CN105929225A - Method for acquiring on-grid and off-grid electric quantities - Google Patents

Method for acquiring on-grid and off-grid electric quantities Download PDF

Info

Publication number
CN105929225A
CN105929225A CN201610561981.6A CN201610561981A CN105929225A CN 105929225 A CN105929225 A CN 105929225A CN 201610561981 A CN201610561981 A CN 201610561981A CN 105929225 A CN105929225 A CN 105929225A
Authority
CN
China
Prior art keywords
electricity
line
summation
reverse
volume
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610561981.6A
Other languages
Chinese (zh)
Inventor
潘沪明
曾智健
杨威
肖苑
毛莉萍
罗序良
王鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Power Grid Co Ltd
Original Assignee
Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Power Grid Co Ltd filed Critical Guangdong Power Grid Co Ltd
Priority to CN201610561981.6A priority Critical patent/CN105929225A/en
Publication of CN105929225A publication Critical patent/CN105929225A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R22/00Arrangements for measuring time integral of electric power or current, e.g. electricity meters

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a method for acquiring on-grid and off-grid electric quantities. The method includes reading all gauges on circuits from automatic metering systems in each preset time interval once to obtain reading data of all the gauges; computing the sums of forward electric quantities of all the gauges and the sums of reverse electric quantities of all the gauges; comparing the sums of the forward electric quantities to the sums of the reverse electric quantities and computing the on-grid electric quantities and the off-grid electric quantities according to comparison results. The forward electric quantities of all the gauges and the reverse electric quantities of all the gauges are acquired in preset time. The method has the advantage that the accuracy of the obtained on-grid and off-grid electric quantities can be enhanced by the aid of the method.

Description

Off line electricity acquisition methods in one
Technical field
The present invention relates to technical field of electric power, particularly relate to off line electricity acquisition methods in one.
Background technology
At present, power plant's electricity volume and off line electricity clearing critical point are the most all to arrange by assets separation, a kind of situation It is typically all to be located at power plant to uprise side and take online, off line electricity mutual as electricity clearing during clearing critical point, normal power generation Electricity volume of only sending after counteracting settles accounts the online electricity charge, and full factory shuts down during not generating electricity and can not cancel each other with net electricity;Another Kind of situation is that clearing critical point is located at power plant and sends on circuit, by having more than two that sends circuit and power plant's bus to pass through trend Cannot calculate, can only be by the forward in the cycle of checking meter, reverse electric quantity accumulation, after aggregate-value is supported mutually, depending on positive and negative values as settling accounts Electricity volume or off line electricity, calculate relatively rough, unreasonable.
Above-mentioned two situations are all failed to measure online, off line electricity the most respectively by current monthly meter reading method. Under normal operating mode, and when not passing through trend on power plant's bus, it is arranged on the energy metering dress that power plant sends on circuit Put forward, reverse electricity can accurately measure online and off line electricity, but actually due between transformer station or the power plant that has Can be surfed the Net by other power plant (or unit) bus, now will pass through tide as producing on power plant's bus in hinge power station Stream, and energy metering device cannot be distinguished by passing through electricity, electricity volume and off line electricity, causes cannot accurately drawing online electricity Amount, off line electricity, it is impossible to the problem of measuring power settlement of transactions accurate, fair and reasonable.
Summary of the invention
It is an object of the invention to provide off line electricity acquisition methods in one, to realize the upper off line electricity of lifting acquisition Accuracy.
For solving above-mentioned technical problem, the present invention provides off line electricity acquisition methods in one, and the method includes:
In each prefixed time interval, to the gauge table meter reading on the line of all dresses from metering automation system Once, it is thus achieved that the meter reading data of all gauge tables;
The summation of the forward electricity of all gauge tables obtained in calculating Preset Time and the reverse electricity of all gauge tables Summation;
The summation of contrast forward electricity and the summation of reverse electricity, calculate electricity volume and off line electricity according to comparing result Amount.
Preferably, in the meter reading data of gauge table from the output of power plant direction for forward electricity, to power plant's direction input For reverse electricity.
Preferably, described in each prefixed time interval, from metering automation system to all dresses on the line Gauge table meter reading once, it is thus achieved that the meter reading data of all gauge tables, including:
Each prefixed time interval j from metering automation system, to n the gauge table meter reading on the line of all dresses Once, obtaining X1 to Xn, Y1 to Yn data and preserve, n is more than or equal to 2.
Preferably, the summation of the forward electricity of all gauge tables obtained in described calculating Preset Time and all gauge tables The summation of reverse electricity, including:
To a prefixed time interval j, obtain forward electricity Xi, the size of reverse electricity Yi, i=1,2 ..., n;N is meter The number of scale, n is more than or equal to 2;
The summation of the forward electricity Xi obtained in calculating each prefixed time interval jAnd the summation of reverse electricity Yi
Preferably, the summation of described contrast forward electricity and the summation of reverse electricity, calculate online electricity according to comparing result Amount and off line electricity, including:
Calculate the summation of forward electricity and difference Q of reverse electricity summationj,
Judge difference QjPower direction of transfer, according to difference QjPower direction of transfer analysis obtain electricity volume Sj and Off line electricity Cj.
Preferably, according to difference QjPower direction of transfer analysis obtain electricity volume Sj and off line electricity Cj, including:
If Qj> 0, power direction of transfer is output, electricity volume Sj=| Qj|, off line electricity Cj=0;
If Qj=0, electricity all Line Flows electricity, electricity volume Sj=0, off line electricity Cj=0;
If Qj< 0, power direction of transfer is input, electricity volume Sj=0, off line electricity Cj=| Q j |.
Preferably, described method also includes:
In each prefixed time interval, meter reading is once, until a billing cycle terminates, number of times of checking meter is that m, m are more than Equal to 2;
According to electricity volume Sj in a billing cycle, off line electricity Cj, the calculating accounting period copies and sees electricity volume, clearing Phase copies and sees below net electricity.
Preferably, the accounting period copies and seesAccounting period copies and sees
Off line electricity acquisition methods in one provided by the present invention, in each prefixed time interval, from metering certainly In dynamicization system to the gauge table meter reading on the line of all dresses once, it is thus achieved that the meter reading data of all gauge tables;Calculate and preset The summation of the forward electricity of all gauge tables obtained in the time and the summation of the reverse electricity of all gauge tables;Contrast forward electricity The summation of amount and the summation of reverse electricity, calculate electricity volume and off line electricity according to comparing result.Visible, utilize metering automatically Change system short time interval meter reading function once, the summation of contrast forward electricity and the summation of reverse electricity, according to contrast knot Fruit calculates electricity volume and off line electricity, and in such time in counting period, forward electricity and the reverse electricity of gauge table cancel each other After the sign of clean power transmission amount, i.e. differentiate the direction that power transmits, discriminate whether that full factory shuts down with this and do not generate electricity, pass through tide Stream, by supporting mutually rear to forward and reverse electricity that adds up at times as the online of final clearing, off line electricity, checks meter once than monthly The metering clearing carrying out differentiating are the most accurate, reasonable, fair, realize upper off line electricity accurate of lifting acquisition in this way Property.
Accompanying drawing explanation
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing In having technology to describe, the required accompanying drawing used is briefly described, it should be apparent that, the accompanying drawing in describing below is only this Inventive embodiment, for those of ordinary skill in the art, on the premise of not paying creative work, it is also possible to according to The accompanying drawing provided obtains other accompanying drawing.
Fig. 1 is the flow chart of a kind of off line electricity acquisition methods provided by the present invention.
Detailed description of the invention
The core of the present invention is to provide off line electricity acquisition methods in one, it is achieved promote the standard of the upper off line electricity obtained Really property.
In order to make those skilled in the art be more fully understood that the present invention program, below in conjunction with in the embodiment of the present invention Accompanying drawing, is clearly and completely described the technical scheme in the embodiment of the present invention, it is clear that described embodiment is only The a part of embodiment of the present invention rather than whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art The every other embodiment obtained under not making creative work premise, broadly falls into the scope of protection of the invention.
Refer to the flow chart that Fig. 1, Fig. 1 are a kind of off line electricity acquisition methods provided by the present invention, the method bag Include:
S11: in each prefixed time interval, to all dresses gauge table on the line from metering automation system Meter reading is once, it is thus achieved that the meter reading data of all gauge tables;
