CN105926965B - One kind building provisions for grouting - Google Patents

One kind building provisions for grouting Download PDF

Info

Publication number
CN105926965B
CN105926965B CN201610309856.6A CN201610309856A CN105926965B CN 105926965 B CN105926965 B CN 105926965B CN 201610309856 A CN201610309856 A CN 201610309856A CN 105926965 B CN105926965 B CN 105926965B
Authority
CN
China
Prior art keywords
shower nozzle
grouting
sliding block
rotation drive
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610309856.6A
Other languages
Chinese (zh)
Other versions
CN105926965A (en
Inventor
王如军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Ronglian Project Management Co.,Ltd.
Original Assignee
王如军
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 王如军 filed Critical 王如军
Priority to CN201610309856.6A priority Critical patent/CN105926965B/en
Publication of CN105926965A publication Critical patent/CN105926965A/en
Application granted granted Critical
Publication of CN105926965B publication Critical patent/CN105926965B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0203Arrangements for filling cracks or cavities in building constructions
    • E04G23/0211Arrangements for filling cracks or cavities in building constructions using injection

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Nozzles (AREA)

Abstract

One kind building provisions for grouting, for building gap(1)It is in the milk, including pedestal(9)And pass through supporting device for sluing mechanisms(88)And with the pedestal(9)Rear wall connection nozzle connecting device(8), wherein, the nozzle connecting device(8)Including clamping cavity with slip(80)Sprinkler rotation drive shell(89), it is described to slide clamping cavity(80)In be sliding combined with shower nozzle motion driving sliding block(6).

Description

One kind building provisions for grouting
Technical field
It is specially a kind of building provisions for grouting the present invention relates to building field.
Background technology
It is overall to strengthen building in building field, it usually needs to being in the milk at the gap or gap of building Steadiness and avoid the later stage of building from damaging.The length in these gaps is often shorter but quantity is more, therefore is unsuitable for The walking mechanism of long stroke carries out automatic filling.Can be using the gap perfusion for waving reciprocating perfusion progress short stroke.But, This has the following problems.Because the bearing of trend in gap is straight longitudinally, and it is then circular arc to wave reciprocating Shape, this causes the perfusion distance for gap(Irrigate the spacing between shower nozzle and gap)Change.Perfusion beginning and At the end of irrigate it is in larger distance and perfusion centre position perfusion it is in small distance.This gives the behaviour of pouring quality and filling process Cause difficulty.
The content of the invention
Provisions for grouting is built it is an object of the invention to provide one kind, for overcoming drawbacks described above of the prior art.
According to the present invention, one kind building provisions for grouting, for being in the milk to building gap, including pedestal and passing through revolves The nozzle connecting device for turning supporting arrangement and being connected with the rear wall of the pedestal, wherein, the nozzle connecting device includes having Slide and shower nozzle motion driving sliding block be sliding combined with the sprinkler rotation drive shell of clamping cavity, the slip clamping cavity, The fluid passage that fore-and-aft direction extension is provided with the shower nozzle motion driving sliding block is used to connect with grouting Showerhead Fluid, described Control valve for fluids is provided with grouting shower nozzle, the control valve for fluids is to control the grouting shower nozzle to export the output of grouting Amount, controls the output quantity of the grouting shower nozzle output grouting to reach use requirement, the stream so as to selection as needed Body control valve is solenoid electric valve, and the upper side of the shower nozzle motion driving sliding block located at described by sliding in clamping cavity Top pressure spring and by compress effect so as to using rotation be installed on the shower nozzle move drive sliding block downside and one The top pressure roller of the end of the top pressure arm of protrusion is resisted against the interior of the curved profile portion being fixedly arranged at the lower wall of the pedestal On wall, the bottom of the sprinkler rotation drive shell is provided with gear wheel segment to the tooth with being driven by rotating motor Wheel engagement is so as to drive the sprinkler rotation drive shell to rotate, and the rotating motor is fixedly connected with the pedestal, Be horizontally arranged with the case surface of the rotating motor multi-disc radiating fin to increasing heat radiation area and be easy to by The rotating motor operationally produced heat absorption and is dissipated, when preventing that the rotating motor is long Between when running temperature it is too high and burn;Two relative lateral surfaces of the left and right of shower nozzle motion driving sliding block respectively with the cunning Two or so relative medial surfaces in dynamic clamping cavity coordinate slideably by the sprinkler rotation drive shell to be turned Dynamic driving, the front end of the fluid passage extends through the antetheca of the sprinkler rotation drive shell to be connected with grouting source, its In, the curve shape of the internal face in the curved profile portion is oval section, the curved profile portion with the internal face The curve shape of relative outside wall surface is circular segments, thus, when the grouting shower nozzle is in orthogonal with the building gap When on direction, the curved profile portion with the contact position of the top pressure roller at the wall thickness that has be less than the contact position The wall thickness that two side positions put have.
By such scheme, as a result of the shower nozzle motion driving sliding block that can be slided in the lumen, profile portion is utilized Regulation driving left and right, the position that can be lifted up in the oval circular arc relative to outside of inner side(As two ends)Form wall At thick thickening, therefore, it is possible at the beginning and end of perfusion by shower nozzle ejection forward, so as to compensate the shape due to arc swing Into at the beginning and end of shower nozzle perfusion apart from it is excessive the problem of, and can perfusion centre position cause shower nozzle relative Recession, so that perfusion is apart from relatively reduced.
Brief description of the drawings
Fig. 1 is the overall structure diagram of the building provisions for grouting of the present invention;
Fig. 2 is schematic cross-section of the device at arrow locations in Fig. 1.
Embodiment
With reference to Fig. 1-2, the present invention is described in detail.
Building provisions for grouting a kind of according to an embodiment of the invention, for being in the milk to building gap 1, including pedestal 9 and the nozzle connecting device 8 that is connected by supporting device for sluing mechanisms 88 with the rear wall of the pedestal 9, wherein, the shower nozzle connects Connection device 8 includes sliding in the sprinkler rotation drive shell 89 with slip clamping cavity 80, the slip clamping cavity 80 and matched somebody with somebody Conjunction has the fluid passage 60 for being provided with fore-and-aft direction extension in shower nozzle motion driving sliding block 6, the shower nozzle motion driving sliding block 6 to use To be in fluid communication with grouting shower nozzle 66, control valve for fluids 33 is provided with the grouting shower nozzle 66, the control valve for fluids 33 is used It is defeated so as to the selection control grouting shower nozzle 66 as needed to control the grouting shower nozzle 66 to export the output quantity of grouting Go out the output quantity of grouting to reach use requirement, the control valve for fluids 33 is solenoid electric valve, the shower nozzle motion driving is slided The upper side of block 6 located at the top pressure spring 83 slided in clamping cavity 80 by being compressed effect and being rotated so as to utilize It is installed on the top pressure roller 62 of the end for the top pressure arm 61 for moving the downside of driving sliding block 6 in the shower nozzle and integrally protruding It is fixedly arranged on to be resisted against on the internal face 912 in the curved profile portion 91 at the lower wall of the pedestal 9, the sprinkler rotation driving shell The bottom of body 89 is provided with gear wheel segment 81 to engage with the gear 71 driven by rotating motor 72 to drive institute State sprinkler rotation drive shell 89 to rotate, the rotating motor 72 is fixedly connected with the pedestal 9, the rotating is driven Being horizontally arranged with that multi-disc radiating fin 23 is easy to increasing heat radiation area in the case surface of dynamic motor 72 will be described positive and negative Turn motor 72 and operationally produced heat absorption and dissipate, prevent the rotating motor 72 from transporting for a long time Temperature is too high and burn during row;Two lateral surfaces that the left and right of the shower nozzle motion driving sliding block 6 is relative are slided with described respectively Two or so the relative medial surfaces clamped in cavity 80 coordinate so as to slideably by the sprinkler rotation drive shell 89 Driving is rotated, the front end of the fluid passage 60 extends through the antetheca of the sprinkler rotation drive shell 89 with grouting source to connect Connect, wherein, the curve shape of the internal face 912 in the curved profile portion 91 is oval section, the curved profile portion 91 The curve shape of the outside wall surface 911 relative with the internal face 912 is circular segments, thus, when the grouting shower nozzle 66 is in When on the direction orthogonal with the building gap 1, the curved profile portion 91 with the contact position of the top pressure roller 62 at The wall thickness 100 being had is less than the wall thickness that two side positions of the contact position have.
It is valuably or exemplary, wherein, when the grouting shower nozzle 66 is on vertical direction, the curved profile portion 91 There is minimum wall thickness (MINI W.) with the contact position of the top pressure roller 62.
It is valuably or exemplary, wherein, the curve shape of the internal face 912 is with the vertical direction at minimum wall thickness (MINI W.) position Axis and it is symmetrical.
By such scheme, as a result of the shower nozzle motion driving sliding block that can be slided in the lumen, profile portion is utilized Regulation driving left and right, the position that can be lifted up in the oval circular arc relative to outside of inner side is that two ends form wall thickness At thickening, therefore, it is possible to, by shower nozzle ejection forward, be formed at the beginning and end of perfusion so as to compensate due to arc swing At the beginning and end of shower nozzle perfusion apart from it is excessive the problem of, and can perfusion centre position cause shower nozzle relatively after Remove, so that perfusion is apart from relatively reduced.Whole device is simple and reliable for structure, stable and easy to use, Neng Gouyou Effect solves above mentioned problem of the prior art, improves pouring quality.
Those skilled in the art can be clear and definite, can in the case of the overall spirit of the present invention and design is not departed from To make the various modifications for above example.It is each fallen within protection scope of the present invention.The protection scheme of the present invention It is defined by claims appended hereto.

Claims (3)

1. one kind building provisions for grouting, for building gap(1)It is in the milk, it is characterised in that:Including pedestal(9)And it is logical Cross supporting device for sluing mechanisms(88)And with the pedestal(9)Rear wall connection nozzle connecting device(8), wherein, the shower nozzle connects Connection device(8)Including clamping cavity with slip(80)Sprinkler rotation drive shell(89), it is described to slide clamping cavity(80) In be sliding combined with shower nozzle motion driving sliding block(6), the shower nozzle motion driving sliding block(6)Inside it is provided with fore-and-aft direction extension Fluid passage(60)To with grouting shower nozzle(66)It is in fluid communication, the grouting shower nozzle(66)On be provided with control valve for fluids (33), the control valve for fluids(33)To control the grouting shower nozzle(66)The output quantity of grouting is exported, so as to basis Need the selection control grouting shower nozzle(66)The output quantity of grouting is exported to reach use requirement, the control valve for fluids(33) For solenoid electric valve, the shower nozzle motion driving sliding block(6)Upper side pass through located at it is described slide clamping cavity(80)In Top pressure spring(83)And compressed effect to be installed in shower nozzle motion driving sliding block using rotation(6)Downside And the top pressure arm integrally protruded(61)End top pressure roller(62)The pedestal is fixedly arranged on to be resisted against(9)Lower wall at Curved profile portion(91)Internal face(912)On, the sprinkler rotation drive shell(89)Bottom be provided with gear wheel segment (81)To with by rotating motor(72)The gear of driving(71)Engagement is so as to drive the sprinkler rotation drive shell (89)Rotate, the rotating motor(72)With the pedestal(9)It is fixedly connected, the rotating motor(72)'s Multi-disc radiating fin is horizontally arranged with case surface(23)It is easy to the rotating driving electricity to increasing heat radiation area Machine(72)Operationally produced heat absorption and dissipate, prevent the rotating motor(72)During long-play Temperature is too high and burns;The shower nozzle motion driving sliding block(6)Relative two lateral surfaces in left and right respectively with the slip clamp Hold cavity(80)In two or so relative medial surfaces coordinate so as to slideably by the sprinkler rotation drive shell(89) Rotation driving, the fluid passage(60)Front end extend through the sprinkler rotation drive shell(89)Antetheca with filling Slurry source is connected, wherein, the curved profile portion(91)Internal face(912)Curve shape be oval section, the curve Profile portion(91)With the internal face(912)Relative outside wall surface(911)Curve shape be circular segments, thus, work as institute State grouting shower nozzle(66)In with the building gap(1)When on orthogonal direction, the curved profile portion(91)With it is described Top pressure roller(62)Contact position at the wall thickness that has(100)The wall having less than two side positions of the contact position It is thick.
2. a kind of building provisions for grouting according to claim 1, it is characterised in that:When the grouting shower nozzle(66)In perpendicular When Nogata is upward, the curved profile portion(91)With the top pressure roller(62)Contact position there is minimum wall thickness (MINI W.).
3. a kind of building provisions for grouting according to claim 1 or 2, it is characterised in that:The internal face(912)Curve Shape is symmetrical with the axis of the vertical direction at minimum wall thickness (MINI W.) position.
CN201610309856.6A 2016-05-11 2016-05-11 One kind building provisions for grouting Active CN105926965B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610309856.6A CN105926965B (en) 2016-05-11 2016-05-11 One kind building provisions for grouting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610309856.6A CN105926965B (en) 2016-05-11 2016-05-11 One kind building provisions for grouting

Publications (2)

Publication Number Publication Date
CN105926965A CN105926965A (en) 2016-09-07
CN105926965B true CN105926965B (en) 2017-11-03

Family

ID=56834889

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610309856.6A Active CN105926965B (en) 2016-05-11 2016-05-11 One kind building provisions for grouting

Country Status (1)

Country Link
CN (1) CN105926965B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07251367A (en) * 1994-03-15 1995-10-03 Fujita Corp Derusting device
US5761855A (en) * 1996-06-28 1998-06-09 Vanguard Semiconductor Corporation Structure and method of implementing a supplementary column for supporting a raised floor
JP3075366B2 (en) * 1991-04-03 2000-08-14 豊和工業株式会社 Polishing equipment such as floor polishing machines
KR100776397B1 (en) * 2007-06-28 2007-11-16 (주)아이엠건설 Apparatus and method for removing asbestos
CN104196259A (en) * 2014-08-21 2014-12-10 四川金锋建设有限公司 Device for maintaining suspended stretch-across section of building

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3075366B2 (en) * 1991-04-03 2000-08-14 豊和工業株式会社 Polishing equipment such as floor polishing machines
JPH07251367A (en) * 1994-03-15 1995-10-03 Fujita Corp Derusting device
US5761855A (en) * 1996-06-28 1998-06-09 Vanguard Semiconductor Corporation Structure and method of implementing a supplementary column for supporting a raised floor
KR100776397B1 (en) * 2007-06-28 2007-11-16 (주)아이엠건설 Apparatus and method for removing asbestos
CN104196259A (en) * 2014-08-21 2014-12-10 四川金锋建设有限公司 Device for maintaining suspended stretch-across section of building

Also Published As

Publication number Publication date
CN105926965A (en) 2016-09-07

Similar Documents

Publication Publication Date Title
CN105822083B (en) A kind of energy saving building gap provisions for grouting
CN105926965B (en) One kind building provisions for grouting
CN105971301B (en) A kind of gap provisions for grouting for building
CN105822082B (en) A kind of controllable gap provisions for grouting
CN105926973B (en) A kind of building gap provisions for grouting with LED spotlight
CN105822081B (en) A kind of modified builds gap provisions for grouting
CN105804430B (en) A kind of heat radiating type builds gap provisions for grouting
CN105926967B (en) A kind of solar energy gap provisions for grouting
CN105888284B (en) A kind of gap provisions for grouting for building with control valve for fluids
CN106013830B (en) It is a kind of to build the gap provisions for grouting used
CN105735670B (en) A kind of gap provisions for grouting for building with rotary connecting joint
CN105822085B (en) A kind of building gap provisions for grouting of convenient use
CN105952177B (en) A kind of damping provisions for grouting for building gap
CN105926972B (en) A kind of building gap provisions for grouting with ventilating fan
CN105839943B (en) A kind of solar powered building gap provisions for grouting
CN105952178B (en) A kind of heat radiating type gap for building provisions for grouting
CN105822086B (en) A kind of provisions for grouting for building gap
CN105888285B (en) A kind of gap grouting system for building
CN105908951B (en) A kind of durable gap provisions for grouting
CN105926970B (en) It is a kind of can noise reduction building gap provisions for grouting
CN105822087B (en) A kind of provisions for grouting for building gap
CN106013829B (en) A kind of controllable gap provisions for grouting of filling speed
CN105839942B (en) It is a kind of can lamplight pointing building gap provisions for grouting
CN105926903B (en) A kind of band LED spotlight and adjustable building provisions for grouting
CN105735669B (en) It is a kind of can alarm building gap provisions for grouting

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Wang Rujun

Inventor before: Zhang Fan

CB03 Change of inventor or designer information
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20170928

Address after: Taizhou City, Zhejiang Province, 317000 Coastal City Town Village No. 70 Taozhu

Applicant after: Wang Rujun

Address before: At Shangyu village, Baiguan street 312300 city in Zhejiang province Shaoxing city building 26 room 104 East

Applicant before: Zhang Fan

GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190822

Address after: 223700 No. 29, 3rd floor, Xindu Agricultural Trade Market, Wencheng, Zhongxing Town, Siyang County, Suqian City, Jiangsu Province

Patentee after: Suqian Ronggang Construction Engineering Co., Ltd.

Address before: No. 70, Xiangzhuang Village, Taozhu Town, Linhai City, Taizhou City, Zhejiang Province

Patentee before: Wang Rujun

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201117

Address after: 3 / F, block a, Haipai City, Yunhe South Road, Sucheng District, Suqian City, Jiangsu Province

Patentee after: Jiangsu Qizhi Construction Engineering Co.,Ltd.

Address before: 223700 No. 29, 3rd floor, Xindu Agricultural Trade Market, Wencheng, Zhongxing Town, Siyang County, Suqian City, Jiangsu Province

Patentee before: Suqian Ronggang Construction Engineering Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201221

Address after: No.5-906, Wancheng yujingyuan, west side of Taoyuan North Road, Zhongxing Town, Siyang County, Suqian City, Jiangsu Province

Patentee after: Jiangsu Ronglian Project Management Co.,Ltd.

Address before: 3 / F, block a, Haipai City, Yunhe South Road, Sucheng District, Suqian City, Jiangsu Province

Patentee before: Jiangsu Qizhi Construction Engineering Co.,Ltd.