CN105932732B - Circuit breaker control circuit, electric automobile battery charger running control circuit and method - Google Patents

Circuit breaker control circuit, electric automobile battery charger running control circuit and method Download PDF

Info

Publication number
CN105932732B
CN105932732B CN201610318756.XA CN201610318756A CN105932732B CN 105932732 B CN105932732 B CN 105932732B CN 201610318756 A CN201610318756 A CN 201610318756A CN 105932732 B CN105932732 B CN 105932732B
Authority
CN
China
Prior art keywords
signal
circuit
charger
logical
input
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610318756.XA
Other languages
Chinese (zh)
Other versions
CN105932732A (en
Inventor
王建
陈玉峰
朱文兵
姚金霞
辜超
朱孟兆
彭飞
李�杰
朱庆东
白德盟
马艳
杜修明
周加斌
任敬国
朱振华
袁海燕
张振军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610318756.XA priority Critical patent/CN105932732B/en
Publication of CN105932732A publication Critical patent/CN105932732A/en
Application granted granted Critical
Publication of CN105932732B publication Critical patent/CN105932732B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • H02J7/0027
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/327Testing of circuit interrupters, switches or circuit-breakers
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01MPROCESSES OR MEANS, e.g. BATTERIES, FOR THE DIRECT CONVERSION OF CHEMICAL ENERGY INTO ELECTRICAL ENERGY
    • H01M10/00Secondary cells; Manufacture thereof
    • H01M10/42Methods or arrangements for servicing or maintenance of secondary cells or secondary half-cells
    • H01M10/44Methods for charging or discharging
    • H01M10/441Methods for charging or discharging for several batteries or cells simultaneously or sequentially
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J7/00Circuit arrangements for charging or depolarising batteries or for supplying loads from batteries
    • H02J7/0029Circuit arrangements for charging or depolarising batteries or for supplying loads from batteries with safety or protection devices or circuits
    • H02J7/0036Circuit arrangements for charging or depolarising batteries or for supplying loads from batteries with safety or protection devices or circuits using connection detecting circuits
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J7/00Circuit arrangements for charging or depolarising batteries or for supplying loads from batteries
    • H02J7/0069Charging or discharging for charge maintenance, battery initiation or rejuvenation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/10Energy storage using batteries

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • General Chemical & Material Sciences (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)

Abstract

The invention discloses circuit breaker control circuit, electric automobile battery charger running control circuit and method, circuit breaker control circuit includes logical AND non-device, its input terminal is respectively connected with charging current judgment module and charger input moment judgment module;Charging current judgment module includes first comparator, its first input end and the second input terminal are connected with charging current signal Acquisition Circuit and current threshold input circuit respectively, and the first comparison circuit will receive signal and be compared and export high level signal or low level signal is to logical AND non-device;Charger input moment judgment module includes the second comparator, respectively with charger input moment pulse signal input circuit and putting into moment threshold value pulse signal input circuit and being connected, the second comparison circuit will receive signal and be compared and export high level signal or low level signal is to logical AND non-device for its first input end and the second input terminal;Logical AND non-device exports trigger signal to control the opening and closing of breaker.

Description

Circuit breaker control circuit, electric automobile battery charger running control circuit and method
Technical field
The invention belongs to electric automobile field, more particularly to a kind of circuit breaker control circuit, electric automobile battery charger to run Control circuit and method.
Background technology
In order to reduce greenhouse gas emission and reduce the dependence to petroleum import, clean energy resource development, country are promoted energetically Grid company adds up to build up intelligent substation 2300, electric charging station 1537, charging pile 2.96 ten thousand in the whole nation.With electronic Automobile accesses power grid, it is necessary to realize effective management and control to the charging pile in charging station on a large scale.
Electric automobile battery charger is a kind of equipment for the Vehicular battery charging for aiming at electric automobile, is used when being and charging to battery To the power inverter for having specific function.The necessary means that electric automobile battery charger charges as battery, its performance it is good Bad and process complexity directly affects the service life of battery and the popularization of electric automobile.Existing electric automobile battery charger operation Control circuit is more complicated, and hardware configuration is fixed, and expansibility is poor, and existing electric automobile battery charger running control circuit is equal Charging station actual demand is not accounted for, control charger is not provided with and puts into operation the time, and then can not achieve charging station peak valley intelligence Charging to carry out effective management and control to whole charging station, ultimately causes the wasting of resources and adds charging cost.
The content of the invention
The shortcomings that in order to solve the prior art, the present invention provide a kind of circuit breaker control circuit, electric automobile battery charger fortune Line control circuit and method.The electric automobile battery charger running control circuit is simple and reliable, and economy is high, and hardware configuration spirit Live, it can be achieved that multi-vector input controls, consideration charging station actual demand, adds the function of intelligent preset charged time, pass through Control charger puts into operation the time, it can be achieved that charging station peak valley intelligent charge, and then carries out effective management and control to whole charging station, greatly Save charging cost.
To achieve the above object, the present invention uses following technical scheme:
A kind of circuit breaker control circuit, including logical AND non-device, input terminal and the charging electricity of the logical AND non-device Stream judgment module and charger input moment judgment module are respectively connected with;
The charging current judgment module includes first comparator, the first input end of the first comparator and second defeated Enter end respectively with charging current signal Acquisition Circuit and current threshold input circuit to be connected, the first comparison circuit will receive signal It is compared and exports high level signal or low level signal is to logical AND non-device;
Charger input moment judgment module includes the second comparator, the first input end of second comparator with Second input terminal puts into moment pulse signal input circuit and input moment threshold value pulse signal input circuit with charger respectively It is connected, the second comparison circuit will receive signal and be compared and export high level signal or low level signal is to the non-device of logical AND Part;The logical AND non-device carries out logical process to received signal, exports trigger signal to control the opening and closing of breaker.
The circuit breaker control circuit, which further includes charger operation, allows signal input circuit;The charger operation allows Signal input circuit output charger operation allows signal, is sent to logical AND non-device;The charger operation allows signal For high level signal or low level signal.
The charging current signal Acquisition Circuit includes current transformer, one end connection charging of the current transformer Machine, the other end connect the first input end of first comparator.
The charger operation allows signal input circuit to be pulse-generating circuit.
A kind of method of work of circuit breaker control circuit, including:
Step (1):The charging current signal collected is sent in first comparator by charging current signal Acquisition Circuit, First comparator by the charging current signal of reception compared with the current threshold that current threshold input circuit exports, if the former is more than Or equal to the latter, then high level signal is exported to logical AND non-device;Otherwise, low level signal is exported to logical AND non-device;
Step (2):Charger puts into moment pulse signal input circuit and charger input time-ofday signals is sent to second In comparator, the second comparator is defeated by the charger input time-ofday signals of reception and input moment threshold value pulse signal input circuit The input moment threshold value comparison gone out, if the former is greater than or equal to the latter, output high level signal to logical AND non-device;It is no Then, low level signal is exported to logical AND non-device;
Step (3):Charger operation, which allows signal input circuit to run charger, to be allowed signal to be sent to logical AND non- Device;
Step (4):Logical AND non-device carries out logical process to received signal, when logical AND non-device received signal It is high level signal, then exports trigger signal to control the closure of breaker;Otherwise, trigger signal is exported to control breaker Opening;Wherein, the order of step (1), step (2) and step (3) can be replaced arbitrarily.
A kind of electric automobile battery charger running control circuit, including breaker, its output terminal connection charger, input terminal connect Connect circuit breaker control circuit;
The circuit breaker control circuit includes logical AND non-device, the input terminal and charging current of the logical AND non-device Judgment module and charger input moment judgment module are respectively connected with;
The charging current judgment module includes first comparator, the first input end of the first comparator and second defeated Enter end respectively with charging current signal Acquisition Circuit and current threshold input circuit to be connected, the first comparison circuit will receive signal It is compared and exports high level signal or low level signal is to logical AND non-device;
Charger input moment judgment module includes the second comparator, the first input end of second comparator with Second input terminal puts into moment pulse signal input circuit and input moment threshold value pulse signal input circuit with charger respectively It is connected, the second comparison circuit will receive signal and be compared and export high level signal or low level signal is to the non-device of logical AND Part;The logical AND non-device carries out logical process to received signal, exports trigger signal to control the opening and closing of breaker.
The circuit breaker control circuit, which further includes charger operation, allows signal input circuit;The charger operation allows Signal input circuit output charger operation allows signal, is sent to logical AND non-device;The charger operation allows signal For high level signal or low level signal.
The charging current signal Acquisition Circuit includes current transformer, one end connection charging of the current transformer Machine, the other end connect the first input end of first comparator.
The charger operation allows signal input circuit to be pulse-generating circuit.
A kind of method of work of electric automobile battery charger running control circuit, including:
Step (1):The charging current signal collected is sent in first comparator by charging current signal Acquisition Circuit, First comparator by the charging current signal of reception compared with the current threshold that current threshold input circuit exports, if the former is more than Or equal to the latter, then high level signal is exported to logical AND non-device;Otherwise, low level signal is exported to logical AND non-device;
Step (2):Charger puts into moment pulse signal input circuit and charger input time-ofday signals is sent to second In comparator, the second comparator is defeated by the charger input time-ofday signals of reception and input moment threshold value pulse signal input circuit The input moment threshold value comparison gone out, if the former is greater than or equal to the latter, output high level signal to logical AND non-device;It is no Then, low level signal is exported to logical AND non-device;
Step (3):Charger operation, which allows signal input circuit to run charger, to be allowed signal to be sent to logical AND non- Device;
Step (4):Logical AND non-device carries out logical process to received signal, when logical AND non-device received signal It is high level signal, then exports trigger signal to control the closure of breaker, charger work;Otherwise, trigger signal is exported To control the opening of breaker, charger does not work;
Wherein, the order of step (1), step (2) and step (3) can be replaced arbitrarily.
Beneficial effects of the present invention are:
(1) present invention is simple and reliable for structure using logic control circuit and hardware configuration is flexible, hardware configuration scalability By force, the collection and control to charger major parameter can effectively be realized, and control charger to put into operation by the break-make of breaker.
(2) present invention judges rechargeable battery charged state by detecting charging current, and control charger in time connects switching Open, avoid over-charging of battery, cause permanent lesion, while consider charging station actual demand, add the intelligent preset charged time Function, by controlling charger to put into operation the time, it can be achieved that charging station peak valley intelligent charge, and then have to whole charging station Management and control is imitated, greatly saves charging cost.
Brief description of the drawings
Fig. 1 is the circuit breaker control circuit structure diagram of the present invention;
Fig. 2 is the charging current judgment module structure diagram of the present invention;
Fig. 3 is the charger input moment judgment module structure diagram of the present invention;
Fig. 4 is the electric automobile battery charger running control circuit structure diagram of the present invention.
Embodiment
The present invention will be further described with embodiment below in conjunction with the accompanying drawings:
As shown in Figure 1, a kind of circuit breaker control circuit embodiment of the present invention is as follows:
Circuit breaker control circuit includes logical AND non-device, and input terminal and the charging current of the logical AND non-device judge Module and charger input moment judgment module are respectively connected with.
As shown in Fig. 2, charging current judgment module includes first comparator, the first input end of the first comparator and Second input terminal is connected with charging current signal Acquisition Circuit and current threshold input circuit respectively, and the first comparison circuit will receive It is compared to signal and exports high level signal or low level signal is to logical AND non-device.
As shown in figure 3, charger input moment judgment module includes the second comparator, the first of second comparator is defeated It is defeated with charger input moment pulse signal input circuit and input moment threshold value pulse signal respectively to enter end and the second input terminal Enter circuit to be connected, the second comparison circuit will receive signal and be compared and export high level signal or low level signal is to logic With non-device;The logical AND non-device carries out logical process to received signal, exports trigger signal to control breaker Opening and closing.
