CN1059012C - Technology for quickly resuming normal construction after wellhole submerged by sudden water - Google Patents
Technology for quickly resuming normal construction after wellhole submerged by sudden water Download PDFInfo
- Publication number
- CN1059012C CN1059012C CN98110054A CN98110054A CN1059012C CN 1059012 C CN1059012 C CN 1059012C CN 98110054 A CN98110054 A CN 98110054A CN 98110054 A CN98110054 A CN 98110054A CN 1059012 C CN1059012 C CN 1059012C
- Authority
- CN
- China
- Prior art keywords
- water
- grouting
- normal construction
- shaft
- shaft bottom
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The present invention relates to a technological method for rapidly recovering normal construction after shafts are submerged by water inrush, which is characterized in that a water stopping pad is built on the bottom of a well by a method for filling stones and injecting slurry; then, inrushing water on the bottom of the well is drawn out, holes are drilled and slurry is injected to surrounding rock, cracks are blocked, and the normal construction can be recovered by pad breaking tunnelling. The method has the advantages of good water stopping effect, small engineering quantity, short construction period and little investment, is especially suitable for water inrush happening to shaft digging of salt mineral deposits, and is a method for recovering the normal construction with special effect to shaft submersion whose water depth is more than 60m.
Description
The invention belongs to the special construction method of pit shaft engineering in the mine construction.
At surface water enrichment basement rock is that the salt deposit shaft of vertical well of limestone is dug well in the construction, prominent watered-out well accident often takes place, analyzing reason mainly is that bedrock fracture is grown and surface water forms pure conduit pipe, in case prominent watered-out well takes place, is difficult to resume production, causes pitshaft to scrap.Dawenkou, Shandong gypsum mining area for example, existing three water bursting in mine are scrapped and are caused huge economy to decrease.They preferably adopt surface grout injection method and all not successes of constructing concrete waterstop pad method under water in resuming production.In the shaft building of colliery, also have and adopt pre grouting from the surface religious services or rituals elder generation shutoff crack to prevent gushing water, its method is that slip casting is carried out, shutoff crack, tunneling construction then in the hole of drilling in the pit shaft country rock on ground.This method is resumed production as being used for prominent watered-out well, and the boring amount is big, and grouting amount is big, the construction costs height, and the construction period is long, reaches eight months time, and effect is also undesirable.Constructing concrete waterstop pad method under water, be by pipeline placing of concrete in the water of shaft bottom on ground, after treating concrete setting, draw water again to country rock perforating slip casting, this method is suitable for being flooded 60 meters shallow water pit shafts with the interior depth of water, and concrete easily produces segregation Qinshui phenomenon when the depth of water, and waterstop pad intensity is low, plugging effect is bad, still can not recover normal construction.
Purpose of the present invention, provide a kind of more than 60 meters behind the well depth wellhole submerged by sudden water stagnant water effect good, the boring amount is few, grouting amount is few, the construction period is short, the new method of the rapid recovery normal construction of small investment.
Technical scheme of the present invention is: 1, flooded the shaft bottom with the slip casting method of rockfilling at quilt and construct the coagulation waterstop pad, construction method is:
(1) at first makes a round platform formula metallic structures, metallic structures comprises the Grouting Pipe framework, the base diameter of this framework is to be advisable by pit shaft, fix a waterstop pad Grouting Pipe at frame center, fixing some breeches pipes of side direction welding around Grouting Pipe, prop up breeches pipe and be connected, fixing some pre-buried slip casting sleeve pipes around framework with Grouting Pipe.
(2) metallic structures is transferred to the shaft bottom of being flooded pit shaft, insert stone to the shaft bottom then, insert highly to calculate and decide on the pressure size of gushing water pressure head;
(3) to connect grouting method routinely injects cement grout, cement grout in the stone in shaft bottom water/binder ratio be 0.6-1 to the waterstop pad Grouting Pipe in ground configuration grouting pump and pit shaft: 1, and mix the early strength admixture of cement amount 3-5%, inject the cement grout after coagulation and form waterstop pad.
2. draw water and bore injected hole
After waterstop pad forms, extract the gushing water flooded in the pit shaft out, in design pit shaft country rock, bore the degree of depth that injected hole, hole depth surpass the fractured rock that leaks by the pre-buried slip casting sleeve pipe on the metallic structures with water pump.
3. to the slip casting of pit shaft wall-rock crack
Grouting method is to injected hole cement injection or other grouting for water blocking materials routinely by the surface grout injection pump, and during as the injection cement paste, water/binder ratio should be grasped 1.5~0.75 according to the wall-rock crack size: between 1, until the crack all is full of.
4. broken pad driving
After the slurries of waiting to inject wall-rock crack solidify, also can adopt the broken pad driving of drilling and blasting method, recover normal construction.
The present invention has following good effect: can recover normal construction at short notice after the pit shaft gushing water is flooded, water plugging effect is good, and the boring amount is few, and grouting amount is little, the small investment instant effect.Flooded for the deep-well of well depth especially, also communication quick-recovery normal construction above 60 meters.
Specific embodiment of the present invention is described according to Fig. 1, Fig. 2.
Fig. 1 is the metallic structures schematic diagram, 1-framework among the figure, and 2-waterstop pad Grouting Pipe, 3-props up breeches pipe, the pre-buried slip casting sleeve pipe of 4-;
Fig. 2 is a construction schematic diagram of the present invention, the 5-borehole wall among the figure, and the 6-grouting pump, 7-concrete waterstop pad, the 8-inlet well, the 9-aquifer, 10-is flooded gushing water.
One, after pit shaft is flooded, at shaft bottom constructing concrete grout cover (7), at first makes metallic structures before constructing with the slip casting method of rockfilling.The structure of metallic structures such as Fig. 1 weld fixedly waterstop pad Grouting Pipe (2) at the center of round platform formula metal framework (1), and a breeches pipe (3) is welded in the some holes of the staggered reservation in side on every hole around Grouting Pipe (2), and propping up on the breeches pipe (3) has some apertures; The evenly fixing some pre-buried slip casting sleeve pipes (4) of around framework (1), how much quantity decides to be generally the 6-8 root on the size of rock crack.
Metallic structures as shown in Figure 2, is transferred to shaft bottom with wire rope suspensioning with winch with metallic structures after making, and the border is consistent as far as possible and vertical as far as possible with the wellbore centre line with the spacing all around of the borehole wall (5).Insert stone to the shaft bottom then, the granularity of stone is advisable with 20-40mm, and filling thickness is decided according to the size and the grouting pressure of gushing water pressure head.As calculated generally in 5-10 rice; After stone is filled to design thickness, connect by grouting pump (6) and center Grouting Pipe (2) that ground is provided with, grouting method injects cement grout routinely, size levelling water/binder ratio according to the grouting pressure value, water/binder ratio is at 0.6-1.1: between 1, the early strength admixture of cement amount 3-5% to be mixed in the slurries, waterstop pad (7) can be solidified as after cement paste is filled with 7 days.
Two, extract the gushing water (10) that is flooded pit shaft out by the water pump on ground, rock drill is set in pit shaft then bores injected hole (8) by pre-buried slip casting sleeve pipe (4) fissure rock around pit shaft, drilling depth surpasses aquifer (9), and the foot of hole circle directly is greater than the 3-5 rice of pit shaft intended diameter.
Three, after boring is accomplished fluently, in boring, inject the water blockoff slurries by surface grout injection pump (6) with conventional grouting method, generally select cement grout for use, water/binder ratio is aligned at any time according to grouting pressure, reduce water/binder ratio when pressure is big, generally levelling between 1.5: 1 and 0.75: 1, stifled real until crack around the pit shaft is filled with.
Four, also available drill eye blasting method broke waterstop pad after slurries to be injected solidified, and recovered normal pit shaft tunneling construction.
Claims (1)
1. recover the technical method of normal construction behind the wellhole submerged by sudden water rapidly, it is characterized in that;
1.1 at first adopt the slip casting method of rockfilling being flooded shaft bottom constructing concrete waterstop pad, construction method is:
1.1.1 make metallic structures according to mineshaft diameter, it comprises the Grouting Pipe framework, frame center is fixed with the waterstop pad Grouting Pipe, welds some breeches pipes around the Grouting Pipe, is fixed with pre-buried slip casting sleeve pipe around the framework;
1.1.2 metallic structures transferred to flooded the shaft bottom, insert stone to the shaft bottom then;
In the stone of shaft bottom, inject cement grout according to a conventional method 1.1.3 connect Grouting Pipe, solidify the back and form waterstop pad at the ground configuration grouting pump;
1.2 waterstop pad blocks after the shaft bottom leaks, and extracts the gushing water that is flooded in the pit shaft out with water pump, bores injected hole by pre-buried slip casting sleeve pipe in the country rock of design pit shaft;
1.3 grouting method injects the water blockoff slurries by injected hole to the pit shaft wall-rock crack routinely, is full of until the crack;
1.4 also can break the pad driving after slurries to be injected solidify, recover normal construction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN98110054A CN1059012C (en) | 1998-02-09 | 1998-02-09 | Technology for quickly resuming normal construction after wellhole submerged by sudden water |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN98110054A CN1059012C (en) | 1998-02-09 | 1998-02-09 | Technology for quickly resuming normal construction after wellhole submerged by sudden water |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1225974A CN1225974A (en) | 1999-08-18 |
CN1059012C true CN1059012C (en) | 2000-11-29 |
Family
ID=5220144
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN98110054A Expired - Fee Related CN1059012C (en) | 1998-02-09 | 1998-02-09 | Technology for quickly resuming normal construction after wellhole submerged by sudden water |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN1059012C (en) |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102536247B (en) * | 2010-12-30 | 2014-07-30 | 中国华冶科工集团有限公司 | Construction method of still-water cement grout pad |
CN102168564B (en) * | 2011-04-22 | 2012-11-07 | 北京科技大学 | Reconstruction and recovery technology for upright mine and vertical mine shafts after catastrophic collapse |
CN102587859A (en) * | 2012-04-17 | 2012-07-18 | 中国矿业大学(北京) | Technology for blocking mine water bursting through backflow grouting |
CN103046558B (en) * | 2012-12-27 | 2015-06-17 | 湖南省交通规划勘察设计院 | Shallow-buried karst cave filing construction method and shallow-buried karst cave filing construction structure |
CN108868776B (en) * | 2018-07-06 | 2019-10-25 | 中钢集团马鞍山矿山研究院有限公司 | The high pressure-bearing broken rock of deep-well induces pre-pouring grout reinforcement means in advance |
CN108915690B (en) * | 2018-07-06 | 2020-01-17 | 中钢集团马鞍山矿山研究院有限公司 | Novel method for preventing water gushing of vertical shaft well wall in vertical shaft aquifer tunneling |
CN109162731B (en) * | 2018-08-16 | 2020-02-07 | 山东科技大学 | Water inrush grouting treatment method for deep mining of iron mine area |
CN108975829B (en) * | 2018-09-11 | 2021-03-16 | 中铁隧道局集团有限公司 | Plugging material and plugging method for burst of deep shaft working surface of railway tunnel |
CN109209387A (en) * | 2018-09-17 | 2019-01-15 | 龙口矿业集团有限公司 | Concrete grout cover construction method under deep water level |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1063740A (en) * | 1992-03-06 | 1992-08-19 | 张燮 | Shaft and raise construction method |
CN1078016A (en) * | 1993-01-15 | 1993-11-03 | 山西矿业学院 | All supporting type well rigs of vertical borehole wall ring and job practices thereof |
-
1998
- 1998-02-09 CN CN98110054A patent/CN1059012C/en not_active Expired - Fee Related
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1063740A (en) * | 1992-03-06 | 1992-08-19 | 张燮 | Shaft and raise construction method |
CN1078016A (en) * | 1993-01-15 | 1993-11-03 | 山西矿业学院 | All supporting type well rigs of vertical borehole wall ring and job practices thereof |
Also Published As
Publication number | Publication date |
---|---|
CN1225974A (en) | 1999-08-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110230309B (en) | Karst area bridge karst cave pile foundation construction method | |
CN102705005B (en) | Technology for plugging water bursting in mine by directional diversion grouting | |
CN110821503B (en) | Construction method for main body of ultra-deep shield section air shaft after tunnel advance | |
CN104453913A (en) | Vertical shaft working face ahead pre-grouting method | |
CN104481560A (en) | Roadway roof aquifer treatment method | |
CN102587859A (en) | Technology for blocking mine water bursting through backflow grouting | |
CN111075478A (en) | Pre-grouting reinforcement process for ground construction of broken belt of excavation working face structure | |
CN1059012C (en) | Technology for quickly resuming normal construction after wellhole submerged by sudden water | |
CN109798140A (en) | Km Deep Soft Rock fracture grouting support reinforcement method | |
CN108915690B (en) | Novel method for preventing water gushing of vertical shaft well wall in vertical shaft aquifer tunneling | |
CN111764960B (en) | Coal mining separation layer water damage prevention and control method | |
CN107217987A (en) | Colliery flood administers well boring method | |
CN104711973A (en) | Construction method for small-diameter pile composite foundation | |
CN111577346B (en) | Rock salt stratum tunnel grouting process | |
CN109026011A (en) | Huge thickness rich water Denying Formation dolomite shaft of vertical well water-stop curtain controls grouting process | |
CN107035389B (en) | A kind of construction method for grouting reinforcement and earth's surface construction method | |
CN113445527A (en) | Method for treating leakage of grouting waterproof curtain in underground platform of rail transit | |
CN109162736A (en) | A kind of liquid mixed deep hole circulation Application of High pressure Split Grouting method of air-water mud | |
CN106968252B (en) | Pile pulling recharging method and pile pulling recharging system | |
CN1051226A (en) | Displacement grouting process for aven shaft sinking through quick sand layer | |
CN112523170A (en) | Seepage-proofing treatment method for deep-buried karst seepage channel of reservoir | |
CN114991774A (en) | Ground subsection descending type grouting method for crushed andesite basalt stratum | |
CN111042820B (en) | Construction method for sand layer with oversized pilot hole by vertical shaft raise-shaft method | |
CN202989919U (en) | Pressure-bearing water-sand-layer anchor rod mounting structure | |
CN113445976B (en) | Fracturing method and application of high-plasticity stratum |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C19 | Lapse of patent right due to non-payment of the annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |