CN105839774B CN201610341152.7A CN201610341152A CN105839774B CN 105839774 B CN105839774 B CN 105839774B CN 201610341152 A CN201610341152 A CN 201610341152A CN 105839774 B CN105839774 B CN 105839774B
Authority
CN
China
Prior art keywords
square steel
side plate
steel
plate
square
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610341152.7A
Other languages
Chinese (zh)
Other versions
CN105839774A (en
Inventor
郝际平
何梦楠
薛强
樊春雷
孙晓岭
黄育琪
陈永昌
刘斌
王磊
尹伟康
刘瀚超
赵子健
张峻铭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xi'an Jianda Assembly Steel Structure Research Institute Co ltd
Original Assignee
Xian University of Architecture and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Architecture and Technology filed Critical Xian University of Architecture and Technology
Priority to CN201610341152.7A priority Critical patent/CN105839774B/en
Publication of CN105839774A publication Critical patent/CN105839774A/en
Application granted granted Critical
Publication of CN105839774B publication Critical patent/CN105839774B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • E04B1/215Connections specially adapted therefor comprising metallic plates or parts

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a kind of prefabricated T-shaped power consumption connecting node, including power consumption connector, the first concrete combination column and the second concrete combination column, the first concrete combination column to include the first side plate, the second side plate, the first square steel, the second square steel and the first stiffener;Second concrete combination column includes third steel, four square steel, the 5th square steel, the 3rd side plate, the 4th side plate, the 5th side plate and the 6th side plate.Bearing capacity of the present invention, ductility, ornamental are preferable, and save space, and the engineering time is shorter.

Description

A kind of prefabricated T-shaped power consumption connecting node
Technical field
The present invention relates to a kind of connecting node, and in particular to a kind of prefabricated T-shaped power consumption connecting node.
Background technology
China at present《Rectangular steel tube with concrete infilled technical regulation》(GECS159:2004) the T-shaped connection that is used for provided saves Point is mainly by the node for the form such as internal partition formula, outer shroud be board-like, but up to the present, existing T-shaped connecting node often occurs Local buckling phenomenon, bearing capacity and ductility are poor, and indoor-bollard often protrudes corner angle, so as to be effectively reduced house Usable floor area and ornamental, in addition, most of existing T-shaped connecting node is to be poured at the construction field (site), construction is inconvenient, And the engineering time is longer, so as to the serious influence duration.
The content of the invention
The shortcomings that it is an object of the invention to overcome above-mentioned prior art, there is provided a kind of prefabricated T-shaped power consumption connecting node, The bearing capacity of the connecting node, ductility, ornamental are preferable, and save space, and the engineering time is shorter.
To reach above-mentioned purpose, prefabricated T-shaped power consumption connecting node of the present invention includes power consumption connector, the first Combined concrete Post and the second concrete combination column, the first concrete combination column include the first side plate, the second side plate, the first square steel, the second square steel And first stiffener, the two sides of the first stiffener are connected with the medial surface of the first side plate and the medial surface of the second side plate respectively Connecing, the both ends of the first side plate are connected with the right flank of the first square steel and the left surface of the second square steel respectively, and the two of the second side plate End is connected with the right flank of the first square steel and the left surface of the second square steel respectively, and the first side plate and the first square steel positive and The front flush of second square steel, the second side plate flush with the back side of the first square steel and the back side of the second square steel, the first stiffener position Between the first square steel and the second square steel, the first square steel is interior, the second square steel is interior and the first stiffener and the first square steel and second Concrete has been poured between square steel;
Second concrete combination column includes third steel, four square steel, the 5th square steel, the 3rd side plate, the 4th side plate, the 5th Side plate and the 6th side plate, wherein, third steel, four square steel and the 5th square steel are from left to right sequentially distributed, and the two of the 3rd side plate End is connected with the side of third steel and the side of four square steel, the both ends of the 4th side plate respectively with the side of third steel and The side of four square steel is connected, and the both ends of the 5th side plate are connected with the side of four square steel and the side of the 5th square steel respectively Connect, the both ends of the 6th side plate are connected with the side of four square steel and the side of the 5th square steel respectively, the 3rd side plate and the 5th side The front of plate and third steel, the front of four square steel and the front flush of the 5th square steel, the 4th side plate and the 6th side plate and the The back side at the back side of three square steel, the back side of four square steel and the 5th square steel flushes, and third steel is interior, four square steel is interior, the 5th side Concrete is filled with steel, between third steel and four square steel and between four square steel and the 5th square steel;
The right flank of second square steel is connected with the front of four square steel by the connector that consumes energy.
Also include heptalateral plate, the 8th side plate, the 9th side plate and the tenth side plate, wherein, the side of heptalateral plate one end and The side of the 8th side plate one end is connected with the front of the second square steel and the back side respectively, and one end of the 9th side plate passes through the 3rd side plate It is connected with the left surface of four square steel, one end of the tenth side plate is connected through the 5th side plate with the right flank of four square steel, Heptalateral plate and the tenth side plate are fixed on the left surface of power consumption connector, and the 8th side plate and the 9th side plate are fixed on power consumption connection On the right flank of part.
The power consumption connector includes the first channel-section steel, the second channel-section steel and some second stiffeners, and the one of each second stiffener The medial surface of the first channel-section steel is fixed at end, and the other end of each second stiffener is fixed on the medial surface of the second channel-section steel, wherein, first The left surface of channel-section steel is connected by some first bolts with the side of the tenth side plate, and the right flank of the first channel-section steel passes through some Two bolts are connected with the side of the 9th side plate, the side that the left surface of the second channel-section steel passes through some 3rd bolts and heptalateral plate It is connected, the right flank of the second channel-section steel is connected by some 4th bolts with the side of the 8th side plate.
Each first bolt equidistantly distributed successively, each second bolt equidistantly distributed successively.
Each 3rd bolt equidistantly distributed successively, each 4th bolt equidistantly distributed successively.
The left surface and right flank of each second stiffener open up fluted.
The middle part of each second stiffener offers through hole.
The invention has the advantages that:
Prefabricated T-shaped power consumption connecting node of the present invention includes power consumption connector, the first concrete combination column and second Concrete combination column, the first concrete combination column add including the first side plate, the second side plate, the first square steel, the second square steel and first Strength plate, the first square steel, the second square steel and the first stiffener are located between the first side plate and the second side plate, in the first square steel, second Concrete is filled with square steel, between the first stiffener and the first square steel and the second square steel, is used as by concrete whole mixed The edge constraint component of solidifying local soil type zygostyle, greatly improve the bearing capacity and energy dissipation capacity of the first concrete combination column.Lead to simultaneously Cross the first stiffener and the cavity between the first side plate, the second side plate, the first square steel and the second square steel is divided into two small chambers, carry The bearing capacity and ductility of high first concrete combination column and the second concrete combination column, the first side plate and the second side plate is avoided to occur Flexing phenomenon.Second concrete combination column includes third steel, four square steel and the 5th square steel, third steel, four directions It is connected between steel and the 5th square steel by the 3rd side plate, the 4th side plate, the 5th side plate and the 6th side plate, then pours coagulation again Soil, so that the second concrete combination column has stronger bearing capacity and ductility.In addition, when making, can be according to wall The square steel of width adjusting first, the second square steel, third steel, four square steel, the width of the 5th square steel and six square steel, so as to Enough make the first concrete combination column and the second concrete combination column and the same width of wall, increase the usable floor area of building, raising is built The ornamental built.Meanwhile the present invention in the first concrete combination column and the second concrete combination column can in the factory batch Production, is then transported to job site, then the first concrete combination column and the second concrete combination column are passed through into the connector that consumes energy It is connected, you can form the prefabricated T-shaped power consumption connecting node, avoid poured in place concrete, reduce the engineering time, raising is applied The quality of work.
Brief description of the drawings
Fig. 1 is the exploded view of the first concrete combination column 1 in the present invention;
Fig. 2 is the exploded view of the second concrete combination column 2 in the present invention;
Fig. 3 is the structural representation of the first concrete combination column 1 in the present invention;
Fig. 4 is the structural representation of power consumption connector in the present invention;
Fig. 5 is the exploded view of the present invention;
Fig. 6 is the structural representation of the present invention.
Wherein, 1 be the first concrete combination column, 2 be the second concrete combination column, 3 be the first square steel, 4 be the second square steel, 5 it is the first side plate, 6 be the second side plate, 7 be the first stiffener, 8 be third steel, 9 be four square steel, 10 is the 5th square steel, 11 For the 3rd side plate, 12 be the 4th side plate, 13 be the 5th side plate, 14 be the 6th side plate, 15 be heptalateral plate, 16 be the 8th side plate, 17 it is the 9th side plate, 18 be the tenth side plate, 19 be the first channel-section steel, 20 be the second channel-section steel, 21 is the second stiffener.
Embodiment
The present invention is described in further detail below in conjunction with the accompanying drawings:
With reference to figure 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5 and Fig. 6, prefabricated T-shaped power consumption connecting node of the present invention includes power consumption Connector, the first concrete combination column 1 and the second concrete combination column 2, the first concrete combination column 1 include the first side plate 5, the Two side plates 6, the first square steel 3, the second square steel 4 and the first stiffener 7, the two sides of the first stiffener 7 respectively with the first side plate 5 The medial surface of medial surface and the second side plate 6 is connected, the both ends of the first side plate 5 right flank and second with the first square steel 3 respectively The left surface of square steel 4 is connected, the both ends of the second side plate 6 respectively with the right flank of the first square steel 3 and the left surface of the second square steel 4 It is connected, and positive and the second square steel 4 the front flush of the first side plate 5 and the first square steel 3, the second side plate 6 and the first square steel 3 The back side and the back side of the second square steel 4 flush, the first stiffener 7 is between the first square steel 3 and the second square steel 4, the first square steel 3 Concrete has been poured in interior, the second square steel 4 and between the first stiffener 7 and the first square steel 3 and the second square steel 4;Second is mixed Solidifying local soil type zygostyle 2 includes third steel 8, four square steel 9, the 5th square steel 10, the 3rd side plate 11, the 4th side plate 12, the 5th side plate 13 and the 6th side plate 14, wherein, third steel 8, the square steel 10 of four square steel 9 and the 5th are from left to right sequentially distributed, the 3rd side plate 11 both ends are connected with the side of third steel 8 and the side of four square steel 9, the both ends of the 4th side plate 12 respectively with third party The side of steel 8 and the side of four square steel 9 are connected, the both ends of the 5th side plate 13 respectively with the side of four square steel 9 and the 5th The side of square steel 10 is connected, the both ends of the 6th side plate 14 respectively with the side of four square steel 9 and the side phase of the 5th square steel 10 Connection, the 3rd side plate 11 and the front of the 5th side plate 13 and third steel 8, the front of four square steel 9 and the 5th square steel 10 are just Face flushes, the back side, the back side of four square steel 9 and the back of the body of the 5th square steel 10 of the 4th side plate and the 6th side plate 14 and third steel 8 Face flushes, in third steel 8, in four square steel 9, in the 5th square steel 10, between third steel 8 and four square steel 9 and the 4th Concrete is filled between the square steel 10 of square steel 9 and the 5th;The right flank of second square steel 4 and the front of four square steel 9 pass through consumption Energy connector is connected.
Present invention additionally comprises heptalateral plate 15, the 8th side plate 16, the 9th side plate 17 and the tenth side plate 18, wherein, heptalateral The side of the one end of plate 15 and the side of the one end of the 8th side plate 16 are connected with the front of the second square steel 4 and the back side respectively, the 9th side One end of plate 17 is connected through the 3rd side plate 11 with the left surface of four square steel 9, and one end of the tenth side plate 18 passes through the 5th side Plate 13 is connected with the right flank of four square steel 9, and the side plate 18 of heptalateral plate 15 and the tenth is fixed on the left surface of power consumption connector On, the 8th side plate 16 and the 9th side plate 17 are fixed on the right flank of power consumption connector.
The power consumption connector includes the first channel-section steel 19, the second channel-section steel 20 and some second stiffeners 21, and each second puts more energy into The medial surface of the first channel-section steel 19 is fixed in one end of plate 21, and the other end of each second stiffener 21 is fixed on the interior of the second channel-section steel 20 Side, the left surface and right flank of each second stiffener 21 open up fluted;The middle part of each second stiffener 21 offers Through hole, wherein, the left surface of the first channel-section steel 19 is connected by some first bolts with the side of the tenth side plate 18, the first channel-section steel 19 right flank is connected by some second bolts with the side of the 9th side plate 17, and the left surface of the second channel-section steel 20 passes through some 3rd bolt is connected with the side of heptalateral plate 15, and the right flank of the second channel-section steel 20 passes through some 4th bolts and the 8th side plate 16 side is connected;Each first bolt equidistantly distributed successively, each second bolt equidistantly distributed successively;Each 3rd bolt according to Secondary equidistantly distributed, each 4th bolt equidistantly distributed successively.
The present invention work progress be:
1) construction of the first concrete combination column 1 is carried out, Specific construction process is:First complete the first side plate 5, the second side plate 6th, the welding of the first square steel 3, the second square steel 4, the first stiffener 7, the side plate 16 of heptalateral plate 15 and the 8th, then again by concrete Pour in the first square steel 3, in the second square steel 4 and between the first stiffener 7 and the first square steel 3 and the second square steel 4, complete The preparation of first concrete combination column 1;2) construction of the second concrete combination column 2 is carried out, Specific construction process is:Present 5th The end fluting of the side plate 11 of side plate 13 and the 3rd, then carries out the 3rd side plate 11, the 4th side plate 12, the 5th side plate the 13, the 6th again Side plate 14, the 9th side plate 17, the tenth side plate 18, third steel 8, the welding of four square steel 9, the 5th square steel 10, then by coagulation Soil pours in the third steel 8, in four square steel 9, in the 5th square steel 10, between third steel 8 and four square steel 9, Yi Ji Between the square steel 10 of four square steel 9 and the 5th, the preparation of the second concrete combination column 2 is completed;4) welding of power consumption connector is carried out;3) Power consumption connector, the first concrete combination column 1 and the second concrete combination column 2 are transported to job site, pass through the first bolt The left surface of first channel-section steel 19 is connected with the side of the tenth side plate 18, by the second bolt by the right flank of the first channel-section steel 19 It is connected with the side of the 9th side plate 17, by the 3rd bolt by the side phase of the left surface and heptalateral plate 15 of the second channel-section steel 20 The right flank of second channel-section steel 20, is connected by connection by the 4th bolt with the side of the 8th side plate 16, you can completes prefabricated T-shaped The construction for the connecting node that consumes energy.

Claims (3)

  1. The connecting node 1. a kind of prefabricated T-shaped consumes energy, it is characterised in that including power consumption connector, the first concrete combination column (1) and Second concrete combination column (2);
    First concrete combination column (1) include the first side plate (5), the second side plate (6), the first square steel (3), the second square steel (4) and First stiffener (7), the two sides of the first stiffener (7) are interior with the medial surface of the first side plate (5) and the second side plate (6) respectively Side is connected, the both ends of the first side plate (5) respectively with the right flank of the first square steel (3) and the left surface phase of the second square steel (4) Connection, the both ends of the second side plate (6) are connected with the right flank of the first square steel (3) and the left surface of the second square steel (4) respectively, and First side plate (5) and the front of the first square steel (3) and the front flush of the second square steel (4), the second side plate (6) and the first square steel (3) the back side and the back side of the second square steel (4) flushes, the first stiffener (7) be located at the first square steel (3) and the second square steel (4) it Between, in the first square steel (3), in the second square steel (4) and the first stiffener (7) and the first square steel (3) and the second square steel (4) it Between poured concrete;
    Second concrete combination column (2) include third steel (8), four square steel (9), the 5th square steel (10), the 3rd side plate (11), 4th side plate (12), the 5th side plate (13) and the 6th side plate (14), wherein, third steel (8), four square steel (9) and the 5th side Steel (10) is from left to right sequentially distributed, both ends and the side of third steel (8) and the side of four square steel (9) of the 3rd side plate (11) Face is connected, and the both ends of the 4th side plate (12) are connected with the side of third steel (8) and the side of four square steel (9) respectively, The both ends of 5th side plate (13) are connected with the side of four square steel (9) and the side of the 5th square steel (10) respectively, the 6th side plate (14) both ends are connected with the side of four square steel (9) and the side of the 5th square steel (10) respectively, the 3rd side plate (11) and The front, the front of four square steel (9) and the front flush of the 5th square steel (10) of five side plates (13) and third steel (8), the 4th Side plate and the 6th side plate (14) and the back side at the back side of third steel (8), the back side of four square steel (9) and the 5th square steel (10) are neat It is flat, in third steel (8), in four square steel (9), in the 5th square steel (10), between third steel (8) and four square steel (9), with And it is filled with concrete between four square steel (9) and the 5th square steel (10);
    The right flank of second square steel (4) is connected with the front of four square steel (9) by the connector that consumes energy;
    Also include heptalateral plate (15), the 8th side plate (16), the 9th side plate (17) and the tenth side plate (18), wherein, heptalateral plate (15) side of the side of one end and the 8th side plate (16) one end is connected with the front of the second square steel (4) and the back side respectively, the One end of nine side plates (17) is connected through the 3rd side plate (11) with the left surface of four square steel (9), and the one of the tenth side plate (18) End is connected through the 5th side plate (13) with the right flank of four square steel (9), and heptalateral plate (15) and the tenth side plate (18) are fixed In on the left surface of power consumption connector, the 8th side plate (16) and the 9th side plate (17) are fixed on the right flank of power consumption connector;
    The power consumption connector includes the first channel-section steel (19), the second channel-section steel (20) and some second stiffeners (21), and each second adds The medial surface of the first channel-section steel (19) is fixed in one end of strength plate (21), and the other end of each second stiffener (21) is fixed on the second groove The medial surface of steel (20), wherein, the side that the left surface of the first channel-section steel (19) passes through some first bolts and the tenth side plate (18) It is connected, the right flank of the first channel-section steel (19) is connected by some second bolts with the side of the 9th side plate (17), the second groove The left surface of steel (20) is connected by some 3rd bolts with the side of heptalateral plate (15), the right flank of the second channel-section steel (20) It is connected by some 4th bolts with the side of the 8th side plate (16);
    Each first bolt equidistantly distributed successively, each second bolt equidistantly distributed successively;
    Each 3rd bolt equidistantly distributed successively, each 4th bolt equidistantly distributed successively.
  2. The connecting node 2. prefabricated T-shaped according to claim 1 consumes energy a, it is characterised in that left side for each second stiffener (21) Side and right flank open up fluted.
  3. The connecting node 3. prefabricated T-shaped according to claim 1 consumes energy, it is characterised in that in each second stiffener (21) Portion offers through hole.
CN201610341152.7A 2016-05-20 2016-05-20 A kind of prefabricated T-shaped power consumption connecting node Expired - Fee Related CN105839774B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610341152.7A CN105839774B (en) 2016-05-20 2016-05-20 A kind of prefabricated T-shaped power consumption connecting node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610341152.7A CN105839774B (en) 2016-05-20 2016-05-20 A kind of prefabricated T-shaped power consumption connecting node

Publications (2)

Publication Number Publication Date
CN105839774A CN105839774A (en) 2016-08-10
CN105839774B true CN105839774B (en) 2018-04-06

Family

ID=56594001

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610341152.7A Expired - Fee Related CN105839774B (en) 2016-05-20 2016-05-20 A kind of prefabricated T-shaped power consumption connecting node

Country Status (1)

Country Link
CN (1) CN105839774B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108360745B (en) * 2018-02-27 2020-05-19 青岛理工大学 Assembled double-energy-consumption recoverable square concrete filled steel tube combination column and installation method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100197759B1 (en) * 1996-10-08 1999-06-15 김세중 A conjunctive construction part for joining a concrete column and iron beam of a building
KR20110133126A (en) * 2010-06-04 2011-12-12 재단법인 포항산업과학연구원 Steel tube for filling concrete
CN102587577A (en) * 2012-03-15 2012-07-18 天津大学 Steel tube-I beam combination steel tube concrete special-shaped columns and manufacture method thereof
CN104233944A (en) * 2014-09-05 2014-12-24 湖州市交通工程总公司 Double-L-shaped combined type T-shaped energy-consuming connector and manufacturing technique thereof
CN105239726A (en) * 2015-09-01 2016-01-13 同济大学 Prefabricated steel-reinforced concrete combined special-shaped energy-dissipating column
CN105484388A (en) * 2015-11-18 2016-04-13 福建工程学院 Prefabricated assembly type shear wall vertical slit connecting structure and construction method thereof
CN205663027U (en) * 2016-05-20 2016-10-26 西安建筑科技大学 Prefabricated T type power consumption connected node

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100197759B1 (en) * 1996-10-08 1999-06-15 김세중 A conjunctive construction part for joining a concrete column and iron beam of a building
KR20110133126A (en) * 2010-06-04 2011-12-12 재단법인 포항산업과학연구원 Steel tube for filling concrete
CN102587577A (en) * 2012-03-15 2012-07-18 天津大学 Steel tube-I beam combination steel tube concrete special-shaped columns and manufacture method thereof
CN104233944A (en) * 2014-09-05 2014-12-24 湖州市交通工程总公司 Double-L-shaped combined type T-shaped energy-consuming connector and manufacturing technique thereof
CN105239726A (en) * 2015-09-01 2016-01-13 同济大学 Prefabricated steel-reinforced concrete combined special-shaped energy-dissipating column
CN105484388A (en) * 2015-11-18 2016-04-13 福建工程学院 Prefabricated assembly type shear wall vertical slit connecting structure and construction method thereof
CN205663027U (en) * 2016-05-20 2016-10-26 西安建筑科技大学 Prefabricated T type power consumption connected node

Also Published As

Publication number Publication date
CN105839774A (en) 2016-08-10

Similar Documents

Publication Publication Date Title
CN207988220U (en) Combined steel plate shearing force wall
CN104912232B (en) Assembly-type special-shaped composite wall made by thin-walled cold-formed steel
CN205296481U (en) A compound shear wall structure system that is used for civilian steel construction of industrialization construction to construct
CN105839774B (en) A kind of prefabricated T-shaped power consumption connecting node
CN105863163B (en) A kind of Prefabricated L-shaped composite pile prepared from special section steel tube concrete based on square steel connector
CN205637332U (en) Prefabricated L type dysmorphism steel pipe -concrete composite post based on square steel connecting piece
CN205663027U (en) Prefabricated T type power consumption connected node
CN205637336U (en) Prefabricated L shape post power consumption connected node
CN105863166B (en) A kind of prefabricated L-shaped column energy consumption connecting node
CN207314537U (en) A kind of assembled Outsourcing-type steel chain type combining structure
CN206916998U (en) A kind of frame joint assembled wall body construction
CN204876542U (en) A combination plastic formwork for concrete wall pours
CN205663030U (en) Prefabricated T type dysmorphism steel pipe -concrete composite post
CN206110650U (en) Assembled aluminum alloy compound template
CN105821967B (en) A kind of prefabricated T-shaped composite pile prepared from special section steel tube concrete
CN206800657U (en) A kind of connecting plate being used between prefabricated wallboard
CN206289803U (en) Prefabricated formwork built-in profile steel concrete walls
CN205637335U (en) Prefabricated L type dysmorphism steel pipe -concrete composite post
CN105839852B (en) A kind of Prefabricated L-shaped composite pile prepared from special section steel tube concrete
CN103850348A (en) Industrial steel tube bindle composite structure building system
CN103850349A (en) Frame-steel pipe bundle combined structure system for industrial residential building
CN209369028U (en) A kind of assembled beam-column connecting node
CN207988157U (en) Prefabricated partition wall connecting node
CN206646649U (en) The connecting joint structure of column and girder steel
CN207846658U (en) The modularization node of prefabricated buildings

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190729

Address after: 710055 Shaanxi province Xi'an Beilin District Yanta Road No. 13

Patentee after: Xi'an construction division big Assets Management Co.,Ltd.

Address before: 710055 Shaanxi province Xi'an Beilin District Yanta Road No. 13

Patentee before: XIAN University OF ARCHITECTURE AND TECHNOLOG

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190807

Address after: 710055 Campus of Xi'an University of Architectural Science and Technology, No. 13 Yanta Road, Beilin District, Xi'an City, Shaanxi Province

Patentee after: Xi'an Jianda Assembly Steel Structure Research Institute Co.,Ltd.

Address before: 710055 Shaanxi province Xi'an Beilin District Yanta Road No. 13

Patentee before: Xi'an construction division big Assets Management Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180406