The present invention another circuit breaker control circuit embodiment be:
Circuit breaker control circuit in the embodiment, which further includes charger operation, allows signal input circuit;The charger Operation, which allows signal input circuit to export charger and run, allows signal, is sent to logical AND non-device;The charger operation It is high level signal or low level signal to allow signal.
Charging current signal Acquisition Circuit includes current transformer, and one end of the current transformer connects charger, separately One end connects the first input end of first comparator.
Charging current signal Acquisition Circuit further includes filter circuit, dry in the charging current signal collected for filtering out Disturb signal.
Wherein, charger operation allows signal input circuit to be pulse-generating circuit.The pulse-generating circuit can use DSP Chip or existing circuit structure are achieved, and will be not repeated herein.
Current threshold input circuit and input moment threshold value pulse signal input circuit can also use pulse-generating circuit It is achieved or existing signal generating circuit produces.
The present invention is simple and reliable for structure using logic control circuit and hardware configuration is flexible, and hardware configuration scalability is strong, It can effectively realize the collection and control to charger major parameter, and control charger to put into operation by the break-make of breaker;This hair It is bright that rechargeable battery state is also monitored by charging current, it can relatively accurately realize the monitoring to rechargeable battery.In addition, This, which only chooses charging current, charging interval and charger operation, allows signal, these three key parameters control filling for charger Electric size of current, charging interval and charger operation number of units, greatly simplify circuit, while also ensure that to the effective of charger Management and control, such as realize time-of-use tariffs charging strategy and reduce charger harmonic current.
The method of work of the circuit breaker control circuit of the present invention, including:
Step (1):The charging current signal collected is sent in first comparator by charging current signal Acquisition Circuit, First comparator by the charging current signal of reception compared with the current threshold that current threshold input circuit exports, if the former is more than Or equal to the latter, then high level signal is exported to logical AND non-device;Otherwise, low level signal is exported to logical AND non-device;
Step (2):Charger puts into moment pulse signal input circuit and charger input time-ofday signals is sent to second In comparator, the second comparator is defeated by the charger input time-ofday signals of reception and input moment threshold value pulse signal input circuit The input moment threshold value comparison gone out, if the former is greater than or equal to the latter, output high level signal to logical AND non-device;It is no Then, low level signal is exported to logical AND non-device;
Step (3):Charger operation, which allows signal input circuit to run charger, to be allowed signal to be sent to logical AND non- Device;
Step (4):Logical AND non-device carries out logical process to received signal, when logical AND non-device received signal It is high level signal, then exports trigger signal to control the closure of breaker;Otherwise, trigger signal is exported to control breaker Opening;Wherein, the order of step (1), step (2) and step (3) can be replaced arbitrarily.
As shown in figure 4, a kind of embodiment of the electric automobile battery charger running control circuit of the present invention is:
Electric automobile battery charger running control circuit in the embodiment, including breaker, its output terminal connection charger, Input terminal connects circuit breaker control circuit;
The circuit breaker control circuit includes logical AND non-device, the input terminal and charging current of the logical AND non-device Judgment module and charger input moment judgment module are respectively connected with;
The charging current judgment module includes first comparator, the first input end of the first comparator and second defeated Enter end respectively with charging current signal Acquisition Circuit and current threshold input circuit to be connected, the first comparison circuit will receive signal It is compared and exports high level signal or low level signal is to logical AND non-device;
Charger input moment judgment module includes the second comparator, the first input end of second comparator with Second input terminal puts into moment pulse signal input circuit and input moment threshold value pulse signal input circuit with charger respectively It is connected, the second comparison circuit will receive signal and be compared and export high level signal or low level signal is to the non-device of logical AND Part;The logical AND non-device carries out logical process to received signal, exports trigger signal to control the opening and closing of breaker.
The embodiment of another electric automobile battery charger running control circuit of the present invention is:
Circuit breaker control circuit in the electric automobile battery charger running control circuit, further including charger operation allows letter Number input circuit;The charger operation, which allows signal input circuit to export charger and run, allows signal, is sent to logical AND Non-device;The charger operation allows signal to be high level signal or low level signal.
Wherein, charging current signal Acquisition Circuit includes current transformer, one end connection charging of the current transformer Machine, the other end connect the first input end of first comparator.
Charging current signal Acquisition Circuit further includes filter circuit, dry in the charging current signal collected for filtering out Disturb signal.
Wherein, charger operation allows signal input circuit to be pulse-generating circuit.The pulse-generating circuit can use DSP Chip or existing circuit structure are achieved, and will be not repeated herein.
