CN105863588B - A kind of heavy crude heat extraction horizontal well equilibrium note mining method - Google Patents

A kind of heavy crude heat extraction horizontal well equilibrium note mining method Download PDF

Info

Publication number
CN105863588B
CN105863588B CN201610280362.XA CN201610280362A CN105863588B CN 105863588 B CN105863588 B CN 105863588B CN 201610280362 A CN201610280362 A CN 201610280362A CN 105863588 B CN105863588 B CN 105863588B
Authority
CN
China
Prior art keywords
production
section
horizontal
injection
design
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610280362.XA
Other languages
Chinese (zh)
Other versions
CN105863588A (en
Inventor
徐家年
刘虹利
王郑库
李凤霞
张振军
史海涛
黄显德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing University of Science and Technology
Original Assignee
Chongqing University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing University of Science and Technology filed Critical Chongqing University of Science and Technology
Priority to CN201610280362.XA priority Critical patent/CN105863588B/en
Publication of CN105863588A publication Critical patent/CN105863588A/en
Application granted granted Critical
Publication of CN105863588B publication Critical patent/CN105863588B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E21—EARTH OR ROCK DRILLING; MINING
    • E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/16—Enhanced recovery methods for obtaining hydrocarbons
    • E21B43/24—Enhanced recovery methods for obtaining hydrocarbons using heat, e.g. steam injection

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Extraction Or Liquid Replacement (AREA)

Abstract

The present invention relates to a kind of heavy crude heat extraction horizontal well equilibriums to infuse mining method comprising following steps before horizontal well completion, are distributed according to horizontal segment permeability, oil saturation, carry out segment design to net horizontal section;The steam injection for the horizontal segment that combining step 1 is designed, production, Wellbore Flow, design level section traffic intensity;It is distributed according to stratum fineness of sand and carries out sand control screen sand block accuracy Design;According to the design result of step 1 to 3, simultaneously tripping in completion tubular column is designed;It designs and tripping in note adopts integral tubular column, to net horizontal section steam injection, steam can inject corresponding well section from each section of flow control apparatus;It acts note and adopts integral tubular column, lower routine flow string production, each section production fluid of dividing can flow into pit shaft from respective flow control apparatus.Providing one kind can be realized in horizontal well thermal recovery steam injection stage net horizontal section pipe, manages outer uniform steam injection;Production phase net horizontal section equilibrium produces liquid, while can play the horizontal well thermal recovery equilibrium note mining method of sand-proof function again.

Description

一种稠油热采水平井均衡注采方法A method for balanced injection and production of heavy oil thermal recovery horizontal wells

技术领域technical field

本发明涉及一种稠油热采水平井均衡注采方法。The invention relates to a balanced injection and production method for heavy oil thermal recovery horizontal wells.

背景技术Background technique

稠油热采水平井注蒸汽过程中,由于水平井段具有一定长度,常规注汽管柱只有一个注汽点,使水平段管柱内压力分布不均,加上油层非均质性,容易造成水平段吸汽不均,形成局部突进,发生汽窜,使蒸汽外溢,造成产能损失。国内某稠油油田热采水平井监测资料分析表明,水平井注汽时“汽窜”非常严重,70%以上存在不同程度汽窜,水平段动用不均的井约占80%,严重影响稠油热采水平井生产效果。目前,国内外对热采水平井水平段进行均匀注汽,主要采取两种方式,即水平井段双管注汽和多点注汽。水平井段双管注汽技术,即采用井口“双悬挂”、管中管注汽方式,蒸汽从两个通道注入,一个是从小尺寸无接箍油管注入到水平段趾端,一个是从真空隔热管和小尺寸无接箍油管环空注到水平井段跟端;由地面流量调解阀门进行流量控制,实现二个出汽点不同排量的控制。水平井段多点注汽技术是在水平段注汽管柱上安装多个注汽阀,各注汽阀之间采用蒸汽伞进行分隔,使各水平井段形成独立的注汽单元;通过注汽阀调节水平段各注汽点注汽量,从而达到水平段均匀注汽的目的。水平井段双管注汽的缺点是,只有两个注汽点,对长水平段均匀注汽调节能力有限。多点注汽方式由于筛管外水平段未进行分割,蒸汽仍然易被低压、高渗层段吸收,对水平井段实际均匀吸气调节作用有限。两种注汽方式水平井段没有均衡产液控制装置,受水平段渗透率差异、井筒流动压降影响,生产时仍然会造成水平井段动用不均,影响水平井产能。两种注汽方式均需在水平段下入注汽管柱,施工工序复杂,作业风险高。In the process of steam injection in horizontal wells in thermal recovery of heavy oil, because the horizontal well section has a certain length, the conventional steam injection string has only one steam injection point, which makes the pressure distribution in the horizontal section of the string uneven. This causes uneven steam absorption in the horizontal section, forming a local sudden advance, steam channeling, and steam overflowing, resulting in loss of production capacity. Analysis of the monitoring data of thermal recovery horizontal wells in a heavy oil oilfield in China shows that “steam channeling” is very serious during steam injection in horizontal wells, more than 70% of which have different degrees of steam channeling. Production effect of horizontal wells in thermal oil recovery. At present, there are two main methods for uniform steam injection in the horizontal section of thermal recovery horizontal wells at home and abroad, that is, double-pipe steam injection and multi-point steam injection in the horizontal well section. The dual-pipe steam injection technology in the horizontal well section adopts the wellhead "double suspension" and the pipe-in-pipe steam injection method. The thermal insulation pipe and the small size uncoupling tubing are annulus injected into the heel end of the horizontal well section; the flow is controlled by the surface flow adjustment valve to realize the control of the different displacements of the two steam outlet points. The multi-point steam injection technology in the horizontal well section is to install multiple steam injection valves on the steam injection pipe string in the horizontal section. The steam valve adjusts the steam injection volume of each steam injection point in the horizontal section, so as to achieve the purpose of uniform steam injection in the horizontal section. The disadvantage of dual-pipe steam injection in horizontal well sections is that there are only two steam injection points, and the ability to regulate uniform steam injection in long horizontal sections is limited. In the multi-point steam injection method, since the horizontal section outside the screen is not divided, the steam is still easily absorbed by the low-pressure and high-permeability layers, which has limited effect on the actual uniform suction adjustment of the horizontal well section. There is no balanced liquid production control device in the horizontal well section of the two steam injection methods. Affected by the permeability difference of the horizontal section and the pressure drop of the wellbore flow, the production of the horizontal well section will still be uneven during production, which will affect the horizontal well productivity. Both steam injection methods need to inject the steam injection pipe string in the horizontal section, the construction process is complicated, and the operation risk is high.

发明内容SUMMARY OF THE INVENTION

本发明要解决的技术问题是如何克服现有技术的上述缺陷,提供一种稠油热采水平井均衡注采方法。The technical problem to be solved by the present invention is how to overcome the above-mentioned defects of the prior art and provide a balanced injection and production method for heavy oil thermal recovery horizontal wells.

为解决上述技术问题,本稠油热采水平井均衡注采方法包括以下步骤,In order to solve the above technical problems, the balanced injection and production method for heavy oil thermal recovery horizontal wells includes the following steps:

步骤1:水平井完井前,根据水平段渗透率、含油饱和度分布,对水平井段进行分段设计;Step 1: Before the completion of the horizontal well, according to the permeability and oil saturation distribution of the horizontal section, design the horizontal well section in sections;

步骤2:综合步骤1设计出的水平段的注汽、生产、井筒流动,设计水平段流量强度;Step 2: Combine the steam injection, production, and wellbore flow in the horizontal section designed in Step 1, and design the flow intensity of the horizontal section;

步骤3:根据地层砂粒度分布进行防砂筛管挡砂精度设计;Step 3: Design the sand retaining accuracy of the sand control screen according to the particle size distribution of the formation sand;

步骤4:根据步骤1至3的设计结果,设计并下入完井管柱;Step 4: According to the design results of steps 1 to 3, design and run the completion string;

步骤5:设计并下入注采一体管柱,对水平井段注汽,蒸汽会从各段流动控制装置注入相应井段;Step 5: Design and run the injection-production integrated pipe string, inject steam into the horizontal well section, and the steam will be injected into the corresponding well section from the flow control device of each section;

步骤6:起出注采一体管柱,下常规生产管柱生产,各分割段产出液会从各自流动控制装置流入井筒。Step 6: Pull out the integrated injection-production string, and run down the conventional production string for production. The produced fluid of each segment will flow into the wellbore from its respective flow control device.

作为优化完善,步骤4所述完井管柱由悬挂器、光套管、耐高温裸眼管外封隔器、带有流动控制装置的调流控砂筛管组接而成;所述耐高温裸眼管外封隔器为膨胀密封,所述悬挂封隔器悬挂密封,所述完井管柱整体为悬挂密封。As an optimization and improvement, the completion string described in step 4 is composed of hangers, light casings, high temperature resistant open hole outer packers, and flow regulating sand control screens with flow control devices; the high temperature resistant The open-hole pipe outer packer is an expansion seal, the suspension packer is a suspension seal, and the completion string is a suspension seal as a whole.

作为优化完善,步骤5所述注采一体管柱下于完井管柱柱腔内,注采一体管柱外壁与完井管柱内壁之间设有生产封隔器。As an optimization and improvement, the integrated injection-production string described in step 5 is placed in the cavity of the completion string, and a production packer is provided between the outer wall of the integrated injection-production string and the inner wall of the completion string.

作为优化完善,所述水平端各段产液量随流动控制装置控制强度不同而变化。As an optimization and perfection, the liquid production volume of each section of the horizontal end varies with the control intensity of the flow control device.

通过上述技术方案设计,本发明提供了一种能够实现热采水平井注汽阶段水平井段管内、管外均匀注汽;生产阶段水平井段均衡产液,同时又能起到防砂功能的热采水平井均衡注采方法。Through the design of the above-mentioned technical solutions, the present invention provides a thermal recovery method that can realize uniform steam injection inside and outside the pipe of the horizontal well section in the steam injection stage of the thermal recovery horizontal well; Balanced injection-production method for horizontal wells.

本发明一种稠油热采水平井均衡注采方法,在水平段下入带有流动控制装置的调流控砂筛管,利用耐高温管外封隔器对水平井段进行分隔完井。利用注采一体管柱进行注采,不用在水平井段下入双管,或小尺寸油管、蒸汽伞、流量调节阀等工具,施工方便可靠。注汽时流动控制装置会自动调节各分隔段的吸汽量,生产时会自动调节各分隔段产液量,从而实现全水平段均衡注采,提高水平井段动用程度,发挥水平井产能优势。The invention discloses a method for balanced injection and production of heavy oil thermal recovery horizontal wells. A flow regulating sand control screen tube with a flow control device is run in a horizontal section, and a high temperature resistant tube outer packer is used to separate and complete the horizontal well section. The injection and production integrated pipe string is used for injection and production, and there is no need to run double pipes in the horizontal well section, or tools such as small-sized oil pipes, steam umbrellas, flow control valves, etc., and the construction is convenient and reliable. During steam injection, the flow control device will automatically adjust the steam intake of each partition, and automatically adjust the liquid production of each partition during production, so as to achieve balanced injection and production in the whole horizontal section, improve the production degree of the horizontal well section, and give full play to the productivity advantage of the horizontal well. .

附图说明Description of drawings

下面结合附图对本发明一种稠油热采水平井均衡注采方法作进一步说明:Below in conjunction with accompanying drawing, a kind of balanced injection and production method of heavy oil thermal recovery horizontal well of the present invention will be further described:

图1是本稠油热采水平井均衡注采方法的完井管柱的结构示意图;Fig. 1 is the structural schematic diagram of the well completion string of the balanced injection and production method of the heavy oil thermal recovery horizontal well;

图2是本稠油热采水平井均衡注采方法的注采一体管柱的结构示意图。Fig. 2 is a schematic structural diagram of the injection-production integrated pipe string of the balanced injection-production method of the heavy oil thermal recovery horizontal well.

图中:8-完井管柱、1-悬挂器、2-光套管、3-耐高温裸眼管外封隔器、4-带有流动控制装置、5-调流控砂筛管、6-生产封隔器、7-注采一体管柱、8-完井管柱。In the picture: 8- completion string, 1- hanger, 2- bare casing, 3- high temperature open-hole pipe outer packer, 4- with flow control device, 5- flow regulating sand control screen, 6- -Production packer, 7-Injection-production integrated string, 8-Completion string.

具体实施方式Detailed ways

步骤1:水平井完井前,根据水平段渗透率、含油饱和度分布,对水平井段进行分段设计;Step 1: Before the completion of the horizontal well, according to the permeability and oil saturation distribution of the horizontal section, design the horizontal well section in sections;

步骤2:综合步骤1设计出的水平段的注汽、生产、井筒流动,设计水平段流量强度;Step 2: Combine the steam injection, production, and wellbore flow in the horizontal section designed in Step 1, and design the flow intensity of the horizontal section;

步骤3:根据地层砂粒度分布进行防砂筛管挡砂精度设计;Step 3: Design the sand retaining accuracy of the sand control screen according to the particle size distribution of the formation sand;

步骤4:根据步骤1至3的设计结果,设计并下入完井管柱8;所述完井管柱8由悬挂器1、光套管2、耐高温裸眼管外封隔器3、带有流动控制装置4的调流控砂筛管5组接而成;所述耐高温裸眼管外封隔器3为膨胀密封,所述悬挂封隔器1悬挂密封,所述完井管柱8整体为悬挂密封;Step 4: Design and run a completion string 8 according to the design results of steps 1 to 3; The flow regulating sand control screen 5 with the flow control device 4 is assembled; the outer packer 3 of the high temperature resistant open-hole pipe is an expansion seal, the suspension packer 1 is suspended and sealed, and the completion string 8 The whole is a suspension seal;

步骤5:设计并下入注采一体管柱7,对水平井段注汽,蒸汽会从各段流动控制装置注入相应井段;所述注采一体管柱7下于完井管柱8柱腔内,注采一体管柱7外壁与完井管柱8内壁之间设有生产封隔器6;Step 5: Design and run the injection-production integrated pipe string 7, inject steam into the horizontal well section, and the steam will be injected into the corresponding well section from the flow control device of each section; the injection-production integrated pipe string 7 is lowered into the completion pipe string 8 In the cavity, a production packer 6 is arranged between the outer wall of the injection-production integrated pipe string 7 and the inner wall of the completion pipe string 8;

步骤6:起出注采一体管柱7,下常规生产管柱生产,各分割段产出液会从各自流动控制装置流入井筒。Step 6: Pull out the injection-production integrated pipe string 7, and run down the conventional production pipe string for production. The produced fluid of each segment will flow into the wellbore from its respective flow control device.

所述水平端各段产液量随流动控制装置4控制强度不同而变化。The liquid production volume of each section of the horizontal end varies with the control strength of the flow control device 4 .

上述实施方式旨在举例说明本发明可为本领域专业技术人员实现或使用,对上述实施方式进行修改对本领域的专业技术人员来说将是显而易见的,故本发明包括但不限于上述实施方式,任何符合本权利要求书或说明书描述,符合与本文所公开的原理和新颖性、创造性特点的方法、工艺、产品,均落入本发明的保护范围之内。The above-mentioned embodiments are intended to illustrate that the present invention can be realized or used by those skilled in the art. It will be obvious to those skilled in the art to modify the above-mentioned embodiments. Therefore, the present invention includes but is not limited to the above-mentioned embodiments. Any method, process, or product that conforms to the descriptions in the claims or the specification, and conforms to the principles, novelty, and inventive features disclosed herein fall within the protection scope of the present invention.

Claims (2)

1.一种稠油热采水平井均衡注采方法,其特征是:该方法包括以下步骤,1. a heavy oil thermal recovery horizontal well balanced injection and production method, is characterized in that: the method comprises the following steps, 步骤1:水平井完井前,根据水平段渗透率、含油饱和度分布,对水平井段进行分段设计;Step 1: Before the completion of the horizontal well, according to the permeability and oil saturation distribution of the horizontal section, design the horizontal well section in sections; 步骤2:综合步骤1设计出的水平段的注汽、生产、井筒流动,设计水平段流量强度;Step 2: Combine the steam injection, production, and wellbore flow in the horizontal section designed in Step 1, and design the flow intensity of the horizontal section; 步骤3:根据地层砂粒度分布进行防砂筛管挡砂精度设计;Step 3: Design the sand retaining accuracy of the sand control screen according to the particle size distribution of the formation sand; 步骤4:根据步骤1至3的设计结果,设计并下入完井管柱(8),所述完井管柱(8)由悬挂器(1)、光套管(2)、耐高温裸眼管外封隔器(3)、带有流动控制装置(4)的调流控砂筛管(5)组接而成;所述耐高温裸眼管外封隔器(3)为膨胀密封,所述悬挂器(1)悬挂密封,所述完井管柱(8)整体为悬挂密封;Step 4: Design and run a completion string (8) according to the design results of steps 1 to 3. The completion string (8) consists of a hanger (1), a light casing (2), a high temperature resistant open hole The outer tube packer (3) and the flow regulating sand control screen tube (5) with the flow control device (4) are assembled; the high temperature resistant open-hole tube outer packer (3) is an expansion seal, so the The hanger (1) is suspended and sealed, and the completion string (8) is a suspended seal as a whole; 步骤5:设计并下入注采一体管柱(7),对水平井段注汽,蒸汽会从各段流动控制装置注入相应井段;所述注采一体管柱(7)下于完井管柱(8)柱腔内,注采一体管柱(7)外壁与完井管柱(8)内壁之间设有生产封隔器(6);Step 5: Design and run the injection-production integrated pipe string (7), inject steam into the horizontal well section, and the steam will be injected into the corresponding well section from the flow control device of each section; the injection-production integrated pipe string (7) is run into the well completion In the column cavity of the pipe string (8), a production packer (6) is arranged between the outer wall of the injection-production integrated pipe string (7) and the inner wall of the completion pipe string (8); 步骤6:起出注采一体管柱(7),下常规生产管柱生产,各分割段产出液会从各自流动控制装置流入井筒。Step 6: Pull out the injection-production integrated pipe string (7), and run down the conventional production pipe string for production. The produced fluid of each segment will flow into the wellbore from the respective flow control devices. 2.根据权利要求1所述的稠油热采水平井均衡注采方法,其特征是:所述光套管(2)的水平端各段产液量随流动控制装置(4)控制强度不同而变化。2. The method for balanced injection and production of heavy oil thermal recovery horizontal wells according to claim 1, characterized in that: the liquid production volume of each section of the horizontal end of the light casing (2) varies with the control intensity of the flow control device (4). and change.
CN201610280362.XA 2016-04-28 2016-04-28 A kind of heavy crude heat extraction horizontal well equilibrium note mining method Expired - Fee Related CN105863588B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610280362.XA CN105863588B (en) 2016-04-28 2016-04-28 A kind of heavy crude heat extraction horizontal well equilibrium note mining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610280362.XA CN105863588B (en) 2016-04-28 2016-04-28 A kind of heavy crude heat extraction horizontal well equilibrium note mining method

Publications (2)

Publication Number Publication Date
CN105863588A CN105863588A (en) 2016-08-17
CN105863588B true CN105863588B (en) 2019-07-26

Family

ID=56629979

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610280362.XA Expired - Fee Related CN105863588B (en) 2016-04-28 2016-04-28 A kind of heavy crude heat extraction horizontal well equilibrium note mining method

Country Status (1)

Country Link
CN (1) CN105863588B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108547603B (en) * 2018-02-28 2021-03-30 中国石油天然气股份有限公司 Water injection and oil extraction integrated tubular column and water injection and oil extraction method
CN110630234B (en) * 2018-06-21 2021-11-02 中国石油天然气股份有限公司 Steam Injection Method for Heavy Oil Thermal Recovery Well
CN111946314B (en) * 2019-05-15 2022-12-02 中国石油天然气股份有限公司 Injection and extraction control pipe column for thickened oil horizontal well
CN111411927B (en) * 2020-03-30 2022-07-29 中国石油大学(华东) Method for adjusting steam injection mode in steam huff and puff process
CN115247543B (en) * 2021-04-28 2024-04-09 中国石油化工股份有限公司 Fixed-point segmented water shutoff and dislocation accurate steam injection method for horizontal well of heavy oil reservoir

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892827A (en) * 2010-04-30 2010-11-24 钟立国 Optimized steam injection technology for horizontal well in segments
CN102108851A (en) * 2010-12-30 2011-06-29 中国石油天然气股份有限公司 Horizontal well steam injection method and system
CN202064920U (en) * 2011-06-01 2011-12-07 中国石油天然气股份有限公司 Segmented Completion Technology String for Heavy Oil Horizontal Wells
CN102536172A (en) * 2012-02-23 2012-07-04 石云夫 Sectional production tubular pile for horizontal well
CN102852502A (en) * 2012-04-18 2013-01-02 中国石油天然气股份有限公司 Intelligent steam distribution process string for horizontal steam injection well
CN104481484A (en) * 2014-12-26 2015-04-01 东营市福利德石油科技开发有限责任公司 Horizontal well segmented intermittent steam huff and puff injection-production integrated pipe column

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101718190B (en) * 2009-12-08 2012-10-24 安东石油技术(集团)有限公司 Completed well body structure with temporary plugging function screen pipe and well completion method for suspending screen pipe at tail pipe
CN204041030U (en) * 2014-05-15 2014-12-24 成都北方石油勘探开发技术有限公司 With the horizontal well in segments completion tubular column of the close screen casing of variable orifice
CN204283379U (en) * 2014-12-08 2015-04-22 众通(北京)能源技术有限公司 Screen casing completes oil well intelligent water control pipe post
CN204283367U (en) * 2014-12-08 2015-04-22 众通(北京)能源技术有限公司 Horizontal well Intelligent water-controlled completion tubular column

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892827A (en) * 2010-04-30 2010-11-24 钟立国 Optimized steam injection technology for horizontal well in segments
CN102108851A (en) * 2010-12-30 2011-06-29 中国石油天然气股份有限公司 Horizontal well steam injection method and system
CN202064920U (en) * 2011-06-01 2011-12-07 中国石油天然气股份有限公司 Segmented Completion Technology String for Heavy Oil Horizontal Wells
CN102536172A (en) * 2012-02-23 2012-07-04 石云夫 Sectional production tubular pile for horizontal well
CN102852502A (en) * 2012-04-18 2013-01-02 中国石油天然气股份有限公司 Intelligent steam distribution process string for horizontal steam injection well
CN104481484A (en) * 2014-12-26 2015-04-01 东营市福利德石油科技开发有限责任公司 Horizontal well segmented intermittent steam huff and puff injection-production integrated pipe column

Also Published As

Publication number Publication date
CN105863588A (en) 2016-08-17

Similar Documents

Publication Publication Date Title
CN201474673U (en) Oil production pipe column for sectional water control of horizontal well
CN201165866Y (en) Horizontal well separate mining and combined mining pipe column
CN101787854B (en) Subsection well completion system of bottom water reservoir horizontal well
CN105134141B (en) A process column
CN204266939U (en) A kind of water and oil control second completion pipe string combination
CN104481487B (en) The multistage many seam staged fracturing methods of horizontal well
CN205225215U (en) A mining device for layered mining of two sets of oil layers
CN201963283U (en) Double tubing high temperature gas lift process string
CN105863588A (en) Balanced injection and recovery method of thickened oil thermal recovery horizontal well
CN103939071A (en) A horizontal well steam flooding well pattern structure and steam flooding method
CN104100237B (en) A kind of drainage method of coalbed methane well
CN206917640U (en) The steady oil system of offshore oilfield horizontal well automatic control water
Stone et al. Advanced wellbore simulation of flow control devices with feedback control for thermal operations
CN202531037U (en) Segmented Completion Strings for Horizontal Wells in Tight Gas Reservoirs with Bottom Water
CN204941480U (en) The horizontal well completion sleeve pipe of segmentation exploitation and the tubing string of formation thereof can be realized
CN103470233B (en) A natural gas huff and puff oil recovery process system and oil recovery method for heavy oil reservoirs
CN105822252B (en) Cementing String Combination and Cementing Method
CN104405355A (en) Horizontal well injection and production string
CN201963286U (en) Horizontal well center pipe to reduce water cut production string
CN114427386A (en) A kind of infinite stage segmented sand control and water control completion string and method
CN104632195B (en) A water-seeking pipe string and method for a gas-lift-aided horizontal well
CN202810675U (en) Mechanical water plugging pipe string for multi-stage fracturing horizontal well with casing completion and multi-point water outlet
CN202832453U (en) A SAGD production well single tubing pumping process string
CN204532233U (en) Cementing string combination
CN103122760B (en) Completion pipe string for suspending bottom water coning

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190726

CF01 Termination of patent right due to non-payment of annual fee