CN105908966A - Creeping formwork system for oblique wall construction and construction method of creeping formwork system - Google Patents

Creeping formwork system for oblique wall construction and construction method of creeping formwork system Download PDF

Info

Publication number
CN105908966A
CN105908966A CN201610383392.3A CN201610383392A CN105908966A CN 105908966 A CN105908966 A CN 105908966A CN 201610383392 A CN201610383392 A CN 201610383392A CN 105908966 A CN105908966 A CN 105908966A
Authority
CN
China
Prior art keywords
creeping formwork
sloping core
regulation
support
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610383392.3A
Other languages
Chinese (zh)
Other versions
CN105908966B (en
Inventor
唐际宇
戈祥林
林忠和
陈勇辉
唐阁威
梁月利
陆仕颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan No.6 Construction Co., Ltd.
China Construction Eighth Engineering Division Co Ltd
China Huashi Enterprises Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201610383392.3A priority Critical patent/CN105908966B/en
Publication of CN105908966A publication Critical patent/CN105908966A/en
Application granted granted Critical
Publication of CN105908966B publication Critical patent/CN105908966B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/28Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Abstract

The invention relates to a creeping formwork system for oblique wall construction and a method of the creeping formwork system. The creeping formwork system comprises a wall-attached guide rail, a creeping formwork rail, a bearing platform, adjustment supporting rods and a creeping formwork frame body, wherein the wall-attached guide rail is attached to a first oblique wall section on a straight wall section; the creeping formwork rail is connected to the wall-attached guide rail; the bearing platform is laid at the top of the creeping formwork rail and hinged to the creeping formwork rail; the adjustment supporting rods are arranged between the bearing platform and the creeping formwork rail in a supporting mode; and the creeping formwork frame body is supported on the bearing platform, the inclination angle of the creeping formwork frame body can be adjusted, and the creeping formwork frame body can be made to incline toward the first oblique wall section by adjusting the inclination angle of the creeping formwork frame body. By adjusting the inclination angle of the creeping formwork frame body, the distance between a construction platform on the creeping formwork frame body and a construction area of the oblique wall section is reduced, construction is facilitated, and safety risks during construction are reduced.

Description

Climbing form system and construction method thereof for sloping core construction
Technical field
The present invention relates to the realm of building construction, refer in particular to a kind of climbing form system for sloping core construction and execute Work method.
Background technology
At present, in the construction of high level or Super High Core Walls Structure, general plate uses hydraulic climbing formwork system.Creeping formwork There is saving template, install that easy, easy to operate, safety, speed of application be fast, labour force puts into The plurality of advantages such as low.When constructing for sloping core, lean-in owing to being positioned at the sloping core section on stalk section Tiltedly so that lifting rail can be in heeling condition, and then makes creeping formwork support body correspondingly be also at State, does not meets the requirement of construction safety.Existing common practices be sloping core section arrange protrude out add consolidation Structure, so that lifting rail fixing in sloping core section and stalk section is in plumbness, so that it is guaranteed that climb Mould bases body vertically with the steady statue of horizontal direction, it is ensured that the safety of construction.But due to The intilted angle of sloping core section is relatively big, and makes vertically to hang on executing on the climbing form system of stalk section Distant between the construction area of work platform and sloping core section, and make the operation inconvenience of workmen, Construction for sloping core section brings security risk.In addition, it is necessary to individually construct the ruggedized construction later stage protruded out Also need to remove so that working procedure is relatively complicated, and adds construction procedure, abolishes ruggedized construction Time the most more bother, and then the construction period can be affected.
Summary of the invention
It is an object of the invention to overcome the defect of prior art, it is provided that a kind of climbing for sloping core construction Modular system and construction method thereof, the ruggedized construction solving to use setting to protrude out in prior art carries out creeping formwork The construction distance that construction exists remote and make to operate inconvenience, construction safety risk, working procedure loaded down with trivial details, The problem more bothering and affecting the construction period when increasing working procedure, dismounting.
The technical scheme realizing above-mentioned purpose is:
The invention provides a kind of climbing form system for sloping core construction, including:
Attached wall guide rail, is attached to be positioned in the first sloping core section on stalk section;
It is connected to the creeping formwork rail on described attached wall guide rail;
Being layed in the support platform at described creeping formwork rail top, described support platform cuts with scissors with described creeping formwork rail Connect;
Prop up and be located at the regulation support bar between described support platform and described creeping formwork rail;And
Propping up and be located at described support platform and adjustable inclination creeping formwork support body, described creeping formwork support body leads to Cross adjustment inclination angle to tilt to described first sloping core section.
Utilize the inclination angle adjusting creeping formwork support body, and the operation platform reduced on creeping formwork support body is executed with sloping core section The distance in territory, work area, convenient construction operates, and reduces construction safety risk.And creeping formwork support body is when tilting, Being able to ensure that operation platform is horizontal, Stability Analysis of Structures is firm, it is ensured that construction safety.In stalk section and During the climbing formwork for construction of sloping core section, climb attached wall guide rail still according to conventional method, although attached wall guide rail At sloping core inclined, but by adjust regulation support bar so that support platform is level Shape, would not affect the stability of creeping formwork support body on support platform, it is ensured that the construction peace of creeping formwork support body Entirely.The climbing form method of the present invention, compared to the method for the existing ruggedized construction set up and protrude out, construction Simplicity, operation is simple, and the regulation support bar i.e. utilizing setting is horizontal to regulate support platform, Can be the most time-consuming, and then the construction period can be shortened.
Further improvement is that of the climbing form system that the present invention constructs for sloping core, described creeping formwork support body bag Include the carrier unit being erected on the adjustable inclination on described support platform, the angle of described carrier unit Portion is hinged, and has installed regulation push rod on described carrier unit.
Further improvement is that of the climbing form system that the present invention constructs for sloping core, described creeping formwork support body is also Including propping up the bracket unit being located at described support mesa base, the corner of described bracket unit is hinged, And installed regulation screw mandrel in described bracket unit.
Further improvement is that of the climbing form system that the present invention constructs for sloping core, described regulation support bar Including being positioned at the adjusting sleeve pipe at middle part and being screwed together in the studdle at described adjusting sleeve pipe two ends, it is positioned at The described studdle in portion is fastenedly connected with described support platform, be positioned at the described studdle of bottom with Described creeping formwork rail is fastenedly connected.
Further improvement is that of the climbing form system that the present invention constructs for sloping core, described attached wall guide rail Bottom is connected with described stalk section by attached wall cushion block.
Present invention also offers a kind of construction method applying the above-mentioned climbing form system for sloping core construction, Including:
Adjust the inclination angle of creeping formwork support body being positioned on described support platform so that described creeping formwork support body to First sloping core section to be onstructed tilts;
The creeping formwork support body tilted is utilized to complete the construction of the first sloping core section;
In described first sloping core section, climbing boots is installed;
Climb attached wall guide rail, and the climbing boots of described attached wall guide rail Yu described first sloping core section is fixed this chain Connect, so that described attached wall guide rail is in the heeling condition drawn close to described first sloping core section;
Described regulation support bar is utilized to be adjusted to horizontal by described support platform;
Described creeping formwork support body is utilized to carry out sloping core construction on described first sloping core section.
Further improvement is that of the construction method of the present invention, adjusts and is positioned at climbing on described support platform The inclination angle of mould bases body, including:
Described creeping formwork support body includes the support list being erected on the adjustable inclination on described support platform Unit, the corner of described carrier unit is hinged, and has installed regulation push rod on described carrier unit;
Utilize described regulation push rod regulate described carrier unit inclination angle, with realize described carrier unit to The heeling condition that described first sloping core section is drawn close.
Further improvement is that of the construction method of the present invention, after the attached wall guide rail that climbs, also includes adjusting The inclination angle of the whole creeping formwork support body being positioned at described support mesa base,
Described creeping formwork support body includes a bracket unit being located at described support mesa base, described bracket list The corner of unit is hinged, and has installed regulation screw mandrel in described bracket unit;
Described regulation screw mandrel is utilized to regulate described bracket unit, to realize described bracket unit to described the The heeling condition that one sloping core section is drawn close.
Further improvement is that of the construction method of the present invention, utilizes described regulation support bar to hold described Torr platform is adjusted to horizontal, including:
Described regulation support bar includes being positioned at the adjusting sleeve pipe at middle part and being screwed together in described adjusting sleeve pipe two The studdle of end, the described studdle that will be located in top is fastenedly connected with described support platform, will The described studdle being positioned at bottom is fastenedly connected with described creeping formwork rail;
When described first sloping core section slopes inwardly, screw described of described adjusting sleeve pipe regulation two ends Support screw rod screws in described regulating sleeve, until described support platform is horizontal;
When described first sloping core section is outward-dipping, screw described of described adjusting sleeve pipe regulation two ends Support screw rod screws out described regulating sleeve, until described support platform is horizontal.
Further improvement is that of the construction method of the present invention, climb attached wall guide rail time, by described attached wall The bottom of guide rail is connected with described stalk section by attached wall cushion block.
Accompanying drawing explanation
Fig. 1 is that the climbing form system that the present invention constructs for sloping core shows in the structure of construction the first sloping core section It is intended to.
Oblique on construction the first sloping core section of the climbing form system that Fig. 2 is the present invention to construct for sloping core The structural representation of wall.
Fig. 3 is present invention support platform when being positioned at stalk section in the climbing form system that sloping core is constructed Structural representation.
Fig. 4 is the structural representation saving stalk section and bracket unit in Fig. 3.
Fig. 5 and Fig. 6 is the structural representation regulating support plateau levels shape in the first sloping core section.
Fig. 7 is present invention carrier unit in the climbing form system that sloping core is constructed in creeping formwork support body Structural representation.
Detailed description of the invention
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings.
Present invention provide for climbing form system and the construction method thereof of sloping core construction, be primarily adapted for use in Construct on stalk section inside body of wall or the situation of sloping core section that outside tilts.Sloping core due to top Section is inside body of wall or outside tilts, and vertical attached wall guide rail cannot be climbed, and then result in The creeping formwork difficulty of climbing form system.Prior art adds consolidation frequently with what setting at sloping core section protruded out Structure, vertically climbs to make attached wall guide rail continue, it is ensured that the normal creeping formwork of climbing form system, but due to Sloping core section tilts, and climbing form system vertically climbs, and result in the operating platform on climbing form system with oblique , there is construction safety risk in distant between wall section construction area so that constructing operation inconvenience.For Solving the problems referred to above, the climbing form system for sloping core construction of the present invention and construction method thereof have employed can The creeping formwork support body of adjustable inclination, when constructing sloping core section, adjusts inclination angle and the sloping core section of creeping formwork support body Inclination angle is close, and reduces the spacing of operating platform and construction area, and convenient construction operates, it is ensured that construction Safety.Below in conjunction with the accompanying drawings the present invention is carried out for climbing form system and the construction method thereof of sloping core construction Explanation.
Refering to shown in Fig. 1, it is shown that the present invention is oblique in construction first for the climbing form system of sloping core construction The structural representation of wall section.Below in conjunction with Fig. 1, the present invention is entered for the climbing form system of sloping core construction Row explanation.
As it is shown in figure 1, the present invention includes attached wall guide rail 23 for the climbing form system of sloping core construction, climbs Mould rail 24, support platform 31, regulation support bar 32 and creeping formwork support body 40, attached wall guide rail 23 with The fixing connection of climbing boots 21 in stalk section 11, now first on stalk section 11 of constructing Sloping core section 12, shown in Fig. 2, after construction completes the first sloping core section 12, at the first sloping core Installing climbing boots 21 in section 12, climb attached wall guide rail 23, by attached wall guide rail 23 and the first sloping core section The fixing connection of climbing boots 21 on 12, this attached wall guide rail 23 is in inclining of drawing close to the first sloping core section 12 Ramp-like state.This attached wall guide rail 23 tilts to first sloping core section 12 direction on body of wall 10.Creeping formwork Rail 24 is connected on attached wall guide rail 23, this creeping formwork rail 24 along with attached wall guide rail 23 inclination and in inclining Ramp-like.Support platform 31 is layed in creeping formwork rail 24 top, this support platform 31 and creeping formwork rail 24 Top hinged so that support platform 31 can rotate around hinged end, creeping formwork rail 24 Not only supporting support platform 31, the most also the scalable for support platform 31 provides possible.Regulation Support bar 32 is located between support platform 31 and creeping formwork rail 24, and this regulation support bar 32 is length Adjustable structure, utilizes regulation support bar 32 to regulate length and is adjusted to horizontal by support platform 31, Make support platform 31 not tilted to be affected by attached wall guide rail 23, continue to keep horizontal, it is provided that flat The supporting construction of straight shape.Creeping formwork support body 40 adjustable ground props up is located at support platform 31, creeping formwork support body 40 The inclination angle of scalable self, being positioned at the creeping formwork support body 40 above and below support platform 31 can adjust Joint inclination angle.When constructing the first sloping core section 12, adjust and be positioned at the creeping formwork support body above support platform 31 The inclination angle of 40, so that this creeping formwork support body tilts to the first sloping core section 12, makes climbing form frame by inclination Operating platform and the construction area spacing of the first sloping core section 12 on body 40 reduce, and facilitate the first sloping core The constructing operation of section 12, also ensure that construction safety.After the first sloping core section 12 has been constructed, climb Rise attached wall guide rail 23, during this attached wall guide rail 23 inclined shape, adjusted by regulation support bar 32 and hold Torr platform 31 is horizontal, provides firm support for the creeping formwork support body 40 above support platform 31.
At the sloping core of body of wall 10, due to during the climbing of climbing form system, attached wall guide rail 23 Along with sloping core is inclined, adjust support platform 31 followed by regulation support bar 32 horizontal, Provide stable support, it is ensured that the steadiness of creeping formwork support body 40, it is ensured that the safety of construction. Also simplify the working procedure of the process of climbing, there is easy construction, effectively save engineering time, it is possible to Shorten the construction period.
As shown in Figure 3 and Figure 4, regulation support bar 32 includes adjusting sleeve pipe 321 He being positioned at middle part It is screwed together in the studdle 322,323 at adjusting sleeve pipe 321 two ends, superposed studdle 322 Being fastenedly connected with support platform 31, the studdle 322 on top is by connecting channel-section steel and support platform 31 connect.The studdle 323 being positioned at bottom is fastenedly connected with creeping formwork rail 24, by screwing regulation Sleeve pipe 321 regulates studdle 322,323 precession at two ends or screws out to realize regulation support bar 32 Length adjustment.It is preferred that regulation support bar 32 is located on support platform 31 away from creeping formwork rail Between side and the bottom of creeping formwork rail 24 of 24, to facilitate regulation.Concrete regulation process is: suitable Hour hands screw adjusting sleeve pipe 321, along with the rotation of adjusting sleeve pipe 321, make two by threaded engagement The studdle 322,323 of end screws out outside adjusting sleeve pipe 321, it is achieved that regulation support bar 32 Length, now, the side that support platform 31 is connected with regulation support bar 32 can be along with regulation The length of strut 32 and be lifted up.Screw adjusting sleeve pipe 321 counterclockwise, along with regulation set The rotation of pipe 321, makes the studdle 322,323 at two ends to adjusting sleeve pipe 321 by threaded engagement Interior screw-in, it is achieved that the length of regulation support bar 32 shortens, now, support platform 31 and regulation The side that strut 32 connects can shorten along with the length of regulation support bar 32 and sink downwards, regulation The length of strut 32 shortens and is applicable to the first sloping core section 12 and slopes inwardly state.
As depicted in figs. 1 and 2, what creeping formwork support body 40 included being erected on support platform 31 is adjustable The carrier unit 41 at joint inclination angle is located at the bracket unit 42 bottom support platform 31, support list with propping up The rational height of unit 41 and bracket unit 42 can need to select according to practice of construction.Carrier unit The corner of 41 is hinged so that this carrier unit 41 can by corner hinged based on realize inclination angle Regulation, carrier unit 41 has installed regulation push rod 411, by regulation push rod 411 regulate The inclination angle of carrier unit 41.The corner of bracket unit 42 is also hinged so that this bracket unit 42 Can by corner hinged based on realize the regulation at inclination angle, bracket unit 42 has installed regulation Screw mandrel 421, by regulating the inclination angle of screw mandrel 421 bracket unit 42.
As it is shown in fig. 7, the vertical rod 412 of carrier unit 41 and the cross bar 413 that is connected with vertical rod 412, Vertical rod 412 and cross bar 413 constitute frame-type support body.Enclosed by cross bar 413 and vertical rod 412 Form carrier unit 41, support platform 31 can arrange multiple according to required use height Carrier unit 41, each carrier unit 41 has all installed a regulation push rod 411.Vertical rod 412 Bottom be hingeably secured on support platform 31 so that this vertical rod 412 can around hinged end to The direction of body of wall 10 draw close or away from.The two ends of cross bar 413 are hinged with vertical rod 412 fixing, make The junction of cross bar 413 and vertical rod 412 can relatively rotate.Vertical rod between two cross bars 413 Angularly disposed between 412 have regulation push rod 411, and this regulation push rod 411 is located on creeping formwork support body 40 vertically Between two vertical rods 412 of the side of the alien invasion of body of wall 10, controlled by regulation push rod 411 Vertical rod 412 draw close to body of wall 10 or away from angle of inclination.Regulation push rod 411 is adjustable length Structure, by regulate push rod 411 length adjustment, in conjunction with between cross bar 413 and vertical rod 412 It is articulated and connected so that creeping formwork support body 40 can be in frame structure, it is also possible to the frame of parallelogram Body.Regulation push rod 411 is arranged higher than the one end away from body of wall 10 near one end of body of wall 10.When So, regulation push rod 411 can also prop up and be located between cross bar 413 and vertical rod 412, it is also possible to will regulation Push rod 411 is located between two cross bars 413, can realize inclination angle to carrier unit 41 Regulation.
Below to regulate shown in Fig. 7 as a example by push rod 411 is located between two vertical rods 412 regulation The concrete regulatory function of push rod 411 illustrates: combine shown in Fig. 1 and Fig. 7, adjusts regulation push rod The length of 411 so that vertical rod 412 tilts to the direction that body of wall 10 is drawn close, in vertical rod 412 During inclination, cross bar 413 keeps horizontal, and whole creeping formwork support body 40 is rendered as to body of wall 10 close The state that direction tilts, so makes the operating platform of creeping formwork support body 40 still for horizontal, it is possible to carry For the operation platform of firm safety, also make operation platform closer to body of wall 10, convenient construction.Adjust Joint regulation push rod 411 length diminish so that vertical rod 412 to body of wall 10 away from direction tilt, When vertical rod 412 tilts, cross bar 413 keeps horizontal, and whole creeping formwork support body 40 is rendered as to wall Body 10 away from the state that tilts of direction, so make the operating platform of creeping formwork support body 40 still for level Shape, using the teaching of the invention it is possible to provide the operation platform of firm safety so that operation platform is away from body of wall 10, for body of wall Space is dodged in the construction of 10.
For guaranteeing the firm of climbing mould system structure, attached wall guide rail 23 is being risen to the first sloping core section 12 During place, the bottom of attached wall guide rail 23 is connected with the attached wall cushion block 111 in stalk section 11.At attached wall When guide rail 23 needs to climb, then this connection is released.
As it is shown in figure 1, below the work progress of the first sloping core section is illustrated.First sloping core section is executed In man-hour, attached wall guide rail 23 is fixed in stalk section 11, and attached wall guide rail 23 and creeping formwork rail 24 are in vertical Straight shape, support platform 31 is in horizontal, the formwork erecting structure 51 on mobile support platform 31, makes Obtain the template on this formwork erecting structure 51 and be resisted against at the first sloping core section to be onstructed, coordinate body of wall 10 Interior medial branch mode structure 13 together form the casting space of the first sloping core section.Now adjust support Creeping formwork support body 40 above platform 31, shown in Fig. 7, i.e. simultaneously on adjusting pole unit 41 The regulation push rod 411 arranged, by adjusting the length of regulation push rod 411 so that carrier unit 41 to the direction of the first sloping core 12 tilt, it is preferred that adjust carrier unit 41 inclination angle with The inclination angle of the first sloping core 12 is identical.When carrier unit 41 tilts, vertical rod 412 is inclined, horizontal Bar 413 is still the level of state, and the operating platform arranged at carrier unit 41 top is also level, Utilize operating platform in the casting space of the first sloping core section casting concrete to form the first sloping core section 12, utilize the creeping formwork support body of adjustable inclination to guarantee convenience and the safety of construction.
As in figure 2 it is shown, below the sloping core work progress on the first sloping core section is illustrated.First Sloping core section 12 tilts to the inner side of body of wall 10, and the attached wall guide rail 23 climbed is connected to the first sloping core The climbing boots 21 installed in section 12, what the bottom of this attached wall guide rail 23 and stalk section 11 were fixed is attached Wall cushion block 111 connects fixing, and attached wall guide rail 23 is in the state tilted to the first sloping core section 12, creeping formwork Rail 24 is fixed on attached wall guide rail 23, the state that this creeping formwork rail 24 also tilts in the first sloping core section 12, Shown in Fig. 5, result in the side that support platform 31 is connected with creeping formwork rail 24 downward, with regulation Support bar 32 connect one on the side, i.e. support platform 31 with regulate the side that support bar 32 is connected In Fig. 5, the direction of arrow A is moved, and now, the length of regulation regulation support bar 32 diminishes, Owing to support platform 31 and the connection of creeping formwork rail 24 are hinged so that this support platform 31 can be around Rotate with the articulated section of creeping formwork rail 24, by regulation support bar 32 by support platform 31 and regulation The side that strut 32 connects pulls down, and shown in Fig. 6, utilizes regulation support bar 32 support to be put down Direction of arrow B along Fig. 6, side that platform 31 is connected with regulation support bar 32 is moved, until should Support platform 31 is horizontal, it is ensured that the support of creeping formwork support body 40 consolidates, firm safety.When holding Torr platform 31 be horizontal after, due to construction the first sloping core section 12 time, carrier unit 41 is Skewed, now this carrier unit 41 is still skewed, can inclining without adjusting pole unit 41 Angle, the formwork erecting structure 51 on the most mobile support platform 31 carries out formwork, coordinates medial branch mode structure 13 casting space forming sloping core, then utilize the operating platform on carrier unit 41 to casting space Interior casting concrete forms sloping core, circulates the step of the above-mentioned attached wall guide rail that climbs, until sloping core has been constructed Become.
The bracket unit 42 installed in the bottom of support platform 31 can be arranged as required to multiple, at figure Shown in example in, the bottom of support platform 31 is provided with two bracket unit 42.Bracket unit 41 include vertical rod 422 and cross bar 423, hinged between vertical rod 422 and cross bar 423, regulate screw mandrel Between 421 oblique two vertical rods 422 being located at the side being perpendicular to Core Walls Structure 10, regulate screw mandrel The adjustable length of 421, by the length adjustment of regulation 421, controls the angle of inclination of vertical rod 422. Certainly, regulation screw mandrel 421 can also prop up and be located between two cross bars 423, it is also possible to will regulate screw mandrel Prop up and be located between cross bar 423 and vertical rod 422, all can realize the inclination angle of bracket unit 42.Top The top of two vertical rods 422 of the bracket unit 42 in portion is supported by I-steel and is connected to support platform The bottom of 31.Bracket unit 42 provides working place for operator, when creeping formwork, and constructor Member needs lower at bracket unit 42, checks the attached wall guide rail of bottom.
Below the present invention is applied the construction method of the above-mentioned climbing form system for variable cross-section wall construction Illustrate.
The present invention applies the above-mentioned construction method for the climbing form system of sloping core construction to comprise the steps:
As it is shown in figure 1, adjust the inclination angle of the creeping formwork support body 40 being positioned on support platform 31, so that Creeping formwork support body 40 tilts to the first sloping core section 12 to be onstructed, thus reduces on creeping formwork support body 40 The spacing of the construction area of operating platform and the first sloping core section 12, convenient construction operates, it is ensured that construction Safety.Attached wall guide rail 23 now is fixed in stalk section 11, and attached wall guide rail 23 is vertical shape, Creeping formwork rail 24 is connected with attached wall guide rail 23, also in vertical shape.It is connected to holding of creeping formwork rail 24 top Torr platform 31 is horizontal, provides support smoothly for creeping formwork support body 40.By support platform 31 On formwork erecting structure 51 at body of wall 10, move to install the template of the first sloping core section 12, in coordinating Collateral mode structure 13 defines the casting space of the first sloping core section 12, by creeping formwork support body 40 to first After sloping core section 12 tilts, utilize operating platform the watering to the first sloping core section 12 on creeping formwork support body 40 In building space, casting concrete is the formation of the first sloping core section 12.
Shown in Fig. 2, after the first sloping core section 12 of having constructed, the first sloping core section 12 is installed Climbing boots 21.Climb attached wall guide rail 23, by attached wall guide rail 23 and climbing in the first sloping core section 12 Boots 21 are fixing to be connected, and this attached wall guide rail 23 is in the heeling condition drawn close to the first sloping core section 12, edge Attached wall guide rail 23 to climb creeping formwork rail 24, creeping formwork rail 24 is connected fixing with attached wall guide rail 23, by Inclined in attached wall guide rail 23, therefore creeping formwork rail 24 also becomes heeling condition.Fig. 2 shows, attached Wall guide rail 23 and creeping formwork rail 24 tilt in the direction drawn close to the first sloping core section 12.Owing to being laid on The support platform 31 at creeping formwork rail 24 top is articulated and connected with creeping formwork rail 24 so that support platform 31 Can be able to rotate around the junction with creeping formwork rail 24.Utilize support platform 31 and creeping formwork rail 24 it Between install regulation support bar 32, this regulation support bar 32 be adjustable in length structure, utilize regulation props up Support platform 31 is adjusted to horizontal by strut 32.
A creeping formwork support body 40 being located on support platform 31 is utilized to carry out on the first sloping core section 12 Sloping core is constructed.Now, formwork erecting structure 51 is promoted to the direction of body of wall 10 so that formwork erecting structure Template on 51, against the alien invasion to body of wall 10, coordinates medial branch mode structure 13 to form sloping core Casting space, then pours, on the first sloping core section 12, the wall body structure that one end is new.Weigh the most again Retire from active military service mould, climb and the step of formwork is until sloping core has been constructed.
As shown in Figure 3 and Figure 4, regulation support bar 32 includes adjusting sleeve pipe 321 He being positioned at middle part It is screwed together in the studdle 322,323 at adjusting sleeve pipe 321 two ends, superposed studdle 322 Being fastenedly connected with support platform 31, studdle 322 fastens with support platform 31 by connecting channel-section steel Connect.The studdle 323 being positioned at bottom is fastenedly connected with creeping formwork rail 24, by screwing regulation set Pipe 321 regulates studdle 322,323 precession at two ends or screws out to realize regulation support bar 32 Length adjustment.It is preferred that regulation support bar 32 is located on support platform 31 away from creeping formwork rail 24 Side and the bottom of creeping formwork rail 24 between, to facilitate regulation.Concrete regulation process is: up time Pin screws adjusting sleeve pipe 321, along with the rotation of adjusting sleeve pipe 321, makes two ends by threaded engagement Studdle 322,323 screw out outside adjusting sleeve pipe 321, it is achieved that regulation support bar 32 length Spending elongated, now, the side that support platform 31 is connected with regulation support bar 32 can support along with regulation The length of bar 32 and be lifted up.Screw adjusting sleeve pipe 321 counterclockwise, along with adjusting sleeve pipe The rotation of 321, makes the studdle 322,323 at two ends to adjusting sleeve pipe 321 by threaded engagement Interior screw-in, it is achieved that the length of regulation support bar 32 shortens, now, support platform 31 and regulation The side that strut 32 connects can shorten along with the length of regulation support bar 32 and sink downwards, regulation The length of strut 32 shortens and is applicable to the heeling condition of the first sloping core 12 shown in Fig. 2.
Adjust the inclination angle of the creeping formwork support body 40 being positioned on support platform 31, including: such as Fig. 1 and Fig. 2 Shown in, creeping formwork support body 40 includes the carrier unit being erected on the adjustable inclination on support platform 31 41 are located at the bracket unit 42 bottom support platform 31, carrier unit 41 and bracket unit 42 with propping up Rational height can according to practice of construction need select.The corner of carrier unit 41 is hinged, Make this carrier unit 41 can by corner hinged based on realize the regulation at inclination angle, at support list Install regulation push rod 411 in unit 41, regulated the inclination angle of carrier unit 41 by regulation push rod 411, Utilize regulation push rod 411 can realize carrier unit 41 to the first sloping core section 12 draw close skewed State.The corner of bracket unit 42 is also hinged so that this bracket unit 42 can hinged with corner Based on realize the regulation at inclination angle, bracket unit 42 has installed regulation screw mandrel 421, by adjusting The inclination angle of joint screw mandrel 421 bracket unit 42, utilizes regulation screw mandrel 421 can realize bracket list The heeling condition that unit 42 is drawn close to the first sloping core section 12.
Carrier unit 41 includes the vertical rod 412 erecting on support platform 31 and is connected with vertical rod 412 Cross bar 413.Enclosed by cross bar 413 and vertical rod 412 and form carrier unit 41, at support platform Multiple carrier unit 41, each carrier unit 41 can be set according to required use height on 31 On all installed one regulation push rod 411.The bottom of vertical rod 412 is hingedly fixed in support platform 31 On so that this vertical rod 412 can be drawn close around hinged end to the direction of body of wall 10 or away from; Cross bar 413 is hinged fixing with the vertical rod 412 at two ends so that cross bar 413 and the connection of vertical rod 412 Place is rotating structure;Angularly disposed regulation push rod in vertical rod 412 between two cross bars 413 411, this regulation push rod 411 is located between the vertical rod 412 of the side being perpendicular to body of wall 10, by adjusting Joint push rod 411 control vertical rod 412 draw close to body of wall 10 or away from angle of inclination.Regulation push rod 411 is length-adjustable structure, by regulating the length adjustment of push rod 411, in conjunction with cross bar 413 with Being articulated and connected between vertical rod 412 so that creeping formwork support body 40 can be in frame structure, it is also possible in The framework of parallelogram.It is preferred that the tilt adjustable of creeping formwork support body 40 is whole it is and the first sloping core section The inclination angle of 12 is identical.Certainly, regulation push rod 411 can also prop up and be located at cross bar 413 and vertical rod 412 Between, it is also possible to regulation push rod 411 is located between two cross bars 413, can realize propping up The regulation at the inclination angle of frame unit 41.
As a example by regulation push rod 411 shown in Fig. 7 is located between two vertical rods 412, regulation is pushed away below The concrete regulation of bar 411 illustrates: adjust the length of regulation push rod 411 so that vertical rod 412 tilt to the direction that body of wall 10 is drawn close, and when vertical rod 412 tilts, cross bar 413 keeps level Shape, whole carrier unit 41 is rendered as the state tilted to the direction that body of wall 10 is close, so makes The operating platform of carrier unit 41 is still horizontal, using the teaching of the invention it is possible to provide the operation platform of firm safety, also Make operation platform closer to body of wall 10, convenient construction.The length of regulation regulation push rod 411 diminishes, Make vertical rod 412 to body of wall 10 away from direction tilt, when vertical rod 412 tilts, cross bar 413 Keep horizontal, whole carrier unit 41 be rendered as to body of wall 10 away from direction tilt state, So make the operating platform of carrier unit 41 still for horizontal, using the teaching of the invention it is possible to provide the construction of firm safety Platform so that operation platform dodges space away from body of wall 10, the construction for body of wall 10.
For guaranteeing the firm of climbing mould system structure, attached wall guide rail 23 is being risen to the first sloping core section 12 During place, the bottom of attached wall guide rail 23 is connected with stalk section 11 by attached wall cushion block 111.At attached wall When guide rail 23 needs to climb, then this connection is released.
The bracket unit 42 installed in the bottom of support platform 31 can be arranged as required to multiple, at figure Shown in example in, the bottom of support platform 31 is provided with two bracket unit 42.Bracket unit 41 include vertical rod 422 and cross bar 423, hinged between vertical rod 422 and cross bar 423, regulate screw mandrel Between 421 oblique two vertical rods 422 being located at the side being perpendicular to Core Walls Structure 10, regulate screw mandrel The adjustable length of 421, by the length adjustment of regulation 421, controls the angle of inclination of vertical rod 422. Certainly, regulation screw mandrel 421 can also prop up and be located between two cross bars 423, it is also possible to will regulate screw mandrel Prop up and be located between cross bar 423 and vertical rod 422, all can realize the inclination angle of bracket unit 42.Top The top of two vertical rods 422 of the bracket unit 42 in portion is supported by I-steel and is connected to support platform The bottom of 31.Bracket unit 42 provides working place for operator, when creeping formwork, and constructor Member needs lower at bracket unit 42, checks the attached wall guide rail of bottom.
Utilize the inclination angle adjusting creeping formwork support body, and the operation platform reduced on creeping formwork support body is executed with sloping core section The distance in territory, work area, convenient construction operates, and reduces construction safety risk.And creeping formwork support body is when tilting, Being able to ensure that operation platform is horizontal, Stability Analysis of Structures is firm, it is ensured that construction safety.In stalk section and During the climbing formwork for construction of sloping core section, climb attached wall guide rail still according to conventional method, although attached wall guide rail At sloping core inclined, but by adjust regulation support bar so that support platform is level Shape, would not affect the stability of creeping formwork support body on support platform, it is ensured that the construction peace of creeping formwork support body Entirely.The climbing form method of the present invention, compared to the method for the existing ruggedized construction set up and protrude out, construction Simplicity, operation is simple, and the regulation support bar i.e. utilizing setting is horizontal to regulate support platform, Can be the most time-consuming, and then the construction period can be shortened.
Above in association with accompanying drawing embodiment, the present invention is described in detail, ordinary skill people in this area The present invention can be made many variations example by member according to the above description.Thus, some details in embodiment Should not constitute limitation of the invention, the present invention by the scope that defines using appended claims as this The protection domain of invention.

Claims (10)

1. the climbing form system for sloping core construction, it is characterised in that including:
Attached wall guide rail, is attached to be positioned in the first sloping core section on stalk section;
It is connected to the creeping formwork rail on described attached wall guide rail;
Being layed in the support platform at described creeping formwork rail top, described support platform cuts with scissors with described creeping formwork rail Connect;
Prop up and be located at the regulation support bar between described support platform and described creeping formwork rail;And
Propping up and be located at described support platform and adjustable inclination creeping formwork support body, described creeping formwork support body leads to Cross adjustment inclination angle to tilt to described first sloping core section.
2. the climbing form system for sloping core construction as claimed in claim 1, it is characterised in that institute State creeping formwork support body and include being erected on the carrier unit of the adjustable inclination on described support platform, described The corner of carrier unit is hinged, and has installed regulation push rod on described carrier unit.
3. the climbing form system for sloping core construction as claimed in claim 1 or 2, it is characterised in that Described creeping formwork support body also includes a bracket unit being located at described support mesa base, described bracket unit Corner be hinged, and in described bracket unit, installed regulation screw mandrel.
4. the climbing form system for sloping core construction as claimed in claim 1, it is characterised in that institute State regulation support bar include being positioned at the adjusting sleeve pipe at middle part and be screwed together in propping up of described adjusting sleeve pipe two ends Support screw rod, superposed described studdle is fastenedly connected with described support platform, is positioned at bottom Described studdle is fastenedly connected with described creeping formwork rail.
5. the climbing form system for sloping core construction as claimed in claim 1, it is characterised in that institute The bottom stating attached wall guide rail is connected with described stalk section by attached wall cushion block.
6. a construction method for the climbing form system that application is constructed for sloping core as claimed in claim 1, It is characterized in that, including:
Adjust the inclination angle of creeping formwork support body being positioned on described support platform so that described creeping formwork support body to First sloping core section to be onstructed tilts;
The creeping formwork support body tilted is utilized to complete the construction of the first sloping core section;
In described first sloping core section, climbing boots is installed;
Climb attached wall guide rail, and the climbing boots of described attached wall guide rail Yu described first sloping core section is fixed this chain Connect, so that described attached wall guide rail is in the heeling condition drawn close to described first sloping core section;
Described regulation support bar is utilized to be adjusted to horizontal by described support platform;
Described creeping formwork support body is utilized to carry out sloping core construction on described first sloping core section.
7. construction method as claimed in claim 6, it is characterised in that adjust and be positioned at described support The inclination angle of the creeping formwork support body on platform, including:
Described creeping formwork support body includes the support list being erected on the adjustable inclination on described support platform Unit, the corner of described carrier unit is hinged, and has installed regulation push rod on described carrier unit;
Utilize described regulation push rod regulate described carrier unit inclination angle, with realize described carrier unit to The heeling condition that described first sloping core section is drawn close.
Construction method the most as claimed in claims 6 or 7, it is characterised in that climb attached wall guide rail Afterwards, also include the inclination angle adjusting the creeping formwork support body being positioned at described support mesa base,
Described creeping formwork support body includes a bracket unit being located at described support mesa base, described bracket list The corner of unit is hinged, and has installed regulation screw mandrel in described bracket unit;
Described regulation screw mandrel is utilized to regulate described bracket unit, to realize described bracket unit to described the The heeling condition that one sloping core section is drawn close.
9. construction method as claimed in claim 6, it is characterised in that utilize described regulation to support Described support platform is adjusted to horizontal by bar, including:
Described regulation support bar includes being positioned at the adjusting sleeve pipe at middle part and being screwed together in described adjusting sleeve pipe two The studdle of end, the described studdle that will be located in top is fastenedly connected with described support platform, will The described studdle being positioned at bottom is fastenedly connected with described creeping formwork rail;
When described first sloping core section slopes inwardly, screw described of described adjusting sleeve pipe regulation two ends Support screw rod screws in described regulating sleeve, until described support platform is horizontal;
When described first sloping core section is outward-dipping, screw described of described adjusting sleeve pipe regulation two ends Support screw rod screws out described regulating sleeve, until described support platform is horizontal.
10. construction method as claimed in claim 6, it is characterised in that climb attached wall guide rail time, The bottom of described attached wall guide rail is connected with described stalk section by attached wall cushion block.
CN201610383392.3A 2016-06-02 2016-06-02 Climbing form system and its construction method for sloping core construction Active CN105908966B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610383392.3A CN105908966B (en) 2016-06-02 2016-06-02 Climbing form system and its construction method for sloping core construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610383392.3A CN105908966B (en) 2016-06-02 2016-06-02 Climbing form system and its construction method for sloping core construction

Publications (2)

Publication Number Publication Date
CN105908966A true CN105908966A (en) 2016-08-31
CN105908966B CN105908966B (en) 2017-12-22

Family

ID=56741991

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610383392.3A Active CN105908966B (en) 2016-06-02 2016-06-02 Climbing form system and its construction method for sloping core construction

Country Status (1)

Country Link
CN (1) CN105908966B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107165412A (en) * 2017-07-17 2017-09-15 北京市建筑工程研究院有限责任公司 A kind of rotatable attachment device and construction method for attached plate formula creeping formwork
CN107558728A (en) * 2017-06-30 2018-01-09 上海建工集团股份有限公司 Hydraulic climbing formwork climbs device for adjusting posture, hydraulic climbing formwork and attitude adjusting method
CN107607991A (en) * 2017-09-27 2018-01-19 舟山北化聚合物加工技术研究所有限责任公司 A kind of Simple earthquake earthquake intensity instrument mounting bracket and installation method
CN108678366A (en) * 2018-06-13 2018-10-19 四川省第六建筑有限公司 From the huge column form frame system of angle
CN110945195A (en) * 2017-06-30 2020-03-31 Hws混凝土塔有限公司 Self-climbing apparatus for vertical and quasi-vertical concrete surfaces
CN111705662A (en) * 2020-05-22 2020-09-25 中建三局集团有限公司 Deformable frame suitable for inclined structure construction
CN114541626A (en) * 2022-03-04 2022-05-27 中建八局第二建设有限公司 Construction method for core tube inclined wall of super high-rise building
CN114541740A (en) * 2022-01-06 2022-05-27 上海建工一建集团有限公司 Integral steel platform formwork equipment for inclined wall construction and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2622840C2 (en) * 1975-06-05 1983-10-13 Coignet S.A., Paris Climbing frame unit with associated formwork
JPH07122253B2 (en) * 1992-11-20 1995-12-25 伸光企業株式会社 Concrete formwork support member
CN1912314A (en) * 2006-08-28 2007-02-14 杨秋利 Automatic hydraulic climbing shuttering
KR20090105907A (en) * 2009-09-18 2009-10-07 진성토건 주식회사 Lifting unit mounting apparatus for auto climbing system
CN103422668A (en) * 2013-08-09 2013-12-04 中建四局第六建筑工程有限公司 Construction method of super-thick large-slope shear wall and hydraulic self-jacking inclined creeping framework thereof
CN204662951U (en) * 2015-05-12 2015-09-23 浙江欣捷建设有限公司 High tower hydraulic climbing scaffold
CN204983639U (en) * 2015-07-03 2016-01-20 中国十七冶集团有限公司 Super high -rise building outer wall variable cross section department creeping formwork device
CN206289964U (en) * 2016-06-02 2017-06-30 中国建筑第八工程局有限公司 For the climbing form system of sloping core construction