Current threshold input circuit and input moment threshold value pulse signal input circuit can also use pulse-generating circuit It is achieved or existing signal generating circuit produces.
The present invention is simple and reliable for structure using logic control circuit and hardware configuration is flexible, and hardware configuration scalability is strong, It can effectively realize the collection and control to charger major parameter, and control charger to put into operation by the break-make of breaker;This hair It is bright that rechargeable battery state is also monitored by charging current, it can relatively accurately realize the monitoring to rechargeable battery.In addition, This, which only chooses charging current, charging interval and charger operation, allows signal, these three key parameters control filling for charger Electric size of current, charging interval and charger operation number of units, greatly simplify circuit, while also ensure that to the effective of charger Management and control, such as realize time-of-use tariffs charging strategy and reduce charger harmonic current.
The method of work of the electric automobile battery charger running control circuit of the present invention, including:
Step (1):The charging current signal collected is sent in first comparator by charging current signal Acquisition Circuit, First comparator by the charging current signal of reception compared with the current threshold that current threshold input circuit exports, if the former is more than Or equal to the latter, then high level signal is exported to logical AND non-device;Otherwise, low level signal is exported to logical AND non-device;
Step (2):Charger puts into moment pulse signal input circuit and charger input time-ofday signals is sent to second In comparator, the second comparator is defeated by the charger input time-ofday signals of reception and input moment threshold value pulse signal input circuit The input moment threshold value comparison gone out, if the former is greater than or equal to the latter, output high level signal to logical AND non-device;It is no Then, low level signal is exported to logical AND non-device;
Step (3):Charger operation, which allows signal input circuit to run charger, to be allowed signal to be sent to logical AND non- Device;
Step (4):Logical AND non-device carries out logical process to received signal, when logical AND non-device received signal It is high level signal, then exports trigger signal to control the closure of breaker, charger work;Otherwise, trigger signal is exported To control the opening of breaker, charger does not work;
Wherein, the order of step (1), step (2) and step (3) can be replaced arbitrarily.
The present invention relies on the switching of breaker, realizes the input of charger and cuts out.Three tunnel control input data are set with, As source or specific data signal;First via input data is charging current compared with 0.015C as a result, wherein C represents that battery is total Capacity;Second tunnel input data puts into the moment for charger;3rd tunnel input data represents the number of units of input charger.
The technical solution of the present invention is verified using emulation below:
In PSCAD environment, control planning, first via input parameter charging are reflected by electric operation control circuit figure various logic door Machine signal out of service represents with A, actual charge current y2Compared with 0.015C, work as y2During < 0.015C, A 0, works as y2≥ During 0.015C, A 1.
Second tunnel inputs parameter and is represented with B, T1Represent the input moment of charging station parameter setting, the moment is according to peak-trough electricity Determined in valency and charging station with overall height peak time, usual B puts into signal for charger in charging station, when program runs to charging Stand the T1 set in Parameter Set element when, signal B is 1, thus controls the input moment of charger.
3rd tunnel input parameter represented with control Matrix C, each charger accessed in charging station, if putting into operation this C is 1, and it is 0 that the charger, which corresponds to C, if out of service, to sum up, can be each by charging station parameter matrix C, setting member, control Charger puts into operation.
Finally by whether logic gate control breaker, only when three tunnel input signal A, B, C are 1, for controlling The signal BRK of breaker, is at this time 0, breaker closing;Otherwise, as long as three conditions have one to be unsatisfactory for, breaker will become Off-state.
In Simulation simulated environment, it is assumed that one operation charging station, stand in have 64 chargers.Can be to charger All kinds of parameter settings, including input moment, initial capacity, battery basic parameter, input number of units etc..Actual bus charging station fills The electric time has a certain rule, and Qingdao Xue Jiadao fills that to change the integrated Demonstration Station charge data statistics of storage as follows.
1 electric bus of table, 10 days charging load measurement data units:MW
On the basis of the actual data analysis to being completed and putting into effect, using least square method, carry out curve fitting Obtain the load curve of charging station.Bus charging station peak period has twice, and one is at night (20:00~05:00), both right and wrong Service time is again using time-of-use tariffs;Another peak period is noon (10:00~14:00).
According to above charging station data, the present invention can be applied to be controlled above public transport charging station.
Although above-mentioned be described the embodiment of the present invention with reference to attached drawing, model not is protected to the present invention The limitation enclosed, those skilled in the art should understand that, on the basis of technical scheme, those skilled in the art are not Need to make the creative labor the various modifications that can be made or deformation still within protection scope of the present invention.

Claims (2)

1. a kind of method of work of circuit breaker control circuit, it is characterised in that it is non-that the circuit breaker control circuit includes logical AND Device, input terminal and the charging current judgment module and charger input moment judgment module difference phase of the logical AND non-device Even;
The charging current judgment module includes first comparator, the first input end of the first comparator and the second input terminal It is connected respectively with charging current signal Acquisition Circuit and current threshold input circuit, the first comparison circuit will receive signal progress Relatively and high level signal or low level signal are exported to logical AND non-device;
The charger input moment judgment module includes the second comparator, the first input end and second of second comparator Input terminal puts into moment pulse signal input circuit with charger respectively and input moment threshold value pulse signal input circuit is connected, Second comparison circuit will receive signal and be compared and export high level signal or low level signal is to logical AND non-device;Institute State logical AND non-device and logical process is carried out to received signal, export trigger signal to control the opening and closing of breaker;
The circuit breaker control circuit, which further includes charger operation, allows signal input circuit;The charger operation allows signal Input circuit output charger operation allows signal, is sent to logical AND non-device;The charger operation allows signal for height Level signal or low level signal;
The method of work of the circuit breaker control circuit, including:
Step (1):The charging current signal collected is sent in first comparator by charging current signal Acquisition Circuit, and first Comparator by the charging current signal of reception compared with the current threshold that current threshold input circuit exports, if the former is more than or waits In the latter, then high level signal is exported to logical AND non-device;Otherwise, low level signal is exported to logical AND non-device;
Step (2):Charger input time-ofday signals are sent to second and compared by charger input moment pulse signal input circuit In device, the second comparator exports the charger input time-ofday signals of reception with putting into moment threshold value pulse signal input circuit Moment threshold value comparison is put into, if the former is greater than or equal to the latter, output high level signal to logical AND non-device;Otherwise, it is defeated Go out low level signal to logical AND non-device;
Step (3):Charger operation, which allows signal input circuit to run charger, allows signal to be sent to logical AND non-device;
Step (4):Logical AND non-device carries out logical process to received signal, when logical AND non-device received signal is High level signal, then export trigger signal to control the closure of breaker;Otherwise, trigger signal is exported to control beating for breaker Open;Wherein, the order of step (1), step (2) and step (3) can be replaced arbitrarily.
A kind of 2. method of work of electric automobile battery charger running control circuit, it is characterised in that the electric automobile battery charger Running control circuit includes circuit breaker control circuit, and the circuit breaker control circuit includes logical AND non-device, described to patrol Collect and be respectively connected with the input terminal of non-device and charging current judgment module and charger input moment judgment module;
The charging current judgment module includes first comparator, the first input end of the first comparator and the second input terminal It is connected respectively with charging current signal Acquisition Circuit and current threshold input circuit, the first comparison circuit will receive signal progress Relatively and high level signal or low level signal are exported to logical AND non-device;
The charger input moment judgment module includes the second comparator, the first input end and second of second comparator Input terminal puts into moment pulse signal input circuit with charger respectively and input moment threshold value pulse signal input circuit is connected, Second comparison circuit will receive signal and be compared and export high level signal or low level signal is to logical AND non-device;Institute State logical AND non-device and logical process is carried out to received signal, export trigger signal to control the opening and closing of breaker;
The circuit breaker control circuit, which further includes charger operation, allows signal input circuit;The charger operation allows signal Input circuit output charger operation allows signal, is sent to logical AND non-device;The charger operation allows signal for height Level signal or low level signal;
The method of work of the electric automobile battery charger running control circuit, including:
Step (1):The charging current signal collected is sent in first comparator by charging current signal Acquisition Circuit, and first Comparator by the charging current signal of reception compared with the current threshold that current threshold input circuit exports, if the former is more than or waits In the latter, then high level signal is exported to logical AND non-device;Otherwise, low level signal is exported to logical AND non-device;
Step (2):Charger input time-ofday signals are sent to second and compared by charger input moment pulse signal input circuit In device, the second comparator exports the charger input time-ofday signals of reception with putting into moment threshold value pulse signal input circuit Moment threshold value comparison is put into, if the former is greater than or equal to the latter, output high level signal to logical AND non-device;Otherwise, it is defeated Go out low level signal to logical AND non-device;
Step (3):Charger operation, which allows signal input circuit to run charger, allows signal to be sent to logical AND non-device;
Step (4):Logical AND non-device carries out logical process to received signal, when logical AND non-device received signal is High level signal, then export trigger signal to control the closure of breaker, charger work;Otherwise, trigger signal is exported to control The opening of breaker processed, charger do not work;
Wherein, the order of step (1), step (2) and step (3) can be replaced arbitrarily.
CN201610318756.XA 2016-05-12 2016-05-12 Circuit breaker control circuit, electric automobile battery charger running control circuit and method Active CN105932732B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610318756.XA CN105932732B (en) 2016-05-12 2016-05-12 Circuit breaker control circuit, electric automobile battery charger running control circuit and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610318756.XA CN105932732B (en) 2016-05-12 2016-05-12 Circuit breaker control circuit, electric automobile battery charger running control circuit and method

Publications (2)

Publication Number Publication Date
CN105932732A CN105932732A (en) 2016-09-07
CN105932732B true CN105932732B (en) 2018-05-04

Family

ID=56834995

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610318756.XA Active CN105932732B (en) 2016-05-12 2016-05-12 Circuit breaker control circuit, electric automobile battery charger running control circuit and method

Country Status (1)

Country Link
CN (1) CN105932732B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106772006A (en) * 2016-12-13 2017-05-31 四川赛科安全技术有限公司 A kind of circuit and its diagnostic method of automatic diagnosis manual pull station failure
CN107122553B (en) * 2017-05-02 2021-11-05 国网山东省电力公司电力科学研究院 Charger harmonic characteristic analysis simulation method considering random characteristic
CN112491010B (en) * 2020-12-02 2023-03-28 上海力申科学仪器有限公司 Oil pump motor real-time monitoring circuit and monitoring method thereof
CN113791341B (en) * 2021-09-14 2024-04-09 云南电网有限责任公司电力科学研究院 Component switching state discrimination system based on electric quantity and switching information

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105514939A (en) * 2016-01-18 2016-04-20 中国石油大学(北京) Charging and discharging control device and control method for energy storage super-capacitor of electric workover rig

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20150015140A (en) * 2013-07-31 2015-02-10 정덕영 Charging and discharging control circuit for battery device

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105514939A (en) * 2016-01-18 2016-04-20 中国石油大学(北京) Charging and discharging control device and control method for energy storage super-capacitor of electric workover rig

Also Published As

Publication number Publication date
CN105932732A (en) 2016-09-07

Similar Documents

Publication Publication Date Title
CN105932732B (en) Circuit breaker control circuit, electric automobile battery charger running control circuit and method
CN102208815B (en) Household multi-energy system and control method thereof
CN104218875B (en) Independent photovoltaic generating railway power supply control system and control method thereof
CN103227491B (en) For the data acquisition of electric vehicle lithium battery group and energy balance control device and method
CN204012834U (en) A kind of lithium iron phosphate dynamic battery management system
CN104810894A (en) Split type direct-current charging piles for electric automobiles, system and method
CN203232115U (en) FTU on-site tester using storage battery for power supply
CN109301850A (en) A kind of novel energy-storing system experimental platform and working method
CN103401262A (en) Wind power and battery energy storage hybrid power station as well as capacity-determining off-line simulation and on-line operation method for energy storage system
CN103066679A (en) Universal communication base station solar and wind energy centralized power supply system and control method thereof
CN207173346U (en) Anti-overcharge device applied to intelligent charging spot
CN205017073U (en) Electric automobile flexibility machine that charges
CN202471925U (en) Test system for high-voltage battery pack
CN203339742U (en) Switch for charging and discharging electric automobile and control circuit thereof
CN103219552B (en) Device for detection maintenance and balanced maintenance of power battery pack
CN202586386U (en) An inspection and maintenance and equalizing maintenance device of motive power battery pack
CN206976517U (en) A kind of on-Line Monitor Device based on cell batteries
CN205657475U (en) Circuit breaker control circuit and electric vehicle charger operation control circuit
CN204441972U (en) Multifunctional vehicle mounted charge control system
CN205960736U (en) Stereo garage's alternating -current charging stake control system
CN204886310U (en) Lithium battery management system based on ARM
CN202918019U (en) Lithium ion power battery emergency power supply unit
CN204883824U (en) Bidirectional metering power consumption management system
CN209037420U (en) A kind of Intelligent charging system of electric automobile
CN203069761U (en) Battery formation detecting system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant