Fixation of the fixing bolt 5 through pressure ring 4 and locating module 2 Locating module 2 is fastened on base 1 by hole;Described trim ring 6 is fixed in the screwed hole of centre of base 1 by depression bar 3;Described Rubber plug 7 is 4, and the one end of rubber plug 7 is arranged on the groove on the inner surface at the middle part of locating module 2 of each two contact Interior, the other end is arranged in the center hole of coil rack 18;The side of the bottom of locating module 2 of each two contact is all corresponding to open There are parallel two radial direction half slots up and down, combination is coordinated and parallel first crosses glue hole 8 and second up and down and cross glue hole 9;Each two The side top part of locating module 2 of contact is all corresponding to be provided with groove, forms storage glue groove 11, the side below respective groove On it is all corresponding be provided with axial half slot, combine to form hole for injecting glue 10 in the top surface of the locating module of each two contact, hole for injecting glue 10 Lower end connects with the first glue hole 9 excessively of glue hole 8 and second excessively respectively, and hole for injecting glue 10 is located at the central part of storage glue groove 11.
First glue hole 8, second glue hole 9, hole for injecting glue 10 and storage glue groove 11 excessively excessively is all 4.
Step 3, embedding, the bonding agent of insulation is poured into the feed bin 17 of four mouthfuls of synchronous perfusion frocks, piston 16 is installed;Instead To four mouthfuls of synchronous perfusion frocks are placed, slowly promote piston 16, until four mouthfuls it is synchronous irrigate 4 targeted ducts 14 of frock have it is viscous Untill connecing a small amount of outflow of agent, then to 4 installation perfusion interfaces 13 of targeted ducts 14;4 perfusion interfaces 13 are directed at embedding 4 hole for injecting glue 10 of forming frock, slowly promote piston 16, it is ensured that 3~5min completes the perfusion of a coil rack, binding agent Crossed by hole for injecting glue 10 into forming frock first after glue hole 9 is crossed in glue hole 8, second and reperfusion space is filled;In reperfusion space Air excluded from bottom to top by steam vent 12;Four mouthfuls of synchronous perfusion frocks irrigate four faces of coil rack simultaneously, according to viscous Connect agent and judge whether that perfusion is complete in the spill-out of the storage glue groove 11 of forming frock, when 1/2 of bonding agent full of storage glue groove 11~ Stop perfusion during 3/4 volume, remove four mouthfuls of synchronous perfusion frocks;With the preliminary solidification of bonding agent, bonding agent volume can be carried out Certain contraction, the bonding agent in storage glue groove 11 play a part of supplement simultaneously, it is ensured that the pouring qualities in four perfusion faces.Normal temperature Forming frock is dismantled after standing 20~24 hours, completes embedding;The synchronous perfusion frock of four mouthfuls of the present invention is directed to coil rack four Individual face irrigates simultaneously, and the method can effectively control the bonding agent flux of four perfusing holes, ensures that four hand-holes flow into pressure Power uniformity, avoid due to pressure difference and produce the problem of irrigating space.
As shown in figure 3, described four mouthfuls synchronous perfusion frocks include:Targeted duct 14, sealing ring 15, piston 16 and feed bin 17, the bottom shape of described piston 16 is consistent with the shape of feed bin 17, and is arranged in feed bin 17, and described seal 15 is set Between piston 16 and feed bin 17, multiple targeted ducts 14 are uniformly arranged on the bottom of feed bin 17, and each targeted duct 14 connects It is connected to perfusion interface 13.Here seal 15 is 2, up and down arrangement;Targeted duct 14 is 4.
The coil rack irrigated by process above method and frock, it is conveniently stripped, it is simple and convenient once to fill 8~10 products of note;Embedding body surface face is smooth, and moulding property is good, and potting compound parcel coil is intact, and coil rack is enriched without sky completely Gap;After certain Product Assembly, coil frame electricity, magnetic property are good.The present invention application not only ensure that product quality but also Greatly improve production efficiency.This instillation process, which is appointed, is in artisan craftsmanship process, need to be improved to full-automatic direction, to meet The demand that certain product is produced in enormous quantities.
Embodiment 3
On the basis of embodiment 2, described bonding agent is by 50 by first component, component B and the third component:(1-5):(5- 8)Mass ratio composition;Described first component is that molecular weight is 1200-3000 liquid polysulphide rubbers and liquid-state epoxy resin by 1:1 Mass ratio mix;Component B is triethylene tetramine;Third component is the silicon powder of 1200-2000 mesh.
The preparation method of bonding agent is:
1)By 50:(1-5):(5-8)Mass ratio weigh first component, component B and the third component;
2)After the first component and component B of formula ratio are well mixed, mixed liquor is formed;
3)In step 2)Mixed liquor in add formula ratio the third component, stir.
The bonding agent of the invention used can ensure adhesive effect, while the bonding agent mobility is optimal.
Part and structure and the well-known components and common structure of the technique category industry that the present embodiment does not describe in detail or Conventional means, do not describe one by one here.

Claims (5)

1. a kind of method for filling to special-shaped coils skeleton form, it is characterized in that:This method specifically comprises the following steps:
Step 1, bonding agent is pre-processed, the mode deaeration processing of pressure drop is stirred to bonding agent, i.e., using vacuumizing and normal pressure Alternately;
Step 2, workpiece is installed, by 4 locating modules of forming frock(2)Take out, to all positions that can touch bonding agent Painting a layer thickness is 0.03~0.10mm lubricating grease, and checks that the first of forming frock crosses glue hole(8), second cross glue hole(9)With Steam vent(12)Smoothness;By the coil rack of non-embedding(18)It is placed at forming frock center, with 4 locating modules(2)Will Coil rack(18)Primary Location after parcel;Pass through pressure ring(4)By 4 locating modules(2)Compacting, it is in close contact;With 4 rubber Plug(7)The center hole of coil rack is blocked;Junction at the top of coil rack with forming frock is sealed with lute, And use trim ring(6)And depression bar(3)Fastening;With 4 fixing bolts(5)By pressure ring(4)And locating module(2)It is fixed on base (1)On;By process installed above, by coil rack(18)Load in forming frock;
Step 3, embedding, the bonding agent of insulation is poured into the feed bin of four mouthfuls of synchronous perfusion frocks(17)In, piston is installed(16);Instead To four mouthfuls of synchronous perfusion frocks are placed, piston is slowly promoted(16), until four mouthfuls of synchronous perfusion 4 targeted ducts of frock(14)All Have untill bonding agent flows out on a small quantity, then to 4 targeted ducts(14)Installation perfusion interface(13);Interface is irrigated by 4(13) It is directed at 4 hole for injecting glue of the forming frock of embedding(10), slowly promote piston(16), it is ensured that 3~5min completes a coil bone The perfusion of frame, binding agent is by hole for injecting glue(10)Glue hole is crossed into forming frock first(8), second cross glue hole(9)It is empty to perfusion afterwards Between be filled;Air in reperfusion space is by steam vent(12)Exclude from bottom to top;Four mouthfuls of synchronous perfusion frocks are to coil bone Four faces of frame irrigate simultaneously, storage glue groove of the foundation bonding agent in forming frock(11)Spill-out judge whether that perfusion is complete, when Bonding agent is full of storage glue groove(11)1/2~3/4 volume when stop perfusion, remove four mouthfuls of synchronous perfusion frocks;Normal temperature stands 20 Forming frock is dismantled after~24 hours, completes embedding.
2. a kind of method for filling to special-shaped coils skeleton form according to claim 1, it is characterized in that:The step Rapid 1 use vacuumizes alternately to be comprised the concrete steps that with normal pressure:The electric blender that bonding agent is placed in vacuum tank first Under, stirring rod is placed in the magazine equipped with bonding agent using lifting platform;Normal pressure at the uniform velocity stirs 2~5min of bonding agent, then will Pressure is evacuated to 0.05~0.06MPa, keeps 1~4min, is slowly dropped to normal pressure, continues to vacuumize simultaneously after the bubble extracted out disappears And with being slowly stirred, be so repeated, deaeration is carried out to embedding bonding agent;The bonding agent being stirred finally is put into high temperature 10~15min is incubated at being 40~70 DEG C in temperature in case, treats embedding.
3. a kind of method for filling to special-shaped coils skeleton form according to claim 1, it is characterized in that:The step Forming frock in rapid 2 includes base(1), locating module(2), depression bar(3), pressure ring(4), fixing bolt(5), trim ring(6)With Rubber plug(7)Composition, described base(1)For disc-shaped base, 4 tops are uniformly distributed steam vent with 3(12)'s Locating module(2)Installed in base(1)Locating groove in, 4 locating modules(2)Form a cylindrical shape;Pressure ring(4)It is enclosed on Cylindrical exterior, fixing bolt(5)Through pressure ring(4)And locating module(2)Fixing hole by locating module(2)It is fastened on base (1)On;Described trim ring(6)Pass through depression bar(3)It is fixed on base(1)In screwed hole of centre;Described rubber plug(7)For 4 It is individual, rubber plug(7)One end is arranged on the locating module of each two contact(2)In groove on the inner surface at middle part, the other end It is arranged on coil rack(18)Center hole in;The locating module of each two contact(2)The side of bottom is all corresponding to be provided with Under parallel two radial direction half slots, combination coordinates and parallel first crosses glue hole up and down(8)Glue hole is crossed with second(9);Each two The locating module of contact(2)Side top part is all corresponding to be provided with groove, forms storage glue groove(11), below respective groove It is all corresponding on side to be provided with axial half slot, combine to form hole for injecting glue in the top surface of the locating module of each two contact(10), note Glue hole(10)Glue hole is crossed in lower end with first respectively(8)Glue hole is crossed with second(9)Connection, hole for injecting glue(10)Positioned at storage glue groove(11)'s Central part.
4. a kind of method for filling to special-shaped coils skeleton form according to claim 1, it is characterized in that:The step Four mouthfuls of synchronous perfusion frocks in rapid 3 include:Targeted duct(14), sealing ring(15), piston(16)And feed bin(17), it is described Piston(16)Bottom shape and feed bin(17)Shape it is consistent, and be arranged on feed bin(17)Interior, described sealing ring(15)If Put in piston(16)With feed bin(17)Between, multiple targeted ducts(14)It is uniformly arranged on feed bin(17)Bottom, each positioning Pipeline(14)All it is connected with perfusion interface(13).
5. a kind of method for filling to special-shaped coils skeleton form according to claim 4, it is characterized in that:Described Sealing ring(15)It is 2, arranges up and down;Targeted duct(14)It is 4.
CN201610385200.2A 2016-06-03 2016-06-03 A kind of method for filling to special-shaped coils skeleton form Active CN105965738B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610385200.2A CN105965738B (en) 2016-06-03 2016-06-03 A kind of method for filling to special-shaped coils skeleton form

