CN105785942B - Large-scale cement produced with the dry method scattered control system packet joining adjustment method - Google Patents

Large-scale cement produced with the dry method scattered control system packet joining adjustment method Download PDF

Info

Publication number
CN105785942B
CN105785942B CN201410850079.7A CN201410850079A CN105785942B CN 105785942 B CN105785942 B CN 105785942B CN 201410850079 A CN201410850079 A CN 201410850079A CN 105785942 B CN105785942 B CN 105785942B
Authority
CN
China
Prior art keywords
debugging
equipment
control
group
station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410850079.7A
Other languages
Chinese (zh)
Other versions
CN105785942A (en
Inventor
李雪峰
刘民业
刘星
韩晓松
陈民泰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201410850079.7A priority Critical patent/CN105785942B/en
Publication of CN105785942A publication Critical patent/CN105785942A/en
Application granted granted Critical
Publication of CN105785942B publication Critical patent/CN105785942B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • Testing And Monitoring For Control Systems (AREA)
  • Programmable Controllers (AREA)

Abstract

The present invention relates to a kind of large-scale cement produced with the dry method scattered control system packet joining adjustment methods, include the following steps, step 1:Subregion, grouping;It is distributed according to cement production process flow and equipment region, scene is overall to be divided into three regions, and the equipment for having serial relation and interlock connection on process sequence, control station or relatively independent complete set of equipments are divided into several groups in each region;Step 2:Subregion, packet joining debugging;1) I/O signals and scattered control system combined debugging are respectively grouped;2) single machine simulation control is adjusted debugging, 3) examination of packet equipment list with parameter, algorithm and is examined, 4) equipment complete set start-up, 5) Regional Linking;After the Regional Linking in each area meets the requirements, all fronts refrigeration duty test run is just proceeded by according to technological process.The present invention improves field adjustable efficiency, shortens debug time, reduces manpower, time cost, increases economic efficiency.

Description

Large-scale cement produced with the dry method scattered control system packet joining adjustment method
Technical field
The present invention relates to a kind of large-scale cement produced with the dry method scattered control system packet joining adjustment methods.
Background technology
Due to the process characteristic of dry cement production line, main production equipments are more dispersed, so most dry method now Cement producing line uses " Distributed Control System(DCS)" to realize the efficiency such as decentralised control, centralized operation, multi-zone supervision.
For small-sized dry cement production line according to the technological process of production equipment, I/O surveys are carried out to all devices successively Examination;Substep carries out solo test run by process control station again after the completion of I/O tests, program adjusts;Then by active station to work Skill process operation monitors and operation;Last all devices carry out linkage trial run, can efficiently accomplish debugging efforts.But for production capacity The large-scale production line of 5000t/D or so, plant area take up an area up to 300,000 m2, nearly 10,000 points of I/O signals, and debugging work load increases several times, Adjustment method routinely is debugged, and manpower, time cost increase sharply, and the low of working efficiency
Invention content
The present invention is directed to overcome the deficiencies of existing technologies, a kind of large-scale cement produced with the dry method scattered control system packet joining is provided Adjustment method improves field adjustable efficiency, shortens debug time, reduces manpower, time cost, increases economic efficiency.
In order to solve the above-mentioned technical problem, the invention is realized in this way:
A kind of large size cement produced with the dry method scattered control system packet joining adjustment method, which is characterized in that include the following steps:
Step 1:Subregion, grouping
It is distributed according to cement production process flow and equipment region, scene is overall to be divided into three regions:
1) lime stone stockyard, material allocation, raw mill are an area, and raw material homogenizing silo is the buffering area of technique linking;
2) coal dust mill, calcining kiln, cement grinding mill, slag mill are an area, and cement clinker library is the buffering area of technique linking;
3) cement allotment, warehouse for finished product, cement packing are an area;
In each region by the equipment for having serial relation and interlock connection on process sequence, control station or it is relatively independent at Complete equipment is divided into several groups;
Step 2:Subregion, packet joining debugging
Region and grouping divide it is good after, each group commissioning staff enters scene, energy medium and motor main circuit not Debugging efforts are started simultaneously to the device packets that it is responsible in the case of input;Different subregions and grouping, because it is not done mutually Immunity can be at the different debugging stages, and respectively grouping can simultaneously supervise its decentralized detection process layer, process control station, concentration It controls the soft and hardware equipment test of operation layer and carries out interlayer combined debugging, operating procedure and main points are as follows:
1) I/O signals and scattered control system combined debugging are respectively grouped
Confirm that I/O signals and the soft and hardware configuration of each layer real time data of scattered control system must correspond, in I/O Joint carries out following debugging while test:
1. checking whether the operation of I/O modules is normal in the field control station of decentralized detection process layer, whether point bit allocation accords with Close the design of signal table;
2. opening engineering process, each measuring point arrangement and each I/ in practical cabinet of checking process control layer in engineer station Whether O module is consistent, and whether the real time data for getting the stations each I/O debugging group test ready with test interface is correct, with software configuration It is consistent;
3. the comprehensively monitoring picture of operator station is recalled in Centralized Monitoring operation layer, to each I/O stand, each debugging group it is each Kind of signal is monitored test, that operator station picture is shown the result is that have passed through all hardware input and output, at signal filtering The final result that reason, the conversion of physical quantity, network data are transmitted, obtained after the docking of software data interface;
2) single machine simulation control adjusts debugging with parameter, algorithm
After I/O signal testings, single machine simulation control, and control program parameter, algorithm are carried out to the equipment in grouping Adjust debugging;
1. single machine simulation control debugging
Local mode is used to operate equipment start-stop at the scene first, it is whether correct to control loop operation in detection plate cabinet, Engineer station controls whether program executive condition is normal, and whether just operator station monitored picture corresponds to the real-time display of equipment state Often;
After local control simulation is correct, long-range firing test need to be carried out, start stop operation is carried out to equipment by operator station, Channel, range, signal transformation, interlocking and the alarm that operator station corresponds to picture are checked, are confirmed, the connection being related to remotely is started Lock protection must test each interlocking point, and it is logically true to ensure;
2. parameter, algorithm adjust debugging
The sampling period for the various types of signal being related to for stand-alone device, adjustable range, the signal transformation for participating in interlocked control More limit value and proportional-integral derivative controller parameter must be verified and be adjusted in simulative debugging, can not temporarily be simulated Whether the equipment application analogue system testing algorithm of control, the executive condition of logic meet the requirements;
3) examination of packet equipment list and examination
After by equipment simulating control debugging and parameter tuning debugging, the equipment in grouping can carry out solo test run, Solo test run includes the local test run in scene and controls test run two parts in long-range, and local test run starts at the scene, and middle control test run is by grasping Work person, which stands, to be started, and whole process mainly in the process control station of automatic control system and concentrates supervisory layers to each stand-alone device Commissioning content is checked and is confirmed;
1. operator station observes the given feedback of each control loop, output valve and its curve with device packets picture, monitoring The warning message and fault message of picture, the whether correct start and stop of equipment;Coordinate with engineer station commissioning staff, processing routine is repaiied Change, configuration, monitoring debugging efforts;
2. engineer station by configuration software, program composing software check field control station operating condition, belt deviation, Velocity anomaly, all kinds of limit signals, valve switch state, electric current, pressure, temperature signal confirm that interlock logic executes;To control Algorithm, the correctness of correlation curve and numerical check algorithm performs;And adjustment programme logic and group are changed according to technological requirement State;
3. carrying out post-installation review stand-alone device, the stability and installation accuracy of detecting electric control and machine operation, to fortune Turn the time, electric current, electrical equipment temperature, mechanical equipment temperature, vibration data accurately record.
4) equipment complete set start-up
After stand-alone device test running qualification in grouping, that is, enters equipment complete set start-up and debug the stage, debugging is mainly in The engineer station and operator station for controlling room execute, and field adjustable personnel are responsible for monitoring device operating condition, when physical condition cannot Simulated failure and interlock condition are needed when meeting to reach the target of single group and multigroup startup and stopping;
Complete set start-up commissioning content includes:
1. group requires to include electric current, power, temperature, pressure, the various signals of vibration simulation amount when starting and puts into as possible;
2. the interlock logic test of equipment, the test of complete set start-up interlock logic in single group;
3. process sequence is tested between group, signal is quoted between group, and group boot sequence and stopping interlocking being debugged;
4. equipment starts the interlocking, alarm, fault message Real-time Feedback situation of time-division group picture in operator station inspection group;
5. engineer station need to be to group starting a control program executive condition, programmed logic reasonability, equipment starts suitable in each group Whether sequence meets design requirement, and to the modification requirement that technologist proposes, organizing the problem of Start-up and Adjustment is found will be timely and reasonably Processing;
5) Regional Linking
After the debugging of equipment complete set start-up is qualified, that is, enter the Regional Linking stage, feelings are distributed according to the configuration of live master station Condition and the technological process of production divide material allocation area, raw mill and pulverized coal preparation area, calcining kiln area, cement and slag milling area, Performance is debugged depending on each differentiation group, the region joint-trial in two to three areas can be carried out at the same time, and is gradually extended to completely in finished product area Each region joint-trial;
After the Regional Linking in each area meets the requirements, all fronts refrigeration duty test run is just proceeded by according to technological process.
The large-scale cement produced with the dry method scattered control system packet joining adjustment method, it is characterised in that:Three in step 1 Lime stone stockyard, material allocation, raw mill in big region, coal dust mill, calcining kiln, cement grinding mill, slag mill, cement allocate, at Product library and cement packing are respectively one group respectively, totally ten groupings.
The beneficial effects of the invention are as follows:Using nested design adjustment method, according to cement production process flow and battery limits Domain, which is reasonably distributed, divides region and grouping, and the debugging efforts being respectively grouped can be carried out at the same time, non-interference, can be at different debugging Stage, and when being debugged, while the decentralized detection process layer to DCS system, process control station, Centralized Monitoring operation layer Soft and hardware equipment is tested and interlayer combined debugging.The method has rationally decomposed debugging region, simplifies debugging flow, work Improved efficiency is apparent, effectively shortens debug time;It is responsible for relatively-stationary debugging region, workload using the method commissioning staff Reduction, improves working efficiency, and each grouping is carried out at the same time debugging, highly shortened debug time.DCS is scattered control system.
Description of the drawings
The present invention is described in further detail with embodiment below in conjunction with the accompanying drawings:
Fig. 1 is the structural diagram of the present invention.
Specific implementation mode
As shown in Figure 1:A kind of large size cement produced with the dry method scattered control system packet joining adjustment method, which is characterized in that packet Include following steps:
Step 1:Subregion, grouping
It is distributed according to cement production process flow and equipment region, scene generally will arrangement material allocation, raw mill, coal dust The main main controller station such as mill, calcining kiln, cement grinding mill, slag mill, cement allotment, warehouse for finished product, cement packing.It is big that three can be totally divided into Region:
1) lime stone stockyard, material allocation, raw mill are an area, and raw material homogenizing silo is the buffering area of technique linking;
2) coal dust mill, calcining kiln, cement grinding mill, slag mill are an area, and cement clinker library is the buffering area of technique linking;
3) cement allotment, warehouse for finished product, cement packing are an area.
By the equipment for having more strongly continuous relationship and interlock connection on process sequence, control station or relatively independent in each region Complete set of equipments be divided into several groups.
Step 2:Subregion, packet joining debugging
After debugging region and grouping divide well, each group commissioning staff enters scene, is returned in energy medium and motor master Road starts simultaneously at debugging efforts in the case of not putting into the equipment group that it is responsible for.Different subregions and grouping, mutually not because of it The characteristics of interference, can be at the different debugging stages, and each group can be simultaneously to its decentralized detection process layer, process control station, collection Interlayer combined debugging is tested and carried out to the soft and hardware equipment of middle policer operation layer, and operating procedure and main points are as follows:
1) I/O signals and DCS system combined debugging are respectively grouped
In order to ensure the various functions of system, especially controls to adjust function operation correctly, confirm I/O signals and DCS systems The soft and hardware configuration for each layer real time data of uniting must correspond, and joint carries out following debugging while I/O is tested:
1. checking whether I/O modules 11 are run normal in the field control station of decentralized detection process layer 1, whether point bit allocation Meet the design of signal table;
2. opening engineering process, each measuring point arrangement of checking process control layer 2 in engineer station 31(Physical address, type) Whether consistent with each I/O modules in practical cabinet, getting the stations each I/O debugging group the real time data of test ready with test interface is It is no correct, it is consistent with software configuration;
3. recalling the comprehensively monitoring picture of operator station 32 in Centralized Monitoring operation layer 3, stand to each I/O, each debugging group Various signals be monitored test, it is that operator station picture is shown the result is that have passed through all hardware input and output, signal filter The final result that wave processing, the conversion of physical quantity, network data are transmitted, obtained after the docking of software data interface, can be comprehensively anti- Reflect the correctness of signal;
2) single machine simulation control adjusts debugging with parameter, algorithm
After I/O signal testings, single machine simulation control, and control program parameter, algorithm are carried out to the equipment in grouping Adjust debugging.
1. single machine simulation control debugging
Local mode is used to operate equipment start-stop at the scene first, it is whether correct to control loop operation in detection plate cabinet, Engineer station controls whether program executive condition is normal, and whether just operator station monitored picture corresponds to the real-time display of equipment state Often.
After local control simulation is correct, need to remotely it be started(Middle control starts)Experiment, by operator station to equipment into Row start stop operation, detection operator station correspond to channel, range, signal transformation, interlocking and alarm of picture etc. and are checked, really Recognize, middle control, which starts the interlock protection being related to, to test each interlocking point, and it is logically true to ensure.
2. parameter, algorithm adjust debugging
According to the technological requirement and control logic of equipment, the sampling period for the various types of signal being related to for stand-alone device adjusts Adjusting range, the signal for participating in interlocked control convert and more limit value and proportional-integral derivative controller parameter must simulate It verifies and adjusts when debugging, the executive condition of the equipment application analogue system testing algorithm, logic that can not temporarily simulate control is It is no to meet the requirements.
3) examination of packet equipment list and examination
After by equipment simulating control debugging and parameter tuning debugging, the equipment in grouping can carry out solo test run, Solo test run includes the local test run in scene and controls test run two parts in long-range, and local test run starts at the scene, and middle control test run is by grasping Work person, which stands, to be started, and whole process mainly in the process control station of automatic control system and concentrates supervisory layers to each stand-alone device Commissioning content is checked and is confirmed.
1. operator station observes the given feedback of each control loop, output valve and its curve with device packets picture, monitoring The warning message and fault message of picture, the whether correct start and stop of equipment.Coordinate with engineer station commissioning staff, processing routine is repaiied Change, configuration, the debugging efforts such as monitoring.
2. engineer station checks the operating condition of field control station, such as belt by configuration software, program composing software etc. The signals such as sideslip, velocity anomaly, all kinds of limit signals, valve switch state, electric current, pressure, temperature confirm that interlock logic executes. To control algolithm, the correctness of correlation curve and numerical check algorithm performs.And according to technological requirement, modification adjustment programme is patrolled It collects and configuration is to meet design requirement.
3. post-installation review, the stability and installation essence of detecting electric control and machine operation will be carried out in accordance with regulations in stand-alone device Degree, accurately records the data such as the duration of runs, electric current, electrical equipment temperature, mechanical equipment temperature, vibration.
4) equipment complete set start-up
After stand-alone device test running qualification in grouping, that is, enters equipment complete set start-up and debug stage, the debugging in this stage It is mainly executed with the engineer station of Central Control Room and operator station, field adjustable personnel are responsible for monitoring device operating condition, when necessary Simulated failure and interlock condition are to reach the target of single group and multigroup startup and stopping.Complete set start-up commissioning content includes:
1. group requires to include the various signals of the analog quantitys such as electric current, power, temperature, pressure, vibration when starting and puts into as possible;
2. the interlock logic test of equipment, the test of complete set start-up interlock logic in single group;
3. process sequence is tested between group, signal is quoted between group, and group boot sequence and stopping interlocking being debugged;
4. equipment starts the information Real-time Feedback feelings such as interlocking, alarm, the failure of time-division group picture in operator station inspection group Condition;
5. engineer station need to be to group starting a control program executive condition, programmed logic reasonability, equipment starts suitable in each group Whether sequence meets design requirement, and to the modification requirement that technologist proposes, organizing the problem of Start-up and Adjustment is found will be timely and reasonably Processing;
5) Regional Linking
After the debugging of equipment complete set start-up is qualified, that is, enter the Regional Linking stage, feelings are distributed according to the configuration of live master station Condition and the technological process of production are divided such as material allocation area, raw mill and pulverized coal preparation area, calcining kiln area, cement and slag milling Area, finished product area etc. debug performance depending on each differentiation group, can be carried out at the same time the region joint-trial in two to three areas, and gradually extend To completely each region joint-trial.This stage mainly examines whether each area's technological process of verification meets design requirement, and automation control is patrolled Whether accurate, whether interlockings at different levels are reliable if collecting, whether the equipment operation of each level of DCS system stablizes, fiber optic network, live master control Whether device, database, engineer station, the various types of hardware of operator station and software performance reach design requirement.
After the Regional Linking in each area meets the requirements, all fronts refrigeration duty test run is just proceeded by according to technological process.
It is distributed, the close signal of technique first line of a couplet system is intensively allocated to same according to the technological process of production and equipment region In standing, the mutual reference of signal between station is reduced, different websites influencing each other in debugging is reduced, it will be on process sequence at each station There is the equipment of serial relation and interlock connection to distribute to same group, form several debugging groups, to reach the mesh of subregion, grouping debugging 's;
Based on ripe DCS system Soft and hard establishment, optical fiber ring network, live main controller, data server, system power supply Deng all having done redundant configuration, and soft and hardware autgmentability is strong, support program, parameter modification unperturbed under fill, go out in debugging process Existing soft and hardware problem can seamless excision or modification, do not influence other groupings debugging;
For different subregions and grouping, the characteristics of not interfere with each other because of it, can be at different debugging stages, and each group The soft and hardware equipment test of its decentralized detection process layer, process control station, Centralized Monitoring operation layer and interlayer are combined simultaneously Debugging, interregional combined debugging is carried out to reach the target of all fronts refrigeration duty test run into the linkage trial run stage.

Claims (2)

1. a kind of large size cement produced with the dry method scattered control system packet joining adjustment method, which is characterized in that include the following steps:
Step 1:Subregion, grouping
It is distributed according to cement production process flow and equipment region, scene is overall to be divided into three regions:
1) lime stone stockyard, material allocation, raw mill are an area, and raw material homogenizing silo is the buffering area of technique linking;
2) coal dust mill, calcining kiln, cement grinding mill, slag mill are an area, and cement clinker library is the buffering area of technique linking;
3) cement allotment, warehouse for finished product, cement packing are an area;
By the equipment for having serial relation and interlock connection on process sequence, control station or relatively independent at being arranged in each region Back-up is at several groups;
Step 2:Subregion, packet joining debugging
After region and grouping divide well, each group commissioning staff enters scene, is not put into energy medium and motor main circuit In the case of debugging efforts are started simultaneously to the device packets that it is responsible for;Different subregions and grouping, because of its not interfereing with each other property The different debugging stages is can be at, and respectively grouping can simultaneously grasp its decentralized detection process layer, process control station, Centralized Monitoring Make the soft and hardware equipment test of layer and carry out interlayer combined debugging, operating procedure and main points are as follows:
1) I/O signals and scattered control system combined debugging are respectively grouped
Confirm that I/O signals and the soft and hardware configuration of each layer real time data of scattered control system must correspond, is tested in I/O While joint carry out following debugging:
1. checking whether the operation of I/O modules is normal in the field control station of decentralized detection process layer, whether point bit allocation meets letter The design of number table;
2. opening engineering process, each measuring point arrangement and each I/O moulds in practical cabinet of checking process control layer in engineer station Whether block is consistent, and whether the real time data for getting the stations each I/O debugging group test ready with test interface is correct, with software configuration phase Symbol;
3. recalling the comprehensively monitoring picture of operator station in Centralized Monitoring operation layer, stand to each I/O, the various letters of each debugging group Number it is monitored test, it is that operator station picture is shown the result is that have passed through all hardware input and output, signal is filtered, object The final result that the conversion of reason amount, network data are transmitted, obtained after the docking of software data interface;
2) single machine simulation control adjusts debugging with parameter, algorithm
After I/O signal testings, single machine simulation control is carried out to the equipment in grouping, and control program parameter, algorithm are adjusted Debugging;
1. single machine simulation control debugging
It uses local mode to operate equipment start-stop at the scene first, whether correct, engineering is run to control loop in detection plate cabinet Whether teacher's stand control program executive condition is normal, and whether the real-time display that operator station monitored picture corresponds to equipment state is normal;
After local control simulation is correct, long-range firing test need to be carried out, start stop operation, operation are carried out to equipment by operator station Channel, range, signal transformation, interlocking and the alarm of the corresponding picture in member station are checked, are confirmed, are remotely started the interlocking being related to and are protected Shield must test each interlocking point, and it is logically true to ensure;
2. parameter, algorithm adjust debugging
Sampling period of the various types of signal being related to for stand-alone device, adjustable range, the signal transformation for participating in interlocked control and more Limit value and proportional-integral derivative controller parameter must be verified and be adjusted in simulative debugging, and control can not be temporarily simulated Equipment application analogue system testing algorithm, logic executive condition whether meet the requirements;
3) examination of packet equipment list and examination
After by equipment simulating control debugging and parameter tuning debugging, the equipment in grouping can carry out solo test run, single machine Test run includes the local test run in scene and controls test run two parts in long-range, and local test run starts at the scene, and middle control test run is by operator It stands startup, whole process mainly in the process control station of automatic control system and concentrates the debugging of supervisory layers to each stand-alone device Content is checked and is confirmed;
1. operator station observes the given feedback of each control loop, output valve and its curve, monitored picture with device packets picture Warning message and fault message, the whether correct start and stop of equipment;Coordinate with engineer station commissioning staff, processing routine modification, group State, monitoring debugging efforts;
2. engineer station checks the operating condition of field control station, belt deviation, speed by configuration software, program composing software Abnormal, all kinds of limit signal, valve switch state, electric current, pressure, temperature signal confirm that interlock logic executes;To control algolithm, The correctness of correlation curve and numerical check algorithm performs;And adjustment programme logic and configuration are changed according to technological requirement;
3. carrying out post-installation review stand-alone device, the stability and installation accuracy of detecting electric control and machine operation, when to operating Between, electric current, electrical equipment temperature, mechanical equipment temperature, vibration data accurately record;
4) equipment complete set start-up
After stand-alone device test running qualification in grouping, that is, enters equipment complete set start-up and debug the stage, debug mainly with Central Control Room Engineer station and operator station execute, field adjustable personnel are responsible for monitoring device operating condition, when physical condition cannot meet When need simulated failure and interlock condition with reach single group and it is multigroup startup and stopping target;
Complete set start-up commissioning content includes:
1. group requires to include electric current, power, temperature, pressure, the various signals of vibration simulation amount when starting and puts into as possible;
2. the interlock logic test of equipment, the test of complete set start-up interlock logic in single group;
3. process sequence is tested between group, signal is quoted between group, and group boot sequence and stopping interlocking being debugged;
4. equipment starts the interlocking, alarm, fault message Real-time Feedback situation of time-division group picture in operator station inspection group;
5. engineer station need to be to group starting a control program executive condition, programmed logic reasonability, equipment boot sequence is in each group No to meet design requirement, to the modification requirement that technologist proposes, organizing the problem of Start-up and Adjustment is found will be handled timely and reasonably;
5) Regional Linking
After the debugging of equipment complete set start-up is qualified, that is, enter the Regional Linking stage, according to the configuration distribution situation of live master station and The technological process of production divides material allocation area, raw mill and pulverized coal preparation area, calcining kiln area, cement and slag milling area, finished product Area debugs performance depending on each differentiation group, can be carried out at the same time the region joint-trial in two to three areas, and gradually extends to completely each area Domain joint-trial;
After the Regional Linking in each area meets the requirements, all fronts refrigeration duty test run is just proceeded by according to technological process.
2. large size cement produced with the dry method scattered control system packet joining adjustment method according to claim 1, it is characterised in that: Lime stone stockyard, material allocation, raw mill in step 1 in three regions, coal dust mill, calcining kiln, cement grinding mill, slag mill, water Mud allotment, warehouse for finished product and cement packing are respectively one group respectively, totally ten groupings.
CN201410850079.7A 2014-12-26 2014-12-26 Large-scale cement produced with the dry method scattered control system packet joining adjustment method Active CN105785942B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410850079.7A CN105785942B (en) 2014-12-26 2014-12-26 Large-scale cement produced with the dry method scattered control system packet joining adjustment method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410850079.7A CN105785942B (en) 2014-12-26 2014-12-26 Large-scale cement produced with the dry method scattered control system packet joining adjustment method

Publications (2)

Publication Number Publication Date
CN105785942A CN105785942A (en) 2016-07-20
CN105785942B true CN105785942B (en) 2018-09-14

Family

ID=56389175

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410850079.7A Active CN105785942B (en) 2014-12-26 2014-12-26 Large-scale cement produced with the dry method scattered control system packet joining adjustment method

Country Status (1)

Country Link
CN (1) CN105785942B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI742043B (en) * 2017-02-22 2021-10-11 國聯機械實業股份有限公司 Intelligent control system for spheroidized metal wire
CN115373344A (en) * 2020-12-31 2022-11-22 贵州西电电力股份有限公司黔北发电厂 Control method for realizing equipment interlocking according to equipment running current signal
CN116030544A (en) * 2022-12-30 2023-04-28 深圳科瑞技术股份有限公司 Method and device for recording debugging data of automation equipment

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN87211407U (en) * 1987-08-03 1988-07-06 山东建材学院 Dry cement grading program-controlled laser analyser
CN103204642A (en) * 2013-04-02 2013-07-17 广西中盟世纪环保咨询有限责任公司 Novel dry-process cement kiln household garbage incineration method
EP2708968A2 (en) * 2012-09-12 2014-03-19 Kabushiki Kaisha Topcon Construction machine control method and construction machine control system
CN103913548A (en) * 2014-04-08 2014-07-09 北京航空航天大学 Experimental device and method for researching selective non-catalytic reducing property in new dry process cement decomposing furnace

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2014212083A1 (en) * 2013-02-04 2015-08-06 Coldcrete, Inc. System and method of applying carbon dioxide during the production of concrete

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN87211407U (en) * 1987-08-03 1988-07-06 山东建材学院 Dry cement grading program-controlled laser analyser
EP2708968A2 (en) * 2012-09-12 2014-03-19 Kabushiki Kaisha Topcon Construction machine control method and construction machine control system
CN103204642A (en) * 2013-04-02 2013-07-17 广西中盟世纪环保咨询有限责任公司 Novel dry-process cement kiln household garbage incineration method
CN103913548A (en) * 2014-04-08 2014-07-09 北京航空航天大学 Experimental device and method for researching selective non-catalytic reducing property in new dry process cement decomposing furnace

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
基于现场总线的新型干法水泥回转窑控制系统研究与设计;时国平;《工业控制计算机》;20081025;第21卷(第10期);第27-29页 *
论2500t/d新干法水泥生产线DCS控制策略;李长丹;《科技资讯》;20100103(第1期);第105页 *

Also Published As

Publication number Publication date
CN105785942A (en) 2016-07-20

Similar Documents

Publication Publication Date Title
US20110202163A1 (en) Plant protection system and method using field programmable gate array
CN105785942B (en) Large-scale cement produced with the dry method scattered control system packet joining adjustment method
CN103744424B (en) Field device logic control test method
CN103885411B (en) Power plant complex automatic system
CN104331042A (en) State evaluation method of hydropower plant computer monitoring system
CN104020761A (en) Automatic feeder testing system free of networking
CN109519233A (en) For nuclear power plant's steam turbine into the on-line monitoring method and system of steam control valve
CN103346497B (en) Intelligent substation electrical virtual circuit isolation method and system
CN105700480B (en) A kind of the multimachine bed grouping control system and its control method of production line
CN106448778A (en) Serious accident instrument control system for nuclear power station
CN102546227A (en) Method and device for monitoring working status of different system devices
CN110350660B (en) Online monitoring method and system for relay protection function pressing plate
CN102508053B (en) Area backup automatic switch testing system based on digital simulation technology
CN203965886U (en) Power plant electricity thermal technology integral control system
CN112861421A (en) Intelligent analysis early warning system and method for power equipment
CN117526553A (en) Power grid data acquisition system
CN101738974A (en) System for monitoring auxiliary engine state
CN104317259A (en) Method for establishing PLC/DCS platform device logic model
CN104133954A (en) Protection logic simulation device and dynamic verification system using protection logic simulation device
CN207636997U (en) A kind of experiment TT&C system for special centrifugal pump
Miller et al. PacifiCorp’s Jim Bridger RAS: A dual triple modular redundant case study
CN112306039B (en) Debugging method and system for full-electronic interlocking system
CN109324597A (en) A kind of engineering adaptability test method of two generation of nuclear power station pressurization water-water reactor safety level DCS
CN204538823U (en) A kind of step hydropower station is unattended and remote central control
CN203870470U (en) Feeder automation test system without network

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant