Concrete prefabricated element template fixing component
Technical field
The present invention relates to the prefabricated apparatus fields of concrete component, fix more particularly to a kind of concrete prefabricated element template
Component.
Background technique
Occur the phenomenon that crack too early to make up concrete, used (load) in the past in component, and gave concrete one in advance
A precompression, i.e., in the tensile region of concrete, reinforcing bar is carried out tensioning, utilizes the retraction of reinforcing bar by the method manually reinforced
Power makes concrete in tension area in advance by pressure.This precharge pressure stored, when component bears to generate pulling force by external load
When, the precompression in concrete in tension zone is offset first, then increases with load, just makes concrete in tension, and which limits mixed
The elongation for coagulating soil, delays or crack occurs, the concrete of such form is prestressed concrete.Due to prestressed concrete
Soil has many advantages, such as that crack resistance is good, rigidity is big, self weight vertical shear and principal tensile stress small, that can reduce beams of concrete, can
The stability and fatigue performance for significantly improving compression member have excellent applying value in existing building construction.
The link that slurries leak when preventing concreting is directed in prestressed concrete casting process, and it is many anti-
The effect of spillage technology fails to get a desired effect, and leads to the quality for directly affecting construction efficiency and concreting.It is existing
It is generally all directly being contacted using steel plate with steel plate and is compressing, increases to stop and starch item etc., to prevent concrete slurry from leaking, but this side
Method not only increases certain difficulty to construction, also fails to reach ideal mortar leakage prevention effect.
Summary of the invention
For be directed in above-mentioned prestressed concrete casting process prevent concreting when slurries leakage link,
And the effect of many mortar leakage prevention technologies fails to get a desired effect, and leads to directly affect construction efficiency and concreting
The problem of quality, the present invention provides a kind of concrete prefabricated element template fixing components.
To solve the above problems, concrete prefabricated element template fixing component provided by the invention passes through following technical essential
To solve the problems, such as: concrete prefabricated element template fixing component, including grillage, fixation clip and movable pressing board, the fixed pressure
Plate is fixed on grillage, and fixation clip and movable pressing board are in face relationship, is had between fixation clip and movable pressing board for pressing from both sides
The gap for holding template, further includes the hold-down bolt being threadedly connected on grillage, and the axis of the hold-down bolt is located at the gap
Width direction, the end of the hold-down bolt and the outer side contacts of movable pressing board further include spring and check bolt, described anti-
Loose bolt thread is connected on grillage, and the axis of check bolt is parallel with the axis of hold-down bolt, and the spring is set to work
Between dynamic pressure plate and check bolt, in working condition, both ends of the spring is located by the compression of movable pressing board and check bolt respectively
In elastic compression.
Specifically, the clamping of concrete prefabricated element template is used for upper fixture, it is mixed to be inserted in the template after clamping
Solidifying soil sand slurry, in this way, type chamber of the template as concrete mortar, concrete prefabricated required for obtaining after concrete mortar solidification
Component.In the prior art, it to reduce shrinkage of the concrete mortar in process of setting, can generally be added in concrete mortar
Swelling agent, however, concrete mortar still has small contraction under normal circumstances, for prestressed concrete, the above contraction is
The important origin cause of formation that slurries leak when pouring.
In this case, when template closes mould, by rotating hold-down bolt, the end of hold-down bolt acts on the outer of movable pressing board
Side, rotation can be passed through in the above gap after fill concrete mortar by obtaining the specified gap width of fixation clip and movable pressing board
Check bolt, generating spring is in the elastic deformation of compressive state, and the above elastic deformation is that movable pressing board is generated to fixation clip
The thrust of side, in this way, if concrete mortar is shunk, the above spring deformation is produced in mixed mud mortar solidification process
Raw elastic force forces to be fitted closely between template and mixed mud mortar, mixed mud mortar and sealing strip, sealing strip and template, is reached
To reducing spillage amount or avoid the technical effect of spillage.
This case,, can before fill concrete mortar after adjusting movable pressing board and fixation clip spacing when using
Increasing a both ends in movable pressing board and fixation clip, the distance rod with the two interior side contacts, preferably distance rod are located at gap respectively
Upper end, then pass through check bolt compressed spring.After fill concrete mortar, to a certain extent to concrete mortar solidification,
When i.e. concrete mortar has some strength, then remove distance rod, to avoid spring elastic force to fixation clip and movable pressing board
Between the size of type chamber impact.
Further technical solution are as follows:
As a kind of concrete scheme being easily achieved, the grillage is in U-shape, and the fixation clip and movable pressing board distinguish position
In the inside that grillage open end is not ipsilateral.In the above structure, plate can be threadedly connected to simultaneously by check bolt and hold-down bolt
The side of frame, the adjustment for the compression of complete paired springs and to movable pressing board position.
It since the shrinkage of mixed mud mortar is smaller relative to gap width between fixation clip and movable pressing board, therefore is benefit
In mortar leakage prevention effect, the biggish spring of coefficient of elasticity is preferably selected, the spring is the bullet being formed by stacking by multiple disk springs
Spring group.
It is described conducive to prefabricated components forming quality to avoid movable pressing board that excessive skew occurs under the bullet stress of spring
Spring is one, and the axis of the spring and the axis collinear of hold-down bolt, further include locking with hold-down bolt clearance fit
Plate, the locking plate are set between spring and check bolt, and the locking plate is for the stress between spring and check bolt
Transmitting, more than one of the check bolt, and different check bolts are set to the not ipsilateral of hold-down bolt.
It is described conducive to prefabricated components forming quality to avoid movable pressing board that excessive skew occurs under the bullet stress of spring
Spring is more, and more springs are annularly uniformly distributed relative to the axis of hold-down bolt, further includes and hold-down bolt clearance fit
Locking plate, the locking plate are set between spring and check bolt, and the locking plate is used between spring and check bolt
Stress transfer, more than one of the check bolt, and different check bolts are set to the not ipsilateral of hold-down bolt.
To be provided with for braking on the hold-down bolt and check bolt convenient for rotating hold-down bolt and check bolt
The turning handle of each autorotation.
The invention has the following advantages:
In this case, when template closes mould, by rotating hold-down bolt, the end of hold-down bolt acts on the outer of movable pressing board
Side, rotation can be passed through in the above gap after fill concrete mortar by obtaining the specified gap width of fixation clip and movable pressing board
Check bolt, generating spring is in the elastic deformation of compressive state, and the above elastic deformation is that movable pressing board is generated to fixation clip
The thrust of side, in this way, if concrete mortar is shunk, the above spring deformation is produced in mixed mud mortar solidification process
Raw elastic force forces to be fitted closely between template and mixed mud mortar, mixed mud mortar and sealing strip, sealing strip and template, is reached
To reducing spillage amount or avoid the technical effect of spillage.
Detailed description of the invention
Fig. 1 is the structural representation of one specific embodiment of concrete prefabricated element template fixing component of the present invention
Figure.
Figure acceptance of the bid note is respectively as follows: 1, fixation clip, 2, movable pressing board, 3, grillage, 4, check bolt, 5, locking plate, 6, pressure
Tight bolt, 7, spring.
Specific embodiment
The present invention provides a kind of concrete prefabricated element template fixing components, for solving: prestressing force in the prior art
It is directed to the link that slurries when preventing concreting leak in concreting process, and the effect of many mortar leakage prevention technologies
The problem of failing to get a desired effect, leading to directly affect the quality of construction efficiency and concreting.Below with reference to reality
Applying example, the present invention is described in further detail, but the present invention is not limited only to following embodiment:
Embodiment 1:
As shown in Figure 1, concrete prefabricated element template fixing component, including grillage 3, fixation clip 1 and movable pressing board 2,
The fixation clip 1 is fixed on grillage 3, and fixation clip 1 and movable pressing board 2 are in face relationship, fixation clip 1 and movable pressing board
There is the gap for clamping template between 2, further include the hold-down bolt being threadedly connected on grillage 3, the hold-down bolt
Axis is located at the width direction in the gap, the end of the hold-down bolt and the outer side contacts of movable pressing board 2, further includes spring
7 and check bolt 4, the check bolt 4 is threadedly connected on grillage 3, and the axis of the axis of check bolt 4 and hold-down bolt 6
Line is parallel, and the spring 7 is set between movable pressing board 2 and check bolt 4, and in working condition, 7 both ends of spring are respectively by activity
The compression of pressing plate 2 and check bolt 4 and be in elastic compression.
Specifically, the clamping of concrete prefabricated element template is used for upper fixture, it is mixed to be inserted in the template after clamping
Solidifying soil sand slurry, in this way, type chamber of the template as concrete mortar, concrete prefabricated required for obtaining after concrete mortar solidification
Component.In the prior art, it to reduce shrinkage of the concrete mortar in process of setting, can generally be added in concrete mortar
Swelling agent, however, concrete mortar still has small contraction under normal circumstances, for prestressed concrete, the above contraction is
The important origin cause of formation that slurries leak when pouring.
In the present embodiment, when template closes mould, by rotating hold-down bolt 6, the end of hold-down bolt 6 acts on movable pressure
The outside of plate 2 obtains the specified gap width of fixation clip 1 Yu movable pressing board 2, in the above gap after fill concrete mortar,
It can be by rotating check bolt 4, generating spring 7 is in the elastic deformation of compressive state, and the above elastic deformation is the production of movable pressing board 2
The raw thrust to 1 side of fixation clip, in this way, in mixed mud mortar solidification process, if concrete mortar is shunk, with upper spring
Elastic force caused by flexible deformation force template and mixed mud mortar, mixed mud mortar and sealing strip, sealing strip and template it
Between fit closely, reach and reduce spillage amount or avoid the technical effect of spillage.
This case is when using, after adjusting movable pressing board 2 and 1 spacing of fixation clip, before fill concrete mortar,
A both ends being increased in movable pressing board 2 and fixation clip 1, the distance rod with the two interior side contacts, preferably distance rod are located at respectively
The upper end in gap, then pass through 4 compressed spring 7 of check bolt.After fill concrete mortar, it is cured to centainly to concrete mortar
When degree, i.e. concrete mortar have some strength, then distance rod is removed, to fixation clip 1 and lived to avoid the elastic force of spring 7
The size of type chamber impacts between dynamic pressure plate 2.
Embodiment 2:
The present embodiment is further qualified on the basis of embodiment 1, as shown in Figure 1, as a kind of tool being easily achieved
Body scheme, the grillage 3 are in U-shape, and the fixation clip 1 and movable pressing board 2 are located at not ipsilateral interior in 3 open end of grillage
Side.In the above structure, the side of grillage 3 can be threadedly connected to simultaneously by check bolt 4 and hold-down bolt 6, for completion pair
The compression of spring 7 and adjustment to 2 position of movable pressing board.
Since the shrinkage of mixed mud mortar is smaller relative to gap width between fixation clip 1 and movable pressing board 2, therefore it is
Conducive to mortar leakage prevention effect, the biggish spring 7 of coefficient of elasticity is preferably selected, the spring 7 is to be formed by stacking by multiple disk springs
Groups of springs.
To avoid movable pressing board 2 that excessive skew occurs under the bullet stress of spring 7, it is conducive to prefabricated components forming quality, institute
Stating spring 7 is one, and the axis of the spring 7 and the axis collinear of hold-down bolt 6 further include and 6 clearance fit of hold-down bolt
Locking plate 5, the locking plate 5 is set between spring 7 and check bolt 4, and the locking plate 5 is for spring 7 and locking spiral shell
Stress transfer between bolt 4, the check bolt 4 more than one, and different check bolts 4 are set to the difference of hold-down bolt 6
Side.
Embodiment 3:
The present embodiment is on the basis of embodiment 1 further qualified the present invention, as shown in Figure 1, to avoid movable pressure
Under the bullet stress of spring 7 excessive skew occurs for plate 2, is conducive to prefabricated components forming quality, and the spring 7 is more, more bullets
Spring 7 is annularly uniformly distributed relative to the axis of hold-down bolt 6, further includes the locking plate 5 with 6 clearance fit of hold-down bolt, described anti-
Deals 5 is set between spring 7 and check bolt 4, and the locking plate 5 is passed for the stress between spring 7 and check bolt 4
It passs, the check bolt 4 more than one, and different check bolts 4 are set to the not ipsilateral of hold-down bolt 6.
Embodiment 4:
The present embodiment is further qualified on the basis of any of the above one embodiment, as shown in Figure 1, for convenient for rotation
Hold-down bolt 6 and check bolt 4 are provided on the hold-down bolt 6 and check bolt 4 for braking turning for each autorotation
Handle.
The above content is combine specific preferred embodiment to the further description of the invention made, and it cannot be said that originally
The specific embodiment of invention is only limited to these instructions.For those of ordinary skill in the art to which the present invention belongs,
The other embodiments obtained in the case where not departing from technical solution of the present invention, should be included within the scope of the present invention.