S12: calculate the summation of the forward electricity of the interior all gauge tables obtained of Preset Time and the reverse of all gauge tables The summation of electricity;
S13: the summation of summation and the reverse electricity of contrast forward electricity, calculates electricity volume and off line according to comparing result Electricity.
Visible, utilize metering automation system short time interval meter reading function once, the summation of contrast forward electricity with The reversely summation of electricity, calculates electricity volume and off line electricity, gauge table in such time in counting period according to comparing result Forward electricity and reverse electricity cancel each other after the sign of clean power transmission amount, i.e. differentiate the direction that power transmits, differentiate with this Full factory shuts down and does not generates electricity, passes through trend, by supporting rear mutually to upper as final clearing of forward and reverse electricity that adds up at times Net, off line electricity, the most accurate, reasonable, more fair than the monthly metering clearing once carrying out differentiating of checking meter, realize in this way Promote the accuracy of the upper off line electricity obtained.
Concrete, in the meter reading data of gauge table from power plant's direction output for forward electricity, to power plant's direction input For reverse electricity.
Wherein, the process of step S11 particularly as follows: from metering automation system each prefixed time interval j, to all Dress n gauge table meter reading on the line once, obtains X1 to Xn, Y1 to Yn data and preserves, and n is more than or equal to 2.
Step S12 preferably employs following steps and realizes:
S21: to a prefixed time interval j, obtains forward electricity Xi, the size of reverse electricity Yi, i=1, and 2 ..., n;n For the number of gauge table, n is more than or equal to 2;
S22: the summation of the forward electricity Xi obtained in calculating each prefixed time interval jAnd reverse electricity Yi Summation
Step S13 preferably employs following steps and realizes:
S31: the summation of summation and the reverse electricity of contrast forward electricity, calculates electricity volume and off line according to comparing result Electricity, including:
S32: calculate the summation of forward electricity and difference Q of reverse electricity summationj,
S33: judge difference QjPower direction of transfer, according to difference QjPower direction of transfer analysis obtain electricity volume Sj and off line electricity Cj.
Foundation difference Q in step S33jPower direction of transfer analysis obtain electricity volume Sj and the mistake of off line electricity Cj Journey preferably employs following steps and realizes:
S41: if Qj> 0, power direction of transfer is output, electricity volume Sj=| Qj|, off line electricity Cj=0;
S42: if Qj=0, electricity all Line Flows electricity, electricity volume Sj=0, off line electricity Cj=0;
S43: if Qj< 0, power direction of transfer is input, electricity volume Sj=0, off line electricity Cj=| Q j |.
Concrete, said method is further comprising the steps of:
S14: meter reading is once in each prefixed time interval, until a billing cycle terminates, number of times of checking meter is m, m More than or equal to 2;
S15: according to electricity volume Sj in a billing cycle, off line electricity Cj, calculate the accounting period copy see electricity volume, Accounting period copies and sees below net electricity.
Wherein, the accounting period copies and seesAccounting period copies and sees
Said method utilizes metering automation system to read the function of gauge table in real time, and calculating forward, reverse electricity are mutual The sign of the clean power transmission amount after counteracting, determines the direction that this short term power transmits at that time, discriminates whether that full factory shuts down not with this Generating, pass through trend, see online electricity to the forward electricity that adds up at times, reverse electricity as copying of final clearing by supporting mutually rear Amount, copy and see below net electricity.
Based on said method, detailed, specific implementation process is as follows:
Step 1: the expression number electricity arranging gauge table is output as forward electricity X from power plant direction, to power plant's direction input For reverse electricity Y.
Step 2: obtain and preserve data.
Each short time interval j from metering automation system, the most every five minutes, to all dresses n on the line Individual gauge table meter reading once, obtains X1j to Xnj, Y1j to Ynj data and preserves.
Step 3: comparing.
To a short time every j, contrast respectively the forward electricity Xij of acquisition, reverse electricity Yij size (i=1, 2 ..., n), the direction transmitted according to the size differentiation power of data:
Q j = Σ i = 1 n X i - Σ i = 1 n Y i ;
If Q is j > 0, Q j is on the occasion of, general power direction was output at that time, electricity volume Sj=| Q j |, off line electricity Cj=0;
If Q is j=0, Q j is 0 value, the most all Line Flow electricity, electricity volume Sj=0, off line electricity Cj= 0;
If Q is j, < 0, Q j is negative value, and general power direction was input, electricity volume Sj=0, off line electricity Cj=at that time |Q j|。
To a short time every j, preserve the difference of both direction electricity, if the difference of electricity be on the occasion of, save as electricity volume Sj, if the difference of electricity is negative value, saves as off line electricity Cj, all takes Q j absolute value.
Step 4: repeat the step of above-mentioned 2 to 3, until the end of a billing cycle, all number of times of checking meter are m.
Step 5: add up respectively.
Cumulative for electricity volume Sj in one billing cycle, off line electricity Cj being added up, aggregate-value respectively copies see upper Net electricity, copy the off line electricity seen, as follows:
Visible, utilize the metering automation system short time every the most every five points of kinds, at most 15 minutes, meter reading merit once Can, counting period online, off line electricity cancel each other after the sign of clean power transmission amount, i.e. differentiate the side that this short term power transmits To, discriminate whether that full factory shuts down with this and do not generate electricity, pass through trend, by supporting rear mutually to forward and reverse electricity that adds up at times as The online that termination is calculated, off line electricity, the most accurate, reasonable, more fair than the monthly metering clearing once carrying out differentiating of checking meter.
To sum up, off line electricity acquisition methods in one provided by the present invention, in each prefixed time interval, from meter In amount automated system to the gauge table meter reading on the line of all dresses once, it is thus achieved that the meter reading data of all gauge tables;Calculate The summation of the forward electricity of all gauge tables obtained in Preset Time and the summation of the reverse electricity of all gauge tables;Contrast is just To the summation of the summation of electricity Yu reverse electricity, calculate electricity volume and off line electricity according to comparing result.Visible, utilize metering Automated system short time interval meter reading function once, the summation of contrast forward electricity and the summation of reverse electricity, according to right Calculating electricity volume and off line electricity than result, in such time in counting period, forward electricity and the reverse electricity of gauge table are mutual The sign of the clean power transmission amount after counteracting, i.e. differentiates the direction that power transmits, and discriminates whether that the shutdown of full factory does not generates electricity, passes through with this Trend, by supporting mutually rear to forward and reverse electricity that adds up at times as the online of final clearing, off line electricity, checks meter one than monthly The secondary metering clearing carrying out differentiating are the most accurate, reasonable, fair, realize promoting the standard of the upper off line electricity obtained in this way Really property.
Above electricity acquisition methods off line in one provided by the present invention is described in detail.Used herein Principle and the embodiment of the present invention are set forth by specific case, and the explanation of above example is only intended to help to understand this The method of invention and core concept thereof.It should be pointed out that, for those skilled in the art, without departing from this On the premise of bright principle, it is also possible to the present invention is carried out some improvement and modification, these improve and modification also falls into present invention power In the protection domain that profit requires.

Claims (8)

1. a upper off line electricity acquisition methods, it is characterised in that including:
In each prefixed time interval, to the gauge table meter reading one on the line of all dresses from metering automation system Secondary, it is thus achieved that the meter reading data of all gauge tables;
Calculate the total of the summation of the forward electricity of all gauge tables obtained in Preset Time and the reverse electricity of all gauge tables With;
The summation of contrast forward electricity and the summation of reverse electricity, calculate electricity volume and off line electricity according to comparing result.
2. the method for claim 1, it is characterised in that export from power plant direction in the meter reading data of gauge table is just To electricity, to power plant's direction input for reverse electricity.
3. the method for claim 1, it is characterised in that described in each prefixed time interval, from metering automatically In change system to the gauge table meter reading on the line of all dresses once, it is thus achieved that the meter reading data of all gauge tables, including:
Each prefixed time interval j from metering automation system, to n the gauge table meter reading one on the line of all dresses Secondary, obtain X1 to Xn, Y1 to Yn data and preserve, n is more than or equal to 2.
4. the method for claim 1, it is characterised in that all gauge tables obtained in described calculating Preset Time are just To the summation of electricity and the summation of the reverse electricity of all gauge tables, including:
To a prefixed time interval j, obtain forward electricity Xi, the size of reverse electricity Yi, i=1,2 ..., n;N is gauge table Number, n be more than or equal to 2;
The summation of the forward electricity Xi obtained in calculating each prefixed time interval jAnd the summation of reverse electricity Yi
5. method as claimed in claim 4, it is characterised in that the summation of described contrast forward electricity is total with reverse electricity With, calculate electricity volume and off line electricity according to comparing result, including:
Calculate the summation of forward electricity and difference Q of reverse electricity summationj,Judge difference QjPower Direction of transfer, according to difference QjPower direction of transfer analysis obtain electricity volume Sj and off line electricity Cj.
6. method as claimed in claim 5, it is characterised in that according to difference QjPower direction of transfer analysis obtain online electricity Amount Sj and off line electricity Cj, including:
If Qj> 0, power direction of transfer is output, electricity volume Sj=| Qj|, off line electricity Cj=0;
If Qj=0, electricity all Line Flows electricity, electricity volume Sj=0, off line electricity Cj=0;
If Qj< 0, power direction of transfer is input, electricity volume Sj=0, off line electricity Cj=| Qj |.
7. the method as described in any one in claim 1 to 6, it is characterised in that also include:
In each prefixed time interval, meter reading is once, until a billing cycle terminates, number of times of checking meter is that m, m are more than or equal to 2;
According to electricity volume Sj in a billing cycle, off line electricity Cj, the calculating accounting period copies and sees that electricity volume, accounting period copy See below net electricity.
8. method as claimed in claim 7, it is characterised in that the accounting period copies and sees Accounting period copies and sees
CN201610561981.6A 2016-07-13 2016-07-13 Method for acquiring on-grid and off-grid electric quantities Pending CN105929225A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610561981.6A CN105929225A (en) 2016-07-13 2016-07-13 Method for acquiring on-grid and off-grid electric quantities

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610561981.6A CN105929225A (en) 2016-07-13 2016-07-13 Method for acquiring on-grid and off-grid electric quantities

Publications (1)

Publication Number Publication Date
CN105929225A true CN105929225A (en) 2016-09-07

Family

ID=56827400

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610561981.6A Pending CN105929225A (en) 2016-07-13 2016-07-13 Method for acquiring on-grid and off-grid electric quantities

Country Status (1)

Country Link
CN (1) CN105929225A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107785928A (en) * 2017-09-19 2018-03-09 福建福清核电有限公司 A kind of method for measuring multicomputer nuclear power station generated energy
CN109637109A (en) * 2018-12-11 2019-04-16 国家电网有限公司 A kind of method that electric quantity data acquisition passes through in power plant
CN110824242A (en) * 2019-10-25 2020-02-21 国网四川省电力公司成都供电公司 Metering method and system for eliminating ride-through power
CN112014634A (en) * 2020-08-21 2020-12-01 国核电力规划设计研究院重庆有限公司 Multi-loop bidirectional dynamic electric energy metering device and method
CN112398162A (en) * 2020-10-13 2021-02-23 国网甘肃省电力公司嘉峪关供电公司 Multi-power-supply centralized bundling internet-surfing electric energy settlement method
CN113125848A (en) * 2021-03-10 2021-07-16 国家电网有限公司华东分部 Method and system for measuring through electric quantity of power supply plant and method for settling electric quantity
CN114137300A (en) * 2021-11-22 2022-03-04 西安热工研究院有限公司 Metering system and method for offshore wind farm gateway of shared switching station
CN114236229A (en) * 2021-11-24 2022-03-25 国网山东省电力公司日照供电公司 Metering method of settlement electric quantity for power plant
CN115967120A (en) * 2023-01-10 2023-04-14 国网湖南省电力有限公司 220 KV power grid network access substation judgment method and capacity-to-load ratio calculation method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1680817A (en) * 2005-01-31 2005-10-12 南京迪玛斯电气有限公司 Metering and charging system of electric energy amount
CN101714234A (en) * 2009-10-23 2010-05-26 西北电网有限公司 Grid line loss monitoring and analyzing system
CN102054130A (en) * 2010-12-31 2011-05-11 江苏省电力公司 System for visual configuration of power formula
US20110285382A1 (en) * 2010-05-18 2011-11-24 General Electric Company Power meter phase identification
CN103513085A (en) * 2013-09-29 2014-01-15 国家电网公司 Current transformer capable of switching transformation ratios for metering off-grid energy of wind power plants

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1680817A (en) * 2005-01-31 2005-10-12 南京迪玛斯电气有限公司 Metering and charging system of electric energy amount
CN101714234A (en) * 2009-10-23 2010-05-26 西北电网有限公司 Grid line loss monitoring and analyzing system
US20110285382A1 (en) * 2010-05-18 2011-11-24 General Electric Company Power meter phase identification
CN102054130A (en) * 2010-12-31 2011-05-11 江苏省电力公司 System for visual configuration of power formula
CN103513085A (en) * 2013-09-29 2014-01-15 国家电网公司 Current transformer capable of switching transformation ratios for metering off-grid energy of wind power plants

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
唐小川: "适应智能电网的计量自动化系统实施体现", 《企业技术开发》 *
陈晔 等: "广东电网省级集中式电能计量自动化系统建设", 《广东电力》 *
高利明 等: "发电厂上下网电量关口计量点设置与计算方法研究", 《河北电力技术》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107785928A (en) * 2017-09-19 2018-03-09 福建福清核电有限公司 A kind of method for measuring multicomputer nuclear power station generated energy
CN107785928B (en) * 2017-09-19 2019-10-22 福建福清核电有限公司 A method of metering multicomputer nuclear power station generated energy
CN109637109A (en) * 2018-12-11 2019-04-16 国家电网有限公司 A kind of method that electric quantity data acquisition passes through in power plant
CN110824242A (en) * 2019-10-25 2020-02-21 国网四川省电力公司成都供电公司 Metering method and system for eliminating ride-through power
CN112014634A (en) * 2020-08-21 2020-12-01 国核电力规划设计研究院重庆有限公司 Multi-loop bidirectional dynamic electric energy metering device and method
CN112014634B (en) * 2020-08-21 2024-02-09 国核电力规划设计研究院重庆有限公司 Multi-loop bidirectional dynamic electric energy metering device and method
CN112398162A (en) * 2020-10-13 2021-02-23 国网甘肃省电力公司嘉峪关供电公司 Multi-power-supply centralized bundling internet-surfing electric energy settlement method
CN113125848A (en) * 2021-03-10 2021-07-16 国家电网有限公司华东分部 Method and system for measuring through electric quantity of power supply plant and method for settling electric quantity
CN114137300A (en) * 2021-11-22 2022-03-04 西安热工研究院有限公司 Metering system and method for offshore wind farm gateway of shared switching station
CN114137300B (en) * 2021-11-22 2024-01-19 西安热工研究院有限公司 System and method for metering gateway of offshore wind farm of shared switching station
CN114236229A (en) * 2021-11-24 2022-03-25 国网山东省电力公司日照供电公司 Metering method of settlement electric quantity for power plant
CN115967120A (en) * 2023-01-10 2023-04-14 国网湖南省电力有限公司 220 KV power grid network access substation judgment method and capacity-to-load ratio calculation method

Similar Documents

Publication Publication Date Title
CN105929225A (en) Method for acquiring on-grid and off-grid electric quantities
CN106569164A (en) Method and system for synchronization testing of electric quantity of double-core electric energy meter
CN104765945A (en) Device failure rate detecting method based on quantity confidence coefficient
CN101806876A (en) Electronic type transformer checking system
CN101958544A (en) System and method for calculating line loss rate of electric power distribution line
CN104483650B (en) A kind of correction method of ammeter
CN106251236A (en) A kind of electricity electricity charge checking method
CN103424734A (en) On-line calibration method of electronic watt-hour meter
CN107944680A (en) A kind of substation&#39;s electric energy balance monitoring method based on intelligent electric energy meter
CN102081143B (en) Estimation method and system of battery capacity
CN108646089A (en) Power consumption calculation method and device and electronic equipment
CN106918737A (en) A kind of method and reactive power detection device for detecting power network dynamic reactive power
CN204154892U (en) A kind of device for energy meter standard automatic verification system
CN102200544A (en) Method for accumulating aggregate capacitances of smart meter capable of realizing bidirectional metering
CN108320081A (en) A kind of meter reading business datum analysis and processing method and system based on automation
CN203037770U (en) Multifunctional on-line electricity consumption tester
CN102682212B (en) Reliability measurement method for mechanical and electrical product
CN202815204U (en) A verification system for alternating current instrument inspection devices
CN106526305B (en) It is a kind of for judging the phasor analysis device of three-phase second loop return wiring correctness
CN101762771B (en) Wiring analysis method for bus differential protecting CT loop in electric system
CN109541520A (en) The split-phase calculating method of electric energy metering device failure wrong electric energy
CN117455418A (en) Automatic settlement method and system for industrial and commercial photovoltaic benefits
CN115575884B (en) Method for aligning charging quantity of charging piles in charging station and calculating metering error
CN205450247U (en) Watt -hour meter calibrating
CN104101856A (en) Method and device for detecting error of electronic measurement unit of zero-flux DC (Direct Current) current transformer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160907