CN105737696A - Riverway blasting method - Google Patents

Riverway blasting method Download PDF

Info

Publication number
CN105737696A
CN105737696A CN201410754174.7A CN201410754174A CN105737696A CN 105737696 A CN105737696 A CN 105737696A CN 201410754174 A CN201410754174 A CN 201410754174A CN 105737696 A CN105737696 A CN 105737696A
Authority
CN
China
Prior art keywords
hole
sleeve pipe
blasting method
explosive
explosion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410754174.7A
Other languages
Chinese (zh)
Inventor
庄静波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410754174.7A priority Critical patent/CN105737696A/en
Publication of CN105737696A publication Critical patent/CN105737696A/en
Pending legal-status Critical Current

Links

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

The invention discloses a riverway blasting method and relates to a drilling and charging blasting method. The method comprises the steps that firstly, an operation zone is positioned, a down-the-hole drill and a casing pipe are prepared, and the length of the casing pipe is required to be greater than the water depth of the selected operation zone; secondly, the down-the-hole drill is used for drilling a hole in the operation zone of the step 1; thirdly, the casing pipe in the step 1 is immediately inserted into the drilled hole after the hole is drilled; fourthly, explosive is charged into the casing pipe in the step 3, and a leading wire is reserved; fifthly, the leading wire in the step 4 is ignited to conduct blasting; and sixthly, the blasted zone is cleaned up through an excavating machine. The down-the-hole drill is used for drilling the hole, so that convenience is achieved, and manpower is saved; and a plastic pipe is used for positioning and charging of the explosive, so that the cost is reduced, the operation time is shortened, and the efficiency is improved.

Description

A kind of river course blasting method
[technical field]
The present invention relates to a kind of borehole charge blasting method, particularly relate to a kind of for the blasting method under urban river water.
[background technology]
Drawing water in river course borehole blasting rock many employings cofferdam both at home and abroad now, it is necessary to then the water draining burst region clear up silt with ditcher, expose rock and implement explosion, such method is loaded down with trivial details, and greatly, efficiency is also low for artificial and energy expenditure;Also there is the method loading explosive at lower water, but owing to being directly load explosive under water, it is easy to soak explosive, and bad location and an ignition, consuming time and success rate is not high.
[summary of the invention]
It is an object of the invention to effectively overcome the deficiency of above-mentioned technology, it is provided that a kind of river course blasting method, the method is simple, speed is fast, cost is low, efficiency is high and can save manpower.
The present invention is achieved through the following technical solutions:
It comprises the following steps:
Step one, positioning operation region, prepare hidden hole drilling and sleeve pipe, and the length of this sleeve pipe is greater than the depth of water of selected operating area;
With described hidden hole drilling boring in step 2, operating area in step one;
Step 3, be drilled hole after immediately the sleeve pipe in step one is inserted in the hole bored;
Filling explosive in step 4, sleeve pipe in step 3, and reserve lead-in wire;
Step 5, the lead-in wire lighted in step 4, carry out explosion;
Step 6, the region excavation machinery after explosion is cleaned out.
Preferably, described sleeve pipe is the plastic tube that can prevent mud from blocking.
Preferably, the hole count that in described step 2, hidden hole drilling bores is determined according to practical situation, and is immediately inserted into described sleeve pipe after being drilled each hole, waits hole to load explosive after all having beaten, and reserves lead-in wire, then carries out unified explosion.
The beneficial effects of the present invention is: it is holed with hidden hole drilling, conveniently save manpower;It, with preventing the plastic tube that mud blocks from carrying out location and the filling of explosive, provides cost savings and the activity duration, also improves efficiency.
[detailed description of the invention]
Below in conjunction with detailed description of the invention, the invention will be further described.
Specific embodiments of the invention are: the present invention is suitable for the river course explosion of phytal zone.First positioning operation region and the hole count to beat on river course, get out plastic tube and the hidden hole drilling machine of explosion, the length of this plastic tube is greater than the depth of water of selected operating area, and this plastic tube can prevent mud from entering inside pipe, thus preventing blocking pipeline, this plastic tube percentage of explosive can reach 100%.The operative employee of specialty drives hidden hole drilling and starts boring, plastic tube is inserted in the hole behind a complete hole by hidden hole drilling every dozen immediately, all beat rear chargehand in hole to begin in plastic tube, add explosive and reserve lead-in wire, until all of hole beat finish bundle and dynamite charge complete after, every plastic tube all exceeds horizontal plane proper alignment, all of lead-in wire is linked together, begin to carry out unified explosion, implement the region after explosion to clean out with excavation machinery again, just complete the demolition duty of operating area, 100% demolition effect can be reached through the practice present invention.
Present invention hidden hole drilling is holed, and conveniently saves manpower;The present invention, with preventing the plastic tube that mud blocks from positioning and loading explosive, provides cost savings and the activity duration, also improves efficiency.It is more than 5 times of old-fashioned method through calculating the speed of the method explosion, cost savings 70%, manually also save half.
Described above is only presently preferred embodiments of the present invention, and above-mentioned specific embodiment is not limitation of the present invention.In the technological thought category of the present invention, it is possible to various deformation and amendment occur, retouching, amendment or the equivalent replacement that all those of ordinary skill in the art make as described above, belong to the scope that the present invention protects.

Claims (3)

1. a river course blasting method, it is characterised in that:
Step one, positioning operation region, prepare hidden hole drilling and sleeve pipe, and the length of this sleeve pipe is greater than the depth of water of selected operating area;
With described hidden hole drilling boring in step 2, operating area in step one;
Step 3, be drilled hole after immediately the sleeve pipe in step one is inserted in the hole bored;
Filling explosive in step 4, sleeve pipe in step 3, and reserve lead-in wire;
Step 5, the lead-in wire lighted in step 4, carry out explosion;
Step 6, the region excavation machinery after explosion is cleaned out.
2. a kind of river course blasting method according to claim 1, it is characterised in that: described sleeve pipe is the plastic tube that can prevent mud from blocking.
3. a kind of river course blasting method according to claim 1, it is characterized in that: the hole count that in described step 2, hidden hole drilling bores is determined according to practical situation, and after being drilled each hole, it is immediately inserted into described sleeve pipe, explosive is loaded in hole after all having beaten, and reserve lead-in wire, then carry out unified explosion.
CN201410754174.7A 2014-12-10 2014-12-10 Riverway blasting method Pending CN105737696A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410754174.7A CN105737696A (en) 2014-12-10 2014-12-10 Riverway blasting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410754174.7A CN105737696A (en) 2014-12-10 2014-12-10 Riverway blasting method

Publications (1)

Publication Number Publication Date
CN105737696A true CN105737696A (en) 2016-07-06

Family

ID=56238700

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410754174.7A Pending CN105737696A (en) 2014-12-10 2014-12-10 Riverway blasting method

Country Status (1)

Country Link
CN (1) CN105737696A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107726935A (en) * 2017-10-13 2018-02-23 中国建筑土木建设有限公司 The pile base construction method of oblique plane with large-angle competent bed

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0146411B1 (en) * 1995-06-07 1998-10-15 이정우 Rock blasting method
CN1776348A (en) * 2005-11-22 2006-05-24 裘尧云 Underwater reef explosion method and special tool
CN1884962A (en) * 2006-07-04 2006-12-27 裘尧云 Reef blasting method in underwater complex geological condition
CN201074990Y (en) * 2007-09-20 2008-06-18 武汉钢铁(集团)公司 Shooting blast hole sleeve
CN101608885A (en) * 2009-07-08 2009-12-23 长江重庆航道工程局 Underwater drilling and blasting construction method of mountain river
CN101713624A (en) * 2009-11-17 2010-05-26 广东爆破工程有限公司 Explosion and crushing method for underground concealed rock ground drilling
CN103900428A (en) * 2014-03-31 2014-07-02 中国水利水电第六工程局有限公司 Borehole charging method for underwater silt seam disturbance blasting

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0146411B1 (en) * 1995-06-07 1998-10-15 이정우 Rock blasting method
CN1776348A (en) * 2005-11-22 2006-05-24 裘尧云 Underwater reef explosion method and special tool
CN1884962A (en) * 2006-07-04 2006-12-27 裘尧云 Reef blasting method in underwater complex geological condition
CN201074990Y (en) * 2007-09-20 2008-06-18 武汉钢铁(集团)公司 Shooting blast hole sleeve
CN101608885A (en) * 2009-07-08 2009-12-23 长江重庆航道工程局 Underwater drilling and blasting construction method of mountain river
CN101713624A (en) * 2009-11-17 2010-05-26 广东爆破工程有限公司 Explosion and crushing method for underground concealed rock ground drilling
CN103900428A (en) * 2014-03-31 2014-07-02 中国水利水电第六工程局有限公司 Borehole charging method for underwater silt seam disturbance blasting

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107726935A (en) * 2017-10-13 2018-02-23 中国建筑土木建设有限公司 The pile base construction method of oblique plane with large-angle competent bed
CN107726935B (en) * 2017-10-13 2021-02-12 中国建筑土木建设有限公司 Pile foundation construction method for large-angle inclined plane hard rock stratum

Similar Documents

Publication Publication Date Title
CN102758633B (en) The construction method of the good large cross-section tunnel of a kind of country rock situation
CN101614134B (en) Drilling-explosion-pumping triadic pressure-relief outburst-prevention method
CN103499255A (en) Method for directional energy-gathered blasting of retaining wall with low damage
CN104913696A (en) Side slope excavation smooth-surface blasting-method construction method
CN104405434B (en) A kind of method and its device of hypotonic seam area pit shaft gas phase pressure break rapid uncovering coal
CN104819670A (en) Pre-drilling mesopore shaft excavation blasting method
CN203362135U (en) Perforating device improving gas permeability of coal beds
CN102817633A (en) Device for draining gas by deep hole crack control blasting and precracking method
CN107654213B (en) High-energy negative pressure blocking remover
CN201074990Y (en) Shooting blast hole sleeve
CN109238053A (en) It is a kind of depth coal seam explosion water filling hole sealing device and its explosion water filling method
CN101581232B (en) Method for pre-pumping coal body gas by concussion fracture of high-pressure gas
CN102620614B (en) Cave depot is slagged tap the construction method of funnel
CN105737696A (en) Riverway blasting method
CN106121644A (en) Water-filling pressure-bearing unloading pressure by blasting based on drilling in coal and rock plane crosslinking cellular structure and supporting reinforcement
CN101493305A (en) Damping blasting method for tunnel diggin
CN203050780U (en) Pipe-jacking ground-water lowering device of low-permeability saturated silty sand stratum tunnel construction
KR101252138B1 (en) Water tube blasting method
CN110455137A (en) Elementary errors is networked construction method outside a kind of hole for bored tunnel buffer blasting
CN203405132U (en) Simple spacer tube for air-spacing blasting
CN102889064B (en) Method for fixing underground corrugated pipe
CN102927863B (en) A kind of new method of total rock tunnel blasting construction
CN103075935B (en) Rockblast stress relief water storage guide hole type blasting method for deep-buried round tunnel
CN109029175A (en) House slight dynamite construction method and blast hole loading structure are worn under subway tunnel low coverage
CN103924603A (en) Tool for preventing pole pit soil collapse and method for using same to dig pole pit

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160706