CN105862603A - Simple and easy steel pipe arch bridge and arch rib closure device - Google Patents

Simple and easy steel pipe arch bridge and arch rib closure device Download PDF

Info

Publication number
CN105862603A
CN105862603A CN201610381237.8A CN201610381237A CN105862603A CN 105862603 A CN105862603 A CN 105862603A CN 201610381237 A CN201610381237 A CN 201610381237A CN 105862603 A CN105862603 A CN 105862603A
Authority
CN
China
Prior art keywords
pipe
steel pipe
closure device
string
arch bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610381237.8A
Other languages
Chinese (zh)
Other versions
CN105862603B (en
Inventor
岳文军
武亚超
程波
宋大成
王栋
张鹏勃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Communications Construction Group Fifth Engineering Co ltd
CCCC Construction Group Co Ltd
Original Assignee
Engineering Co Ltd Of Middle Public Office Of Friendship Four 5th
CCCC Fourth Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Engineering Co Ltd Of Middle Public Office Of Friendship Four 5th, CCCC Fourth Highway Engineering Co Ltd filed Critical Engineering Co Ltd Of Middle Public Office Of Friendship Four 5th
Priority to CN201610381237.8A priority Critical patent/CN105862603B/en
Publication of CN105862603A publication Critical patent/CN105862603A/en
Application granted granted Critical
Publication of CN105862603B publication Critical patent/CN105862603B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to the field of machinery and particularly relates to a simple and easy steel pipe arch bridge and arch rib closure device. The simple and easy steel pipe arch bridge and arch rib closure device comprises chord pipes, wherein a butt joint part of the two chord pipes is a butt joint sleeve; the butt joint sleeve comprises a basket-like nut; the inner wall of the basket-like nut comprises a thread and further comprises basket-like screw rods which are spirally connected to the two sides in the basket-like nut; a base plate is connected with the basket-like screw rod on each side; and the base plates are connected with the chord pipes. The simple and easy steel pipe arch bridge and arch rib closure device is simple and reasonable in structural design and is convenient to construct and operate; instant closure construction of a steel pipe arch bridge can be finished in a time-saving and labor-saving manner; the closure precision and arch rib stress are adjusted relatively well, and safety risks of long-time overhead work is alleviated; and the simple and easy steel pipe arch bridge and arch rib closure device has the advantages of reasonable structural design, simplicity in operation and low construction cost.

Description

A kind of easy steel pipe arch bridge arch rib closure device
Technical field
The present invention relates to mechanical field, particularly relate to a kind of easy steel pipe arch bridge arch rib closure device.
Background technology
Along with the constantly bringing forth new ideas of construction technology, the improving constantly of environmental requirement, crossing over the Large Span Bridges such as large reservoir, navigable river, precipitous valley and be constantly used, CFST Arch Bridge is exactly wherein to fit to select one of bridge type;Hanging without bracket buckle that free cantilever erection, structure be complicated, in the installation process of the steel pipe arch bridge of construction sections weight super large, must be the key of steel pipe arch bridge Cheng Qiao especially in vault closure section structure, the linear and Stress Control of joining the two sections of a bridge, etc.
The technology of steel pipe arch bridge closure at present arranges gad joint in mainly having pipe, minimum temperature main arch steel pipe directly carries out welding and completes instantaneous closure.Both approaches construction operation time is longer, and operating personnel, equipment and material all demands are relatively big, more cannot meet linear, the Stress Control requirement of Long span rib-lifting section assembly main arch large diameter steel pipe.
Summary of the invention
The purpose of invention: in order to provide a kind of effect preferably easy steel pipe arch bridge arch rib closure device, specific purposes are shown in the multiple substantial technological effects being embodied as part.
In order to reach as above purpose, the present invention adopts the following technical scheme that:
A kind of easy steel pipe arch bridge arch rib closure device, it is characterized in that, comprise string pipe, the position of two string pipe docking is docking sleeve pipe, comprising in docking sleeve pipe and spend blue nut, spend blue nut inner wall to comprise screw thread, also comprise that spiral accesses the both sides spent in blue nut spends blue screw rod, the blue screw rod of spending of both sides each connects a backing plate, and backing plate chord pipe connects.
The further technical scheme of the present invention is, described backing plate avris comprises locating slot, spends blue screw rod through location steel tank, location steel tank also comprises and spends blue bolt spacing hole.
The further technical scheme of the present invention is, described backing plate connects floor.
The further technical scheme of the present invention is, described floor comprises more than a piece of, and a piece of above floor is respectively positioned on inside string pipe around floor central distribution, floor and backing plate.
The further technical scheme of the present invention is, also comprises internal lining pipe between described floor.
The further technical scheme of the present invention is, described floor is welded to connect the inwall of string pipe.
The further technical scheme of the present invention is, the mouth of pipe of Guan Zhongyi string pipe of said two string comprises apron, and apron comprises apron periphery, and the when of two string pipe docking, apron can be extruded.
The further technical scheme of the present invention is, the mouth of pipe of Guan Zhongyi string pipe of said two string comprises extruding plate, and extruding plate is round and can push down apron periphery.
The further technical scheme of the present invention is, each self-contained inclined wall of part of said two string pipe docking.
Use the present invention of as above technical scheme, have the advantages that relative to prior art: present configuration design is simple, rationally, constructing operation is convenient, the instantaneous closing construction completing steel pipe arch bridge that can be time saving and energy saving, and join the two sections of a bridge, etc precision and stress of arch costal can preferably be adjusted, reduce the security risk of long-time work high above the ground, there is reasonable in design, the advantage that simple to operate and construction cost is low.
Accompanying drawing explanation
In order to further illustrate the present invention, it is further illustrated below in conjunction with the accompanying drawings:
Fig. 1 is instantaneous closure structural texture figure;
Fig. 2 is backing plate side structural representation;
Fig. 3 is backing plate opposite side structural representation;
Fig. 4 is for spending blue nut structure schematic diagram;
Fig. 5 is for spending blue screw-rod structure schematic diagram;
Fig. 6 is the structural representation of string pipe docking;
Wherein: 1. spend blue screw rod;2. spend blue nut;3. backing plate;4. floor on the right side of;5. docking sleeve pipe;6. location steel tank;7. internal lining pipe;8. floor on the left of;9. spend blue bolt spacing hole;10. string pipe;11. aprons;12. apron peripheries;13. extruding plates;14. inclined walls;101. string pipes one;102. string pipes two.
Detailed description of the invention
Illustrating embodiments of the invention below in conjunction with the accompanying drawings, embodiment is not construed as limiting the invention:
A kind of easy steel pipe arch bridge arch rib closure device, it is characterized in that, comprise string pipe, the position of two string pipe docking is docking sleeve pipe, comprising in docking sleeve pipe and spend blue nut, spend blue nut inner wall to comprise screw thread, also comprise that spiral accesses the both sides spent in blue nut spends blue screw rod, the blue screw rod of spending of both sides each connects a backing plate, and backing plate chord pipe connects.Technique effect and the process that realizes thereof of the essence that the technical scheme at this place is played are as follows: rotate and spend blue nut, drives two spend blue screw rod close to or far away from, convenient dock.
Described backing plate avris comprises locating slot, spends blue screw rod through location steel tank, location steel tank also comprises and spends blue bolt spacing hole.Described backing plate connects floor.Described floor comprises more than a piece of, and a piece of above floor is respectively positioned on inside string pipe around floor central distribution, floor and backing plate.Internal lining pipe is also comprised between described floor.Described floor is welded to connect the inwall of string pipe.
More specifically realize process as follows:
Main arch steel pipe about when steel pipe arch bridge closure connects, main arch steel pipe i.e. string pipe, it is respectively provided with in main arch steel pipe and is evenly arranged eight pieces of ribs for base and backing plate, it is provided with location steel tank connection, steel tank horizontally arranged limited location hole, location and backing plate before backing plate to be connected by bolt with location steel tank and be connected, instantaneous closure is configured to spend blue bolt, spends blue bolt to include bolt and positions, with being provided with on screw rod, screw rod, the spacing hole that steel tank is identical.The operation principle spending blue bolt is: spending blue nut to be fabricated to reverse thread, rotating and spending blue nut is that blue screw rod into or out simultaneously is spent in both sides.
Closing construction job content is as follows: rib for base is welded in before sections installation steel pipe arch bridge inwall in advance, after completing the installation of left and right sides main arch sections, install to put in place and adjust its position by location steel tank on left and right sides backing plate and be up to the standard, treat environment temperature, after arch rib absolute altitude reaches closure condition, instantaneous closure structure is installed, the nut spending blue bolt is loaded in the steel tank of location with screw rod, and adjust the spacing hole position spending blue screw rod, the spacing hole making location steel tank and Hua Lan screw rod is in same position and limits its rotation with wearing pin, rotary flower orchid nut makes both sides arch rib hold out against simultaneously, complete instantaneous closure;Having captured that the operation of existing steel pipe arch bridge closing construction is complicated, closure operation elapsed time is longer, safety coefficient is relatively low and closes up precision and the problem of main arch Stress non-homogeneity.
Present configuration design is simple, rationally, constructing operation is convenient, the instantaneous closing construction completing steel pipe arch bridge that can be time saving and energy saving, and join the two sections of a bridge, etc precision and stress of arch costal can preferably be adjusted, reduce the security risk of long-time work high above the ground, there is reasonable in design, the advantage that simple to operate and construction cost is low.
Adjusting the main arch lifting sections of the left and right sides, in advance rib for base and base are welded on left and right sides rib-lifting section, the rib for base of welding is evenly arranged on supervisor's inwall, and the center internal lining pipe in rib for base is fixed.During environment temperature and arch rib Pass line adjustment, installing location steel tank, the angle of regulation location steel is close to vertically.Under the conditions of suitable closure, blue bolt will be spent to put into location steel tank, both sides spend blue screw rod and the spacing hole positioning steel tank to fix spacing with wearing pin, spend blue nut to make both sides arch rib hold out against under instantaneous closure constructs in the middle of regulation.
In specific implementation process: steel tube arch rib uses non-support cable crane system system to install, the most symmetrical free cantilever erection in two sides, stayed knotting method installation, arch rib reserves closure section in vault span centre portion;After both sides main arch rib is installed to closure section, adjust arch rib integral linear, adjust the length spending blue bolt according to the distance of location, the both sides steel tank of closure condition, and carry out the instantaneous closure of installation.
The mouth of pipe of Guan Zhongyi string pipe of said two string comprises apron, and apron comprises apron periphery, and the when of two string pipe docking, apron can be extruded.Technique effect and the process that realizes thereof of the essence that the technical scheme at this place is played are as follows: can extrude at the apron of two string pipes when of extruding, it is possible to form waterproof structure, it is to avoid water flows between two string pipes.
The mouth of pipe of Guan Zhongyi string pipe of said two string comprises extruding plate, and extruding plate is round and can push down apron periphery.Technique effect and the process that realizes thereof of the essence that the technical scheme at this place is played are as follows: extruding plate is round and can push down apron periphery, therefore, it is possible to cover sealing, it is possible to the position water inlet avoided contact with, and then affect sealing.
The each self-contained inclined wall of part of said two string pipe docking.Technique effect and the process that realizes thereof of the essence that the technical scheme at this place is played are as follows: inclined wall can water guide, be avoided that water is entered to interface position.
In a creative way, each effect above is individually present, moreover it is possible to complete the combination of the above results with a nested structure.
The technique effect that above structure realizes realizes clear, and discounting for additional technical scheme, this patent title can also is that a kind of closure structure.Part details not shown in figure.
It should be noted that multiple schemes that this patent provides comprise the basic scheme of itself, separate, the most mutually restrict, but it can also be mutually combined in the case of not conflicting, reach multiple effect and jointly realize.
The general principle of the present invention, principal character and advantages of the present invention have more than been shown and described.Those skilled in the art is it should be recognized that the present invention is not restricted to the described embodiments; the principle that the present invention is simply described described in above-described embodiment and specification; without departing from the spirit and scope of the present invention; the present invention also has various changes and modifications, and these changes and improvements both fall within claimed scope.

Claims (9)

1. an easy steel pipe arch bridge arch rib closure device, it is characterized in that, comprise string pipe, the position of two string pipe docking is docking sleeve pipe, comprising in docking sleeve pipe and spend blue nut, spend blue nut inner wall to comprise screw thread, also comprise that spiral accesses the both sides spent in blue nut spends blue screw rod, the blue screw rod of spending of both sides each connects a backing plate, and backing plate chord pipe connects.
2. a kind of easy steel pipe arch bridge arch rib closure device as claimed in claim 1, it is characterised in that described backing plate avris comprises locating slot, spends blue screw rod through location steel tank, location steel tank also comprises and spends blue bolt spacing hole.
3. a kind of easy steel pipe arch bridge arch rib closure device as claimed in claim 1, it is characterised in that described backing plate connects floor.
4. a kind of easy steel pipe arch bridge arch rib closure device as claimed in claim 3, it is characterised in that described floor comprises more than a piece of, and a piece of above floor is distributed around string tube hub, and floor and backing plate are respectively positioned on inside string pipe.
5. a kind of easy steel pipe arch bridge arch rib closure device as claimed in claim 4, it is characterised in that also comprise internal lining pipe between described floor.
6. a kind of easy steel pipe arch bridge arch rib closure device as claimed in claim 4, it is characterised in that described floor is welded to connect the inwall of string pipe.
7. a kind of easy steel pipe arch bridge arch rib closure device as claimed in claim 1, it is characterised in that the mouth of pipe of Guan Zhongyi string pipe of said two string comprises apron, and apron comprises apron periphery, and the when of two string pipe docking, apron can be extruded.
8. a kind of easy steel pipe arch bridge arch rib closure device as claimed in claim 7, it is characterised in that the mouth of pipe of Guan Zhongyi string pipe of said two string comprises extruding plate, and extruding plate is round and can push down apron periphery.
9. a kind of easy steel pipe arch bridge arch rib closure device as claimed in claim 7, it is characterised in that each self-contained inclined wall of part of said two string pipe docking.
CN201610381237.8A 2016-06-01 2016-06-01 A kind of easy steel pipe arch bridge arch rib closure device Active CN105862603B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610381237.8A CN105862603B (en) 2016-06-01 2016-06-01 A kind of easy steel pipe arch bridge arch rib closure device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610381237.8A CN105862603B (en) 2016-06-01 2016-06-01 A kind of easy steel pipe arch bridge arch rib closure device

Publications (2)

Publication Number Publication Date
CN105862603A true CN105862603A (en) 2016-08-17
CN105862603B CN105862603B (en) 2018-03-09

Family

ID=56675625

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610381237.8A Active CN105862603B (en) 2016-06-01 2016-06-01 A kind of easy steel pipe arch bridge arch rib closure device

Country Status (1)

Country Link
CN (1) CN105862603B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112049013A (en) * 2020-08-28 2020-12-08 中交第四公路工程局有限公司 Rapid closure construction method for steel pipe arch bridge arch rib
CN113186796A (en) * 2021-04-30 2021-07-30 广州文船重工有限公司 Connecting joint and connecting method for closure opening of arch bridge

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002201609A (en) * 2000-12-28 2002-07-19 Ps Corp Construction method for concrete arch bridge
CN102493347A (en) * 2011-12-13 2012-06-13 武船重型工程有限公司 Method for machining and mounting flanges between sections of steel pipe arch
CN102864738A (en) * 2012-09-29 2013-01-09 中铁十五局集团第二工程有限公司 Device and method for accelerating closure of arch ribs of arch bridge
CN204959580U (en) * 2015-09-22 2016-01-13 中国铁路总公司 Steel pipe arched bridge closure connecting device
CN205711770U (en) * 2016-06-01 2016-11-23 中交四公局第五工程有限公司 A kind of easy steel pipe arch bridge arch rib closure device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002201609A (en) * 2000-12-28 2002-07-19 Ps Corp Construction method for concrete arch bridge
CN102493347A (en) * 2011-12-13 2012-06-13 武船重型工程有限公司 Method for machining and mounting flanges between sections of steel pipe arch
CN102864738A (en) * 2012-09-29 2013-01-09 中铁十五局集团第二工程有限公司 Device and method for accelerating closure of arch ribs of arch bridge
CN204959580U (en) * 2015-09-22 2016-01-13 中国铁路总公司 Steel pipe arched bridge closure connecting device
CN205711770U (en) * 2016-06-01 2016-11-23 中交四公局第五工程有限公司 A kind of easy steel pipe arch bridge arch rib closure device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112049013A (en) * 2020-08-28 2020-12-08 中交第四公路工程局有限公司 Rapid closure construction method for steel pipe arch bridge arch rib
CN113186796A (en) * 2021-04-30 2021-07-30 广州文船重工有限公司 Connecting joint and connecting method for closure opening of arch bridge

Also Published As

Publication number Publication date
CN105862603B (en) 2018-03-09

Similar Documents

Publication Publication Date Title
CN204959580U (en) Steel pipe arched bridge closure connecting device
CN107606309B (en) A kind of deep-water subsea pipeline pipeline section connection operation device
CN206693980U (en) The antifouling flow-controlled device of oil pipe
CN105862603A (en) Simple and easy steel pipe arch bridge and arch rib closure device
CN205711770U (en) A kind of easy steel pipe arch bridge arch rib closure device
CN105862990A (en) Prefabricated assembly well wall structure and construction method thereof
CN206329923U (en) Explosion-proof water supply line
CN105598630A (en) Hydraulic docking device used outside large-caliber gathering and transportation pipeline
CN203418255U (en) Adjustable pipe fitting fitting-up bracket
CN106402431B (en) A kind of double-channel butterfly valve valve
CN202901532U (en) Novel hydraulic internally-pulling device for prestressed concrete cylinder pipe (PCCP) installation
WO2015158074A1 (en) Construction method for connection and replacement of underground water-supply fiber-reinforced plastic mortar pipe and steel pipe
CN207063007U (en) A kind of walling crib ruggedized construction
CN206225311U (en) A kind of fuse switch
CN206902574U (en) A kind of Filled Steel Tubular Arch Bridge closing device
CN206902570U (en) Steel pipe arch bridge arch rib closing device
CN204114371U (en) Directly buried type heat supply pipeline
CN206916630U (en) Simple steel pipe arch rib closing device
CN203441457U (en) Pipe-in-pipe thickened oil steam injection well mouth device
CN203656365U (en) Combination-type transition cable leading cage based on cable leading towards lower bridge surface
CN206220624U (en) The helicopter servicing unit of extra-high voltage wine glass tower tower head
CN202790905U (en) Pipeline crossing device for pipeline crossing construction
CN209412659U (en) One kind is repaired the roads engineering tamping unit
CN106340825B (en) A kind of cable wire-binding device
CN204339976U (en) Self-propelled beam slab intelligent spray health-preservation device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: Room 21207, unit 2, building 1, No.1 zhangbayi Road, high tech Zone, Xi'an, Shaanxi 710000

Patentee after: China Communications Construction Group Fifth Engineering Co.,Ltd.

Patentee after: CCCC Construction Group Co.,Ltd.

Address before: Room 21207, unit 2, building 1, No.1 zhangbayi Road, high tech Zone, Xi'an, Shaanxi 710000

Patentee before: NO.5 ENGINEERING CO.,LTD. OF CCCC FOURTH HIGHWAY ENGINEERING CO.,LTD.

Patentee before: CCCC FOURTH HIGHWAY ENGINEERING Co.,Ltd.