CN105862866B - A kind of method for determining thermometer burial place in concrete pouring bin containing cooling water pipe - Google Patents
A kind of method for determining thermometer burial place in concrete pouring bin containing cooling water pipe Download PDFInfo
- Publication number
- CN105862866B CN105862866B CN201610208915.0A CN201610208915A CN105862866B CN 105862866 B CN105862866 B CN 105862866B CN 201610208915 A CN201610208915 A CN 201610208915A CN 105862866 B CN105862866 B CN 105862866B
- Authority
- CN
- China
- Prior art keywords
- temperature
- cooling water
- water pipe
- thermometer
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
一种确定含冷却水管混凝土浇筑仓中温度计埋设位置的方法,该方法包括以下步骤:步骤1:获得含冷却水管的混凝土模型温度场;步骤2:采用形函数来获得截面任意点温度;步骤3:由步骤1得到的含冷却水管的混凝土模型平均温度历程和步骤2得到的任意点温度,建立温度计几何位置优选模型;步骤4:采用优化算法求解温度计几何位置优选模型,获得温度计埋设最优的几何位置坐标。本发明提供的一种确定含冷却水管混凝土浇筑仓中温度计埋设位置的方法,可以解决在混凝土浇筑仓温度计埋设的几何位置不确定的问题,实现了准确确定温度计的埋设位置,达到合理监控温度的目的。
A method for determining the embedding position of a thermometer in a concrete pouring silo containing a cooling water pipe, the method comprising the following steps: Step 1: Obtaining the temperature field of a concrete model containing a cooling water pipe; Step 2: Using a shape function to obtain the temperature at any point in the section; Step 3 : From the average temperature history of the concrete model with cooling water pipes obtained in step 1 and the temperature at any point obtained in step 2, the optimal model of the geometric position of the thermometer is established; step 4: using the optimization algorithm to solve the optimal model of the geometric position of the thermometer, and obtaining the optimal temperature for embedding the thermometer Geometric position coordinates. The method for determining the embedding position of the thermometer in the concrete pouring silo containing the cooling water pipe provided by the present invention can solve the problem of uncertain geometrical position of the thermometer embedding in the concrete pouring silo, realize accurate determination of the embedding position of the thermometer, and achieve reasonable temperature monitoring Purpose.
Description
技术领域technical field
本发明涉及混凝土浇筑领域,尤其是一种确定含冷却水管混凝土浇筑仓中温度计埋设位置的方法。The invention relates to the field of concrete pouring, in particular to a method for determining the embedding position of a thermometer in a concrete pouring bin containing a cooling water pipe.
背景技术Background technique
水管冷却是混凝土坝施工中控制温度防止裂缝的重要方法,自20世纪30年代胡佛(Hoover)拱坝首次采用以来,已在全世界得到广泛应用。但由于水管冷却时产生的温度场十分复杂,它实际上是一把双刃剑,既可有效降低混凝土温度,但如果降温速率过快,又可引起严重的裂缝。针对这个问题,朱伯芳提出了“小温差、早冷却、缓慢冷却”的通水冷却原则。目前,该通水冷却原则在高混凝土坝工程中逐渐得到广泛应用。例如,针对溪洛渡特高拱坝,设计单位将水管冷却分为三期(一期、中期和二期)九个阶段,每个阶段严格控制目标温度和温度变化速率等,施工单位按设计温控过程线进行通水冷却,获得了良好的温控防裂效果。Water pipe cooling is an important method to control temperature and prevent cracks in concrete dam construction, and it has been widely used all over the world since it was first used in the Hoover arch dam in the 1930s. However, because the temperature field generated by the water pipe cooling is very complicated, it is actually a double-edged sword, which can effectively reduce the temperature of the concrete, but if the cooling rate is too fast, it can cause serious cracks. In response to this problem, Zhu Bofang proposed the water cooling principle of "small temperature difference, early cooling, and slow cooling". At present, the principle of water cooling has gradually been widely used in high concrete dam engineering. For example, for the Xiluodu extra-high arch dam, the design unit divided the water pipe cooling into three phases (first, middle and second phases) and nine stages, and strictly controlled the target temperature and temperature change rate in each stage. The process line is cooled by water, and a good temperature control and crack prevention effect is obtained.
对设计院设计温控过程线分析可知,设计温控过程线是混凝土浇筑仓的平均温度历程。显然,为了对混凝土浇筑仓温度进行监控,有必要在混凝土浇筑仓内埋设温度计进行温度监测。由于混凝土浇筑仓尺寸较大,厚度一般1~3m,横河向宽20m左右,顺河向长度20m~60m不等。实际施工时,每个混凝土浇筑仓至多埋设1~2支温度计。在温控实践过程中发现,由于混凝土浇筑仓在通水冷却期间的温度场十分复杂,温度计埋设的位置距离水管近则实测温度偏低,距离水管远则实测温度偏高。在混凝土浇筑仓如何埋设温度计,使实测温度表征混凝土浇筑仓的平均温度为工程建设单位所关注,但迄今该问题尚未见有关文献报导。由于在实际混凝土浇筑仓中埋设温度计的位置存在较大的随意性和盲目性,以致温度计实测温度不能较好地反映混凝土浇筑仓的平均温度历程,难以达到合理监控温度的目的。The analysis of the design temperature control process line of the design institute shows that the design temperature control process line is the average temperature history of the concrete pouring silo. Obviously, in order to monitor the temperature of the concrete pouring silo, it is necessary to embed a thermometer in the concrete pouring silo for temperature monitoring. Due to the large size of the concrete pouring silo, the thickness is generally 1-3m, the width across the river is about 20m, and the length along the river is 20m-60m. During actual construction, at most 1 to 2 thermometers should be buried in each concrete pouring bin. During the practice of temperature control, it was found that because the temperature field of the concrete pouring silo during the water cooling period is very complicated, the measured temperature is low when the thermometer is buried close to the water pipe, and the measured temperature is high when it is far away from the water pipe. How to embed a thermometer in the concrete pouring silo so that the measured temperature represents the average temperature of the concrete pouring silo is of concern to the engineering construction unit, but so far this problem has not been reported in the relevant literature. Due to the randomness and blindness of the position of the buried thermometer in the actual concrete pouring silo, the actual temperature measured by the thermometer cannot reflect the average temperature history of the concrete pouring silo well, and it is difficult to achieve the purpose of reasonable temperature monitoring.
发明内容Contents of the invention
本发明所要解决的技术问题是提供一种确定含冷却水管混凝土浇筑仓中温度计埋设位置的方法,可以解决在混凝土浇筑仓温度计埋设的几何位置不确定的问题,实现了准确确定温度计的埋设位置。The technical problem to be solved by the present invention is to provide a method for determining the embedding position of the thermometer in the concrete pouring silo containing the cooling water pipe, which can solve the problem of uncertain geometrical position of the thermometer in the concrete pouring silo, and realize the accurate determination of the embedding position of the thermometer.
为解决上述技术问题,本发明所采用的技术方案是:一种确定含冷却水管混凝土浇筑仓中温度计埋设位置的方法,该方法包括以下步骤:In order to solve the above-mentioned technical problems, the technical solution adopted in the present invention is: a method for determining the embedding position of the thermometer in the concrete pouring silo containing the cooling water pipe, the method comprising the following steps:
步骤1:建立含冷却水管的混凝土模型,采用水管冷却有限元法进行温度场仿真计算,获得含冷却水管的混凝土模型温度场,Step 1: Establish a concrete model with cooling water pipes, use the water pipe cooling finite element method to simulate the temperature field, and obtain the temperature field of the concrete model with cooling water pipes,
由公式(1)计算获得含冷却水管的混凝土模型的平均温度历程:The average temperature history of the concrete model with cooling water pipes is calculated by formula (1):
设t时刻,混凝土浇筑仓在通水冷却时的平均温度Tave(t)为Assuming time t, the average temperature T ave (t) of the concrete pouring silo during water cooling is
式中:Tg(t)是t时刻单元高斯点温度;Vg为单元高斯点占有体积,可采用该高斯点的雅可比行列式|J|计算得到;为单元高斯点累加;为浇筑仓单元累加;为除去水管所占体积的混凝土浇筑仓体积;In the formula: T g (t) is the temperature of the unit Gauss point at time t; V g is the occupied volume of the unit Gauss point, which can be calculated by using the Jacobian determinant |J| of the Gauss point; Accumulated for the unit Gauss point; Accumulated for the pouring bin unit; The volume of the concrete pouring chamber to remove the volume occupied by the water pipes;
步骤2:选取含冷却水管混凝土模型的典型截面,由截面单元节点温度,采用形函数来获得截面任意点温度Step 2: Select a typical section of the concrete model with cooling water pipes, use the shape function to obtain the temperature at any point of the section from the node temperature of the section element
混凝土浇筑仓内任意点的温度为The temperature at any point in the concrete pouring silo is
式中,Ni(x,y,z)为形函数,Ti(t)为t时刻节点i温度;In the formula, N i (x, y, z) is the shape function, T i (t) is the temperature of node i at time t;
步骤3:由步骤1得到的含冷却水管的混凝土模型平均温度历程Tave(t)和步骤2得到的任意点温度T(x,y,z,t),建立温度计几何位置优选模型;Step 3: From the average temperature history T ave (t) of the concrete model containing the cooling water pipe obtained in step 1 and the temperature T (x, y, z, t) at any point obtained in step 2, an optimal model for the geometric position of the thermometer is established;
步骤4:采用优化算法求解温度计几何位置优选模型,获得温度计埋设最优的几何位置坐标。Step 4: Use the optimization algorithm to solve the optimal model of the geometric position of the thermometer, and obtain the optimal geometric position coordinates of the buried thermometer.
步骤1中,混凝土浇筑仓中的冷却水管采用蛇形布置,建立含冷却水管的混凝土模型为含冷却水管的混凝土棱柱体模型。In step 1, the cooling water pipes in the concrete pouring silo are arranged in a serpentine shape, and the concrete model containing the cooling water pipes is established as a concrete prism model containing the cooling water pipes.
步骤2中,选取的典型截面为混凝土棱柱体模型的中间截面。In step 2, the typical section selected is the middle section of the concrete prism model.
混凝土棱柱体采用6面体8节点单元,则中间截面为四边形4节点单元,引入四边形12节点单元,通过由四边形12节点等参单元替代四边形4节点等参单元来简化截面内任意点温度计算。The concrete prism adopts hexahedral 8-node elements, and the middle section is a quadrilateral 4-node element. A quadrilateral 12-node element is introduced, and the temperature calculation at any point in the section is simplified by replacing the quadrilateral 4-node isoparametric element with the quadrilateral 12-node isoparametric element.
本发明提供的一种确定含冷却水管混凝土浇筑仓中温度计埋设位置的方法,采用优化算法和水管冷却有限元法相结合,可以解决在混凝土浇筑仓温度计埋设的几何位置不确定的问题,实现了准确确定温度计的埋设位置;方法步骤简单,结果精确,适用范围广;为便于由节点温度获得截面内任意点温度,引入四边形12节点单元,通过采用四边形12节点等参单元替代四边形4节点等参单元来简化截面内任意点温度计算,大大简化了计算过程。The invention provides a method for determining the embedding position of the thermometer in the concrete pouring silo containing the cooling water pipe, which adopts the combination of the optimization algorithm and the water pipe cooling finite element method, and can solve the problem of the uncertain geometric position of the thermometer embedding in the concrete pouring silo, and realizes accurate Determine the embedding position of the thermometer; the method is simple, the result is accurate, and the application range is wide; in order to obtain the temperature of any point in the section from the nodal temperature, a quadrilateral 12-node element is introduced, and the quadrilateral 4-node isoparametric element is replaced by the quadrilateral 12-node isoparametric element To simplify the calculation of temperature at any point in the section, it greatly simplifies the calculation process.
附图说明Description of drawings
下面结合附图和实施例对本发明作进一步说明:Below in conjunction with accompanying drawing and embodiment the present invention will be further described:
图1为本发明混凝土浇筑仓中采用蛇形布置的冷却水管;Fig. 1 adopts the cooling water pipe of serpentine arrangement in the concrete pouring silo of the present invention;
图2为本发明实施例中步骤1建立的含冷却水管的混凝土棱柱体模型;Fig. 2 is the concrete prism model containing the cooling water pipe that step 1 establishes in the embodiment of the present invention;
图3为本发明实施例中步骤1第一种棱柱体截面的有限元网格;Fig. 3 is the finite element grid of the first kind of prism section in step 1 in the embodiment of the present invention;
图4为本发明实施例中步骤1第二种棱柱体截面的有限元网格;Fig. 4 is the finite element grid of the second kind of prism section in step 1 in the embodiment of the present invention;
图5为本发明实施例中步骤1第三种棱柱体截面的有限元网格;Fig. 5 is the finite element grid of the third kind of prism section in step 1 in the embodiment of the present invention;
图6为本发明实施例中步骤1第四种棱柱体截面的有限元网格;Fig. 6 is the finite element grid of the fourth prism section in step 1 in the embodiment of the present invention;
图7为本发明实施例中步骤1由公式(1)计算结果绘制出的混凝土棱柱体平均温度过程线;Fig. 7 is the concrete prism average temperature process line drawn by formula (1) calculation result in step 1 in the embodiment of the present invention;
图8为本发明实施例中步骤2第一种棱柱体截面采用的四边形12节点图;Fig. 8 is a quadrilateral 12-node diagram adopted in the first prism cross-section in step 2 in the embodiment of the present invention;
图9为本发明实施例中步骤2第二种棱柱体截面采用的四边形12节点图;Fig. 9 is a quadrilateral 12-node diagram adopted in the second prism section in step 2 in the embodiment of the present invention;
图10为本发明实施例中步骤2第三种棱柱体截面采用的四边形12节点图;Fig. 10 is a quadrilateral 12-node diagram adopted in the third prism section of step 2 in the embodiment of the present invention;
图11为本发明实施例中步骤2第四种棱柱体截面采用的四边形12节点图;Fig. 11 is a quadrilateral 12-node diagram adopted in the fourth prism cross-section in step 2 in the embodiment of the present invention;
图12为本发明实施例中步骤2第一种棱柱体截面采用的四边形12节点的插值温度和仿真计算节点温度差值对比图;Fig. 12 is a comparison diagram of the interpolation temperature of the quadrilateral 12 nodes used in the first prism section in step 2 of the embodiment of the present invention and the simulation calculation node temperature difference;
图13为本发明实施例中步骤4第一种棱柱体冷却水管的几何位置画出的几何位置分布图;Fig. 13 is a geometric position distribution diagram drawn by the geometric position of the first prism cooling water pipe in step 4 in the embodiment of the present invention;
图14为本发明实施例中步骤4第二种棱柱体冷却水管的几何位置画出的几何位置分布图;Fig. 14 is a geometric position distribution diagram drawn by the geometric position of the second prism cooling water pipe in step 4 in the embodiment of the present invention;
图15为本发明实施例中步骤4第三种棱柱体冷却水管的几何位置画出的几何位置分布图;Fig. 15 is a geometric position distribution diagram drawn by the geometric position of the third prism cooling water pipe in step 4 in the embodiment of the present invention;
图16为本发明实施例中步骤4第三种棱柱体冷却水管的几何位置画出的几何位置分布图。Fig. 16 is a geometric position distribution drawing of the geometric position of the third type of prism cooling water pipe in step 4 in the embodiment of the present invention.
具体实施方式detailed description
含冷却水管的混凝土浇筑仓的情况如下:The concrete pouring silo with cooling water pipes is as follows:
据已有工程经验,混凝土坝中埋设的水管间距通常为1.0~3.0m。混凝土绝热温升表达式为θ(t)=25.3(1-e-0.315τ),混凝土导热系数λ=8.49kJ/(m·h·℃),比热c=0.955kJ/(kg·℃),密度ρ=2400kg/m3;通水流量qw=24m3/d,比热cw=4.187kJ/(kgg℃),密度ρw=1000kg/m3。According to existing engineering experience, the distance between water pipes buried in concrete dams is usually 1.0-3.0m. The expression of concrete adiabatic temperature rise is θ(t)=25.3(1-e -0.315τ ), the thermal conductivity of concrete λ=8.49kJ/(m·h·℃), and the specific heat c=0.955kJ/(kg·℃) , density ρ = 2400kg/m 3 ; water flow q w = 24m 3 /d, specific heat c w = 4.187kJ/(kg°C), density ρ w = 1000kg/m 3 .
一种确定含冷却水管混凝土浇筑仓中温度计埋设位置的方法,该方法包括以下步骤:A method for determining the embedding position of a thermometer in a concrete pouring silo containing a cooling water pipe, the method comprising the following steps:
步骤1:建立含冷却水管的混凝土模型,采用水管冷却有限元法进行温度场仿真计算,获得含冷却水管的混凝土模型温度场,Step 1: Establish a concrete model with cooling water pipes, use the water pipe cooling finite element method to simulate the temperature field, and obtain the temperature field of the concrete model with cooling water pipes,
在实际混凝土坝工程中,混凝土浇筑仓中的冷却水管一般采用蛇形布置,如图1所示,沿流水方向的AB和CD面为近似对称面,可以认为该对称面为绝热边界面,为此,建立含冷却水管的混凝土棱柱体模型,如图2所示。In actual concrete dam engineering, the cooling water pipes in the concrete pouring silo are generally arranged in a serpentine shape, as shown in Figure 1, the planes AB and CD along the flow direction are approximately symmetrical planes, which can be considered as adiabatic boundary planes, as Therefore, a concrete prism model containing cooling water pipes is established, as shown in Figure 2.
设混凝土棱柱体长L=100m,设计了4种不同的棱柱体截面尺寸,分别为Assuming that the length of the concrete prism is L=100m, four different cross-sectional dimensions of the prism are designed, which are
第一种:宽×高=1m×1mThe first type: width × height = 1m × 1m
第二种:宽×高=1.5m×1.5mThe second type: width × height = 1.5m × 1.5m
第三种:宽×高=1m×1.5mThe third type: width × height = 1m × 1.5m
第四种:宽×高=2m×1.5m,在混凝土棱柱体横截面的正中心方向布置了一根外径为=32mm的冷却水管,The fourth type: width × height = 2m × 1.5m, a cooling water pipe with an outer diameter of = 32mm is arranged in the direction of the center of the concrete prism cross section,
即第一种棱柱体冷却水管的水平间距为1m,垂直间距为1m;That is, the horizontal spacing of the first type of prism cooling water pipe is 1m, and the vertical spacing is 1m;
第二种棱柱体冷却水管的水平间距为1.5m,垂直间距为1.5m;The horizontal spacing of the second prism cooling water pipe is 1.5m, and the vertical spacing is 1.5m;
第三种棱柱体冷却水管的水平间距为1m,垂直间距为1.5m;The horizontal spacing of the third type of prism cooling water pipe is 1m, and the vertical spacing is 1.5m;
第四种棱柱体冷却水管的水平间距为2m,垂直间距为1.5m,The horizontal spacing of the fourth prism cooling water pipe is 2m, and the vertical spacing is 1.5m.
棱柱体截面的有限元网格如图3-6所示。The finite element mesh of the prism section is shown in Figure 3-6.
假设混凝土棱柱体6个表面均为绝热边界,混凝土的初始温度取10℃,冷却水入口温度为10℃。Assuming that the six surfaces of the concrete prism are all adiabatic boundaries, the initial temperature of the concrete is 10°C, and the inlet temperature of the cooling water is 10°C.
采用水管冷却有限元法进行通水冷却期间的温度场仿真计算,通水开始时间为1d,连续通水10d。The water pipe cooling finite element method is used to simulate the temperature field during the water cooling period. The water flow start time is 1d, and the water flow is continued for 10d.
由公式(1)计算获得含冷却水管的混凝土模型的平均温度历程:The average temperature history of the concrete model with cooling water pipes is calculated by formula (1):
设t时刻,混凝土浇筑仓在通水冷却时的平均温度Tave(t)为Assuming time t, the average temperature T ave (t) of the concrete pouring silo during water cooling is
式中:Tg(t)是t时刻单元高斯点温度;Vg为单元高斯点占有体积,可采用该高斯点的雅可比行列式|J|计算得到;为单元高斯点累加;为浇筑仓单元累加;为除去水管所占体积的混凝土浇筑仓体积;In the formula: T g (t) is the temperature of the unit Gauss point at time t; V g is the occupied volume of the unit Gauss point, which can be calculated by using the Jacobian determinant |J| of the Gauss point; Accumulate for the unit Gauss point; Accumulated for the pouring bin unit; The volume of the concrete pouring chamber to remove the volume occupied by the water pipes;
由公式(1)计算结果绘制出的混凝土棱柱体平均温度过程线如图7所示。The average temperature process line of the concrete prism drawn from the calculation results of formula (1) is shown in Figure 7.
步骤2:选取混凝土棱柱体中间50m所在截面进行分析,由于棱柱体6个表面绝热,截面温度场呈对称分布,为此,对1/4截面的温度场进行分析。Step 2: Select the 50m section in the middle of the concrete prism for analysis. Since the six surfaces of the prism are insulated, the temperature field of the section is symmetrically distributed. Therefore, the temperature field of the 1/4 section is analyzed.
由截面单元节点温度,采用形函数来获得截面任意点温度From the node temperature of the section element, the shape function is used to obtain the temperature of any point of the section
混凝土浇筑仓内任意点的温度为The temperature at any point in the concrete pouring silo is
式中,Ni(x,y,z)为形函数,Ti(t)为t时刻节点i温度;In the formula, N i (x, y, z) is the shape function, T i (t) is the temperature of node i at time t;
在进行水管冷却有限元计算时,混凝土棱柱体采用6面体8节点单元,则中间截面为四边形4节点单元,由式(2)计算截面任意点的温度不方便。为便于由节点温度获得截面内任意点温度,引入四边形12节点单元,通过由四边形12节点等参单元替代四边形4节点等参单元来简化截面内任意点温度计算,结果如图8-11所示。In the finite element calculation of water pipe cooling, the concrete prism adopts hexahedral 8-node elements, and the middle section is a quadrilateral 4-node element. It is inconvenient to calculate the temperature at any point of the section by formula (2). In order to obtain the temperature at any point in the section from the node temperature, a quadrilateral 12-node element is introduced, and the calculation of the temperature at any point in the section is simplified by replacing the quadrilateral 4-node isoparametric element with the quadrilateral 12-node isoparametric element. The results are shown in Figure 8-11 .
依据温度场仿真计算结果,给出了四边形12节点单元的上下限,该四边形12节点单元区域包含9个四边形4节点单元。According to the simulation calculation results of the temperature field, the upper and lower limits of the quadrilateral 12-node unit are given, and the quadrilateral 12-node unit area contains 9 quadrilateral 4-node units.
以图8为例,采用四边形12节点等参单元形函数来计算四边形单元中A、B、C和D 4个点的温度历程,将其与温度场仿真计算的节点温度历程进行对比分析,结构如图12所示。Taking Figure 8 as an example, the temperature history of four points A, B, C, and D in the quadrilateral element is calculated by using the quadrilateral 12-node isoparametric element shape function, and it is compared with the node temperature history calculated by the temperature field simulation. As shown in Figure 12.
由图12分析可知,宽×高=1m×1m截面单元中A、B、C和D 4个点的温度差值分布在[-0.01,0.06]范围内,计算误差在0.03%以内,因此,采用四边形12节点等参单元代替四边形4节点等参单元来简化截面内任意点温度的计算是可行的。From the analysis in Figure 12, it can be seen that the temperature difference distribution of the four points A, B, C and D in the width × height = 1m × 1m section unit is within the range of [-0.01,0.06], and the calculation error is within 0.03%. Therefore, It is feasible to use quadrilateral 12-node isoparametric elements instead of quadrilateral 4-node isoparametric elements to simplify the calculation of temperature at any point in the section.
因此将公式(2)拓展成公式(4)和(5)Therefore, formula (2) is extended into formulas (4) and (5)
引入四边形12节点等参单元获得的截面任意点温度为The temperature at any point of the section obtained by introducing a quadrilateral 12-node isoparametric element is
式中,Ti(t)为对应节点温度,Ni(ξ,η)为四边形12节点等参单元的形函数,其为where T i (t) is the corresponding nodal temperature, N i (ξ,η) is the shape function of the quadrilateral 12-node isoparametric element, which is
步骤3:由步骤1得到的含冷却水管的混凝土模型平均温度历程Tave(t)和步骤2得到的任意点温度T(x,y,z,t),建立温度计几何位置优选模型,Step 3: From the average temperature history T ave (t) of the concrete model containing the cooling water pipe obtained in step 1 and the temperature T(x, y, z, t) at any point obtained in step 2, an optimal model for the geometric position of the thermometer is established,
温度计几何位置优选分析表明,在截面上存在多个几何位置的温度历程和浇筑仓平均温度历程接近。为此,采用固定η的取值,具体按0.1的间距分别取η′=-1,-0.9,-0.8,-0.7,-0.6,-0.5,-0.4,-0.3,-0.2,-0.1,0,0.1,0.2,0.3,0.4,0.5,0.6,0.7,0.8,0.9,1.0,然后采用一维优化搜索法对ξ进行优选。此时,温度计几何位置优选的数学形式为The optimal analysis of the geometric position of the thermometer shows that the temperature history of multiple geometric positions on the section is close to the average temperature history of the pouring chamber. For this reason, adopt the value of fixed n, specifically get n '=-1,-0.9,-0.8,-0.7,-0.6,-0.5,-0.4,-0.3,-0.2,-0.1, 0, 0.1, 0.2, 0.3, 0.4, 0.5, 0.6, 0.7, 0.8, 0.9, 1.0, and then use the one-dimensional optimization search method to optimize ξ. At this time, the preferred mathematical form of the geometric position of the thermometer is
求ξFind ξ
使 Make
满足约束条件:-1≤ξ≤1Satisfy the constraints: -1≤ξ≤1
其中,Num是由温度场仿真计算的时间步来确定,由于在仿真分析时,前11d的时间步为0.1d,11~41d的时间步为0.5d,因此,本次分析Num取170。Among them, Num is determined by the time step calculated by temperature field simulation. Since in the simulation analysis, the time step of the first 11d is 0.1d, and the time step of 11~41d is 0.5d, therefore, Num is taken as 170 in this analysis.
由于在固定η′时,不一定存在对应的ξ来保证式(6)中f(ξ)→min,因此,本次分析采用了最小误差和最大优选次数的双重优选控制标准。Since when η′ is fixed, there does not necessarily exist a corresponding ξ to ensure that f(ξ)→min in formula (6), therefore, this analysis adopts the dual optimization control standard of minimum error and maximum optimization times.
步骤4:采用优化算法求解温度计几何位置优选模型,获得温度计埋设最优的几何位置坐标。Step 4: Use the optimization algorithm to solve the optimal model of the geometric position of the thermometer, and obtain the optimal geometric position coordinates of the buried thermometer.
采用一维优化搜索法对式(6)进行优选求解,获得温度计几何位置ξ-η值,然后采用下式获得x-y坐标值Use the one-dimensional optimization search method to optimally solve formula (6), obtain the geometric position ξ-η value of the thermometer, and then use the following formula to obtain the x-y coordinate value
式中,xi和yi分别为节点i的坐标。In the formula, x i and y i are the coordinates of node i respectively.
由上述公式(7)得到的四种棱柱体冷却水管的几何位置画出的几何位置分布图如图13-16所示,由图13-14可知,第一种、第二种和第四种棱柱体截面温度计几何位置分布呈抛物线分布,第三种棱柱体截面温度计几何位置分布近似为线性分布。The geometric position distribution diagram drawn by the geometric positions of the four prism cooling water pipes obtained by the above formula (7) is shown in Figure 13-16. It can be seen from Figure 13-14 that the first, second and fourth types The geometric position distribution of the prism cross-section thermometer is a parabolic distribution, and the geometric position distribution of the third prism cross-section thermometer is approximately a linear distribution.
在实际混凝土坝工程中,根据混凝土浇筑仓的水管间距,在上述最优的几何位置处埋设温度计,温度计的实测温度历程即可以较好地表征混凝土浇筑仓的平均温度历程。In the actual concrete dam project, according to the water pipe spacing of the concrete pouring silo, a thermometer is buried at the above optimal geometric position, and the measured temperature history of the thermometer can better represent the average temperature history of the concrete pouring silo.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610208915.0A CN105862866B (en) | 2016-04-05 | 2016-04-05 | A kind of method for determining thermometer burial place in concrete pouring bin containing cooling water pipe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610208915.0A CN105862866B (en) | 2016-04-05 | 2016-04-05 | A kind of method for determining thermometer burial place in concrete pouring bin containing cooling water pipe |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105862866A CN105862866A (en) | 2016-08-17 |
CN105862866B true CN105862866B (en) | 2017-09-15 |
Family
ID=56627119
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610208915.0A Active CN105862866B (en) | 2016-04-05 | 2016-04-05 | A kind of method for determining thermometer burial place in concrete pouring bin containing cooling water pipe |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105862866B (en) |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5973845B2 (en) * | 2012-05-28 | 2016-08-23 | 株式会社安藤・間 | Pipe cooling system and pipe cooling method |
CN102979307B (en) * | 2012-12-12 | 2016-04-13 | 新疆生产建设兵团金来建设工程技术研发有限责任公司 | A kind of Temperature-controllcrack crack prevention construction method for concrete structure |
CN103942407B (en) * | 2014-02-17 | 2019-03-19 | 葛洲坝集团试验检测有限公司 | A kind of concrete temperature field emulated computation method based on pour |
CN104499486B (en) * | 2014-11-25 | 2016-01-20 | 三峡大学 | A kind of Optimum Regulation system being applicable to the water flowing of concrete dam middle and later periods |
CN104809334A (en) * | 2015-04-08 | 2015-07-29 | 河海大学 | Calculating method of large-volume concrete cooling temperature field |
-
2016
- 2016-04-05 CN CN201610208915.0A patent/CN105862866B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN105862866A (en) | 2016-08-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Liu et al. | Precise simulation analysis of the thermal field in mass concrete with a pipe water cooling system | |
CN103614498B (en) | Method for reconstructing three-dimensional temperature field positioned on blast furnace wall and computer monitoring system | |
CN104809334A (en) | Calculating method of large-volume concrete cooling temperature field | |
CN113468630B (en) | Optimization method for shield tunnel originating end reinforcing scheme | |
CN104036095B (en) | A Fast Algorithm for Coupling High-Precision Complicated Flow Field Based on Domain Decomposition | |
CN204343295U (en) | Roller compacted concrete storehouse face condenser tube arrangement structure | |
CN117171861A (en) | Prediction method for mud-rock flow formed by erosion of river bed by overtopping and breaking water flow | |
CN110044959A (en) | The method for studying high Rayleigh number fusion pool heat transfer characteristic using improved Finite Volume Method for Air | |
CN103279662A (en) | Method of measuring and calculating distribution of water temperatures of river channel below dam of reservoir | |
JP2016014378A (en) | Water intake method, and water intake system | |
CN106446438B (en) | A kind of nearly far field approach of coupled numerical simulation of power plant's warm water discharge deep water discharge | |
CN105862866B (en) | A kind of method for determining thermometer burial place in concrete pouring bin containing cooling water pipe | |
CN111625967A (en) | Simplified calculation method for heat exchange performance of U-shaped middle-deep buried pipe heat exchanger | |
Shi et al. | Shape optimization of corrugated tube using B-spline curve for convective heat transfer enhancement based on machine learning | |
CN103088176B (en) | Method for detecting air gap on a blast furnace shell | |
CN108073736B (en) | Simplified Equivalent Analysis Method for Heat Insulation Device of Nuclear Main Pump | |
CN110412312A (en) | A Calculation Method of Vertical Distribution of Inrush Current Velocity | |
CN108256266B (en) | A method and system for coupling one-dimensional hydrodynamic model and two-dimensional hydrodynamic model | |
CN105740812B (en) | A kind of city water catchment area extracting method based on digital surface model | |
CN108052729B (en) | Inverse design method of superhydrophobic surface microstructure | |
CN106055774B (en) | A Simulation Method of Surface Water Flow Movement in Surface Irrigation | |
Krzemianowski et al. | Use of non-uniform rational b-splines for discharge calculation in the velocity area method | |
CN202433328U (en) | Dense-phase zone heat transfer coefficient measuring device | |
CN105973319A (en) | Method for computing hydraulic characteristic of sewage system of control rod driving mechanism | |
CN111414677B (en) | A Calculation Method for Transport Properties of Multiphase High Content Granular Materials |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |