CN105807099B - Split conductor stringer - Google Patents

Split conductor stringer Download PDF

Info

Publication number
CN105807099B
CN105807099B CN201610248029.0A CN201610248029A CN105807099B CN 105807099 B CN105807099 B CN 105807099B CN 201610248029 A CN201610248029 A CN 201610248029A CN 105807099 B CN105807099 B CN 105807099B
Authority
CN
China
Prior art keywords
split
disc
rod
disk
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610248029.0A
Other languages
Chinese (zh)
Other versions
CN105807099A (en
Inventor
余虹云
叶成
潘伟建
钱科
王嘉晶
倪国灿
任凯
章益
崔利兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Huadian Equipment Inspection Institute
Electric Power Research Institute of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Zhejiang Huadian Equipment Inspection Institute
Electric Power Research Institute of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Huadian Equipment Inspection Institute, Electric Power Research Institute of State Grid Zhejiang Electric Power Co Ltd filed Critical Zhejiang Huadian Equipment Inspection Institute
Priority to CN201610248029.0A priority Critical patent/CN105807099B/en
Publication of CN105807099A publication Critical patent/CN105807099A/en
Application granted granted Critical
Publication of CN105807099B publication Critical patent/CN105807099B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R1/00Details of instruments or arrangements of the types included in groups G01R5/00 - G01R13/00 and G01R31/00
    • G01R1/02General constructional details
    • G01R1/04Housings; Supporting members; Arrangements of terminals

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

本发明涉及分裂导线架设装置,包括支架和连接有分裂导线的圆盘,圆盘设置在支架上,圆盘上连接有多分裂拉具装置,圆盘上设有固定分裂导线的圆孔,圆孔上连接有连接件,连接件穿过圆孔固定于圆盘上;本发明的优点:通过支架实现圆盘的支撑,并通过圆盘上设有的若干组圆孔固定不同分裂型式的分裂导线,能使圆盘适应于多分裂型式的分裂导线的连接固定,提高了安装效率,防止圆盘的损坏;通过连接件在圆盘处的位置可调,能根据分裂导线子导线线长的差距进行微调补偿,确保装置在拉力状态下子导线的受力平衡;通过连接件在圆盘处的位置可调,能根据分裂导线子导线线长的差距进行微调补偿,确保装置在拉力状态下子导线的受力平衡。

The invention relates to a device for erecting split wires, comprising a bracket and a disk connected with split wires, the disk is arranged on the bracket, and a multi-split puller device is connected to the disk, and a circular hole for fixing the split wires is arranged on the disk. Connectors are connected to the holes, and the connectors pass through the holes and are fixed on the disk; the advantages of the present invention are: the support of the disk is realized through the bracket, and the splits of different split types are fixed through several groups of round holes provided on the disk. The wire can make the disc adapt to the connection and fixation of the multi-split type split wire, which improves the installation efficiency and prevents the damage of the disc; the position of the connector at the disc can be adjusted, and the wire length of the split wire can be adjusted according to the length of the split wire. The gap is fine-tuned and compensated to ensure the force balance of the sub-conductor under the tension state of the device; through the adjustable position of the connector at the disc, fine-tuned compensation can be performed according to the length gap of the split conductor sub-conductor to ensure that the sub-conductor of the device is under tension. force balance.

Description

分裂导线架设装置Split wire erection device

技术领域technical field

本发明涉及分裂导线架设装置。The present invention relates to split conductor erection devices.

背景技术Background technique

分裂导线是一种超高压输电线路为抑制电晕放电和减少线路电抗所采取的一种导线架设方式,目前因科研试验的需要分裂导线应在有一定张力施加的情况下进行载流量、能耗等试验项目,然而分裂导线有不同的分裂型式(包括分裂数及分裂间隔),缺少一套适用于各种分裂型式的分裂导线固定装置,目前试验时需根据分裂导线的分裂型式选择相应的固定结构,且不能模拟分裂导线实际运行工况(施加一定的张力),这样使用成本高,试验效率低,且实用性能低,且现有固定装置安装拆卸时无支撑装置实现支撑,需要通过多名操作人员辅助完成安装,工作强度大,工作效率低,使用效果差。Split conductor is a kind of conductor erection method adopted by ultra-high voltage transmission lines to suppress corona discharge and reduce line reactance. At present, due to the needs of scientific research and experiments, split conductors should be tested for current carrying capacity and energy consumption under the condition of a certain tension. However, split wires have different split types (including split numbers and split intervals), and there is a lack of a set of split wire fixing devices suitable for various split types. At present, it is necessary to select the corresponding fixing device according to the split type of the split wire during the test. structure, and cannot simulate the actual operating conditions of the split conductors (a certain tension is applied), so the cost of use is high, the test efficiency is low, and the practical performance is low, and there is no supporting device to support when the existing fixing device is installed and disassembled. The operator assists in completing the installation, the work intensity is high, the work efficiency is low, and the use effect is poor.

发明内容Contents of the invention

本发明要解决的技术问题就是提供分裂导线架设装置,解决现有分裂导线试验时无适配于多种分裂型式分裂导线的架设装置及安装拆卸时工作强度大的问题。The technical problem to be solved by the present invention is to provide a split wire erecting device, which solves the problems that there is no erecting device suitable for multiple split types of split wires during the test of the existing split wire and the problem of high work intensity during installation and disassembly.

为了解决上述技术问题,本发明是通过以下技术方案实现的:分裂导线架设装置,包括支架和连接有分裂导线的圆盘,圆盘设置在支架上,圆盘上连接有多分裂拉具装置,圆盘上设有若干组固定分裂导线的圆孔,圆孔上连接有与分裂导线相连的连接件,连接件穿过圆孔固定于圆盘上,支架包括底座和设置在底座上高度可调的支撑组件,底座上设有调节支撑组件高度的调节组件。In order to solve the above-mentioned technical problems, the present invention is achieved through the following technical proposals: the split wire erecting device includes a bracket and a disk connected with split wires, the disk is arranged on the bracket, and the disk is connected with a multi-split puller device, There are several groups of round holes for fixing the split wires on the disc, and the connectors connected with the split wires are connected to the round holes, and the connectors pass through the round holes and are fixed on the disc. The support assembly is provided with an adjustment assembly for adjusting the height of the support assembly on the base.

优选的,多分裂拉具装置包括连接盘、活动拉杆和连接销,活动拉杆一端与连接盘相连,活动拉杆的另一端与连接销的一端相连,连接销的另一端与圆盘相连,连接盘上设有拉杆头,通过拉杆头上连接的拉力试验机设定张力来控制圆盘上连接分裂导线的试验,结构简单,安装拆卸方便,使用效果好。Preferably, the multi-split puller device includes a connecting plate, a movable pull rod and a connecting pin, one end of the movable pull rod is connected with the connecting plate, the other end of the movable pull rod is connected with one end of the connecting pin, the other end of the connecting pin is connected with the disc, and the connecting plate There is a pull rod head on the top, and the test of connecting split wires on the disc is controlled by setting the tension of the tensile testing machine connected to the pull rod head. The structure is simple, the installation and disassembly are convenient, and the use effect is good.

优选的,活动拉杆包括长杆和连接杆,长杆的一端与连接盘相连,长杆的另一端设有固定连接杆的连接螺套,连接杆与连接销通过第二销轴转动连接,连接盘上设有连接块,长杆上设有第一连接套,第一连接套与连接块通过第一销轴转动连接,连接螺套内设有内套,长杆通过螺纹固定连接在内套内,圆盘上设有拉头,连接销通过第三销轴与拉头转动连接,结构简单,相对于单根活动拉杆具有结构稳定,使用效果好,能根据不同的分裂导线对活动拉杆进行调节,实用性能好,连接块与第一连接套配合,减少了长杆的损坏,内套的设置提高了整体活动拉杆的可靠性,防止连接螺套和长杆脱离,安全性能好,连接销通过第三销轴与拉头连接可靠,安装拆卸方便,能提高试验的准确性。Preferably, the movable pull rod includes a long rod and a connecting rod, one end of the long rod is connected with the connecting plate, the other end of the long rod is provided with a connecting screw sleeve for fixing the connecting rod, and the connecting rod and the connecting pin are rotatably connected through the second pin shaft. There is a connection block on the disk, a first connection sleeve is provided on the long rod, the first connection sleeve and the connection block are rotatably connected by the first pin shaft, an inner sleeve is provided in the connecting screw sleeve, and the long rod is fixedly connected to the inner sleeve by threads Inside, there is a slider on the disc, and the connecting pin is connected to the slider through the third pin shaft. The structure is simple, and it has a stable structure compared with a single movable rod, and the use effect is good. The movable rod can be adjusted according to different split wires. Adjustment, good practical performance, the connection block cooperates with the first connecting sleeve, which reduces the damage of the long rod, the setting of the inner sleeve improves the reliability of the overall movable rod, prevents the connecting screw sleeve and the long rod from detaching, good safety performance, and the connecting pin The connection between the third pin shaft and the slider is reliable, the installation and disassembly are convenient, and the accuracy of the test can be improved.

优选的,连接件包括过度套、拉力传感器、第二连接套和绝缘子装配体,拉力传感器设置在过度套和第二连接套之间,第二连接套与绝缘子装配体相连,过度套穿过圆孔后通过螺母固定连接在圆盘上,分裂导线连接在绝缘子装配体上,通过调节过度套上螺母的位置来调节连接件在圆盘上的位置,调节方便,能根据连接的分裂导线进行调节,将分裂导线固定连接在绝缘子装配体上,连接可靠,安装拆卸方便,拉力传感器的设置,能有效地检测试验时的数据,调整施加的拉力值,试验效果好。Preferably, the connector includes a transition sleeve, a tension sensor, a second connection sleeve and an insulator assembly, the tension sensor is arranged between the transition sleeve and the second connection sleeve, the second connection sleeve is connected to the insulator assembly, and the transition sleeve passes through the circle After the hole, the nut is fixedly connected to the disc, and the split wire is connected to the insulator assembly. The position of the connector on the disc can be adjusted by adjusting the position of the over-fitted nut. It is easy to adjust and can be adjusted according to the connected split wire. , The split wire is fixedly connected to the insulator assembly, the connection is reliable, the installation and disassembly are convenient, the setting of the tension sensor can effectively detect the data during the test, adjust the applied tension value, and the test effect is good.

优选的,圆盘右端的过度套上也设有另一个螺母,过度套上设有防止螺母脱落的挡块,能保证过度套与圆盘连接的平稳性,防止过度套的松动,挡块的设置能防止螺母的脱落,提高连接的可靠性。Preferably, another nut is also provided on the transition sleeve at the right end of the disk, and a stopper is provided on the transition sleeve to prevent the nut from falling off, which can ensure the stability of the connection between the transition sleeve and the disc, prevent the transition sleeve from loosening, and prevent the stopper from falling off. The setting can prevent the nut from falling off and improve the reliability of the connection.

优选的,支撑组件包括连接部和支撑部,连接部活动连接在底座上,支撑部设置在连接部的顶端,连接部的底端设有限位板,调节组件与限位板相连,通过支撑部实现对圆盘的支撑,并通过调节组件驱动连接部在底座上活动,能根据圆盘上连接的不同型号的分裂导线进行高度调节,实用性能好,限位板的设置,能有效的避免连接部脱离水平横杆,安全性能高。Preferably, the supporting assembly includes a connecting part and a supporting part, the connecting part is movably connected on the base, the supporting part is arranged on the top of the connecting part, the bottom end of the connecting part is provided with a limiting plate, the adjusting component is connected with the limiting plate, and the supporting part Realize the support for the disc, and drive the connecting part to move on the base through the adjustment component, and can adjust the height according to the different types of split wires connected to the disc. The practical performance is good, and the setting of the limit plate can effectively avoid the connection The upper part is separated from the horizontal bar, which has high safety performance.

优选的,连接部包括两根具有光滑表面的竖杆,且两根竖杆关于底座的竖直轴线对称设置,底座上设有供竖杆活动的直线轴承,支撑部固定连接在两根竖杆的顶端,限位板固定连接在两根竖杆的底端,竖杆与直线轴承为过盈配合,通过竖杆的光滑表面在直线轴承内上下活动,活动效果好,且两根竖杆关于水平横杆的竖直轴线对称设置,保证了支撑部的平衡性,限位部固定连接在竖杆的底端,限位效果好,实用性能好,安装可靠,竖杆与直线轴承过盈配合,能有效的防止竖杆与直线轴承的自由滑动。Preferably, the connecting portion includes two vertical rods with smooth surfaces, and the two vertical rods are arranged symmetrically with respect to the vertical axis of the base, the base is provided with linear bearings for the vertical rods to move, and the support portion is fixedly connected to the two vertical rods The top of the vertical rod, the limit plate is fixedly connected to the bottom of the two vertical rods, the vertical rod and the linear bearing are interference fit, the smooth surface of the vertical rod moves up and down in the linear bearing, the movement effect is good, and the two vertical rods are about The vertical axis of the horizontal bar is symmetrically arranged to ensure the balance of the support part. The limit part is fixedly connected to the bottom end of the vertical bar. The limit effect is good, the practical performance is good, and the installation is reliable. The vertical bar and the linear bearing have an interference fit. , can effectively prevent the free sliding of vertical rods and linear bearings.

优选的,支撑部包括设有通槽的底板,通槽的顶端设有支撑圆盘的倒角,通过倒角将圆盘固定在通槽内,通过倒角与圆盘的相切,有效的避免了圆盘内滑动。Preferably, the support part includes a bottom plate provided with a through groove, the top of the through groove is provided with a chamfer supporting the disk, the disk is fixed in the through groove through the chamfer, and the tangency between the chamfer and the disk effectively Sliding within the disc is avoided.

优选的,调节组件包括螺杆和手轮,限位板上设有与螺杆相配合的螺纹孔,螺杆的顶端设有调节块,手轮固定连接在螺杆的底端,底座上设有与螺杆相连的螺套,通过手轮控制螺杆在水平横杆上活动,并通过调节块推动竖杆在直线轴承内活动,操作方便,能提高螺杆的活动量来控制支撑部的高度调节,实用性能好,调节效果好,螺套的设置有利于螺杆活动,实用性能好,防止螺杆的损坏。Preferably, the adjustment assembly includes a screw and a hand wheel, the limit plate is provided with a threaded hole matched with the screw, the top of the screw is provided with an adjustment block, the hand wheel is fixedly connected to the bottom of the screw, and the base is provided with a The screw sleeve controls the movement of the screw on the horizontal bar through the hand wheel, and pushes the vertical bar to move in the linear bearing through the adjustment block. It is easy to operate and can increase the activity of the screw to control the height adjustment of the support part. It has good practical performance. The adjustment effect is good, the setting of the screw sleeve is beneficial to the movement of the screw rod, the practical performance is good, and the damage of the screw rod is prevented.

优选的,底座上还设有导向移动组件,导向移动组件包括导向轮和螺栓组件,螺栓组件固定连接在底座上,导向轮包括一段与地面接触的滚动体和一段保证滚动部平衡的平衡块,且滚动体的宽度小于平衡块的宽度,导向移动组件的设置便于操作人员移动,减少搬运的工作强度,通过滚动体和平衡块的设置,能保证导向轮的平稳性,防止支架的倾斜侧翻,安全性能好,能保证试验的稳定性,并通过螺栓组件将滚动体固定连接在左架体和右架体上,连接可靠,防止松动。Preferably, the base is also provided with a guide moving assembly, the guide moving assembly includes a guide wheel and a bolt assembly, the bolt assembly is fixedly connected to the base, the guide wheel includes a section of rolling body in contact with the ground and a section of balance weight to ensure the balance of the rolling part, And the width of the rolling body is smaller than the width of the balance weight. The setting of the guide moving component is convenient for the operator to move and reduce the work intensity of handling. Through the setting of the rolling body and the balance weight, the stability of the guide wheel can be guaranteed and the tilting and rollover of the bracket can be prevented. , good safety performance, can ensure the stability of the test, and the rolling elements are fixedly connected to the left frame body and the right frame body through the bolt assembly, the connection is reliable and prevents loosening.

综上所述,本发明的优点:1.通过支架实现圆盘的支撑,并通过圆盘上设有的若干组圆孔固定不同分裂型式的分裂导线,能使圆盘适应于多分裂型式的分裂导线的连接固定,实用性能好,也减少了现有安装时的工作强度,提高了试验效率;In summary, the present invention has the following advantages: 1. Realize the support of the disc by the support, and fix the split wires of different split patterns by the several groups of round holes provided on the disc, so that the disc can be adapted to the multi-split pattern. The connection of the split wires is fixed, and the practical performance is good, which also reduces the work intensity of the existing installation and improves the test efficiency;

2.通过多分裂拉具装置连接圆盘,实现对圆盘上连接的分裂导线施加张力,试验效果好,结构简单,连接可靠;2. The disc is connected by a multi-split puller device, so that tension can be applied to the split wires connected on the disc. The test effect is good, the structure is simple, and the connection is reliable;

3.通过连接件在圆盘处的位置可调,能根据分裂导线子导线线长的差距进行微调补偿,确保装置在拉力状态下子导线的受力平衡;3. Through the adjustable position of the connector at the disc, it can be fine-tuned and compensated according to the length difference between the split wire and the sub-wire, so as to ensure the force balance of the sub-wire under the tension state of the device;

4.连接件固定于圆盘上,提高了试验时的可靠性,防止分裂导线脱离圆盘;4. The connector is fixed on the disk, which improves the reliability of the test and prevents the split wire from leaving the disk;

5.将支架设置成底座及高度可调的支撑组件,能根据不同型号的分裂导线对支撑组件进行高度调节,且通过调节组件进行调节,能实现对支撑组件的高度可调,实用性能好,调节方便。5. The bracket is set as a base and a height-adjustable support component, and the height of the support component can be adjusted according to different types of split wires, and the height of the support component can be adjusted through the adjustment component, and the practical performance is good. Easy to adjust.

附图说明Description of drawings

下面结合附图对本发明作进一步说明:The present invention will be further described below in conjunction with accompanying drawing:

图1为本发明分裂导线架设装置中圆盘的结构示意图;Fig. 1 is the structural representation of disc in the split wire erecting device of the present invention;

图2为本发明分裂导线架设装置中支架的结构示意图;Fig. 2 is the schematic structural view of the bracket in the split wire erecting device of the present invention;

图3为本发明连接件与圆盘连接的结构示意图;Fig. 3 is the structural schematic diagram that connector of the present invention is connected with disc;

图4为本发明多分裂拉具装置与圆盘连接的结构示意图;Fig. 4 is the structure schematic diagram that multi-split puller device of the present invention is connected with disc;

图5为本发明活动拉杆的结构示意图;Fig. 5 is a schematic structural view of the movable pull rod of the present invention;

图6为本发明支架的局部示意图;Fig. 6 is a partial schematic view of the stent of the present invention;

图7为本发明支撑部的结构示意图;Fig. 7 is a structural schematic diagram of the support part of the present invention;

图8为本发明导向移动组件的结构示意图。Fig. 8 is a schematic structural diagram of the guiding and moving assembly of the present invention.

具体实施方式Detailed ways

如图1、图2、图3、图4、图5、图6、图7、图8所示,分裂导线架设装置,包括支架1和连接有分裂导线20的圆盘2,圆盘2设置在支架1上,圆盘2上连接有多分裂拉具装置3,圆盘2上设有若干组固定分裂导线20的圆孔21,圆孔21根据不同型号的分裂导线20设置,圆孔21上连接有与分裂导线20相连的连接件4,连接件4穿过圆孔21固定于圆盘2上,支架1包括底座11和设置在底座11上高度可调的支撑组件12,底座11上设有调节支撑组件12高度的调节组件13。As shown in Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, and Fig. 8, the split wire erection device includes a support 1 and a disk 2 connected with a split wire 20, and the disk 2 is set On the support 1, the disk 2 is connected with a multi-split puller device 3, and the disk 2 is provided with several groups of round holes 21 for fixing split wires 20. The round holes 21 are arranged according to different types of split wires 20, and the round holes 21 The connecting piece 4 connected to the split wire 20 is connected to the top, and the connecting piece 4 passes through the round hole 21 and is fixed on the disc 2. The support 1 includes a base 11 and a height-adjustable support assembly 12 arranged on the base 11. On the base 11 An adjustment assembly 13 for adjusting the height of the support assembly 12 is provided.

多分裂拉具装置3包括连接盘31、活动拉杆32和连接销33,活动拉杆32一端与连接盘31相连,活动拉杆32的另一端与连接销33的一端相连,连接销33的另一端与圆盘2相连,连接盘31上设有拉杆头34,通过拉杆头上连接的拉力试验机设定张力来控制圆盘上连接分裂导线的试验,结构简单,安装拆卸方便,使用效果好,活动拉杆32包括长杆35和连接杆36,长杆35的一端与连接盘31相连,长杆35的另一端设有固定连接杆36的连接螺套37,连接杆36与连接销33通过第二销轴100转动连接,连接盘31上设有连接块38,长杆35上设有第一连接套39,第一连接套39与连接块38通过第一销轴101转动连接,连接螺套37内设有内套30,长杆35通过螺纹固定连接在内套30内,圆盘2上设有拉头22,连接销33通过第三销轴102与拉头22转动连接,结构简单,相对于单根活动拉杆具有结构稳定,使用效果好,能根据不同的分裂导线对活动拉杆进行调节,实用性能好,连接块与第一连接套配合,减少了长杆的损坏,内套的设置提高了整体活动拉杆的可靠性,防止连接螺套和长杆脱离,安全性能好,连接销通过第三销轴与拉头连接可靠,安装拆卸方便,能提高试验的准确性。Multi-split puller device 3 comprises connection plate 31, movable pull bar 32 and connecting pin 33, and movable pull bar 32 one ends link to each other with connecting plate 31, and the other end of movable pull bar 32 links to each other with an end of connecting pin 33, and the other end of connecting pin 33 links to each other with The discs 2 are connected, and the connecting disc 31 is provided with a tie rod head 34. The test of connecting the split wires on the disc is controlled by setting the tension of the tensile testing machine connected to the tie rod head. The structure is simple, easy to install and disassemble, and the effect is good. Pull bar 32 comprises long rod 35 and connecting rod 36, and one end of long rod 35 links to each other with connection plate 31, and the other end of long rod 35 is provided with the connecting screw sleeve 37 of fixing connecting rod 36, and connecting rod 36 and connecting pin 33 pass through the second The pin shaft 100 is rotationally connected, the connecting plate 31 is provided with a connecting block 38, the long rod 35 is provided with a first connecting sleeve 39, the first connecting sleeve 39 and the connecting block 38 are rotationally connected through the first pin shaft 101, and the connecting screw sleeve 37 An inner sleeve 30 is provided inside, and the long rod 35 is fixedly connected in the inner sleeve 30 by threads. The disc 2 is provided with a slider 22, and the connecting pin 33 is rotationally connected with the slider 22 through the third pin shaft 102. The structure is simple and relatively Because of the stable structure of a single movable tie rod, the use effect is good, the movable pull rod can be adjusted according to different split wires, and the practical performance is good. The connecting block cooperates with the first connecting sleeve, which reduces the damage of the long rod and improves the setting of the inner sleeve. It improves the reliability of the overall movable pull rod, prevents the connecting screw sleeve from detaching from the long rod, and has good safety performance. The connecting pin is reliably connected to the slider through the third pin shaft, and the installation and disassembly are convenient, which can improve the accuracy of the test.

连接件4包括过度套41、拉力传感器42、第二连接套43和绝缘子装配体44,拉力传感器42设置在过度套41和第二连接套43之间,第二连接套43与绝缘子装配体44相连,过度套41穿过圆孔21后通过螺母45固定连接在圆盘2上,分裂导线20连接在绝缘子装配体44上,通过调节过度套上螺母的位置来调节连接件在圆盘上的位置,调节方便,能根据连接的分裂导线进行调节,将分裂导线固定连接在绝缘子装配体上,连接可靠,安装拆卸方便,拉力传感器的设置,能有效地检测试验时的数据,调整施加的拉力值,试验效果好,圆盘2右端的过度套41上也设有另一个螺母45,过度套41上设有防止螺母脱落的挡块46,能保证过度套与圆盘连接的平稳性,防止过度套的松动,挡块的设置能防止螺母的脱落,提高连接的可靠性。Connector 4 includes transition sleeve 41, tension sensor 42, second connection sleeve 43 and insulator assembly 44, tension sensor 42 is arranged between transition sleeve 41 and second connection sleeve 43, second connection sleeve 43 and insulator assembly 44 Connected, the transition sleeve 41 passes through the round hole 21 and is fixedly connected to the disk 2 through the nut 45, the split wire 20 is connected to the insulator assembly 44, and the position of the connector on the disk is adjusted by adjusting the position of the transition sleeve nut. The location is easy to adjust, and can be adjusted according to the connected split wires. The split wires are fixedly connected to the insulator assembly, the connection is reliable, the installation and disassembly are convenient, and the setting of the tension sensor can effectively detect the data during the test and adjust the applied tension. value, the test effect is good, the transition sleeve 41 on the right end of the disc 2 is also provided with another nut 45, and the transition sleeve 41 is provided with a stopper 46 to prevent the nut from falling off, which can ensure the stability of the connection between the transition sleeve and the disc, and prevent The excessive loosening of the sleeve and the setting of the stopper can prevent the nut from falling off and improve the reliability of the connection.

支撑组件12包括连接部和支撑部,连接部活动连接在底座11上,支撑部设置在连接部的顶端,连接部的底端设有限位板5,调节组件13与限位板5相连,通过支撑部实现对圆盘的支撑,并通过调节组件驱动连接部在底座上活动,能根据圆盘上连接的不同型号的分裂导线进行高度调节,实用性能好,限位板的设置,能有效的避免连接部脱离水平横杆,安全性能高,连接部包括两根具有光滑表面的竖杆6,且两根竖杆6关于底座11的竖直轴线对称设置,底座11上设有供竖杆6活动的直线轴承14,支撑部固定连接在两根竖杆6的顶端,限位板5固定连接在两根竖杆6的底端,竖杆6与直线轴承14为过盈配合,通过竖杆的光滑表面在直线轴承内上下活动,活动效果好,且两根竖杆关于水平横杆的竖直轴线对称设置,保证了支撑部的平衡性,限位部固定连接在竖杆的底端,限位效果好,实用性能好,安装可靠,竖杆与直线轴承过盈配合,能有效的防止竖杆与直线轴承的自由滑动。The supporting assembly 12 includes a connecting portion and a supporting portion, the connecting portion is movably connected on the base 11, the supporting portion is arranged on the top of the connecting portion, the bottom end of the connecting portion is provided with a limiting plate 5, and the adjusting assembly 13 is connected with the limiting plate 5, through The support part realizes the support for the disc, and drives the connecting part to move on the base through the adjustment component, and can adjust the height according to the different types of split wires connected to the disc. The practical performance is good, and the setting of the limit plate can effectively To prevent the connecting part from deviating from the horizontal bar, the safety performance is high. The connecting part includes two vertical bars 6 with smooth surfaces, and the two vertical bars 6 are arranged symmetrically with respect to the vertical axis of the base 11. The base 11 is provided with a vertical bar 6 The movable linear bearing 14, the supporting part is fixedly connected to the top of the two vertical rods 6, the limit plate 5 is fixedly connected to the bottom of the two vertical rods 6, the vertical rod 6 and the linear bearing 14 are interference fit, through the vertical rod The smooth surface of the linear bearing moves up and down in the linear bearing, and the movement effect is good, and the two vertical bars are arranged symmetrically with respect to the vertical axis of the horizontal bar, which ensures the balance of the support part, and the limit part is fixedly connected to the bottom of the vertical bar. The limit effect is good, the practical performance is good, the installation is reliable, and the interference fit between the vertical rod and the linear bearing can effectively prevent the free sliding of the vertical rod and the linear bearing.

支撑部包括设有通槽71的底板7,通槽71的顶端设有支撑圆盘2的倒角72,通过倒角将圆盘固定在通槽内,通过倒角与圆盘的相切,有效的避免了圆盘内滑动,调节组件13包括螺杆15和手轮16,限位板5上设有与螺杆相配合的螺纹孔,螺杆的顶端设有调节块17,手轮16固定连接在螺杆的底端,底座11上设有与螺杆相连的螺套18,通过手轮控制螺杆在水平横杆上活动,并通过调节块推动竖杆在直线轴承内活动,操作方便,能提高螺杆的活动量来控制支撑部的高度调节,实用性能好,调节效果好,螺套的设置有利于螺杆活动,实用性能好,防止螺杆的损坏。The supporting portion includes a base plate 7 provided with a through groove 71, the top of the through groove 71 is provided with a chamfer 72 supporting the disk 2, the disk is fixed in the through groove by the chamfer, and the tangency between the chamfer and the disk, Effectively avoid sliding in the disc, the adjustment assembly 13 includes a screw rod 15 and a hand wheel 16, the limit plate 5 is provided with a threaded hole matched with the screw rod, the top of the screw rod is provided with an adjustment block 17, and the hand wheel 16 is fixedly connected to the The bottom end of the screw rod and the base 11 are provided with a screw sleeve 18 connected to the screw rod. The screw rod is controlled to move on the horizontal bar through the hand wheel, and the vertical rod is pushed to move in the linear bearing through the adjustment block. It is easy to operate and can improve the screw rod. The height adjustment of the support part is controlled by the amount of activity, which has good practical performance and good adjustment effect. The setting of the screw sleeve is conducive to the movement of the screw rod, which has good practical performance and prevents damage to the screw rod.

底座11上还设有导向移动组件8,导向移动组件8包括导向轮81和螺栓组件82,螺栓组件82固定连接在底座11上,导向轮81包括一段与地面接触的滚动体83和一段保证滚动部平衡的平衡块84,且滚动体的宽度小于平衡块的宽度,导向移动组件的设置便于操作人员移动,减少搬运的工作强度,通过滚动体和平衡块的设置,能保证导向轮的平稳性,防止支架的倾斜侧翻,安全性能好,能保证试验的稳定性,并通过螺栓组件将滚动体固定连接在左架体和右架体上,连接可靠,防止松动。The base 11 is also provided with a guide moving assembly 8, the guide moving assembly 8 includes a guide wheel 81 and a bolt assembly 82, the bolt assembly 82 is fixedly connected on the base 11, and the guide wheel 81 includes a section of rolling body 83 in contact with the ground and a section to ensure rolling. The balance weight 84 is fully balanced, and the width of the rolling body is smaller than the width of the weight. The setting of the guide moving component is convenient for the operator to move and reduce the work intensity of handling. The setting of the rolling body and the balance weight can ensure the stability of the guide wheel , to prevent tilting and rollover of the bracket, good safety performance, can ensure the stability of the test, and the rolling elements are fixedly connected to the left and right frame bodies through bolt assemblies, the connection is reliable and prevents loosening.

使用时,将连接有分裂导线20的圆盘2放置在支架1中的底板7上,并通过螺母45调节连接件在圆盘处的位置,使其适应分裂导线子导线线长的差距进行微调补偿,确保装置在拉力状态下子导线的受力平衡,通过通槽71中的倒角72与圆盘2接触,有效的放置了圆盘2的脱落,并根据圆盘2上连接的分裂导线20的分裂型式,通过手轮16调节螺杆15在底座11上活动,使螺杆15上的调节块17调节底板7的高度,使其圆盘2与多分裂拉具装置3连接,当圆盘2连接后,使底板7与圆盘2分离,通过导向移动组件8推动支架1,通过连接盘31上的拉杆头34连接拉力试验机,通过拉力试验机施加张力,就可以对圆盘2上连接的分裂导线20进行试验,并通过连接件4上的拉力传感器42进行检测。When in use, the disc 2 connected with the split wire 20 is placed on the bottom plate 7 in the bracket 1, and the position of the connecting piece at the disc is adjusted by the nut 45, so that it can be fine-tuned according to the difference in the length of the split wire sub-wire Compensation, to ensure the force balance of the sub-conductor under the tension state of the device, contact with the disc 2 through the chamfer 72 in the through groove 71, effectively prevent the disc 2 from falling off, and according to the split conductor 20 connected on the disc 2 The split type, adjust the screw rod 15 to move on the base 11 through the hand wheel 16, so that the adjustment block 17 on the screw rod 15 can adjust the height of the bottom plate 7, so that the disc 2 is connected with the multi-split puller device 3, when the disc 2 is connected Finally, the bottom plate 7 is separated from the disk 2, the support 1 is pushed by the guide moving assembly 8, the tensile testing machine is connected by the pull rod head 34 on the connecting disk 31, and the tensile force is applied by the tensile testing machine, so that the disk 2 can be connected. The split lead 20 is tested and detected by the tension sensor 42 on the connector 4 .

除上述优选实施例外,本发明还有其他的实施方式,本领域技术人员可以根据本发明作出各种改变和变形,只要不脱离本发明的精神,均应属于本发明所附权利要求所定义的范围。Except above-mentioned preferred embodiment, the present invention also has other embodiments, and those skilled in the art can make various changes and deformations according to the present invention, as long as they do not depart from the spirit of the present invention, all should belong to the scope defined in the appended claims of the present invention scope.

Claims (7)

1.分裂导线架设装置,其特征在于:包括支架(1)和连接有分裂导线(20)的圆盘(2),圆盘(2)设置在支架(1)上,圆盘(2)上连接有多分裂拉具装置(3),圆盘(2)上设有若干组固定分裂导线(20)的圆孔(21),圆孔(21)上连接有与分裂导线(20)相连的连接件(4),连接件(4)穿过圆孔(21)固定于圆盘(2)上,支架(1)包括底座(11)和设置在底座(11)上高度可调的支撑组件(12),底座(11)上设有调节支撑组件(12)高度的调节组件(13);1. Split wire erection device is characterized in that: comprise support (1) and the disk (2) that is connected with split wire (20), disk (2) is arranged on the support (1), on the disk (2) Connect multi-split puller device (3), disc (2) is provided with the round hole (21) of some groups of fixed split lead wires (20), is connected with split lead wire (20) to link to each other on the round hole (21). The connecting piece (4), the connecting piece (4) is fixed on the disc (2) through the round hole (21), and the bracket (1) includes a base (11) and a height-adjustable support assembly arranged on the base (11) (12), the base (11) is provided with an adjustment assembly (13) for adjusting the height of the support assembly (12); 多分裂拉具装置(3)包括连接盘(31)、活动拉杆(32)和连接销(33),活动拉杆(32)一端与连接盘(31)相连,活动拉杆(32)的另一端与连接销(33)的一端相连,连接销(33)的另一端与圆盘(2)相连,连接盘(31)上设有拉杆头(34);Multi-split puller device (3) comprises connecting plate (31), movable pull bar (32) and connecting pin (33), and movable pull bar (32) one end links to each other with connecting plate (31), and the other end of movable pull bar (32) is connected with connecting plate (31). One end of connecting pin (33) links to each other, and the other end of connecting pin (33) links to each other with disc (2), and connecting disc (31) is provided with pull bar head (34); 连接件(4)包括过度套(41)、拉力传感器(42)、第二连接套(43)和绝缘子装配体(44),拉力传感器(42)设置在过度套(41)和第二连接套(43)之间,第二连接套(43)与绝缘子装配体(44)相连,过度套(41)穿过圆孔(21)后通过螺母(45)固定连接在圆盘(2)上,分裂导线(20)连接在绝缘子装配体(44)上;The connector (4) comprises a transition sleeve (41), a tension sensor (42), a second connection sleeve (43) and an insulator assembly (44), and the tension sensor (42) is arranged on the transition sleeve (41) and the second connection sleeve (43), the second connection sleeve (43) is connected to the insulator assembly (44), and the transition sleeve (41) is fixedly connected to the disk (2) by a nut (45) after passing through the round hole (21), The split wire (20) is connected to the insulator assembly (44); 支撑组件(12)包括连接部和支撑部,连接部活动连接在底座(11)上,支撑部设置在连接部的顶端,连接部的底端设有限位板(5),调节组件(13)与限位板(5)相连。The supporting assembly (12) includes a connecting portion and a supporting portion, the connecting portion is movably connected on the base (11), the supporting portion is arranged on the top of the connecting portion, the bottom end of the connecting portion is provided with a limiting plate (5), and the adjusting assembly (13) Connect with the limiting plate (5). 2.根据权利要求1所述的分裂导线架设装置,其特征在于:活动拉杆(32)包括长杆(35)和连接杆(36),长杆(35)的一端与连接盘(31)相连,长杆(35)的另一端设有固定连接杆(36)的连接螺套(37),连接杆(36)与连接销(33)通过第二销轴(100)转动连接,连接盘(31)上设有连接块(38),长杆(35)上设有第一连接套(39),第一连接套(39)与连接块(38)通过第一销轴(101)转动连接,连接螺套(37)内设有内套(30),长杆(35)通过螺纹固定连接在内套(30)内,圆盘(2)上设有拉头(22),连接销(33)通过第三销轴(102)与拉头(22)转动连接。2. The split wire erection device according to claim 1, characterized in that: the movable pull rod (32) includes a long rod (35) and a connecting rod (36), and one end of the long rod (35) is connected to the connection plate (31) , the other end of the long rod (35) is provided with a connecting threaded sleeve (37) for fixing the connecting rod (36), the connecting rod (36) is rotationally connected with the connecting pin (33) by the second bearing pin (100), and the connecting disc ( 31) is provided with a connection block (38), the long rod (35) is provided with a first connection sleeve (39), and the first connection sleeve (39) is connected to the connection block (38) through the first pin shaft (101) in rotation , the connecting screw sleeve (37) is provided with an inner sleeve (30), and the long rod (35) is fixedly connected to the inner sleeve (30) by threads, and the disc (2) is provided with a slider (22), and the connecting pin ( 33) Rotately connect with the slider (22) through the third pin shaft (102). 3.根据权利要求1所述的分裂导线架设装置,其特征在于:圆盘(2)右端的过度套(41)上也设有另一个螺母(45),过度套(41)上设有防止螺母脱落的挡块(46)。3. The split wire erection device according to claim 1, characterized in that: the transition sleeve (41) at the right end of the disc (2) is also provided with another nut (45), and the transition sleeve (41) is provided with a preventive Stop (46) where the nut falls off. 4.根据权利要求1所述的分裂导线架设装置,其特征在于:连接部包括两根具有光滑表面的竖杆(6),且两根竖杆(6)关于底座(11)的竖直轴线对称设置,底座(11)上设有供竖杆(6)活动的直线轴承(14),支撑部固定连接在两根竖杆(6)的顶端,限位板(5)固定连接在两根竖杆(6)的底端,竖杆(6)与直线轴承(14)为过盈配合。4. The split wire erection device according to claim 1, characterized in that: the connecting part comprises two vertical rods (6) with smooth surfaces, and the two vertical rods (6) are about the vertical axis of the base (11) Symmetrically arranged, the base (11) is provided with a linear bearing (14) for the vertical rod (6) to move, the support part is fixedly connected to the top of the two vertical rods (6), and the limit plate (5) is fixedly connected to the two vertical rods (6). The bottom end of the vertical rod (6), the vertical rod (6) and the linear bearing (14) are an interference fit. 5.根据权利要求1所述的分裂导线架设装置,其特征在于:支撑部包括设有通槽(71)的底板(7),通槽(71)的顶端设有支撑圆盘(2)的倒角(72)。5. The split wire erection device according to claim 1, characterized in that: the supporting part includes a bottom plate (7) provided with a through groove (71), and the top of the through groove (71) is provided with a support disc (2) Chamfer (72). 6.根据权利要求1所述的分裂导线架设装置,其特征在于:调节组件(13)包括螺杆(15)和手轮(16),限位板(5)上设有与螺杆(15)相配合的螺纹孔,螺杆(15)的顶端设有调节块(17),手轮(16)固定连接在螺杆(15)的底端,底座(11)上设有与螺杆(15)相连的螺套(18)。6. The split wire erection device according to claim 1, characterized in that: the adjustment assembly (13) includes a screw (15) and a hand wheel (16), and the limit plate (5) is provided with a Cooperating threaded holes, the top of the screw rod (15) is provided with an adjustment block (17), the hand wheel (16) is fixedly connected to the bottom end of the screw rod (15), and the base (11) is provided with a screw connected to the screw rod (15). Set (18). 7.根据权利要求1所述的分裂导线架设装置,其特征在于:底座(11)上还设有导向移动组件(8),导向移动组件(8)包括导向轮(81)和螺栓组件(82),螺栓组件(82)固定连接在底座(11)上,导向轮(81)包括一段与地面接触的滚动体(83)和一段保证滚动体(83)平衡的平衡块(84),且滚动体(83)的宽度小于平衡块(84)的宽度。7. The split wire erection device according to claim 1, characterized in that: the base (11) is also provided with a guide moving assembly (8), and the guide moving assembly (8) includes a guide wheel (81) and a bolt assembly (82 ), the bolt assembly (82) is fixedly connected on the base (11), and the guide wheel (81) includes a section of rolling body (83) in contact with the ground and a section of balance weight (84) to ensure the balance of the rolling body (83), and the rolling The width of the body (83) is smaller than the width of the counterweight (84).
CN201610248029.0A 2016-04-19 2016-04-19 Split conductor stringer Active CN105807099B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610248029.0A CN105807099B (en) 2016-04-19 2016-04-19 Split conductor stringer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610248029.0A CN105807099B (en) 2016-04-19 2016-04-19 Split conductor stringer

Publications (2)

Publication Number Publication Date
CN105807099A CN105807099A (en) 2016-07-27
CN105807099B true CN105807099B (en) 2018-08-31

Family

ID=56457366

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610248029.0A Active CN105807099B (en) 2016-04-19 2016-04-19 Split conductor stringer

Country Status (1)

Country Link
CN (1) CN105807099B (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201312080Y (en) * 2008-12-01 2009-09-16 河南省电力公司焦作供电公司 Twin bundled line electrified indirect lifting device
KR101006180B1 (en) * 2010-07-28 2011-01-07 지승건설(주) Spacer means installation work process using spacer means installation device and spacer means installation device for transmission line
JP2011114928A (en) * 2009-11-26 2011-06-09 Chugoku Electric Power Co Inc:The Inter-phase spacer for lead-in line
CN102097189A (en) * 2011-03-01 2011-06-15 中国电力工程顾问集团西南电力设计院 Four-link tension string for +/-800KV heavy ice area
CN202034740U (en) * 2011-03-01 2011-11-09 中国电力工程顾问集团西南电力设计院 Retaining structure of six-multiple conductor
CN102654520A (en) * 2012-05-10 2012-09-05 广东电网公司江门供电局 Small corona cage and wire erection device
CN202817600U (en) * 2012-08-17 2013-03-20 湖北省送变电工程公司 Hoisting clamping apparatus for jumpers of multi-bundled conductors in overhead line construction
CN204205419U (en) * 2014-11-04 2015-03-11 国家电网公司 Conductors on quad bundled bracing or strutting arrangement
CN204905815U (en) * 2015-06-30 2015-12-23 平高集团有限公司 Wire supports fixed gold utensil and conductor spacer support thereof
CN205581150U (en) * 2016-04-19 2016-09-14 浙江华电器材检测研究所 Division wire erection device

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201312080Y (en) * 2008-12-01 2009-09-16 河南省电力公司焦作供电公司 Twin bundled line electrified indirect lifting device
JP2011114928A (en) * 2009-11-26 2011-06-09 Chugoku Electric Power Co Inc:The Inter-phase spacer for lead-in line
KR101006180B1 (en) * 2010-07-28 2011-01-07 지승건설(주) Spacer means installation work process using spacer means installation device and spacer means installation device for transmission line
CN102097189A (en) * 2011-03-01 2011-06-15 中国电力工程顾问集团西南电力设计院 Four-link tension string for +/-800KV heavy ice area
CN202034740U (en) * 2011-03-01 2011-11-09 中国电力工程顾问集团西南电力设计院 Retaining structure of six-multiple conductor
CN102654520A (en) * 2012-05-10 2012-09-05 广东电网公司江门供电局 Small corona cage and wire erection device
CN202817600U (en) * 2012-08-17 2013-03-20 湖北省送变电工程公司 Hoisting clamping apparatus for jumpers of multi-bundled conductors in overhead line construction
CN204205419U (en) * 2014-11-04 2015-03-11 国家电网公司 Conductors on quad bundled bracing or strutting arrangement
CN204905815U (en) * 2015-06-30 2015-12-23 平高集团有限公司 Wire supports fixed gold utensil and conductor spacer support thereof
CN205581150U (en) * 2016-04-19 2016-09-14 浙江华电器材检测研究所 Division wire erection device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
220 kV 同塔双回双分裂导线防覆冰舞动的研究与设计;王晓涵等;《高压电器》;20111130;第47卷(第11期);20-26 *

Also Published As

Publication number Publication date
CN105807099A (en) 2016-07-27

Similar Documents

Publication Publication Date Title
CN106052931A (en) A multi-rope hoisting wire rope tension self-balancing test bench and method
CN104390866B (en) Torsion tester for cable branch box, and test method thereof
CN209727638U (en) A kind of novel square steel load bearing stength detection device
CN103439209A (en) Electric power fitting abrasion test machine
CN205581150U (en) Division wire erection device
CN105807099B (en) Split conductor stringer
CN105268651A (en) Integrated circuit sorting machine test device
CN201266197Y (en) Prestrain device for tyre rubber thermal ageing test
CN105842058B (en) Asphalt beam specimen repeated bend test fixture
CN204314158U (en) Cable hut torsion tester
CN105806699B (en) A kind of mobile lifting device being used to support split conductor disk
CN106744567A (en) A kind of lifting apparatus for overhauling tunnel cable
CN112730096A (en) Rock Rheological Test System
CN205583604U (en) Split conductor fixed knot constructs
CN107097221B (en) Robot tail end linear guide rail
CN218648462U (en) Extension support for live replacement of linear insulator
CN211317975U (en) Support base for simply supported beam bending test and simply supported beam bending test device
KR101533940B1 (en) Loading apparatus for stress relaxation tester
CN211652365U (en) Insulator monaural tensile test device
CN209878478U (en) Fretting fatigue test fixture device
CN223633794U (en) A stress-adjustable bridge cable structure
CN206203836U (en) A kind of lifting apparatus for overhauling tunnel cable
CN116667248B (en) Fixing device for cable bridge
CN105291889A (en) Assembling and debugging tool for flexible suspension non-slide sectional insulator
CN206330696U (en) A kind of contact line downward pressure measuring apparatus of overhead type contact net

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 310015 Taizhou Road, Zhejiang, China, No. 217, No.

Applicant after: Zhejiang Huadian inspection and Research Institute Co., Ltd.

Address before: 310015 Taizhou Road, Zhejiang, China, No. 217, No.

Applicant before: Zhejiang Huadian Equipment Inspection Institute

CB02 Change of applicant information
TA01 Transfer of patent application right

Effective date of registration: 20180207

Address after: 310015 Taizhou Road, Zhejiang, China, No. 217, No.

Applicant after: Zhejiang Huadian inspection and Research Institute Co., Ltd.

Applicant after: Power Science Research Institute of Zhejiang Electric Power Co., Ltd.

Address before: 310015 Taizhou Road, Zhejiang, China, No. 217, No.

Applicant before: Zhejiang Huadian inspection and Research Institute Co., Ltd.

TA01 Transfer of patent application right
GR01 Patent grant