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2622840C2 (en) * 1975-06-05 1983-10-13 Coignet S.A., Paris Climbing frame unit with associated formwork
JPH07122253B2 (en) * 1992-11-20 1995-12-25 伸光企業株式会社 Concrete formwork support member
CN1912314A (en) * 2006-08-28 2007-02-14 杨秋利 Automatic hydraulic climbing shuttering
KR20090105907A (en) * 2009-09-18 2009-10-07 진성토건 주식회사 Lifting unit mounting apparatus for auto climbing system
CN103422668A (en) * 2013-08-09 2013-12-04 中建四局第六建筑工程有限公司 Construction method of super-thick large-slope shear wall and hydraulic self-jacking inclined creeping framework thereof
CN204662951U (en) * 2015-05-12 2015-09-23 浙江欣捷建设有限公司 High tower hydraulic climbing scaffold
CN204983639U (en) * 2015-07-03 2016-01-20 中国十七冶集团有限公司 Super high -rise building outer wall variable cross section department creeping formwork device
CN206289964U (en) * 2016-06-02 2017-06-30 中国建筑第八工程局有限公司 For the climbing form system of sloping core construction

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107558728A (en) * 2017-06-30 2018-01-09 上海建工集团股份有限公司 Hydraulic climbing formwork climbs device for adjusting posture, hydraulic climbing formwork and attitude adjusting method
CN110945195A (en) * 2017-06-30 2020-03-31 Hws混凝土塔有限公司 Self-climbing apparatus for vertical and quasi-vertical concrete surfaces
CN107165412A (en) * 2017-07-17 2017-09-15 北京市建筑工程研究院有限责任公司 A kind of rotatable attachment device and construction method for attached plate formula creeping formwork
CN107165412B (en) * 2017-07-17 2023-06-09 北京市建筑工程研究院有限责任公司 Rotatable attaching device for attaching plate type climbing formwork and construction method
CN107607991A (en) * 2017-09-27 2018-01-19 舟山北化聚合物加工技术研究所有限责任公司 A kind of Simple earthquake earthquake intensity instrument mounting bracket and installation method
CN108678366A (en) * 2018-06-13 2018-10-19 四川省第六建筑有限公司 From the huge column form frame system of angle
CN108678366B (en) * 2018-06-13 2024-02-09 华西工程科技(深圳)股份有限公司 Self-angle-changing large column formwork system
CN111705662A (en) * 2020-05-22 2020-09-25 中建三局集团有限公司 Deformable frame suitable for inclined structure construction
CN114541740A (en) * 2022-01-06 2022-05-27 上海建工一建集团有限公司 Integral steel platform formwork equipment for inclined wall construction and construction method thereof
CN114541626A (en) * 2022-03-04 2022-05-27 中建八局第二建设有限公司 Construction method for core tube inclined wall of super high-rise building

Also Published As

Publication number Publication date
CN105908966B (en) 2017-12-22

Similar Documents

Publication Publication Date Title
CN105908966A (en) Creeping formwork system for oblique wall construction and construction method of creeping formwork system
CN106401174A (en) Creeping formwork system used for construction of variable cross-section core tube and construction method of creeping formwork system
KR100707549B1 (en) Rail mounted climbing system
US8348221B2 (en) Formwork system for constructing a structural concrete floor with projecting floor beams
CN206289964U (en) For the climbing form system of sloping core construction
US20130020732A1 (en) Adjustable Formwork Climber
US4470574A (en) Support structure for building forms
CN109537865A (en) A kind of Super High multi-curvature variation camber line outer climbing frame
CN206736864U (en) Hydraulic self-lifting cantilever heavy type arch dam shuttering work platform
CN206289963U (en) For the climbing form system of section Core tube construction
CN207919556U (en) A kind of device for controlling steel column center and adjusting steel column deflection
CN107816209B (en) The large-scale Roof Truss construction technology of installation is lifted across outer two sides
CN108729640A (en) A kind of supporting rack of assembled architecture cantilevered plate and overhanging method of plate installation
FI126773B (en) Vertical support structure for guardrail construction in roofing
JP3225238U (en) Gazebo tent
CN106567338B (en) A kind of curve tilts the first section steel anchor box installation positioning accuracy regulating device of king-post
CN110359696A (en) A kind of adjustable attachment type raise scaffold and its tiltedly climb method
US10570631B2 (en) Diagonal reinforcement for support structures for floor formwork and method for mounting same
JP3205646U (en) Scaffolding bracket
KR102102440B1 (en) Apparatus for self lifting and pull down jack support using support, and method for lifting and pull down jack support using this same
CN205558259U (en) A adjustable bearing structure for frame template
CN209081267U (en) A kind of fast erecting hanger
CN207878662U (en) Combined type pre-embedded steel slab
CN205243068U (en) Support arrangement for be used for floor template
CN220789460U (en) Small box girder adjusting jacking frame

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190114

Address after: 200122 Pudong New Area, Shanghai, China (Shanghai) free trade trial area 1568 Century Avenue 27

Co-patentee after: China Huashi Enterprises Co., Ltd.

Patentee after: China Construction Eighth Engineering Division Co., Ltd.

Co-patentee after: Sichuan No.6 Construction Co., Ltd.

Address before: 27th Floor, 1568 Century Avenue, China (Shanghai) Free Trade Pilot Area, Pudong New Area, Shanghai, 2013

Patentee before: China Construction Eighth Engineering Division Co., Ltd.

TR01 Transfer of patent right