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610385200.2A CN105965738B (en) 2016-06-03 2016-06-03 A kind of method for filling to special-shaped coils skeleton form

Publications (2)

Publication Number Publication Date
CN105965738A CN105965738A (en) 2016-09-28
CN105965738B true CN105965738B (en) 2018-01-26

Family

ID=57010105

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610385200.2A Active CN105965738B (en) 2016-06-03 2016-06-03 A kind of method for filling to special-shaped coils skeleton form

Country Status (1)

Country Link
CN (1) CN105965738B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106926406B (en) * 2017-05-11 2022-12-06 中环天仪股份有限公司 Filling tool for transmitter amplification plate and using method
CN108748823B (en) * 2018-05-24 2020-04-03 哈尔滨东安实业发展有限公司 Forming method of hydraulic safety shaft
CN110211804A (en) * 2019-05-14 2019-09-06 安徽博微智能电气有限公司 Coil glue-pouring device and method
CN110328792B (en) * 2019-08-13 2024-05-24 四川省众望科希盟科技有限公司 Filling and sealing process and mold for miniature mobile monitoring equipment
CN110732465B (en) * 2019-11-22 2021-07-16 成都凯天电子股份有限公司 Coil sealant filling and sealing device
TWI730623B (en) 2020-02-13 2021-06-11 朋程科技股份有限公司 Method for manufacturing power diode
CN111347606B (en) * 2020-03-10 2022-02-15 长沙金信诺防务技术有限公司 Cable vulcanizing device and vulcanizing method
CN112720969A (en) * 2020-12-12 2021-04-30 贵州航天电子科技有限公司 Encapsulating tool and encapsulating method for electronic product
CN112847998A (en) * 2020-12-30 2021-05-28 贺盛精密塑胶(苏州)有限公司 Pouring process of PU pouring wheel

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4021591A1 (en) * 1990-07-06 1992-01-16 Grundfos Int Encapsulating motor stator in cast resin
CN201859775U (en) * 2010-11-09 2011-06-08 许继集团有限公司 Vertical casting mold for layer coil of dry-type transformer
CN102306989A (en) * 2011-09-08 2012-01-04 中国航空工业第六一八研究所 Bonding and potting method for aerial integrated motor
CN202258780U (en) * 2011-09-05 2012-05-30 上海一电变压器有限公司 Upper-end closing plate device for vertical casting mould of dry-type transformer epoxy resin coil
CN204732287U (en) * 2015-07-13 2015-10-28 山东天燚电力设备有限公司 The apparatus for pouring of epoxy resin cast transformer coil
CN205004172U (en) * 2015-09-15 2016-01-27 宿迁中电电气有限公司 Dry -type transformer casting mold

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4673690B2 (en) * 2005-07-15 2011-04-20 株式会社東芝 Injection device for pressure gelation

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4021591A1 (en) * 1990-07-06 1992-01-16 Grundfos Int Encapsulating motor stator in cast resin
CN201859775U (en) * 2010-11-09 2011-06-08 许继集团有限公司 Vertical casting mold for layer coil of dry-type transformer
CN202258780U (en) * 2011-09-05 2012-05-30 上海一电变压器有限公司 Upper-end closing plate device for vertical casting mould of dry-type transformer epoxy resin coil
CN102306989A (en) * 2011-09-08 2012-01-04 中国航空工业第六一八研究所 Bonding and potting method for aerial integrated motor
CN204732287U (en) * 2015-07-13 2015-10-28 山东天燚电力设备有限公司 The apparatus for pouring of epoxy resin cast transformer coil
CN205004172U (en) * 2015-09-15 2016-01-27 宿迁中电电气有限公司 Dry -type transformer casting mold

Also Published As

Publication number Publication date
CN105965738A (en) 2016-09-28

Similar Documents

Publication Publication Date Title
CN105965738B (en) A kind of method for filling to special-shaped coils skeleton form
CN103546000B (en) A kind of generator end insulation booth glue-pouring method
CN205992556U (en) A kind of battery module
CN103509315B (en) A kind of seismic physical model material of epoxy resin composite polyurethane synthesis and preparation method
CN104766918B (en) A kind of utilize liquid-state epoxy resin carry out SMD LED mould note encapsulation technique and device
CN204809998U (en) Plastic envelope stator device
CN206059088U (en) The environmental protection transformer of lost-wax process encapsulated epoxy resin
CN102635263B (en) Connection construction member capable of regulating tightness and manufacturing and assembling method thereof
CN205437044U (en) Casting device
CN207941440U (en) A kind of solvent naphtha mixing arrangement
CN108891042A (en) A kind of preparation method of processable solid buoyancy material
CN106449020A (en) Environment-friendly transformer for potting epoxy resin employing lost-wax process and preparation method of environment-friendly transformer
CN2698564Y (en) Vacuum injection forming device
CN206076570U (en) Connector, electric connector and connection terminal aggregation
CN201993196U (en) Integral glass sealed base for pressure sensor
CN205437043U (en) Ball casting device
CN207279122U (en) A kind of cooling system pipeline connecting device
CN207224418U (en) Install the profile-followed mould of complex abrasion-proof erosion layer additional on hardware
CN207591677U (en) A kind of casting glue production agitating device
CN112338181A (en) Casting auxiliary assembly of lost foam casting equipment
CN205437053U (en) Casting processingequipment for ball
CN207577883U (en) A kind of stainless steel welded formula combined platform
CN105903649B (en) Machine mouth is in the milk tooling after a kind of solid propellant rocket
CN206355902U (en) A kind of agitator tank with Novel heating structure
CN204338137U (en) A kind of preparation system of transformer resin-cast material

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant