CN105863233A - Scaffold for outer curtain wall of arc-shaped building and mounting method - Google Patents
Scaffold for outer curtain wall of arc-shaped building and mounting method Download PDFInfo
- Publication number
- CN105863233A CN105863233A CN201610374324.0A CN201610374324A CN105863233A CN 105863233 A CN105863233 A CN 105863233A CN 201610374324 A CN201610374324 A CN 201610374324A CN 105863233 A CN105863233 A CN 105863233A
- Authority
- CN
- China
- Prior art keywords
- scaffold
- curtain wall
- outer curtain
- arcuate building
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/36—Scaffolds for particular parts of buildings or buildings of particular shape, e.g. for stairs, cupolas, domes
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/38—Scaffolds partly supported by the building
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/04—Means for fastening, supporting, or bracing scaffolds on or against building constructions
- E04G5/046—Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on walls
Abstract
The invention provides a scaffold for an outer curtain wall of an arc-shaped building and a mounting method, relating to the technical field of building construction. According to the scaffold, the problems of more waste and large occupied space caused by the increase of row number of a traditional scaffold are solved. The scaffold comprises a three-dimensional framework and a base which are fixedly connected, wherein the three-dimensional framework is fixedly connected with arc-shaped building structure pillars through wall connecting pieces and comprises a single-row scaffold unit, the single-row scaffold unit is formed by connecting a plurality of transverse rods, longitudinal transverse rods and vertical rods through buckles, and the degree of the three-dimensional framework inclining towards the direction of the arc-shaped building is coincided with the degree of inclination of the outer curtain wall of the arc-shaped building. The mounting method comprises the following steps: (1) mounting a foundation on the ground; and (2) sequentially mounting the longitudinal rods, the vertical rods and the transverse rods, and mutually connecting the longitudinal rods, the vertical rods and the transverse rods through buckles upwards layer by layer so as to form the three-dimensional framework.
Description
Technical field
The present invention relates to technical field of building construction, particularly to the outer curtain wall scaffold of a kind of arcuate building and peace
Dress method.
Background technology
In recent years, along with the development of Building technology be becoming tight the day of land resource, the building of special shape
More and more.And owing to steel construction application is continuously increased, architectural appearance is increasingly sophisticated, such as common circular cone
External shape.
The scaffold that job site mainly uses at present is substantially vertical or partly outwards encorbelments.And circular cone
The building surface of external shape is to tilt, and common scaffold cannot adapt with this type of building profile.Typically
Single, double row's foot hands be difficult to set up, unstable.According to the scaffold form of common vertical posts, only
Can ensure to encorbelment partially stabilized by increasing scaffold row, there is waste material many, take up room big problem.
Therefore, how to provide that a kind of waste material is few, it is little to take up an area space and meets falling of the outer curtain wall construction requirement of arcuate building
The ground outer curtain wall scaffold of formula arcuate building and installation method, be that those skilled in the art need the technology of solution badly and ask
Topic.
Summary of the invention
Produce because increasing row for the traditional console model scaffold being applicable to the outer curtain wall construction of arcuate building
Waste material many, take up room big problem, it is an object of the invention to provide and a kind of save materials, take up an area space
The outer curtain wall scaffold of little arcuate building and installation method.
The technical solution adopted for the present invention to solve the technical problems is:
The outer curtain wall scaffold of a kind of arcuate building, including the fixing space framework connected and base, described vertical
Body framework is connected by wall-connecting piece and arcuate building structural column are fixing, and described space framework includes single-row of scaffold
Unit, described scaffold unit is formed by connecting by fastener by some transverse bars, longitudinal rod and vertical rod, described
Space framework is consistent with the angle of inclination of curtain wall outside arcuate building to angle of inclination, arcuate building direction.
Further, described wall-connecting piece is formed by axially arranged steel pipe manufacturing, and described wall-connecting piece is with described
Arcuate building structural column is fixing to be connected.
Further, also include bridging, the two ends of described bridging respectively with described vertical rod and transverse bar
Fixing connection, described bridging is arranged at surrounding outside described scaffold unit.
Further, the interlaced setting of joint fastener of of vertically-adjacent two vertical rods.
Further, described base is made by channel-section steel, is provided with timber wedge between described base and ground.
Further, the level interval of described timber wedge is 1 meter.
The invention also discloses the installation method of the outer curtain wall scaffold of a kind of arcuate building, comprise the steps:
Step one, complete the installation of scaffold base on ground;
Step 2, successively installation longitudinal rod, vertical rod and transverse bar on the base of described step one, and phase
Connected by fastener between Hu, the most up form space framework, so far complete the outer curtain wall of whole arcuate building
The installation of scaffold.
Further, the side being additionally included in space framework in described step 2 arranges railing, described railing
Fix with described vertical rod and be connected.
Further, also including arranging bridging in described step 2, described bridging is the most continuous
Being arranged at the outside surrounding of space framework, described bridging is 45 °~60 ° with the angle on ground.
Further, also include step 3, after the outer curtain wall scaffold installation of described arcuate building,
Start, by top to bottom, cladding glass is successively installed, and the arc synchronizing to be removed by top to bottom correspondence is built
Build outer curtain wall scaffold.
Useful the having the technical effect that of the present invention
The outer curtain wall scaffold of the arcuate building of the present invention, including the space framework of single-row of scaffold unit composition,
It is console model scaffold, different from traditional vertical or part builder's jack, has one when it is set up
Fixed angle of inclination, this angle of inclination is identical with arcuate building angle of inclination.The outer curtain wall foot hands of this arcuate building
Frame not only little in floor space, expend material few in the case of provide operation for the outer curtain wall construction of arcuate building
Platform, and solve traditional console model scaffold and meet outside arcuate building by increasing scaffold row
Encorbelmenting in wall surface, stably produced waste material is many, take up room big problem.The outer curtain wall foot hands of this arcuate building
Frame is drawn materials conveniently, and it is convenient to dismount, and provides cost savings, and has preferable promotional value.
Accompanying drawing explanation
Fig. 1 is the site plan of the outer curtain wall scaffold of arcuate building of the present invention;
Fig. 2 is the vertical cross section figure in the outer curtain wall scaffold of arcuate building of the present invention;
Fig. 3 is the arcuate building outer curtain wall scaffold plane graph with wall-connecting piece node of the present invention;
Fig. 4 is the arcuate building outer curtain wall scaffold elevation with wall-connecting piece node of the present invention.
In figure:
10-structural column;20-space framework;30-base;40-cladding glass separator bar;50-curtain wall;60-fastener;
70-longitudinal rod;80-circumference cross bar;90-radially cross bar.
Detailed description of the invention
The outer curtain wall scaffold of a kind of arcuate building present invention proposed below in conjunction with the drawings and specific embodiments
And installation method is described in further detail.According to description below, advantages and features of the invention will be more clear
Chu.Hereinafter accompanying drawing be will be combined by cited embodiment, technology contents and the feature of the present invention described in detail.
Need to additionally illustrate, accompanying drawing all uses the form simplified very much and all uses non-ratio accurately, only in order to
Conveniently, the purpose of the embodiment of the present invention is aided in illustrating lucidly.For sake of convenience, described below " on ",
The upper and lower direction of D score and accompanying drawing is consistent, but this can not become the restriction of technical solution of the present invention.
Embodiment one
The outer curtain wall scaffold of arcuate building and the installation method of the present invention are described in conjunction with Fig. 1 to Fig. 4.
As shown in Figures 1 to 4, the outer curtain wall scaffold of a kind of arcuate building, including the fixing three-dimensional frame connected
Frame 20 and base 30, space framework 20 is solid with arcuate building structural column 10 by wall-connecting piece (not shown)
Fixed connection, space framework 20 includes single-row of scaffold unit, and scaffold unit is by some transverse bars, longitudinal direction
Bar and vertical rod are formed by connecting by fastener 60, and space framework 20 is to angle of inclination, arcuate building direction and arc
The angle of inclination of Architecture Outer Curtain Wall is consistent.
Specifically, in order to meet the construction scaffolding demand of the outer curtain wall of arcuate building, along arcuate building
The console model scaffold identical with arcuate building angle of inclination set up by exterior wall.Meanwhile, in order to meet this scaffold
Stability, the space framework that the space framework 20 of this scaffold forms for single-row of scaffold unit.Thus,
The outer curtain wall scaffold of the arcuate building of the present invention can not only provide operation for the outer curtain wall construction of arcuate building
Platform, and solve traditional console model scaffold and meet outside arcuate building by increasing scaffold row
Encorbelmenting in wall surface, stably produced waste material is many, take up room big problem.
It is preferred that is connected to ensure that this scaffold and arcuate building structural column 10 is fixing, this scaffold and
Fixed as one structure by some spaced wall-connecting pieces between the outer curtain wall of arcuate building.Wall-connecting piece is by axle
Being made to the i.e. circumference cross bar 80 of the steel pipe arranged, wall-connecting piece is fixing with arcuate building structural column 10 to be connected.
In order to realize being stably connected with of scaffold and arcuate building external wall structure post 10, the most cost-effective, adjacent
Wall-connecting piece between spacing be two steps one across, wall-connecting piece according to adjacent two cladding glass separator bars 40 it
Between spacing arrange, the circumferential cross bar 80 of wall-connecting piece is connected with structural column 10 anchor ear, radially cross bar 90
It is connected by fastener 60 is fixing with circumference cross bar 80.
It is preferred that also include the bridging (not shown) for strengthening scaffold stability in the large, bridging
Two ends fixing with vertical rod (not shown) and transverse bar (not shown) be respectively connected, bridging is arranged at foot
Surrounding outside hand cradle unit.Bridging is across away from no more than 6 meters, and vertically and horizontally spacing is less than 10 meters.Cut
Cutter support is arranged to top along the space framework 20 surrounding facade of scaffold continuously by bottom, bridging and ground
The angle in face is maintained at 45 °~60 °.Bridging is fixed on intersecting therewith transverse bar by rotary buckle and stands
On bar, and synchronize to set up with transverse bar and vertical rod.
It is preferred that the interlaced setting of joint fastener of of vertically-adjacent two vertical rods, thus ensure vertical vertical
Connectivity robustness between bar, the stability in the large of further hoisting scaffold.Clasp is answered in vertical rod
Interlaced arrangement;The joint of two adjacent vertical rods should not be arranged in synchronization, every two of a vertical rod in synchronizing
It is separated by the distance preferably less than 500mm that joint staggers in short transverse;Each connector center to host node away from
From not being preferably greater than the 1/3 of step pitch.
It is preferred that pad is provided with base 30 below space framework 20, such that it is able to increase scaffold and ground
Contact area, and then reduce the load of ground unit are, strengthen its stability in the large.Base 30 is by 12#
Channel-section steel is made, and channel-section steel and ground are 8 ° of angles.Below channel-section steel, pad sets timber wedge (not shown), adjacent
Level interval between timber wedge is 1 meter.Set timber wedge by pad so that channel-section steel and plane at an angle, angle
Spend basically identical with scaffold angle of inclination.
Embodiment two
Please continue to refer to Fig. 1 to Fig. 4, describe the installation of the outer curtain wall scaffold of arcuate building of the present invention in detail
Method
The installation method of the outer curtain wall scaffold of arcuate building, comprises the steps:
Step one, complete the installation of scaffold base 30 on ground.
Step 2, successively installation longitudinal rod 70, vertical rod and transverse bar on the base 30 of described step one,
And connected by fastener each other, the most up form space framework 20, so far complete whole arc and build
Build the installation of outer curtain wall scaffold.Especially, in order to provide safe operating platform to workmen, three-dimensional
The side of framework 20 is additionally provided with railing, and railing is fixing with vertical rod to be connected.Certainly, in order to ensure that scaffold is originally
The stability of body, also includes arranging bridging in step 2, bridging is arranged at three-dimensional frame the most continuously
The outside surrounding of frame 20, bridging is 45 °~60 ° with the angle on ground.Certainly, in order to carry further
The safety of high scaffold, provides a safe and reliable construction operation platform, space framework for workmen
Being additionally provided with foot guard plate and scaffold board in 20, space framework 20 top is provided with safety net.
It is preferred that also include step 3, after the outer curtain wall scaffold installation of arcuate building, start by pushing up
Cladding glass is successively installed in portion to bottom, and synchronizes to be removed the outer curtain wall of corresponding arcuate building by top to bottom
Scaffold.Should build up the connection of scaffold clasp before removing scaffold, whether support system meets structure comprehensively
Make requirement.During dismounting, tear open afterwards according to first installing, the rear order first torn open installed, top layer offer, from
Upper and under remove successively: first remove top and found the safety net of extension;Next removes railing;Then gear foot is removed
Plate;Then scaffold board is removed;Then longitudinal cross bar is removed;Then bridging is removed;Then wall-connecting piece is removed;
Then circumference cross bar is removed;Finally removing vertical rod, now cladding glass has synchronized from top to bottom to install,
Thus form complete curtain wall 50.
Especially, in the present embodiment, it is 28.9 meters with scaffold building height, rolls outside arcuate building
As a example by rake angle is the scaffold building of 9 °, according to traditional scaffold building method, ground is to arc
Building top needs to encorbelment to arrange 4 row's scaffolds, also needs to about 6 row's scaffolds and ensure to encorbelment outside it
Part stablize, and the present invention provide only set up the tilting scaffold identical with arcuate building angle of inclination
Need single-row of scaffold unit, knowable to aforementioned comparison, the foot hands of the outer curtain wall of the arcuate building of the embodiment of the present invention
The material of 3/4 at least saved by frame, also saves substantial amounts of construction space simultaneously.
The outer curtain wall scaffold of the arcuate building of the present invention, the construction scaffolding meeting the outer curtain wall of arcuate building needs
Ask, the exterior wall along arcuate building is installed when setting up and sets up identical with arcuate building angle of inclination and for console model
Scaffold.Meanwhile, in order to meet the stability of this scaffold, the space framework of this scaffold is single foot hands
Frame unit forms.Thus, the outer curtain wall scaffold of the arcuate building of the present invention can not only be outside arcuate building
Curtain wall construction provides operating platform, and solves traditional console model scaffold by increasing scaffold row
Meet arcuate building exterior wall surface and encorbelment that stably produced waste material is many, take up room big problem.This arc
Shape Architecture Outer Curtain Wall scaffold is drawn materials conveniently, and it is convenient to dismount, and provides cost savings, and has preferable promotional value.
Foregoing description is only the description to present pre-ferred embodiments, not any limit to the scope of the invention
Fixed, any change that the those of ordinary skill in field of the present invention does according to the disclosure above content, modification, all belong to
Protection domain in claims.
Claims (10)
1. the outer curtain wall scaffold of arcuate building, it is characterised in that include space framework and the end of fixing connection
Seat, described space framework is connected by wall-connecting piece and arcuate building structural column are fixing, and described space framework includes
Single-row of scaffold unit, described scaffold unit is connected by fastener by some transverse bars, longitudinal rod and vertical rod
Forming, described space framework is the angle of inclination one of curtain wall outside angle of inclination, arcuate building direction with arcuate building
Cause.
The outer curtain wall scaffold of arcuate building the most according to claim 1, it is characterised in that described wall-connecting piece
Being formed by axially arranged steel pipe manufacturing, described wall-connecting piece is fixing with described arcuate building structural column to be connected.
The outer curtain wall scaffold of arcuate building the most according to claim 1, it is characterised in that also include shears
Support, the two ends of described bridging are fixing with described vertical rod and transverse bar respectively to be connected, and described bridging is arranged at
Surrounding outside described scaffold unit.
The outer curtain wall scaffold of arcuate building the most according to claim 1, it is characterised in that of vertically-adjacent
The interlaced setting of joint fastener of two vertical rods.
The outer curtain wall scaffold of arcuate building the most according to claim 1, it is characterised in that described base by
Channel-section steel is made, and is provided with timber wedge between described base and ground.
The outer curtain wall scaffold of arcuate building the most according to claim 5, it is characterised in that described timber wedge
Level interval is 1 meter.
7. according to the installation method of the outer curtain wall scaffold of the arcuate building described in any one of claim 1 to 6, its
It is characterised by, comprises the steps:
Step one, complete the installation of scaffold base on ground;
Step 2, successively longitudinal rod, vertical rod and transverse bar be installed on the base of described step one, and mutually it
Between by fastener connect formed scaffold unit, the most up form space framework, so far complete whole arc
The installation of Architecture Outer Curtain Wall scaffold.
The installation method of the outer curtain wall scaffold of arcuate building the most according to claim 7, it is characterised in that
The side being additionally included in space framework in described step 2 arranges railing, and described railing is fixing with described vertical rod even
Connect.
The installation method of the outer curtain wall scaffold of arcuate building the most according to claim 7, it is characterised in that
Also including arranging bridging in described step 2, described bridging is arranged at space framework the most continuously
Outside surrounding, described bridging is 45 °~60 ° with the angle on ground.
The installation method of the outer curtain wall scaffold of arcuate building the most according to claim 7, it is characterised in that
Also include step 3, after the outer curtain wall scaffold installation of described arcuate building, start by top to bottom
Cladding glass is successively installed, and synchronizes to be removed the outer curtain wall scaffold of corresponding arcuate building by top to bottom.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610374324.0A CN105863233A (en) | 2016-05-31 | 2016-05-31 | Scaffold for outer curtain wall of arc-shaped building and mounting method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610374324.0A CN105863233A (en) | 2016-05-31 | 2016-05-31 | Scaffold for outer curtain wall of arc-shaped building and mounting method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105863233A true CN105863233A (en) | 2016-08-17 |
Family
ID=56642848
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610374324.0A Pending CN105863233A (en) | 2016-05-31 | 2016-05-31 | Scaffold for outer curtain wall of arc-shaped building and mounting method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105863233A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110565929A (en) * | 2019-07-26 | 2019-12-13 | 江苏兴厦建设工程集团有限公司 | Scaffold for construction of large-specification wall paving piece of building outer wall |
CN111177829A (en) * | 2019-12-25 | 2020-05-19 | 广联达科技股份有限公司 | Method, system and medium for building external scaffold based on professional knowledge prior partitioning |
CN111191310A (en) * | 2019-12-25 | 2020-05-22 | 广联达科技股份有限公司 | Method, system and medium for constructing external scaffold based on rapid arrangement of preferential blocks |
CN113089820A (en) * | 2021-04-09 | 2021-07-09 | 上海通正铝结构建设科技有限公司 | Construction method of single-layer oblique-crossing special-shaped curved surface aluminum alloy structure in limited space |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS54100117A (en) * | 1978-01-25 | 1979-08-07 | Orion Sogyo Kk | Scaffold for working top surface of cylindrical tank |
JPH01190876A (en) * | 1988-01-27 | 1989-07-31 | Kajima Corp | Scaffold device for concrete column forming device |
CN2506729Y (en) * | 2001-07-13 | 2002-08-21 | 于国杰 | Multi-functional insert disk type scaffold |
CN2538905Y (en) * | 2002-04-17 | 2003-03-05 | 中国建筑第一工程局第三建筑公司 | External use ultra-high single-row of scaffold |
CN2818654Y (en) * | 2005-07-12 | 2006-09-20 | 上海市第二建筑有限公司 | Self-walking straight-arm overhead operating platform |
CN201526152U (en) * | 2009-09-22 | 2010-07-14 | 中建三局建设工程股份有限公司 | Small-angle oblique scaffold cantilevered to external wall |
CN102367700A (en) * | 2011-10-29 | 2012-03-07 | 李欣 | Floor type dual-raw external scaffold |
CN203654708U (en) * | 2013-11-29 | 2014-06-18 | 深圳市工勘岩土工程有限公司 | Side slope scaffold unloading device |
CN205918081U (en) * | 2016-05-31 | 2017-02-01 | 上海建工五建集团有限公司 | Outer curtain scaffold frame of arc building |
-
2016
- 2016-05-31 CN CN201610374324.0A patent/CN105863233A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS54100117A (en) * | 1978-01-25 | 1979-08-07 | Orion Sogyo Kk | Scaffold for working top surface of cylindrical tank |
JPH01190876A (en) * | 1988-01-27 | 1989-07-31 | Kajima Corp | Scaffold device for concrete column forming device |
CN2506729Y (en) * | 2001-07-13 | 2002-08-21 | 于国杰 | Multi-functional insert disk type scaffold |
CN2538905Y (en) * | 2002-04-17 | 2003-03-05 | 中国建筑第一工程局第三建筑公司 | External use ultra-high single-row of scaffold |
CN2818654Y (en) * | 2005-07-12 | 2006-09-20 | 上海市第二建筑有限公司 | Self-walking straight-arm overhead operating platform |
CN201526152U (en) * | 2009-09-22 | 2010-07-14 | 中建三局建设工程股份有限公司 | Small-angle oblique scaffold cantilevered to external wall |
CN102367700A (en) * | 2011-10-29 | 2012-03-07 | 李欣 | Floor type dual-raw external scaffold |
CN203654708U (en) * | 2013-11-29 | 2014-06-18 | 深圳市工勘岩土工程有限公司 | Side slope scaffold unloading device |
CN205918081U (en) * | 2016-05-31 | 2017-02-01 | 上海建工五建集团有限公司 | Outer curtain scaffold frame of arc building |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110565929A (en) * | 2019-07-26 | 2019-12-13 | 江苏兴厦建设工程集团有限公司 | Scaffold for construction of large-specification wall paving piece of building outer wall |
CN111177829A (en) * | 2019-12-25 | 2020-05-19 | 广联达科技股份有限公司 | Method, system and medium for building external scaffold based on professional knowledge prior partitioning |
CN111191310A (en) * | 2019-12-25 | 2020-05-22 | 广联达科技股份有限公司 | Method, system and medium for constructing external scaffold based on rapid arrangement of preferential blocks |
CN113089820A (en) * | 2021-04-09 | 2021-07-09 | 上海通正铝结构建设科技有限公司 | Construction method of single-layer oblique-crossing special-shaped curved surface aluminum alloy structure in limited space |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105863233A (en) | Scaffold for outer curtain wall of arc-shaped building and mounting method | |
CN104100122A (en) | Construction method of cone-shaped top structure of large silo | |
CN205918081U (en) | Outer curtain scaffold frame of arc building | |
CN103603491B (en) | A kind of erection method of beam slab alter-pouring strips mould plate bracing frame | |
CN211899558U (en) | Handling frame encorbelments | |
CN105332506A (en) | Formwork support system for parallel multi-section stair and method for constructing same | |
CN104674997A (en) | Supporting structure of archaized wood structure building roof and construction method thereof | |
CN107806182A (en) | A kind of multilayer cantilever steel construction and its constructive method | |
CN111005547B (en) | Construction method of outer scaffold of two-way bending and twisting staggered floor elevation | |
CN219138351U (en) | High-altitude large-span sliding bailey frame formwork supporting platform | |
CN209799400U (en) | Multifunctional pier column reinforcement jig frame | |
CN103015693A (en) | Three-dimensional construction device for super high-rise core tube beam-slab structure | |
CN106013450A (en) | Core tube skip-floor construction method | |
CN203145432U (en) | steel pipe scaffold ladder stand | |
CN104847108A (en) | Hydraulic climbing formwork structure and construction method of hydraulic climbing formwork structure | |
CN204282788U (en) | Shaping type scaffold can be assembled | |
CN211201184U (en) | Assembled steel structure system | |
CN104196221B (en) | Large area is encorbelmented the construction bearing platform of building and erection method thereof | |
CN203741845U (en) | Structure for assisting in communicating fountain pits in semi-reversed construction method | |
CN207553635U (en) | Elevator shaft safety protection device and elevator | |
CN206873494U (en) | A kind of operating platform for narrow space on the outside of barricade | |
CN115773001B (en) | Steel structure archaizing attic construction method | |
CN111749450A (en) | Safety protection construction method for large-span cast-in-situ dome | |
CN113818691B (en) | Construction method for large cantilever beam platform of high-rise building | |
CN112983049B (en) | Prefabricated wallboard supporting system and using method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160817 |
|
RJ01 | Rejection of invention patent application after publication |