CN105896571A - Transient stability emergent switch-off control method based on sectional connection line energy forecast - Google Patents
Transient stability emergent switch-off control method based on sectional connection line energy forecast Download PDFInfo
- Publication number
- CN105896571A CN105896571A CN201610326724.4A CN201610326724A CN105896571A CN 105896571 A CN105896571 A CN 105896571A CN 201610326724 A CN201610326724 A CN 201610326724A CN 105896571 A CN105896571 A CN 105896571A
- Authority
- CN
- China
- Prior art keywords
- power
- generator
- transient
- theta
- time
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000001052 transient effect Effects 0.000 title claims abstract description 72
- 238000000034 method Methods 0.000 title claims abstract description 48
- 238000005259 measurement Methods 0.000 claims abstract description 26
- 230000010355 oscillation Effects 0.000 claims abstract description 18
- 238000004364 calculation method Methods 0.000 claims abstract description 16
- 238000012546 transfer Methods 0.000 claims abstract description 12
- 238000011217 control strategy Methods 0.000 claims abstract description 10
- 230000008859 change Effects 0.000 claims abstract description 6
- 238000011156 evaluation Methods 0.000 claims abstract description 3
- 230000033228 biological regulation Effects 0.000 claims description 7
- 238000005070 sampling Methods 0.000 claims description 7
- 230000004044 response Effects 0.000 claims description 6
- 238000013213 extrapolation Methods 0.000 claims description 3
- 230000001276 controlling effect Effects 0.000 claims 2
- 230000001105 regulatory effect Effects 0.000 claims 1
- 238000012163 sequencing technique Methods 0.000 claims 1
- 230000006641 stabilisation Effects 0.000 claims 1
- 238000011105 stabilization Methods 0.000 claims 1
- 238000005516 engineering process Methods 0.000 description 5
- 238000004458 analytical method Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 4
- 238000005457 optimization Methods 0.000 description 4
- 238000004870 electrical engineering Methods 0.000 description 3
- 230000008569 process Effects 0.000 description 3
- 238000004088 simulation Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 238000005381 potential energy Methods 0.000 description 2
- 230000001360 synchronised effect Effects 0.000 description 2
- 238000012795 verification Methods 0.000 description 2
- 230000002776 aggregation Effects 0.000 description 1
- 238000004220 aggregation Methods 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 239000012141 concentrate Substances 0.000 description 1
- 230000007123 defense Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000001419 dependent effect Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 238000003012 network analysis Methods 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000011002 quantification Methods 0.000 description 1
- 238000004445 quantitative analysis Methods 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
- H02J3/24—Arrangements for preventing or reducing oscillations of power in networks
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
- H02J3/001—Methods to deal with contingencies, e.g. abnormalities, faults or failures
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
- H02J3/002—Flicker reduction, e.g. compensation of flicker introduced by non-linear load
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E60/00—Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Supply And Distribution Of Alternating Current (AREA)
- Control Of Eletrric Generators (AREA)
Abstract
本发明公开了一种基于区间联络线能量预测的暂态稳定紧急切机控制方法,属于电力系统安全稳定控制技术领域。包括如下步骤:步骤1:紧急控制能量评估,当判定系统暂态失稳后,根据振荡中心所在联络线量测数据,预估系统的完整暂态能量,并计算联络线调节功率;步骤2:采集电网中各地区发电机的转速量测数据,定时计算发电机的暂态动能变化指标,并刷新切机序位表;步骤3:根据离线计算获得的发电机‑联络线功率转移分布因子,制定基于最小切机量的暂态稳定控制策略。本发明克服常规基于发电机量测数据的暂态稳定控制方法所存在依赖全网量测数据、时效性差、工程可行性低的缺点,具备所需量测少、计算效率高、针对性强的特点。
The invention discloses a transient stable emergency cut-off control method based on interval tie line energy prediction, and belongs to the technical field of power system safety and stability control. It includes the following steps: Step 1: Emergency control energy evaluation. When the transient instability of the system is determined, the complete transient energy of the system is estimated according to the measurement data of the tie line where the oscillation center is located, and the adjustment power of the tie line is calculated; Step 2: Collect the speed measurement data of generators in various regions in the power grid, regularly calculate the transient kinetic energy change indicators of the generators, and refresh the machine cut-off sequence table; Step 3: According to the generator-tie line power transfer distribution factor obtained by offline calculation, Formulate a transient stability control strategy based on the minimum shedding amount. The invention overcomes the disadvantages of the conventional transient stability control method based on generator measurement data, such as relying on the measurement data of the entire network, poor timeliness, and low engineering feasibility, and has the advantages of less required measurement, high calculation efficiency, and strong pertinence features.
Description
技术领域technical field
本发明涉及电力系统安全稳定控制技术领域,特别是基于区间联络线能量预测的暂态稳定紧急切机控制方法。The invention relates to the technical field of power system safety and stability control, in particular to a transient stability emergency cut-off control method based on interval tie line energy prediction.
背景技术Background technique
合理、有效的暂态稳定控制是电力系统安全稳定防线的核心内容。现有的电力系统紧急控制通常采用事件驱动的控制技术:通过离线仿真或者在线预算方式得到对象电网在预想故障下的运行轨迹和稳定性特征,从而制定针对性的控制措施,当实际扰动发生后,通过事件匹配触发相应控制策略。该类方法具有简单、快速、针对性强的特点,但控制的可靠性依赖于数值仿真的准确性,且无法应对预想故障外的意外事故。Reasonable and effective transient stability control is the core content of power system security and stability defense. Existing power system emergency control usually adopts event-driven control technology: the operation trajectory and stability characteristics of the target power grid under expected faults are obtained through offline simulation or online budgeting, so as to formulate targeted control measures. When the actual disturbance occurs , and trigger the corresponding control strategy through event matching. This type of method has the characteristics of simplicity, speed, and strong pertinence, but the reliability of control depends on the accuracy of numerical simulation, and it cannot deal with accidents other than expected failures.
随着广域量测技术的广泛应用,响应驱动的暂态稳定控制技术已成为可能。文献一《运动稳定性量化理论》(江苏科学技术出版社,1999年)提出了扩展等面积法则,基于发电机功角量测进行系统暂态失稳判别与控制。该方法机具有理性强、适用性好的优点,但是严重依赖于全网发电机的广域响应,由于广域信息的采集和处理存在不确定性时滞,这将严重影响暂态稳定控制的时效性。With the wide application of wide-area measurement technology, response-driven transient stability control technology has become possible. Document 1 "Motion Stability Quantification Theory" (Jiangsu Science and Technology Press, 1999) proposed the extended equal-area law, based on the measurement of the power angle of the generator to identify and control the transient instability of the system. This method has the advantages of strong rationality and good applicability, but it is heavily dependent on the wide-area response of the whole network generator. Due to the uncertain time-lag in the collection and processing of wide-area information, this will seriously affect the transient stability control. Timeliness.
由于经济发展与能源分布的不平衡,大型互联电网通常具有远距离、大容量输电的特征。文献二《基于受扰电压轨迹的电力系统暂态失稳判别:(二)算例分析》(电力系统自动化,2013年,第37卷第17期第58页)指出:区域电网间联系相对薄弱,系统暂态过程中区间联络线的受扰特征明显,易成为振荡中心。文献三《基于网络信息的暂态稳定性定量分析——支路势能法》(中国电机工程学报,2004年,第24卷第5期第1页)研究表明:随着暂态稳定性的下降,系统的暂态势能将集中于振荡中心所在的主振荡支路上,导致系统的同步运行在该支路“撕开”。在此基础上,文献四《利用实测响应信息的暂态功角失稳实时判别方法》(中国电机工程学报,2013,第33卷第34期第171页)提出一种失稳判别方法:建立振荡中心所在联络线功率及相角差相平面,以轨迹特征分析方法辨识系统的暂态稳定性。该方法主要针对互联电网区间暂态失稳特征,所需量测少。但是该方法仅进行了失稳判别,并未涉及暂态稳定控制。Due to the imbalance of economic development and energy distribution, large-scale interconnected power grids are usually characterized by long-distance and large-capacity power transmission. Document 2 "Discrimination of Power System Transient Instability Based on Disturbed Voltage Trajectories: (2) Case Analysis" (Automation of Electric Power Systems, 2013, Vol. 37, No. 17, Page 58) points out that the connection between regional power grids is relatively weak , in the transient process of the system, the interval tie line has obvious disturbance characteristics, and it is easy to become the oscillation center. Literature 3 "Quantitative Analysis of Transient Stability Based on Network Information - Branch Potential Energy Method" (Proceedings of the Chinese Society for Electrical Engineering, 2004, Vol. 24, No. 5, Page 1) shows that: as the transient , the transient potential energy of the system will concentrate on the main oscillation branch where the oscillation center is located, causing the synchronous operation of the system to "tear apart" in this branch. On this basis, Document 4 "Real-time Judgment Method for Transient Power Angle Instability Using Measured Response Information" (Proceedings of the Chinese Society for Electrical Engineering, 2013, Vol. 33, No. 34, Page 171) proposes a method for judging instability: The power of the tie line where the oscillation center is located and the phase angle difference phase plane are used to identify the transient stability of the system with the method of trajectory characteristic analysis. This method is mainly aimed at the transient instability characteristics of the interconnected grid interval, and requires few measurements. However, this method only conducts instability discrimination, and does not involve transient stability control.
发明内容Contents of the invention
本发明所要解决的技术问题是克服现有技术的不足而提供基于区间联络线能量预测的暂态稳定紧急切机控制方法,具备所需量测少、计算效率高、针对性强的特点。The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art and provide a transient stable emergency cut-off control method based on the energy prediction of the interval tie line, which has the characteristics of less required measurements, high calculation efficiency and strong pertinence.
本发明为解决上述技术问题采用以下技术方案:The present invention adopts the following technical solutions for solving the problems of the technologies described above:
根据本发明提出的一种基于区间联络线能量预测的暂态稳定紧急切机控制方法,包括以下步骤:According to the present invention, a transient stability emergency cut-off control method based on interval tie line energy prediction comprises the following steps:
步骤A、紧急控制能量评估,当判定系统暂态失稳后,根据振荡中心所在联络线量测数据,预估系统的完整暂态能量,并计算联络线调节功率;Step A, emergency control energy evaluation, when the transient instability of the system is determined, the complete transient energy of the system is estimated according to the measurement data of the tie line where the oscillation center is located, and the adjustment power of the tie line is calculated;
步骤B、采集电网中各地区发电机的转速量测数据,定时计算发电机的暂态动能变化指标,并刷新切机序位表;Step B. Collect the speed measurement data of generators in various regions in the power grid, regularly calculate the transient kinetic energy change indicators of the generators, and refresh the machine cut-off sequence table;
步骤C、根据离线计算获得的全网各发电机与联络线间的功率转移分布因子,制定基于最小切机量的暂态稳定控制策略;具体如下:Step C, according to the power transfer distribution factors between the generators and the tie lines in the whole network obtained by off-line calculation, formulate a transient stability control strategy based on the minimum cut-off amount; the details are as follows:
由步骤B得到切机序位表先后顺序选取切机对象,并根据功率转移分布因子估计切除多少发电机能够满足步骤A计算得到的联络线调节功率需求,满足下式的最小切机方式,即为维持系统暂态稳定的最佳控制策略;Select the cut-off objects sequentially from the cut-off sequence table obtained in step B, and estimate how many generators to cut off according to the power transfer distribution factor can meet the adjustment power demand of the tie line calculated in step A, and satisfy the minimum cut-off mode of the following formula, namely The optimal control strategy to maintain the transient stability of the system;
D1P1+D2P2+…+DnPn>ΔP,D 1 P 1 +D 2 P 2 +…+D n P n >ΔP,
其中,P1~Pn为切机序位表1~n的发电机有功功率,D1~Dn为切机序位表1~n的发电机与联络线的功率转移分布因子,n为所切除发电机总数,ΔP为联络线调节功率。Among them, P 1 ~ P n is the active power of the generators in the sequence table 1 ~ n of the machine, D 1 ~ D n is the power transfer distribution factor between the generator and the tie line in the table 1 ~ n of the machine sequence, and n is The total number of generators removed, ΔP is the tie-line regulation power.
作为本发明所述一种基于区间联络线能量预测的暂态稳定紧急切机控制方法进一步优化方案,所述步骤A中,计算联络线调节功率,具体实现方法为:As a further optimization scheme of the transient stability emergency cut-off control method based on the energy prediction of the interval tie line in the present invention, in the step A, the adjustment power of the tie line is calculated, and the specific implementation method is as follows:
根据相量测量单元实时获取的振荡中心所在联络线t时刻的有功功率P(t)和相角差θ(t),t为任意采样时刻;当系统稳定时,联络线的有功功率即为机械功率:According to the active power P(t) and phase angle difference θ(t) of the tie line where the oscillation center is located at time t obtained by the phasor measurement unit in real time, t is any sampling time; when the system is stable, the active power of the tie line is the mechanical power:
Pm=P(ts),P m =P(t s ),
其中,ts为系统稳定时刻,P(ts)为ts时刻联络线的有功功率,Pm为机械功率且是恒定值;Among them, t s is the stable moment of the system, P(t s ) is the active power of the tie line at the time t s , P m is the mechanical power and is a constant value;
根据采样周期T,计算t时刻区间转速偏差Δω(t)的离散值:According to the sampling period T, calculate the discrete value of the interval speed deviation Δω(t) at time t:
在系统实际运行中,实时判断系统是否暂态失稳,若tc时刻判定系统暂态失稳,计算此时振荡系统的动能Vk(tc)为:In the actual operation of the system, it is judged in real time whether the system is transiently unstable. If the system is judged to be transiently unstable at time t c , the kinetic energy V k (t c ) of the oscillating system at this time is calculated as:
利用曲线拟合外推方法,进行未来时刻的有功功率快速预测:Use the curve fitting extrapolation method to quickly predict the active power in the future:
其中,为关于相角差θ的有功功率预测值,A,B,C为拟合参数,通过最小二乘法对A,B,C进行参数辨识;in, is the predicted value of active power with respect to the phase angle difference θ, A, B, and C are fitting parameters, and the parameters of A, B, and C are identified by the least square method;
根据有功功率预测值计算系统不稳定平衡点的相角差θb:According to the predicted value of active power Calculate the phase angle difference θ b of the unstable equilibrium point of the system:
进而预测未进行暂态稳定控制时系统的剩余减速面积Sd:Then predict the remaining deceleration area S d of the system without transient stability control:
其中,θc为系统稳定平衡点的相角差;Among them, θ c is the phase angle difference of the stable equilibrium point of the system;
然后计算得到控制补偿面积Sc为:Then calculate the control compensation area Sc as:
Sc=Vk(tc)-Sd,S c =V k (t c )-S d ,
利用失稳判别时刻tc的转速偏差Δω(tc)近似估计控制执行时刻td的相角差θd:Use the rotational speed deviation Δω(t c ) at the instability discrimination time t c to approximate the phase angle difference θ d at the control execution time t d :
θd=θc-Δω(tc)tdelay,θ d = θ c -Δω(t c )t delay ,
其中,tdelay为失稳判别与控制执行之间所存在的时延;Among them, t delay is the time delay between the instability judgment and the control execution;
因此,联络线调节功率ΔP为:Therefore, the adjustment power ΔP of tie line is:
作为本发明所述一种基于区间联络线能量预测的暂态稳定紧急切机控制方法进一步优化方案,tdelay取0.1s。As a further optimization scheme of the transient stability emergency cut-off control method based on the energy prediction of the section tie line in the present invention, t delay is set to 0.1s.
作为本发明所述一种基于区间联络线能量预测的暂态稳定紧急切机控制方法进一步优化方案,所述步骤B中,刷新切机序位表,具体步骤如下:As a further optimization scheme of the transient stability emergency cut-off control method based on the energy prediction of the interval tie line in the present invention, in the step B, refresh the cut-off sequence table, the specific steps are as follows:
步骤B1:设定受扰观测时间窗To,在实际电网运行过程中,实时采样地区发电机i的转速值wi,定时评估在受扰观测时间窗内全网各发电机的动能量,以此计算发电机的受扰严重程度:Step B1: Set the disturbed observation time window T o , during the actual power grid operation, sample the speed value w i of the generator i in the area in real time, and regularly evaluate the kinetic energy of each generator in the whole network within the disturbed observation time window, Calculate the disturbance severity of the generator by this:
其中,Si为地区发电机i在t时刻至t+To时刻之间的受扰严重程度,wi(t)为地区发电机i在t时刻的转速值;Among them, S i is the disturbance severity of regional generator i from time t to time t+T o , and w i (t) is the speed value of regional generator i at time t;
步骤B2:对每次计算得到的全网发电机受扰严重程度进行排序,由数值从大到小制定基于发电机响应的切机序位表;当系统失稳时,以最新的切机序位表顺序选取切机对象。Step B2: Sort the disturbance severity of generators in the whole network obtained by each calculation, and formulate a machine cut-off sequence table based on the generator response from the numerical value in descending order; when the system is unstable, use the latest cut-off sequence The bit table sequentially selects the cut-off objects.
作为本发明所述一种基于区间联络线能量预测的暂态稳定紧急切机控制方法进一步优化方案,To取0.2s。As a further optimization scheme of the transient stability emergency cut-off control method based on the energy prediction of the interval tie line in the present invention, T o is set to 0.2s.
本发明采用以上技术方案与现有技术相比,具有以下技术效果:Compared with the prior art, the present invention adopts the above technical scheme and has the following technical effects:
(1)本发明区别于常规暂态稳定控制方法,无需进行发电机快速分群与等值聚合,仅需少量数据交互与通信,计算效率相对较高;(1) The present invention is different from the conventional transient stability control method. It does not need to perform fast grouping and equivalent aggregation of generators, and only needs a small amount of data interaction and communication, and the calculation efficiency is relatively high;
(2)本发明针对互联电网区间暂态失稳,所需量测较少,具备工程可实施性;(2) The present invention is aimed at the transient instability of the interconnected power grid, requires less measurement, and has engineering feasibility;
(3)本发明计算得到的联络线调节功率,还可用于生成切负荷等其他紧急控制策略;(3) The tie line regulation power calculated by the present invention can also be used to generate other emergency control strategies such as load shedding;
(4)本发明基于电网中现有的相量测量单元及广域量测系统,当区域互联电网发生大扰动并造成系统暂态失稳后,根据区间量测信息评估系统暂态能量,并执行针对性的紧急切机控制策略,以维持系统暂态稳定性;(4) The present invention is based on the existing phasor measurement unit and wide-area measurement system in the power grid. When a large disturbance occurs in the regional interconnected power grid and causes the transient instability of the system, the transient energy of the system is evaluated according to the interval measurement information, and Implement targeted emergency shutdown control strategies to maintain system transient stability;
(5)克服常规基于发电机量测数据的暂态稳定控制方法所存在依赖全网量测数据、时效性差、工程可行性低的缺点,提供了一种针对互联电网区间暂态失稳的切机控制方法,具备所需量测少、计算效率高、针对性强的特点。(5) To overcome the shortcomings of the conventional transient stability control method based on the measurement data of the generator, such as relying on the measurement data of the whole network, poor timeliness, and low engineering feasibility, and provide a solution for the transient instability of the interconnected grid interval The computer control method has the characteristics of less measurement required, high calculation efficiency and strong pertinence.
附图说明Description of drawings
图1是本发明方法的总体流程框图。Fig. 1 is the general flowchart of the method of the present invention.
图2是互联电网区域振荡模式图。Figure 2 is a diagram of the regional oscillation mode of the interconnected grid.
图3是基于区间暂态能量预测的功率调节示意图。Fig. 3 is a schematic diagram of power regulation based on interval transient energy prediction.
图4是IEEE-39节点系统发电机在故障时的受扰功角轨迹图。Fig. 4 is a diagram of the disturbed power angle trajectory of the IEEE-39 node system generator when it is faulty.
图5是IEEE-39节点系统发电机在紧急切机控制后的受扰功角轨迹图。Fig. 5 is the disturbed power angle trajectory diagram of the IEEE-39 node system generator after emergency shutdown control.
具体实施方式detailed description
下面结合附图对本发明的技术方案做进一步的详细说明:Below in conjunction with accompanying drawing, technical scheme of the present invention is described in further detail:
下面根据图1所示的总体方法流程图,对本发明实现的具体步骤进行详细的说明。The specific steps for realizing the present invention will be described in detail below according to the overall method flow chart shown in FIG. 1 .
对于区域互联电网,当观察到系统发生功率振荡现象时,根据振荡中心所在的联络断面可将系统划分为两区域系统,如图2所示。其中子系统A为送端电网,子系统B为受端电网。此时,区间联络线A-B的有功功率可表示为:For the regional interconnection grid, when power oscillation is observed in the system, the system can be divided into two regional systems according to the contact section where the oscillation center is located, as shown in Figure 2. Among them, subsystem A is the sending end power grid, and subsystem B is the receiving end power grid. At this time, the active power of the section tie line A-B can be expressed as:
式中:P为联络线的有功功率。UA和UB分别为送端与受端的电压幅值,XL为联络线电抗,θ为联络线相角差。Where: P is the active power of the tie line. U A and U B are the voltage amplitudes of the sending end and the receiving end respectively, X L is the reactance of the tie line, and θ is the phase angle difference of the tie line.
假设系统具有较强的电压调节能力,即送端和受端的电压幅值UA和UB均为常数。则振荡中心所在联络线即为系统的主振荡支路。其有功功率P可近似表征为关于联络线相角差θ的正弦变化函数。Assume that the system has a strong voltage regulation capability, that is, the voltage amplitudes U A and U B of the sending end and the receiving end are constant. Then the connecting line where the oscillation center is located is the main oscillation branch of the system. Its active power P can be approximately characterized as a sinusoidal change function with respect to the phase angle difference θ of the tie line.
当电网受扰后,系统A存在不平衡功率。若该扰动造成子系统A与B间失去同步,则区域发电机群相对功角递增,造成区间相角差θ增大,联络线功率P剧烈波动。若受扰后联络线功率能够趋于稳定,则子系统间同步运行;反之,系统将暂态失稳。若能尽早地判定系统暂态失稳,可通过切机控制快速调节区间联络线的有功功率,控制振荡系统间的能量变化,以维持全网机组的同步运行。基于上述原因,本发明提出了一种基于区间联络线暂态能量预测的暂态稳定紧急切机控制方法,主要包含以下步骤。When the power grid is disturbed, system A has unbalanced power. If the disturbance causes the loss of synchronization between subsystems A and B, the relative power angle of the regional generator group will increase, resulting in an increase in the phase angle difference θ between the intervals, and the power P of the tie line will fluctuate violently. If the tie-line power can tend to be stable after being disturbed, the subsystems will run synchronously; otherwise, the system will be transiently unstable. If the transient instability of the system can be determined as early as possible, the active power of the inter-section tie line can be quickly adjusted through the cut-off control, and the energy change between the oscillation systems can be controlled to maintain the synchronous operation of the whole network unit. Based on the above reasons, the present invention proposes a transient stability emergency cut-off control method based on the transient energy prediction of the section tie line, which mainly includes the following steps.
步骤1:当判定系统暂态失稳后,根据振荡中心所在的联络线量测,预测系统的完整暂态能量,并计算联络线调节功率,如图3所示。Step 1: When the transient instability of the system is determined, the complete transient energy of the system is predicted according to the measurement of the tie line where the oscillation center is located, and the tie line regulation power is calculated, as shown in Figure 3.
首先根据相量测量单元,实时获取振荡中心所在的联络线t时刻的有功功率P(t)和相角差θ(t),其中t为任意采样时刻。当系统稳定时,联络线的有功功率即为机械功率:First, according to the phasor measurement unit, the active power P(t) and the phase angle difference θ(t) of the tie line where the oscillation center is located at time t are obtained in real time, where t is any sampling time. When the system is stable, the active power of the tie line is the mechanical power:
Pm=P(ts)P m =P(t s )
式中:ts为系统稳定时刻,P(ts)为ts时刻联络线的有功功率。Pm为机械功率,是恒定值。In the formula: t s is the stable moment of the system, and P(t s ) is the active power of the tie line at the time t s . P m is the mechanical power, which is a constant value.
根据采样周期T,计算t时刻区间转速偏差Δω(t)的离散值:According to the sampling period T, calculate the discrete value of the interval speed deviation Δω(t) at time t:
在系统实际运行中,根据文献二《基于受扰电压轨迹的电力系统暂态失稳判别:(二)算例分析》(电力系统自动化,2013年,第37卷第17期第58页)实时判断系统是否暂态失稳。若tc时刻判定系统暂态失稳,计算此时振荡系统的动能Vk(tc)为:In the actual operation of the system, according to Literature 2 "Discrimination of Power System Transient Instability Based on Disturbed Voltage Trajectories: (2) Case Analysis" (Automation of Power Systems, 2013, Vol. 37, No. 17, Page 58) real-time Determine whether the system is transiently unstable. If the transient instability of the system is determined at time t c , the kinetic energy V k (t c ) of the oscillating system at this time is calculated as:
利用文献五《电力系统暂态稳定实时紧急控制的研究》(中国电机工程学报,2003,第23卷第1期第64页)的曲线拟合外推方法,进行未来时刻的有功功率快速预测:Use the curve fitting extrapolation method of Document 5 "Research on Real-time Emergency Control of Power System Transient Stability" (Proceedings of the Chinese Society for Electrical Engineering, 2003, Vol. 23, No. 1, Page 64) to quickly predict the active power in the future:
式中:为关于相角差θ的有功功率预测值,A,B,C为拟合参数,通过最小二乘法对A,B,C进行参数辨识。In the formula: is the predicted value of the active power with respect to the phase angle difference θ, A, B, and C are the fitting parameters, and the parameters of A, B, and C are identified by the least square method.
根据有功功率预测值计算系统不稳定平衡点的相角差θb:According to the predicted value of active power Calculate the phase angle difference θ b of the unstable equilibrium point of the system:
进而预测未进行暂态稳定控制时系统的剩余减速面积Sd:Then predict the remaining deceleration area S d of the system without transient stability control:
式中,θc为系统稳定平衡点的相角差,为系统相角差θ所对应的有功功率预测值。In the formula, θ c is the phase angle difference of the stable equilibrium point of the system, is the predicted value of active power corresponding to the system phase angle difference θ.
然后计算得到控制补偿面积Sc:Then calculate the control compensation area S c :
Sc=Vk(tc)-Sd S c =V k (t c )-S d
利用失稳判别时刻tc的转速偏差Δω(tc)近似估计控制执行时刻td的相角差θd:Use the rotational speed deviation Δω(t c ) at the instability discrimination time t c to approximate the phase angle difference θ d at the control execution time t d :
θd=θc-Δω(tc)tdelay θ d =θ c -Δω(t c )t delay
式中:tdelay为失稳判别与控制执行之间所存在的时延,优选地取0.1s。In the formula: t delay is the time delay between the instability judgment and the control execution, preferably 0.1s.
因此,联络线调节功率ΔP为:Therefore, the adjustment power ΔP of tie line is:
步骤2:采集电网中各地区发电机的转速量测,定时计算发电机的暂态动能变化指标,并刷新切机序位表。Step 2: Collect the speed measurement of generators in various regions in the power grid, regularly calculate the transient kinetic energy change indicators of the generators, and refresh the machine cut-off sequence table.
设定受扰观测时间窗To。在实际电网运行过程中,实时采样地区发电机i的转速值wi,定时评估在受扰观测时间窗内全网各发电机的动能量,以此计算发电机的受扰严重程度:Set the disturbed observation time window T o . In the actual power grid operation process, the speed value w i of generator i in the area is sampled in real time, and the kinetic energy of each generator in the whole network is regularly evaluated within the disturbance observation time window, so as to calculate the severity of generator disturbance:
式中:Si为地区发电机i在t时刻至t+To时刻之间的受扰严重程度,wi(t)为地区发电机i在t时刻的转速值,数值越大说明受扰越严重。受扰观测时间窗To,优选地取0.2s。In the formula: S i is the disturbance severity of regional generator i from time t to time t+T o , w i (t) is the speed value of regional generator i at time t, and the larger the value, the disturbed more serious. The disturbed observation time window T o is preferably 0.2s.
对每次计算得到的全网发电机受扰严重程度进行排序,由数值从大到小制定基于发电机响应的切机序位表。当系统失稳时,以最新的切机序位表顺序选取切机对象。Sorting the disturbance severity of generators in the whole network obtained by each calculation, and formulating a generator cut-off sequence table based on the generator response from the largest value to the smallest value. When the system is unstable, select the cut-off objects in the order of the latest cut-off sequence table.
步骤3:根据离线计算获得的发电机-联络线功率转移分布因子,制定基于最小切机量的暂态稳定控制策略。Step 3: According to the generator-tie line power transfer distribution factor obtained by off-line calculation, formulate a transient stability control strategy based on the minimum shedding amount.
通过离线计算获取全网各发电机与联络线间的功率转移分布因子。具体计算方法见文献六《高等电力网络分析》(清华大学出版社,2004年)。由步骤2得到切机序位表先后顺序选取切机对象,并根据功率转移分布因子估计切除多少发电机能够满足步骤1计算得到的联络线调节功率需求,如下所示:The power transfer distribution factor between each generator and tie line in the whole network is obtained through off-line calculation. For specific calculation methods, see Document 6 "Advanced Power Network Analysis" (Tsinghua University Press, 2004). Select the cut-off objects sequentially from the cut-off sequence table obtained in step 2, and estimate how many generators to cut off can meet the tie-line regulation power demand calculated in step 1 according to the power transfer distribution factor, as shown below:
D1P1+D2P2+…+DnPn>ΔPD 1 P 1 +D 2 P 2 +…+D n P n >ΔP
式中:P1~Pn为切机序位表1~n的发电机有功功率,D1~Dn为切机序位表1~n的发电机与联络线的功率转移分布因子。n为所切除发电机总数。In the formula: P 1 ~ P n is the active power of the generator in the cut-off sequence table 1 ~ n, and D 1 ~ D n is the power transfer distribution factor between the generator and the tie line in the cut-off sequence table 1 ~ n. n is the total number of generators removed.
满足该式的最小切机方式,即为维持系统暂态稳定的最佳控制策略。The minimum cut-off mode that satisfies this formula is the best control strategy to maintain the transient stability of the system.
结果验证:为了测试本发明所述方法的有效性,应用本发明方法对IEEE-39节点系统故障情况进行了仿真验证。Result verification: In order to test the validity of the method of the present invention, the method of the present invention is applied to carry out simulation verification on the failure situation of the IEEE-39 node system.
算例:0时刻线路4-14的母线4侧开关后发生三相短路,0.2s线路主保护拒动,0.3s后备保护动作切除故障。Calculation example: At time 0, a three-phase short circuit occurs after the switch on bus 4 side of line 4-14, the main protection of the line refuses to operate in 0.2s, and the backup protection operates to remove the fault in 0.3s.
此时39节点机组将与其他机组失去同步,系统的主振荡支路为支路2-1,全网发电机受扰功角轨迹如图4所示。采用文献二《基于受扰电压轨迹的电力系统暂态失稳判别:(二)算例分析》(电力系统自动化,2013年,第37卷第17期第58页)方法于扰动后0.54s判定系统暂态失稳。At this time, the unit at node 39 will lose synchronization with other units, and the main oscillation branch of the system is branch 2-1. The disturbed power angle trajectory of the generators in the whole network is shown in Figure 4. Using the method of Document 2 "Discrimination of Power System Transient Instability Based on Disturbed Voltage Trajectory: (2) Case Analysis" (Automation of Electric Power Systems, 2013, Vol. 37, No. 17, Page 58) to judge 0.54s after the disturbance The system is transiently unstable.
此时根据联络线两端量测预测区间暂态能量,计算得到支路2-1的调节功率为43.7MW。在此过程中,利用发电机转速评估机组受扰严重程度,在0-0.2s及0.2-0.4s完成两次切机序位表刷新工作,其中最新切机序位表中受扰最严重发电机为32节点机组。根据离线计算得到32节点发电机与支路2-1的功率转移分布因子为0.183,计算得到最小切机量为238.8MW。假设该节点由5台相同机组构成,总有功出力为650MW,则可切除其中2台机组,合计260MW,以满足最小切机量要求。At this time, according to the transient energy in the prediction interval measured at both ends of the tie line, the adjusted power of branch 2-1 is calculated to be 43.7MW. During this process, the generator speed is used to assess the severity of the unit disturbance, and two refreshes of the cut-off sequence table are completed at 0-0.2s and 0.2-0.4s, among which the most seriously disturbed power generation in the latest cut-off sequence table The machine is a 32-node unit. According to the off-line calculation, the distribution factor of the power transfer between the 32-node generators and the branch 2-1 is 0.183, and the calculated minimum cut-off capacity is 238.8MW. Assuming that the node is composed of 5 identical units with a total active output of 650MW, two of the units can be removed, totaling 260MW, to meet the minimum cut-off requirement.
计及失稳判别与控制执行之间所存在的时延0.1s,于0.64s执行上述暂态稳定控制,切除32节点下260MW发电机,控制后发电机受扰功角轨迹如图5所示。通过本发明计算得到的暂态稳定措施,系统将恢复暂态稳定。Taking into account the time delay of 0.1s between the instability judgment and the control execution, the above transient stability control is executed at 0.64s, and the 260MW generator under 32 nodes is cut off. After the control, the disturbed power angle trajectory of the generator is shown in Figure 5 . Through the transient stability measures calculated and obtained by the present invention, the system will restore transient stability.
从上述结果中可以发现,本发明方法针对性强、效果好,具备工程可实施性。本发明可用于大型区域互联电网的调度控制中心,基于广域量测系统实现基于区间暂态能量预测的互联电网暂态稳定控制,保障电力系统的安全稳定运行。From the above results, it can be found that the method of the present invention has strong pertinence, good effect and engineering feasibility. The invention can be used in a dispatching control center of a large-scale regional interconnection grid, realizes transient stability control of the interconnection grid based on interval transient energy prediction based on a wide-area measurement system, and ensures safe and stable operation of the power system.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610326724.4A CN105896571B (en) | 2016-05-17 | 2016-05-17 | Transient stability based on section interconnection energy predicting promptly cuts machine control method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610326724.4A CN105896571B (en) | 2016-05-17 | 2016-05-17 | Transient stability based on section interconnection energy predicting promptly cuts machine control method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105896571A true CN105896571A (en) | 2016-08-24 |
CN105896571B CN105896571B (en) | 2018-03-09 |
Family
ID=56717313
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610326724.4A Active CN105896571B (en) | 2016-05-17 | 2016-05-17 | Transient stability based on section interconnection energy predicting promptly cuts machine control method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105896571B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110635474A (en) * | 2019-09-16 | 2019-12-31 | 东北电力大学 | A method for predicting dynamic trajectory trend of power grid based on long short-term memory network |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104184169A (en) * | 2014-09-11 | 2014-12-03 | 国家电网公司 | Transient generator tripping control method considering wind power integration and wind-thermal coordination |
CN104466947A (en) * | 2014-11-06 | 2015-03-25 | 中国南方电网有限责任公司 | Method for making interconnected network transient stability emergency control strategies based on inter-region tie line measurement |
JP2016025715A (en) * | 2014-07-18 | 2016-02-08 | 三菱電機株式会社 | Power system stabilization system and power system stabilization method |
-
2016
- 2016-05-17 CN CN201610326724.4A patent/CN105896571B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2016025715A (en) * | 2014-07-18 | 2016-02-08 | 三菱電機株式会社 | Power system stabilization system and power system stabilization method |
CN104184169A (en) * | 2014-09-11 | 2014-12-03 | 国家电网公司 | Transient generator tripping control method considering wind power integration and wind-thermal coordination |
CN104466947A (en) * | 2014-11-06 | 2015-03-25 | 中国南方电网有限责任公司 | Method for making interconnected network transient stability emergency control strategies based on inter-region tie line measurement |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110635474A (en) * | 2019-09-16 | 2019-12-31 | 东北电力大学 | A method for predicting dynamic trajectory trend of power grid based on long short-term memory network |
CN110635474B (en) * | 2019-09-16 | 2022-01-28 | 东北电力大学 | Power grid dynamic trajectory trend prediction method based on long-term and short-term memory network |
Also Published As
Publication number | Publication date |
---|---|
CN105896571B (en) | 2018-03-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102761125B (en) | Closed-loop system capable of identifying transient stability of power system in real time and performing based on response and control method | |
CN101557110B (en) | On-line analysis and aid decision making method for low-frequency oscillation of electric power system | |
CN103279639B (en) | Receiving end Network Voltage Stability overall process Situation Assessment based on response and preventing control method | |
CN103337904B (en) | Power grid out-of-limit and apparatus overload emergency control method based on multi-source data | |
CN105406460B (en) | Unit based on wide area measurement information is encouraged by force supports control method for coordinating with direct-current emergency power | |
CN113285452B (en) | Method for Predicting Transient Instability of Power System and Generate Shutdown Control Strategy | |
CN102709890A (en) | Distribution network protection method taking randomness of photovoltaic power station into consideration | |
CN100554976C (en) | Regional Voltage Stability Monitoring Method Based on Synchronized Phasor Measurement | |
CN103475010A (en) | Transient stabilization control method for interconnection electrical network after impact disturbance | |
Diao et al. | Decision tree assisted controlled islanding for preventing cascading events | |
CN101902072B (en) | New method for identifying disturbance information of large-scale interconnected power system | |
CN109494765B (en) | EEAC-based AC-DC hybrid system transient stability control method | |
CN102185325A (en) | Method for quantitatively evaluating transient stability of electric power system based on network measuring information | |
CN102445660A (en) | Generator Power Angle Prediction Method Based on Gray Verhulst Model | |
Xue | Some viewpoints and experiences on wide area measurement systems and wide area control systems | |
CN104505827B (en) | Complicated electric power system closed loop control method based on response message | |
CN103577698B (en) | A kind of on-Line Voltage stabilizing determination method of alternating current-direct current combined hybrid system | |
CN105896571B (en) | Transient stability based on section interconnection energy predicting promptly cuts machine control method | |
CN103795090B (en) | Based on the emergency control method that the generator reactive of WAMS is exerted oneself | |
CN102946099A (en) | Method for real-time discrimination of transient power angle stability of multi-machine interconnected electric power system | |
CN105844542A (en) | Power grid single large disturbance online detection method based on WAMS | |
CN104750994A (en) | Method for judging transient instability dominance based on outer region power ratio | |
Wu et al. | Monitoring power system transient stability using synchrophasor data | |
Goh et al. | Power stability monitoring based on voltage instability prediction approach through wide area system | |
Popov et al. | Applications of synchrophasor measurement to improve the reliability and efficiency of power systems |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |