CN105913889A - 一种三环路核能系统 - Google Patents

一种三环路核能系统 Download PDF

Info

Publication number
CN105913889A
CN105913889A CN201610523258.9A CN201610523258A CN105913889A CN 105913889 A CN105913889 A CN 105913889A CN 201610523258 A CN201610523258 A CN 201610523258A CN 105913889 A CN105913889 A CN 105913889A
Authority
CN
China
Prior art keywords
power system
nuclear power
reactor pressure
links theory
pressure vessel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610523258.9A
Other languages
English (en)
Inventor
郑明光
邱忠明
唐特
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Nuclear Engineering Research and Design Institute Co Ltd
Original Assignee
Shanghai Nuclear Engineering Research and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Nuclear Engineering Research and Design Institute Co Ltd filed Critical Shanghai Nuclear Engineering Research and Design Institute Co Ltd
Priority to CN201610523258.9A priority Critical patent/CN105913889A/zh
Publication of CN105913889A publication Critical patent/CN105913889A/zh
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G21NUCLEAR PHYSICS; NUCLEAR ENGINEERING
    • G21DNUCLEAR POWER PLANT
    • G21D1/00Details of nuclear power plant
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin

Abstract

本发明提供一种三环路核能系统,其包括一个反应堆压力容器、三个蒸汽发生器和三个主泵;所述三个蒸汽发生器分布于所述反应堆压力容器连通,每个所述主泵与一个所述蒸汽发生器连通;还包括壳体,所述反应堆压力容器、蒸汽发生器和主泵均设置在所述壳体内。本发明提供的三环路核能系统,用于海洋环境下,适应船舶、平台、沉箱等不同的海洋交通工具或构筑物,具备良好的抗倾斜、摇摆和冲击性能。

Description

一种三环路核能系统
技术领域
本发明涉及一种可用于海洋环境下的三环路核能系统。
背景技术
国内核能系统,主要用于陆地发电。根据发明人进行的查新结果,国内外还未提出一种可用于海洋环境的三环路核能系统。
发明内容
本发明针对现有技术的不足,提出一种三环路核能系统。
三环路核能系统包括一个反应堆压力容器、三个蒸汽发生器和三个主泵;所述三个蒸汽发生器分布于所述反应堆压力容器连通,每个所述主泵与一个所述蒸汽发生器连通;还包括壳体,所述反应堆压力容器、蒸汽发生器和主泵均设置在所述壳体内。
优选地,所述壳体为筒体。
优选地,所述筒体的内径≥5m,轴向长度≥6m。
优选地,所述壳体的体积≥115m3
优选地,还包括支撑结构,所述支撑结构设置在所述壳体内,用于支撑所述反应堆压力容器、蒸汽发生器和主泵。
优选地,所述三个蒸汽发生器相对于所述反应堆压力容器对称设置。
优选地,还包括至少一个控制棒机构,所述控制棒机构位于所述壳体内。
优选地,还包括至少一个稳压器,所述稳压器位于所述壳体内。
优选地,所述筒体竖直放置,即反应堆压力容器、蒸汽发生器或主泵的中心轴线与所述筒体的中心轴向平行。
与现有技术相比,本发明具有以下有益效果:
1、本发明提供的三环路核能系统,用于海洋环境下,适应船舶、平台、沉箱等不同的海洋交通工具或构筑物,具备良好的抗倾斜、摇摆和冲击性能。
附图说明
图1为符合本发明优选实施例的三环路核能系统的三维示意图。
图2为符合本发明优选实施例的三环路核能系统的三维剖视图。
图3为符合本发明优选实施例的三环路核能系统隐去支撑结构后的三维剖视图。
具体实施方式
为使本发明的上述目的、特征和优点能够更加明显易懂,下面结合附图和具体实施方式对本发明作进一步详细的说明。
如图1-3所示,三环路核能系统包括一个反应堆压力容器1、三个蒸汽发生器2和三个主泵3;所述三个蒸汽发生器2分布于所述反应堆压力容器1连通,每个所述主泵3与一个所述蒸汽发生器1连通。三个蒸汽发生器2相对于所述反应堆压力容器1对称设置。
优选地,还包括壳体4,所述反应堆压力容器1、蒸汽发生器2和主泵3均设置在所述壳体4内。所述壳体4为筒体。所述筒体的内径≥5m,轴向长度≥6m。
当然,在其他实施例中,所述壳体也可为非筒体形状的容器,其体积≥115m3
三环路核能系统还包括支撑结构5,所述支撑结构5设置在所述筒体4内,用于支撑所述反应堆压力容器1、蒸汽发生器2和主泵3。
三环路核能系统还包括一个控制棒机构6,所述控制棒机构6位于所述壳体4内。
三环路核能系统还包括一个稳压器7,所述稳压器7位于所述壳体4内。
与现有技术相比,本发明实施例具有以下有益效果:
1、本发明实施例提供的三环路核能系统,用于海洋环境下,适应船舶、平台、沉箱等不同的海洋交通工具或构筑物,具备良好的抗倾斜、摇摆和冲击性能。
本说明书中各个实施例采用递进的方式描述,每个实施例重点说明的都是与其他实施例的不同之处,各个实施例之间相同相似部分互相参见即可。对于实施例公开的系统而言,由于与实施例公开的方法相对应,所以描述的比较简单,相关之处参见方法部分说明即可。
本领域技术人员可以对每个特定的应用来使用不同方法来实现所描述的功能,但是这种实现不应认为超出本发明的范围。
显然,本领域的技术人员可以对发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若本发明的这些修改和变型属于本发明权利要求及其等同技术的范围之内,则本发明也意图包括这些改动和变型在内。

Claims (9)

1.一种三环路核能系统,其特征在于,包括一个反应堆压力容器、三个蒸汽发生器和三个主泵;所述三个蒸汽发生器分布于所述反应堆压力容器连通,每个所述主泵与一个所述蒸汽发生器连通;还包括壳体,所述反应堆压力容器、蒸汽发生器和主泵均设置在所述壳体内。
2.如权利要求1所述的三环路核能系统,其特征在于,所述壳体为筒体。
3.如权利要求2所述的三环路核能系统,其特征在于,所述筒体的内径≥5m,轴向长度≥6m。
4.如权利要求1所述的三环路核能系统,其特征在于,所述壳体的体积≥115m3
5.如权利要求1所述的三环路核能系统,其特征在于,还包括支撑结构,所述支撑结构设置在所述壳体内,用于支撑所述反应堆压力容器、蒸汽发生器和主泵。
6.如权利要求1所述的三环路核能系统,其特征在于,所述三个蒸汽发生器相对于所述反应堆压力容器对称设置。
7.如权利要求1所述的三环路核能系统,其特征在于,还包括至少一个控制棒机构,所述控制棒机构位于所述壳体内。
8.如权利要求1所述的三环路核能系统,其特征在于,还包括至少一个稳压器,所述稳压器位于所述壳体内。
9.如权利要求2所述的三环路核能系统,其特征在于,所述筒体竖直放置。
CN201610523258.9A 2016-07-05 2016-07-05 一种三环路核能系统 Pending CN105913889A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610523258.9A CN105913889A (zh) 2016-07-05 2016-07-05 一种三环路核能系统

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610523258.9A CN105913889A (zh) 2016-07-05 2016-07-05 一种三环路核能系统

Publications (1)

Publication Number Publication Date
CN105913889A true CN105913889A (zh) 2016-08-31

Family

ID=56754255

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610523258.9A Pending CN105913889A (zh) 2016-07-05 2016-07-05 一种三环路核能系统

Country Status (1)

Country Link
CN (1) CN105913889A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108916547A (zh) * 2018-08-01 2018-11-30 中广核研究院有限公司 一回路主设备承载装置
CN111508626A (zh) * 2020-04-28 2020-08-07 中国核动力研究设计院 一种适用于超大型压水堆的三环路反应堆冷却剂系统

Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1641797A (zh) * 2005-01-07 2005-07-20 清华大学 模块式高温气冷堆压力壳的无阻尼器支承系统
CN1836292A (zh) * 2003-08-15 2006-09-20 卵石床模块反应器控股有限公司 支撑结构
CN101620892A (zh) * 2009-07-30 2010-01-06 华北电力大学 一种大功率压水堆核电站一回路系统结构设计
CN102169736A (zh) * 2011-01-19 2011-08-31 中国核工业第五建设有限公司 一种核电站冷却剂系统主管道的安装方法
CN102637463A (zh) * 2012-04-11 2012-08-15 中国核工业二三建设有限公司 安装核电站核岛内主回路系统的方法
CN102760500A (zh) * 2012-07-02 2012-10-31 西安交通大学 一种核电站稳压器波动管结构
CN102822902A (zh) * 2010-09-27 2012-12-12 巴布科克和威尔科克斯核能股份有限公司 带有一体的蒸汽发生器的紧凑型核反应堆
CN103377735A (zh) * 2012-04-27 2013-10-30 上海核工程研究设计院 一种反应堆下部堆内构件
CN203338775U (zh) * 2013-07-18 2013-12-11 中广核工程有限公司 核电站蒸汽发生器防满溢结构
CN103492816A (zh) * 2011-03-01 2014-01-01 西屋电气有限责任公司 核蒸汽发生器支撑和对准结构
CN104252884A (zh) * 2013-06-27 2014-12-31 中广核工程有限公司 核电站一回路主管道安装方法
CN104299663A (zh) * 2014-09-29 2015-01-21 中国核动力研究设计院 一种可潜式动力定位海上核电站
CN204665240U (zh) * 2015-03-10 2015-09-23 中科华核电技术研究院有限公司 蒸汽发生器水室封头结构
CN104992738A (zh) * 2014-07-29 2015-10-21 台山核电合营有限公司 一种基于三维高精度测量的核岛主设备安装工艺
CN105118532A (zh) * 2015-09-11 2015-12-02 中广核(北京)仿真技术有限公司 一体化反应堆
CN105321584A (zh) * 2014-07-17 2016-02-10 尼古拉斯·M·博诺姆 用于水冷却慢化核反应堆的安全壳
JP2016035476A (ja) * 2015-10-15 2016-03-17 琢己 藤田 原子炉支持構造

Patent Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1836292A (zh) * 2003-08-15 2006-09-20 卵石床模块反应器控股有限公司 支撑结构
CN1641797A (zh) * 2005-01-07 2005-07-20 清华大学 模块式高温气冷堆压力壳的无阻尼器支承系统
CN101620892A (zh) * 2009-07-30 2010-01-06 华北电力大学 一种大功率压水堆核电站一回路系统结构设计
CN102822902A (zh) * 2010-09-27 2012-12-12 巴布科克和威尔科克斯核能股份有限公司 带有一体的蒸汽发生器的紧凑型核反应堆
CN102169736A (zh) * 2011-01-19 2011-08-31 中国核工业第五建设有限公司 一种核电站冷却剂系统主管道的安装方法
CN103492816A (zh) * 2011-03-01 2014-01-01 西屋电气有限责任公司 核蒸汽发生器支撑和对准结构
CN102637463A (zh) * 2012-04-11 2012-08-15 中国核工业二三建设有限公司 安装核电站核岛内主回路系统的方法
CN103377735A (zh) * 2012-04-27 2013-10-30 上海核工程研究设计院 一种反应堆下部堆内构件
CN102760500A (zh) * 2012-07-02 2012-10-31 西安交通大学 一种核电站稳压器波动管结构
CN104252884A (zh) * 2013-06-27 2014-12-31 中广核工程有限公司 核电站一回路主管道安装方法
CN203338775U (zh) * 2013-07-18 2013-12-11 中广核工程有限公司 核电站蒸汽发生器防满溢结构
CN105321584A (zh) * 2014-07-17 2016-02-10 尼古拉斯·M·博诺姆 用于水冷却慢化核反应堆的安全壳
CN104992738A (zh) * 2014-07-29 2015-10-21 台山核电合营有限公司 一种基于三维高精度测量的核岛主设备安装工艺
CN104299663A (zh) * 2014-09-29 2015-01-21 中国核动力研究设计院 一种可潜式动力定位海上核电站
CN204665240U (zh) * 2015-03-10 2015-09-23 中科华核电技术研究院有限公司 蒸汽发生器水室封头结构
CN105118532A (zh) * 2015-09-11 2015-12-02 中广核(北京)仿真技术有限公司 一体化反应堆
JP2016035476A (ja) * 2015-10-15 2016-03-17 琢己 藤田 原子炉支持構造

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王金华,周耀中,张亚军: "扩容蒸发器在船用核动力装置中的应用", 核科学与工程, no. 04 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108916547A (zh) * 2018-08-01 2018-11-30 中广核研究院有限公司 一回路主设备承载装置
CN108916547B (zh) * 2018-08-01 2023-12-26 中广核研究院有限公司 一回路主设备承载装置
CN111508626A (zh) * 2020-04-28 2020-08-07 中国核动力研究设计院 一种适用于超大型压水堆的三环路反应堆冷却剂系统

Similar Documents

Publication Publication Date Title
CN105976877A (zh) 一种双环路核能系统
CN105129038A (zh) 一种基于浮塔和潜浮体组合成的轻型波浪能发电平台装置及其使用方法
CN206363772U (zh) 一种三环路核能系统
CN103237728A (zh) 漂浮lng设备
CN105913889A (zh) 一种三环路核能系统
CN103334868B (zh) 磁流体波浪能水下充电平台
CN102704452A (zh) 具有多类型桩腿的超大型自升式风电安装船及其设计方法
CN104029798A (zh) 自安装采油平台
CN111391987A (zh) 中等深度水域的浮式风机装备
CN205221016U (zh) 一种用于波浪能发电的轻型组合体平台装置
CN104389720A (zh) 全自由度海浪发电装置
KR101352095B1 (ko) 석션파일 하부구조물
CN204803838U (zh) 拼装式、具阻尼的、发电的消波装置
CN105957566A (zh) 一种反应堆回路主设备
CN103790708A (zh) 海洋压缩空气储能系统
Wang et al. Dynamic analysis of a tension leg platform for offshore wind turbines
CN104514677A (zh) 一种环形浮筒液压式海浪发电机
CN205280320U (zh) 倾斜摇摆与低频振动复合实验平台
CN104121140B (zh) 一种y型海浪能吸收和转换装置
CN113356257A (zh) 一种海上风电单筒导管架基础结构
CN205579535U (zh) 一种汽水分离器外置的蒸汽发生器
CN110667796A (zh) 快速布放风能-波浪能一体化发电平台
CN104454318A (zh) 一种近海波浪能量转换利用装置
CN204548431U (zh) 海上防爆浮式单元结构
Ramli et al. Hydrodynamic Performance of Heaving Motion on Cylinder and Conical Two-Body Point Absorber in Low Wave Energy

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: No. 29 Hong Cao Road, Xuhui District, Shanghai

Applicant after: Shanghai Nuclear Engineering Research and Design Institute Co.,Ltd.

Address before: No. 29 Hong Cao Road, Xuhui District, Shanghai

Applicant before: SHANGHAI NUCLEAR ENGINEERING RESEARCH & DESIGN INSTITUTE

WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160831