CN105888159A - Waterproofing treatment method for substation roof extending pipeline - Google Patents

Waterproofing treatment method for substation roof extending pipeline Download PDF

Info

Publication number
CN105888159A
CN105888159A CN201610287410.8A CN201610287410A CN105888159A CN 105888159 A CN105888159 A CN 105888159A CN 201610287410 A CN201610287410 A CN 201610287410A CN 105888159 A CN105888159 A CN 105888159A
Authority
CN
China
Prior art keywords
pipeline
layer
roof
coiled material
primer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610287410.8A
Other languages
Chinese (zh)
Inventor
罗中华
刘爱梅
李红
阿里木江·阿布力孜
颜晓东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HAMI POWER SUPPLY COMPANY STATE GRID XINJIANG ELECTRIC POWER Co Ltd
State Grid Corp of China SGCC
Original Assignee
HAMI POWER SUPPLY COMPANY STATE GRID XINJIANG ELECTRIC POWER Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HAMI POWER SUPPLY COMPANY STATE GRID XINJIANG ELECTRIC POWER Co Ltd, State Grid Corp of China SGCC filed Critical HAMI POWER SUPPLY COMPANY STATE GRID XINJIANG ELECTRIC POWER Co Ltd
Priority to CN201610287410.8A priority Critical patent/CN105888159A/en
Publication of CN105888159A publication Critical patent/CN105888159A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage; Sky-lights
    • E04D13/16Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Abstract

The invention relates to a waterproofing treatment method for a substation roof extending pipeline. The method comprises the following steps: (1) filling gland packing in a gap between a pipeline and a roof, wherein the gland packing comprises a stacked structure composed of aggregate filler strips, soil filler strips and foam filler strips; (2) laying a base layer on the roof around the pipeline; (3) coating the base layer with multiple layers of prime coat; (4) laying a waterproof breathable film to serve as a secondary waterproof layer, and compacting; (5) coating the outer wall of the pipeline with a PVC coiled material layer, wherein the PVC coiled material layer is adhered to the outer wall of the pipeline by adopting an epoxy adhesive, and the coiled material layer extends downwards to reach the roof around the pipeline so as to cover the base layer; (6) arranging a fastener on the top of the coiled material layer for sealing; and (7) laying an additional waterproof layer at the joint of the coiled material layer and the base layer, and coating a sealant for sealing. Compared with the prior art, the method disclosed by the invention has the advantages that multiple waterproof layers are arranged between the pipeline and the roof, so that the gap at the joint is completely isolated from water, and waterproof performance at the joint is greatly improved.

Description

A kind of roof of transformer substation stretches out the method for waterproofing of pipeline
Technical field
The present invention relates to a kind of waterproof method, especially relate to a kind of roof of transformer substation and stretch out the method for waterproofing of pipeline.
Background technology
Building often has pipeline to stretch out, in order to make roof durable in use, its water resistance must reach certain requirement, Owing to, in these roof structures, some pipeline needs will necessarily be there are and stretches out via roof, therefore remove the waterproof of roof structure layer Outside effect, the waterproofing design at these pipelines is particularly important for the water resistance on whole roof.
Summary of the invention
The shortcoming of prior art in view of the above, defect that the present invention is contemplated to overcome above-mentioned prior art to exist and provide one Plant roof of transformer substation and stretch out the method for waterproofing of pipeline.
For achieving the above object and other relevant purposes, the present invention provides below scheme:
A kind of roof of transformer substation stretches out the method for waterproofing of pipeline, comprises the following steps:
1) gap location at pipeline with roof fills airtight and watertight padding, and described airtight and watertight padding includes sandstone filler strip, earth filler strip, bubble The stepped construction that foam filler strip is constituted;
2) at the roofing basal layer of pipeline;
3) coated with multiple layer primer on the base layer;
4) waterproof ventilated membrane is laid as secondary waterproof layer, compacting;
5) wrapping up one layer of PVC roll sheet material layers at pipeline outer wall, described PVC roll sheet material layers uses epoxy to be bonded on pipeline outer wall, And this coiled material layer is extended downward on the roof of pipeline, cover basal layer;
6) arrange securing member at coiled material layer top to seal;
7) seam crossing at coiled material layer and basal layer lays additional waterproofing layer, and coats fluid sealant and seal;
Step 3) in primer at least coat more than 4 layers;
The painting method of primer is: after preceding layer primer is completely dried, and removes the dust on preceding layer primer surface, the most uniformly Coating later layer primer, until it reaches the number of plies of needs.
Preferably, step 6) described in securing member be ferrule.
Preferably, described waterproof ventilated membrane is highdensity spunbond polyethylene nonwoven.
As it has been described above, the method have the advantages that the present invention to pass through between pipeline and roof, multiple waterproof layer is set, Make the space of its junction completely and water segregation, substantially increase the water resistance of junction, additionally, by pipeline and roof Sealing material is filled in gap between body of wall, while improving water resistance, can adapt to the breathing of pipeline to a certain extent.
Detailed description of the invention
By particular specific embodiment, embodiments of the present invention being described below, those skilled in the art can be taken off by this specification The content of dew understands other advantages and effect of the present invention easily.
A kind of roof of transformer substation stretches out the method for waterproofing of pipeline, comprises the following steps:
1) gap location at pipeline with roof fills airtight and watertight padding, and described airtight and watertight padding includes sandstone filler strip, earth filler strip, bubble The stepped construction that foam filler strip is constituted;
2) at the roofing basal layer of pipeline;
3) coated with multiple layer primer on the base layer;
4) waterproof ventilated membrane is laid as secondary waterproof layer, compacting;
5) wrapping up one layer of PVC roll sheet material layers at pipeline outer wall, described PVC roll sheet material layers uses epoxy to be bonded on pipeline outer wall, And this coiled material layer is extended downward on the roof of pipeline, cover basal layer;
6) arrange securing member at coiled material layer top to seal;
7) seam crossing at coiled material layer and basal layer lays additional waterproofing layer, and coats fluid sealant and seal;
Step 3) in primer at least coat more than 4 layers;
The painting method of primer is: after preceding layer primer is completely dried, and removes the dust on preceding layer primer surface, the most uniformly Coating later layer primer, until it reaches the number of plies of needs.
Preferably, step 6) described in securing member be ferrule.
Preferably, described waterproof ventilated membrane is highdensity spunbond polyethylene nonwoven.
As it has been described above, the method have the advantages that the present invention to pass through between pipeline and roof, multiple waterproof layer is set, Make the space of its junction completely and water segregation, substantially increase the water resistance of junction, additionally, by pipeline and roof Sealing material is filled in gap between body of wall, while improving water resistance, can adapt to the breathing of pipeline to a certain extent.
The principle of above-described embodiment only illustrative present invention and effect thereof, not for limiting the present invention.Any it is familiar with this skill Above-described embodiment all can be modified under the spirit and the scope of the present invention or change by the personage of art.Therefore, such as All that in art, tool usually intellectual is completed under without departing from disclosed spirit and technological thought etc. Effect is modified or changes, and must be contained by the claim of the present invention.

Claims (3)

1. a roof of transformer substation stretches out the method for waterproofing of pipeline, it is characterised in that comprise the following steps:
1) gap location at pipeline with roof fills airtight and watertight padding, and described airtight and watertight padding includes sandstone filler strip, earth filler strip, bubble The stepped construction that foam filler strip is constituted;
2) at the roofing basal layer of pipeline;
3) coated with multiple layer primer on the base layer;
4) waterproof ventilated membrane is laid as secondary waterproof layer, compacting;
5) wrapping up one layer of PVC roll sheet material layers at pipeline outer wall, described PVC roll sheet material layers uses epoxy to be bonded on pipeline outer wall, And this coiled material layer is extended downward on the roof of pipeline, cover basal layer;
6) arrange securing member at coiled material layer top to seal;
7) seam crossing at coiled material layer and basal layer lays additional waterproofing layer, and coats fluid sealant and seal;
Step 3) in primer at least coat more than 4 layers;
The painting method of primer is: after preceding layer primer is completely dried, and removes the dust on preceding layer primer surface, the most uniformly Coating later layer primer, until it reaches the number of plies of needs.
A kind of roof of transformer substation the most according to claim 1 stretches out the method for waterproofing of pipeline, it is characterised in that step 6) securing member described in is ferrule.
A kind of roof of transformer substation the most according to claim 1 stretches out the method for waterproofing of pipeline, it is characterised in that: described anti- Water ventilated membrane is highdensity spunbond polyethylene nonwoven.
CN201610287410.8A 2016-05-04 2016-05-04 Waterproofing treatment method for substation roof extending pipeline Pending CN105888159A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610287410.8A CN105888159A (en) 2016-05-04 2016-05-04 Waterproofing treatment method for substation roof extending pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610287410.8A CN105888159A (en) 2016-05-04 2016-05-04 Waterproofing treatment method for substation roof extending pipeline

Publications (1)

Publication Number Publication Date
CN105888159A true CN105888159A (en) 2016-08-24

Family

ID=56702066

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610287410.8A Pending CN105888159A (en) 2016-05-04 2016-05-04 Waterproofing treatment method for substation roof extending pipeline

Country Status (1)

Country Link
CN (1) CN105888159A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080180455A1 (en) * 2007-01-31 2008-07-31 Hitachi, Ltd. Image processing apparatus and image displaying device
CN201202229Y (en) * 2008-05-30 2009-03-04 浙江省一建建设集团有限公司 Roof exhaust system
CN101586381A (en) * 2008-05-20 2009-11-25 北京森聚柯高分子材料有限公司 Waterproof structure and manufacturing method thereof
CN101831994A (en) * 2010-04-30 2010-09-15 唐山德生防水材料有限公司 Double-layer waterproof and double-layer water exhaust structure of heat insulation house surface and construction method thereof
CN202492975U (en) * 2012-03-23 2012-10-17 上海市电力公司 Pipeline water-proof structure extending out of roof
CN103437508A (en) * 2013-08-21 2013-12-11 国家电网公司 Waterproofing processing method of pipe stretching out of roof of transformer substation

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080180455A1 (en) * 2007-01-31 2008-07-31 Hitachi, Ltd. Image processing apparatus and image displaying device
CN101586381A (en) * 2008-05-20 2009-11-25 北京森聚柯高分子材料有限公司 Waterproof structure and manufacturing method thereof
CN201202229Y (en) * 2008-05-30 2009-03-04 浙江省一建建设集团有限公司 Roof exhaust system
CN101831994A (en) * 2010-04-30 2010-09-15 唐山德生防水材料有限公司 Double-layer waterproof and double-layer water exhaust structure of heat insulation house surface and construction method thereof
CN202492975U (en) * 2012-03-23 2012-10-17 上海市电力公司 Pipeline water-proof structure extending out of roof
CN103437508A (en) * 2013-08-21 2013-12-11 国家电网公司 Waterproofing processing method of pipe stretching out of roof of transformer substation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张德勒: "《石油沥青的生产与应用》", 31 July 2001, 中国石化出版社 *

Similar Documents

Publication Publication Date Title
MX2020014301A (en) A self-adhering sealing device with an adhesive sealant layer.
BRPI0702324A (en) multi-layer liner for application over a basin and method of applying a liner to a basin to protect the underlying galvanized panels from corrosion in a wet environment
MX2021000697A (en) A self-adhering sealing device with an adhesive layer arrangement.
MX2019002530A (en) Multiple layer substrate for roofing materials.
US20070245894A1 (en) Vapor & moisture resistant conduit
KR101928412B1 (en) Non-woven fabric sheet impregnated with permanent flexible gel and waterproofing method using the same
US20130288051A1 (en) Mechanical and anticorrosive protection vinyl tape
CN107459942A (en) A kind of self-adhering-type EPDM waterproof rolled sheet
US8979433B2 (en) Liquid containment berm and method of use
CN208777580U (en) A kind of hydrocone type drain gully waterproofing node structure
CN105888159A (en) Waterproofing treatment method for substation roof extending pipeline
CN207310696U (en) Strength intersects film composite of water-proof coiled material
CN207063346U (en) A kind of roof waterproof structure
CN206607611U (en) A kind of waterproof roll bridging arrangement
US9309047B2 (en) Liquid containment berm and method of use
US20160097278A1 (en) Waterproofing system for exposed rock surfaces
CN204299383U (en) A kind of waterproofing node structure of door-window opening
CN207525791U (en) A kind of flexible water structure of deformation joint
CN206085865U (en) Waterproof roll
RU2011121365A (en) COMPOSITION OF POLYMERIC FABRIC, METHOD FOR ITS MANUFACTURE AND APPLICATION
JP2012506783A5 (en)
CN104453562A (en) Waterproof joint structure for door/window hole
RU2011110299A (en) COVERED BUILDING CARDBOARD AND METHOD FOR COATING BUILDING CARDBOARD
CN205296622U (en) A waterproof construction for roofing wall pipe
MY186640A (en) Roof outlet assembly

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160824