CN105735227B - High-lift tooth climbs formula ship lift Nut column system construction method and installation accuracy control method - Google Patents

High-lift tooth climbs formula ship lift Nut column system construction method and installation accuracy control method Download PDF

Info

Publication number
CN105735227B
CN105735227B CN201610129328.2A CN201610129328A CN105735227B CN 105735227 B CN105735227 B CN 105735227B CN 201610129328 A CN201610129328 A CN 201610129328A CN 105735227 B CN105735227 B CN 105735227B
Authority
CN
China
Prior art keywords
nut column
nut
installation
embedded part
adjustment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610129328.2A
Other languages
Chinese (zh)
Other versions
CN105735227A (en
Inventor
路卫兵
李智
吴小云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Three Gorges Technology Co ltd
China Three Gorges Corp
Original Assignee
China Three Gorges Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Three Gorges Corp filed Critical China Three Gorges Corp
Priority to CN201610129328.2A priority Critical patent/CN105735227B/en
Publication of CN105735227A publication Critical patent/CN105735227A/en
Application granted granted Critical
Publication of CN105735227B publication Critical patent/CN105735227B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02CSHIP-LIFTING DEVICES OR MECHANISMS
    • E02C5/00Mechanisms for lifting ships vertically

Abstract

Formula ship lift Nut column system construction method and installation accuracy control method are climbed the present invention relates to high-lift tooth, four sets of nut column systems can be installed by this Nut column system construction method, above-mentioned installation method can improve its installation quality and installation effectiveness, and then ensure the safety and reliability of whole construction, the required precision of Nut column installation process can be improved by Nut column installation accuracy control method, it is ensured that its installation accuracy, which is met, to be required.

Description

High-lift tooth climbs formula ship lift Nut column system construction method and installation accuracy control Method
Technical field
The invention belongs to ship lift equipment installation Technology field, and in particular to a kind of high-lift tooth climbs formula ship lift spiral shell It is whole after female column system construction method and installation accuracy control method, many Nut column formation nut column systems that are particularly suitable for use in Installation accuracy control method in body installation method and installation process.
Background technology
Nut column climbs the crucial drive disk assembly of formula ship lift as tooth, and totally four sets of Nut column is arranged in four king-posts In vertical walls in elevator well section groove, often cover Nut column and be made up of two separate cylinders, two symmetrical cloth of cylinder Put, mounted in pairs.Often set Nut column group is by 1 group of nut column assembly(One), 6 groups of nut column assemblies(Two), 18 groups of nut column assemblies (Three), 1 group of nut column assembly(Four), guide rail splice, Nut column dividing plate, the composition such as screw.
In above-mentioned Nut column system installation process is carried out, it should ensure that the installation accuracy between single set Nut column group refers to Mark, ensures the installation accuracy index after many set Nut column group composition systems, and single-piece Nut column chi in Practical Project again The prominent construction Difficulties such as very little big, weight is big, complex structure and setting height(from bottom) height, above-mentioned essence can not be met using conventional mounting arrangements Degree is required, it is therefore desirable to propose new installation method and accuracy control method to overcome various difficult points, realizes smoothly opening for engineering Exhibition.
To have opened a kind of gear nut post climbing type vertical ship lift Nut column efficient for work in publication number CN103696410A Installation method, the method mainly describes the installation process and installation method of single Nut column, meets the peace of single Nut column Fill precision, but using the above method can not meet and control well after many set Nut columns composition nut column systems system it Between required precision, and above-mentioned specific accuracy control method is not disclosed yet;In application publication number:It is public in CN103669314A A kind of rack-and-pinion climbing type vertical ship lift tooth bar Efficient installation method is opened, the method mainly describes the installation side of tooth bar Method, although Nut column and tooth bar contribute to the primary drive support member of ship lift, but its mounting process parameter is different, because This is also not suitable for the installation of tooth bar;A kind of ship lift Nut column is disclosed in CNIO3643667A auxiliary adjustment side is installed Method, but the method is only applicable to the adjustment of Nut column.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of high-lift tooth and climb formula ship lift Nut column system construction side Method and installation accuracy control method, realize the efficient accurate installation that high-lift tooth climbs formula ship lift Nut column, effective to solve Every construction Difficulties, while ensure that the installation accuracy between nut column system, improve installation quality, it is met engineering real Border is needed, it is ensured that whole high-lift ship lift project is smoothed out, while ensure that construction safety.
In order to realize above-mentioned technical characteristic, the object of the present invention is achieved like this:High-lift tooth climbs formula ship lift spiral shell Female column system construction method, comprises the following steps:
1)Fist stage concrete and phase embedded part construction:One phase of Nut column embedded part includes mounting bracket and deformed bar collar Pipe, completes designing and producing for mounting bracket by concreting unit in factory, deformed bar harness sleeve is welded using spot welding It is connected in mounting bracket;Lifted using wall-attachment tower crane, during in-site installation, in construction part relevant position measuring elevational point and spiral shell Female one phase of post embedded part installation center line, installation center, elevation and the seamless steel pipe horizontal level of one phase of adjusting nut post embedded part;One Phase embedded part is installed after the completion of positioning, then carries out reinforcing bar colligation;It is last to add according to phase embedded part design cell merogenesis installation, adjustment Gu, and poured, wherein angle steel is buried in relevant position in storehouse, and the relevant position installed in Nut column sets dowel, most Pouring for whole fist stage concrete king-post is completed eventually;
2)Second stage concrete and the second stage of embedded part construction:Nut column second phase embedded part construction, Nut column second phase embedded part is mixed in a phase Solidifying soil, which is poured to 196m, starts construction, treats that king-post pours completion, while carrying out Second Construction after completing own vol deformation, first The surveying setting-out on king-post, then erection construction framed bent;The second stage of embedded part is to connect I steel composite by many root beads to form, first segment nut Before post second phase embedded part is installed, steel construction is installed in the second stage of embedded part bottom, measured after top of steel elevation, and is put down on steel construction Face adds adjustment cushion block, its cope level is slightly below the Bottom Altitude of Nut column embedded part, after the embedded part lifting in place of Nut column second phase, The dowel that one phase was buried and the second stage of embedded part spot welding, tentatively fix, and are finally completed the installation of whole the second stage of embedded part;Second phase buries After part installation, a connecting tube and steel pipe are penetrated in the deformed bar harness sleeve of a phase embedded part, steel pipe is adjusted To installation center elevation location, and make to fix after its holding level, then by the firm reinforcing of the second stage of embedded part and pre-buried iron plate, finally Complete the pouring construction of second stage concrete;
3)Nut column installs preparation:Before Nut column lifting, the construction platform at erection construction position and top peace Full protection platform, arrangement measurement net, it is ensured that various putting up platform meet construction needs;The corresponding the second stage of embedded part of Nut column will often be saved Terraced flank of tooth surface mortar and other debris are cleaned out, and back is corresponded at the floor layer, groove inner concrete, reinforcing bar of PVC sleeve pipes Cleared up;The quality testing of Nut column is carried out according to design and code requirement, one tower body position of Nut column correspondence is often covered and enters Row is installed;The face that contacted with each other between having installed section, section two to be installed successively is cleared up before Nut column lifting;Section top has been installed Elevation, steel diaphragm elevation and levelness are detected and recorded, analyzed, it is ensured that cope level can meet section Nut column to be installed Elevation installation specification;First section Nut column bracket is finally carried out to install;
4)Nut column is installed:
4.1)Nut column is transported and lifted, and Nut column is lifted on flat car using truck crane and transports ship railway carriage or compartment room base plate Correspondence installation site is put.
4.2)Nut column is lifted using special hanger, suspender tightens high-strength company between suspender and component lifting hole(eyelet) when installing Connecting bolt, Nut column is lifted near installation site, and Nut column is furthered to installation position with guide chain, then connection adjustment spiral shell Tooth bar and the second stage of embedded part, are tentatively connected, 16T press branch are used on bottom bracket by bar using internode adjusting bolt Support, after the completion of carry out tear hook open.
4.3)In every Nut column left and right banks both sides welding adjustment frock, Nut column is subjected to Primary Location and adjustment;
4.4)After Nut column lifting is in place, at top, welding coil holder measures cultellation, utilizes angle square, Steel Ruler, piano Line hangs again vertical method, on the basis of the corresponding coordinate value of every vertical line, and adjusting nut post is controlled according to every technical requirements Mileage, center, elevation, perpendicularity, depth of parallelism etc. control size, carry out just successive step simultaneously to upstream and downstream two panels Nut column;
4.5)After the completion of first successive step, Nut column accurate adjustment is carried out according to the every installation specification of Nut column with total powerstation, Nut column installation site and the adjacent tooth bar installation site installed are positioning datum during adjustment.
4.6)Installation personnel carries out upstream and downstream Nut column range difference and upstream and downstream depth displacement using in-process measurement utensil, interior The 90 ° of control adjustment of circular diameter and double guide pass angles are checked and accepted.
4.6)After Nut column is accurately adjusted in place, jack is adjusted on locking fixture, regulating bolt is tightened and completes reinforcing, Nut column installation site deviation is monitored using vertical line in reinforcing process, such as varies widely, stops in reinforcing process Only reinforce and readjusted.
4.7)Accurate adjustment in place, reinforce complete and measure after acceptance(check), by deformed bar installation site two ends hole profit Carry out sealing blocking with cotton, be then transferred to gap formwork erection process, formwork erection complete and by filling water test after, by deformed bar Installation site two ends hole sealer is taken out, after moisture in pipe is drained, and prestressing force is carried out from Nut column back by workmen Reinforcement installation.
4.8)Carry out needing that Nut column installation site is carried out to check examination before cementing operations, grouting after the completion of formwork erection, it is qualified After can carry out carrying out deformation monitoring with dial gauge in gap grouting, filling process.
4.9)After gap grouting is completed 14 days, deformed bar is installed from Nut column back, deformed bar Pretightning force apply overleaf carry out, the installation of high-strength bolt is then installed before each bolt tensioning, according to tension sequence The adjusting screw rod of corresponding position is removed and installed after high-strength bolt, stretching construction is carried out.
4.10)It is positioning datum with the final check and acceptance result of Nut column for completing to install first, carries out remaining 3 tower body nuts The installation of post, according to positioning datum during installation, carries out every physical dimension such as four sets of nut intercolumniation relative positions and is adjusted, make All sizes meet design requirement.
4.11)It is positioning datum with the final check and acceptance result of Nut column for completing to install first, carries out remaining 3 tower body nuts The installation of post, according to positioning datum during installation, carries out every physical dimension such as four sets of nut intercolumniation relative positions and is adjusted, make All sizes meet design requirement;
5)Check and accept, examination of being tested after all Nut column installations of four king-posts, check and accept after completing and carry out Ship lift operation experiments.
Described 1)Transverse pitch uses the ceiling hammer on Nut column central axis between middle deformed bar harness sleeve Method is adjusted longitudinal pitch between control, sleeve pipe and carries out elevation adjustment control using the method for spirit level;With king-post The rise of height is poured, after the completion of each storehouse concreting, measuring goes out center line and elevational point on wall, in order under The installation of one storehouse embedded part and the installation site inspection of upper storehouse embedded part.
Described 2)Middle construction framed bent is set up using steel pipe and fastener, and landing framed bent, elevation 84m are set up in below elevation 84m Suspention framed bent is set up above, often section suspention framed bent is set up elevation and determined according to each embedded part setting height(from bottom), on often section suspention framed bent If windrow platform, suspention framed bent overhauls the lifting of bridge machine using 63t in main equipment room and mounted;Described 2)The second stage of embedded part of middle Nut column is paired Install, after tentatively fixing, steelframe is installed in certain height and hangs piano wire progress installation accuracy control, a phase is utilized during adjustment Dowel welds adjusting bolt or strainer, adjusts its center line and perpendicularity, and the control that elevation is identified according to manufacturing firm is marked Control is adjusted with level meter, after adjustment is checked out, is welded the second stage of embedded part of Nut column and a phase dowel with lapping plate or angle bar Connect reinforcing.
Described 2)Middle Concrete Construction of Powerhouse comprises the following steps, the face processing of fist stage concrete seam:In fist stage concrete table Face artificial chiseling, then use high pressure water washing;Reinforcement installation:Reinforcing bar peace is carried out after the second stage of embedded part installation site is adjusted in place Dress, reinforcement installation is mainly aided with after manual electric arc welding, reinforcement installation using mechanical connection, then the second stage of embedded part of repetition measurement and adjust plus Gu;Model sheetinstallat:Template is reinforced using the pull head or embedded part on fist stage concrete, sets mixed in every 2m-3m of vertical film Solidifying soil vibrates hole;Second stage concrete is poured:Solidifying soil is poured using a grading concrete, slump 16cm~18cm, using stirring Car horizontal transport concrete, flexible pipe vibrator is vibrated, and concrete is poured using concrete pump and put in storage.
Described 3)Middle first section Nut column originates elevation in the good bracket of bottom welding, pallet top elevation when installing than Nut column Low 10 ~ 20mm, is easy to carry out elevation adjustment using jack;When Nut column bracket is installed, it is thick that carriage width is not more than Nut column Degree, the specific installation site of bracket is determined according to the embedded datum mark position in scene.
Described 4.6)Middle upstream and downstream Nut column depth displacement is 225mm, advanced using total powerstation when carrying out Nut column installation Side Nut column elevation adjustment positioning of the row with 3150mm mark lines, on the basis of its elevation, carries out corresponding opposite side spiral shell Female pillar height journey adjustment, using two pieces of finishing standard cushion blocks during adjustment, coordinates frame level and clearance gauge to carry out elevation tune Whole control;The cushion block includes cushion block one and cushion block two, the length and width and height respectively 300 of the cushion block one, 50,225mm;Pad The length and width and height respectively 1500 of block two, 50,50mm, two cushion block surface roughnesses are Ra1.6, depth of parallelism 0.02mm;
Described 4.6)Middle upstream and downstream Nut column range difference is 1142mm, when carrying out Nut column installation, utilizes inside micrometer Slide measure is coordinated to carry out two panels Nut column respective distances difference 1142mm measurement adjustment controls;
Described 4.6)The middle a diameter of 1365mm of inner circle, double 90 ° of guide pass angles measure adjustment when measuring adjustment Upstream and downstream two panels Nut column X, Y-axis line axiality, the depth of parallelism, perpendicularity and four angular separation 1142mm, make upstream and downstream two panels spiral shell The corresponding every deviation of female post ensures trend in the same direction and controlled in design requirement, it is ensured that interior circular diameter 1365mm and double guide pass 90 ° of deviations of angle meet design requirement.
Described 4)It is middle needed in the Nut column installation process of first section each of the above section in internode mounting and adjusting dividing plate, use Dividing plate just precise control, is portrayed line and measured Nut column internode is reserved, will measured with slide measure during installation to producer As a result fabrication data is contrasted in the factory provided with producer, and spacing is consistent with the fabrication data in factory between envoy, so as to meet Adjacent nut post internode pitch limit deviation reaches 450 ± 0.5mm requirement;Two save Nut column after Nut column gaps are adjusted Positioning, the dividing plate between saving up and down should be with Nut column end face tightening, and the filler for then carrying out internode gap according to design requirement is filled out Fill.
Monitoring is changed to guide-rail plate using dial gauge in the filling process, when monitoring data is varied widely, More than 0.2mm, filling process is temporarily interrupted, site inspection, processing is carried out, grouting is proceeded after completion processing;Filling speed Can not be too fast, and want uniform and stable.
The deformed bar tensioning is carried out by the order of design drawing requirement, each deformed bar and high-strength bolt Prestressing force applies in two times:Defined order applying portion pretightning force and in order pretension are pressed for the first time, treat same section nut The whole deformed bars and high-strength bolt of post are completed after first time pretension, are carried out second of pretension again by design requirement, are made Whole deformed bars of installed Nut column and the pretightning force of high-strength bolt reach respective setting value;After the completion of tensioning, press Seal treatment is carried out using steel bowl and anti-corrosive mixture at the two ends of deformed bar according to installation requirement, deformed bar is exposed Part carries out sealing protection using glass fiber aluminium sheet.
Using nut column system installation accuracy control method is carried out during above-mentioned construction method, it comprises the following steps:
1)After Nut column is installed in place, steelframe is installed in Nut column certain altitude and hangs piano wire, it is accurate to survey four steel of inspection The position of qin line, the straight line and Nut column cross central line for making at wherein 3 points is precisely coincident, and piano wire position deviation should be controlled In the range of ± 0.5mm, after piano wire has been checked, piano wire should be checked simultaneously and relative between mounted rack central line Site error;
2)When Nut column is adjusted, upstream and downstream direction center is adjusted with M30 screw rods, and left and right side direction is buried in Nut column Weldering adjustment support is adjusted with jack on part;
3)After the completion of Nut column adjustment, deformed bar and high-strength bolt are penetrated, and carries out just twisting in order, after just twisting Inspection adjustment is carried out again, and after four groups of Nut column first segment installations, the relative position of four groups of Nut columns is checked through accurate measurement Deviation and its relative position deviation with tooth bar, and be adjusted until meeting installation accuracy requirement, after acceptance(check), Fang Kejin Row PAGEL V1/50 mortar is irrigated, and after the perfusion of PAGEL V1/50 mortar is finished, then carries out repetition measurement, after repetition measurement is complete, carries out diameter Repetition measurement is carried out again after 32mm deformed bar tensioning, checks whether it is subjected to displacement;
4)Adjusting nut on the basis of the control mark identified when first segment Nut column is adjusted by first segment tooth bar manufacturing firm The control of Zhu Shang manufacturing firms mark marks contour, its error≤1mm, and respectively an adjacent pitch controls 450mm dimensional discrepancys successively ≤ 0.5mm, bridging head arbitrarily 7 pitch 3150mm dimensional discrepancys≤0.5mm of measurement, when hereafter often section is installed, with first segment On the basis of be adjusted, often save the joint adjustment internode of Nut column away from when should strictly control its pitch, often save elevation direction and exist Internode is adjusted using taper liner, after adjustment examination is finished, on request welding point cushion block, four groups of Nut column group installations Afterwards, its perpendicularity, Nut column cope level are checked, the mutual parallelism tolerance of four groups of Nut columns answers≤5mm;
5)Often section Nut column mounting and adjusting finish after, it is qualified by inspection after start PAGEL V1/50 mortar perfusion, Nut column It is 14cm with embedded part space, Nut column two ends are using sizing punching block sealing, and template is solid to drawing using a diameter of 16mm tie rods in both sides It is fixed;According to the characteristic of PAGEL V1/50 plaster materials, each influx height is that a Nut column installs section, i.e. 4.95m, grouting Pressure is 0.3MPa, and the water and air in slurry discharge pipe line is used before grouting, it is ensured that whole pipeline does not mix air, pours into Cheng Zhong, injection rate is 15L/min, and pressure limit is 0.3MPa, and filling process tries one's best holding continuously, occurs without improper interruption, After grout outlet emerges slurries, 5~10min of slurry is closed using 0.3MPa grouting pressure, makes slurries more closely knit, uniform.
The method have the advantages that:
1st, by the way that deformed bar harness sleeve is used into spot-welded in mounting bracket, integral installation and adjustment, effectively Ensure that sleeve pipe occurs without deformation or damaged in installation and process of vibrating, so as to ensure energy during Nut column subsequent installation It is enough smoothly to pass through deformed bar, while ensure that the concentricity of sleeve pipe and Nut column both sides deformed bar hole, improve The precision that follow-up Nut column is installed.
2nd, the second stage of embedded part of Nut column is constructed again after the completion of the fist stage concrete of king-post civil engineering, treats that the second stage of embedded part is whole After the completion of construction, from bottom to top, merogenesis carries out the installation of Nut column, grouting again, finally carries out Nut column prestressed stretch-draw, can It is effective to reduce the influence that the king-post deformation of creep is installed to Nut column, it is ensured that Nut column installation quality and installation accuracy.
3rd, by the embedded angle steel in relevant position and dowel in the storehouse of fist stage concrete, a phase in next storehouse can be easy to bury The fixation of part, by the installation, adjustment, reinforcing that also allow for the second stage of embedded part of Nut column.
4th, by being installed a phase embedded part according to design cell merogenesis, adjusting and reinforce, while as king-post pours height Rise, to Nut column center line and the school survey again of each vertical control point, is easy to the installation and inspection of embedded part, effectively prevents embedded part With the rise at position, cumulative errors are excessive for installation.
5th, after phase embedded part adjustment is completed, reinforced by using angle steel, it is ensured that in casting concrete, Embedded part, cannula center is not subjected to displacement.
6th, during Nut column adjustment is carried out, while controlling adjustment upstream and downstream Nut column depth displacement, upstream and downstream nut Post range difference, interior circular diameter and double guide pass angles are 90 ° of installation accuracies for improving Nut column and mounted in pairing mode quality.
7th, Nut column second phase adjustment complete and it is qualified by inspection after, penetrate diameter 63.5mm connecting tubes and diameter 52mm steel Pipe, diameter 52mm steel pipes are adjusted to installation center elevation location and make to fix after its holding level, then by the Nut column second phase Embedded part and the firm reinforcing of pre-buried iron plate, are subjected to displacement when effectively can prevent from pouring second stage concrete.
9th, first tentatively tightened, made every with 8 groups of M30 high intensity connecting bolts in deformed bar stretching process is carried out The stress of group bolt reaches 150kN, then penetrates 12 φ 32mm deformed bars, and deformed bar is opened in order Draw, its stress is reached 200kN, and carry out tensioning or pretension simultaneously, unload simultaneously, make Nut column uniform stressed, can be effective Improve Nut column installation accuracy and installation quality.When preventing deformed bar tensioning simultaneously, Nut column, which produces to turn over, to be stuck up.
10th, by nut column system installation accuracy control method, the installation quality and peace of Nut column can effectively be improved Precision is filled, so that the smooth development of whole ship lift project is ensure that, while improving the quality of ship elevator engineering, it is ensured that rise Ship machine service life and the security using process.
Brief description of the drawings
The invention will be further described with reference to the accompanying drawings and examples.
Fig. 1 is four sets of Nut column integral installation arrangement top views of ship lift of the present invention.
In figure:Fist stage concrete 1, deformed bar harness sleeve 2, second stage concrete 3, the second stage of embedded part 4, deformed bar 5, Number left Nut column 6, right Nut column 7, PAGEL V1/50 mortar 8, No. two left Nut columns 9, a No. two right Nut columns 10, three Number left Nut column 11, No. three right Nut columns 12, No. four left Nut columns 13, No. four right Nut columns 14, tooth bar 15, No. two tooth bars 16th, No. three tooth bars 17, No. four tooth bars 18.
Fig. 2 is the single set Nut column arrangement top view of the present invention and installation site datum mark.
In figure:A、B、C、D、E、F:Respectively Nut column base point of installation.
Fig. 3 is hanger front view in Nut column installation process of the present invention.
Fig. 4 is the section B-B figure of hanger in Fig. 3 in Nut column installation process of the present invention.
In figure:Connecting plate 19, reinforcing plate 20, shackle plate 21.
Fig. 5 is the left and right installation site adjustment structural representation of Nut column of the present invention.
In figure:Jack up hanging basket 22, adjustment support 23, left jack 24, right jack 25.
Fig. 6 is that a pair of Nut columns elevation installation site of the invention adjusts structural representation.
In figure:Lower height adjustment frock 26, adjusting screw rod 27, upper height adjustment frock 28, standard cushion block 29.
Embodiment
Embodiments of the present invention are described further below in conjunction with the accompanying drawings.
Referring to Fig. 1, it is four sets of Nut column integral installation arrangement top views of ship lift of the present invention, first carries out fist stage concrete 1 construction casting, then pouring for second stage concrete 3 and the second stage of embedded part 4 is carried out, finally carry out left Nut column 6, a right spiral shell The installation of female post 7, and Nut column progress tensioning is fixed using deformed bar 5, in a left Nut column 6, a right nut Gap between post 7 and second stage concrete 3 is filled connection using PAGEL V1/50 mortar 8, and ship lift includes four sets of nuts Column system, often covers nut column system and is required, it is necessary to meet corresponding positional precision control, so as to ensure the normal reliable of ship lift Operation, is a tooth bar 15, No. two tooth bars 16, No. three tooth bars 17 and No. four tooth bars 18 also including four sets of rack systems, is installing During need to ensure often to cover installation site between nut column system and four sets of rack systems and installation accuracy control requirement, enter And meet and being smoothed out for whole ship lift project is installed.
Referring to Fig. 2, after Nut column is installed in place, steelframe is installed in Nut column certain altitude and hangs piano wire, Nut column steel Qin line hangs A, B, C, D, E, F that position is seen in Fig. 2, the accurate position for surveying inspection piano wire, makes 3 points of B, C, D straight line and nut Post cross central line is precisely coincident, and piano wire position deviation should be controlled in the range of ± 0.5mm., should after piano wire has been checked Piano wire and the relative position error between mounted rack central line, and in this, as the control that Nut column is adjusted are checked simultaneously Standard processed.
Referring to Fig. 3-4, it is necessary to use Nut column hanger in Nut column installation process is carried out, hanger includes connecting plate 19, Two shackle plates 21 are installed, the side of shackle plate 21 is welded with reinforcing plate 20, by the way that this hanger is installed on connecting plate 19 Nut top end, so that convenient lifted by the way of lifting to it.
Referring to Fig. 5, when carrying out the left and right directions installation site adjustment of Nut column, it is necessary in the both sides point of adjustment support 23 Left jack 24, right jack 25 are not installed, and then its installation site is adjusted.
It is a pair of Nut columns elevation installation site adjustment of the invention, due to there is height between opposing nut post referring to Fig. 6 Difference, be respectively mounted in the both sides up and down of a left Nut column 6 lower height adjustment frock 26, adjusting screw rod 27, on highly adjust work 28, standard cushion block 29 is filled, the height for adjusting a left Nut column 6 by height adjustment frock makes the height that it meets standard cushion block Difference, and then realize a pair of Nut column elevation installation site adjustment.
Referring to Fig. 1-6, high-lift tooth climbs formula ship lift Nut column system construction method, comprises the following steps:
High-lift tooth climbs formula ship lift Nut column system construction method, comprises the following steps:
1)Fist stage concrete and phase embedded part construction:One phase of Nut column embedded part includes mounting bracket and deformed bar collar Pipe, completes designing and producing for mounting bracket by concreting unit in factory, deformed bar harness sleeve is welded using spot welding It is connected in mounting bracket;Lifted using wall-attachment tower crane, during in-site installation, in construction part relevant position measuring elevational point and spiral shell Female one phase of post embedded part installation center line, installation center, elevation and the seamless steel pipe horizontal level of one phase of adjusting nut post embedded part;One Phase embedded part is installed after the completion of positioning, then carries out reinforcing bar colligation;It is last to add according to phase embedded part design cell merogenesis installation, adjustment Gu, and poured, wherein angle steel is buried in relevant position in storehouse, and the relevant position installed in Nut column sets dowel, most Pouring for whole fist stage concrete king-post is completed eventually;
2)Second stage concrete and the second stage of embedded part construction:Nut column second phase embedded part construction, Nut column second phase embedded part is mixed in a phase Solidifying soil, which is poured to 196m, starts construction, treats that king-post pours completion, while carrying out Second Construction after completing own vol deformation, first The surveying setting-out on king-post, then erection construction framed bent;The second stage of embedded part is to connect I steel composite by many root beads to form, first segment nut Before post second phase embedded part is installed, steel construction is installed in the second stage of embedded part bottom, measured after top of steel elevation, and is put down on steel construction Face adds adjustment cushion block, its cope level is slightly below the Bottom Altitude of Nut column embedded part, after the embedded part lifting in place of Nut column second phase, The dowel that one phase was buried and the second stage of embedded part spot welding, tentatively fix, and are finally completed the installation of whole the second stage of embedded part;Second phase buries After part installation, a connecting tube and steel pipe are penetrated in the deformed bar harness sleeve of a phase embedded part, steel pipe is adjusted To installation center elevation location, and make to fix after its holding level, then by the firm reinforcing of the second stage of embedded part and pre-buried iron plate, finally Complete the pouring construction of second stage concrete;
3)Nut column installs preparation:Before Nut column lifting, the construction platform at erection construction position and top peace Full protection platform, arrangement measurement net, it is ensured that various putting up platform meet construction needs;The corresponding the second stage of embedded part of Nut column will often be saved Terraced flank of tooth surface mortar and other debris are cleaned out, and back is corresponded at the floor layer, groove inner concrete, reinforcing bar of PVC sleeve pipes Cleared up;The quality testing of Nut column is carried out according to design and code requirement, one tower body position of Nut column correspondence is often covered and enters Row is installed;The face that contacted with each other between having installed section, section two to be installed successively is cleared up before Nut column lifting;Section top has been installed Elevation, steel diaphragm elevation and levelness are detected and recorded, analyzed, it is ensured that cope level can meet section Nut column to be installed Elevation installation specification;First section Nut column bracket is finally carried out to install;
4)Nut column is installed:
4.1)Nut column is transported and lifted, and Nut column is lifted on flat car using truck crane and transports ship railway carriage or compartment room base plate Correspondence installation site is put.
4.2)Nut column is lifted using special hanger, suspender tightens high-strength company between suspender and component lifting hole(eyelet) when installing Connecting bolt, Nut column is lifted near installation site, and Nut column is furthered to installation position with guide chain, then connection adjustment spiral shell Tooth bar and the second stage of embedded part, are tentatively connected, 16T press branch are used on bottom bracket by bar using internode adjusting bolt Support, after the completion of carry out tear hook open.
4.3)In every Nut column left and right banks both sides welding adjustment frock, Nut column is subjected to Primary Location and adjustment;
4.4)After Nut column lifting is in place, at top, welding coil holder measures cultellation, utilizes angle square, Steel Ruler, piano Line hangs again vertical method, on the basis of the corresponding coordinate value of every vertical line, and adjusting nut post is controlled according to every technical requirements Mileage, center, elevation, perpendicularity, depth of parallelism etc. control size, carry out just successive step simultaneously to upstream and downstream two panels Nut column;
4.5)After the completion of first successive step, Nut column accurate adjustment is carried out according to the every installation specification of Nut column with total powerstation, Nut column installation site and the adjacent tooth bar installation site installed are positioning datum during adjustment.
4.6)Installation personnel carries out upstream and downstream Nut column range difference and upstream and downstream depth displacement using in-process measurement utensil, interior The 90 ° of control adjustment of circular diameter and double guide pass angles are checked and accepted.
4.6)After Nut column is accurately adjusted in place, jack is adjusted on locking fixture, regulating bolt is tightened and completes reinforcing, Nut column installation site deviation is monitored using vertical line in reinforcing process, such as varies widely, stops in reinforcing process Only reinforce and readjusted.
4.7)Accurate adjustment in place, reinforce complete and measure after acceptance(check), by deformed bar installation site two ends hole profit Carry out sealing blocking with cotton, be then transferred to gap formwork erection process, formwork erection complete and by filling water test after, by deformed bar Installation site two ends hole sealer is taken out, after moisture in pipe is drained, and prestressing force is carried out from Nut column back by workmen Reinforcement installation.
4.8)Carry out needing that Nut column installation site is carried out to check examination before cementing operations, grouting after the completion of formwork erection, it is qualified After can carry out carrying out deformation monitoring with dial gauge in gap grouting, filling process.
4.9)After gap grouting is completed 14 days, deformed bar is installed from Nut column back, deformed bar Pretightning force apply overleaf carry out, the installation of high-strength bolt is then installed before each bolt tensioning, according to tension sequence The adjusting screw rod of corresponding position is removed and installed after high-strength bolt, stretching construction is carried out.
4.10)It is positioning datum with the final check and acceptance result of Nut column for completing to install first, carries out remaining 3 tower body nuts The installation of post, according to positioning datum during installation, carries out every physical dimension such as four sets of nut intercolumniation relative positions and is adjusted, make All sizes meet design requirement.
4.11)It is positioning datum with the final check and acceptance result of Nut column for completing to install first, carries out remaining 3 tower body nuts The installation of post, according to positioning datum during installation, carries out every physical dimension such as four sets of nut intercolumniation relative positions and is adjusted, make All sizes meet design requirement;
5)Check and accept, examination of being tested after all Nut column installations of four king-posts, check and accept after completing and carry out Ship lift operation experiments.
Described 1)Transverse pitch uses the ceiling hammer on Nut column central axis between middle deformed bar harness sleeve Method is adjusted longitudinal pitch between control, sleeve pipe and carries out elevation adjustment control using the method for spirit level;With king-post The rise of height is poured, after the completion of each storehouse concreting, measuring goes out center line and elevational point on wall, in order under The installation of one storehouse embedded part and the installation site inspection of upper storehouse embedded part.
Described 2)Middle construction framed bent is set up using steel pipe and fastener, and landing framed bent, elevation 84m are set up in below elevation 84m Suspention framed bent is set up above, often section suspention framed bent is set up elevation and determined according to each embedded part setting height(from bottom), on often section suspention framed bent If windrow platform, suspention framed bent overhauls the lifting of bridge machine using 63t in main equipment room and mounted;Described 2)The second stage of embedded part of middle Nut column is paired Install, after tentatively fixing, steelframe is installed in certain height and hangs piano wire progress installation accuracy control, a phase is utilized during adjustment Dowel welds adjusting bolt or strainer, adjusts its center line and perpendicularity, and the control that elevation is identified according to manufacturing firm is marked Control is adjusted with level meter, after adjustment is checked out, is welded the second stage of embedded part of Nut column and a phase dowel with lapping plate or angle bar Connect reinforcing.
Described 2)Middle Concrete Construction of Powerhouse comprises the following steps, the face processing of fist stage concrete seam:In fist stage concrete table Face artificial chiseling, then use high pressure water washing;Reinforcement installation:Reinforcing bar peace is carried out after the second stage of embedded part installation site is adjusted in place Dress, reinforcement installation is mainly aided with after manual electric arc welding, reinforcement installation using mechanical connection, then the second stage of embedded part of repetition measurement and adjust plus Gu;Model sheetinstallat:Template is reinforced using the pull head or embedded part on fist stage concrete, sets mixed in every 2m-3m of vertical film Solidifying soil vibrates hole;Second stage concrete is poured:Solidifying soil is poured using a grading concrete, slump 16cm~18cm, using stirring Car horizontal transport concrete, flexible pipe vibrator is vibrated, and concrete is poured using concrete pump and put in storage.
Described 3)Middle first section Nut column originates elevation in the good bracket of bottom welding, pallet top elevation when installing than Nut column Low 10 ~ 20mm, is easy to carry out elevation adjustment using jack;When Nut column bracket is installed, it is thick that carriage width is not more than Nut column Degree, the specific installation site of bracket is determined according to the embedded datum mark position in scene.
Described 4.6)Middle upstream and downstream Nut column depth displacement is 225mm, advanced using total powerstation when carrying out Nut column installation Side Nut column elevation adjustment positioning of the row with 3150mm mark lines, on the basis of its elevation, carries out corresponding opposite side spiral shell Female pillar height journey adjustment, using two pieces of finishing standard cushion blocks during adjustment, coordinates frame level and clearance gauge to carry out elevation tune Whole control;The cushion block includes cushion block one and cushion block two, the length and width and height respectively 300 of the cushion block one, 50,225mm;Pad The length and width and height respectively 1500 of block two, 50,50mm, two cushion block surface roughnesses are Ra1.6, depth of parallelism 0.02mm;
Described 4.6)Middle upstream and downstream Nut column range difference is 1142mm, when carrying out Nut column installation, utilizes inside micrometer Slide measure is coordinated to carry out two panels Nut column respective distances difference 1142mm measurement adjustment controls;
Described 4.6)The middle a diameter of 1365mm of inner circle, double 90 ° of guide pass angles measure adjustment when measuring adjustment Upstream and downstream two panels Nut column X, Y-axis line axiality, the depth of parallelism, perpendicularity and four angular separation 1142mm, make upstream and downstream two panels spiral shell The corresponding every deviation of female post ensures trend in the same direction and controlled in design requirement, it is ensured that interior circular diameter 1365mm and double guide pass 90 ° of deviations of angle meet design requirement.
Described 4)It is middle needed in the Nut column installation process of first section each of the above section in internode mounting and adjusting dividing plate, use Dividing plate just precise control, is portrayed line and measured Nut column internode is reserved, will measured with slide measure during installation to producer As a result fabrication data is contrasted in the factory provided with producer, and spacing is consistent with the fabrication data in factory between envoy, so as to meet Adjacent nut post internode pitch limit deviation reaches 450 ± 0.5mm requirement;Two save Nut column after Nut column gaps are adjusted Positioning, the dividing plate between saving up and down should be with Nut column end face tightening, and the filler for then carrying out internode gap according to design requirement is filled out Fill.
Monitoring is changed to guide-rail plate using dial gauge in the filling process, when monitoring data is varied widely, More than 0.2mm, filling process is temporarily interrupted, site inspection, processing is carried out, grouting is proceeded after completion processing;Filling speed Can not be too fast, and want uniform and stable.
The deformed bar tensioning is carried out by the order of design drawing requirement, each deformed bar and high-strength bolt Prestressing force applies in two times:Defined order applying portion pretightning force and in order pretension are pressed for the first time, treat same section nut The whole deformed bars and high-strength bolt of post are completed after first time pretension, are carried out second of pretension again by design requirement, are made Whole deformed bars of installed Nut column and the pretightning force of high-strength bolt reach respective setting value;After the completion of tensioning, press Seal treatment is carried out using steel bowl and anti-corrosive mixture at the two ends of deformed bar according to installation requirement, deformed bar is exposed Part carries out sealing protection using glass fiber aluminium sheet.
Using nut column system installation accuracy control method is carried out during above-mentioned construction method, it comprises the following steps:
1)After Nut column is installed in place, steelframe is installed in Nut column certain altitude and hangs piano wire, it is accurate to survey four steel of inspection The position of qin line, the straight line and Nut column cross central line for making at wherein 3 points is precisely coincident, and piano wire position deviation should be controlled In the range of ± 0.5mm, after piano wire has been checked, piano wire should be checked simultaneously and relative between mounted rack central line Site error;
2)When Nut column is adjusted, upstream and downstream direction center is adjusted with M30 screw rods, and left and right side direction is buried in Nut column Weldering adjustment support is adjusted with jack on part;
3)After the completion of Nut column adjustment, deformed bar and high-strength bolt are penetrated, and carries out just twisting in order, after just twisting Inspection adjustment is carried out again, and after four groups of Nut column first segment installations, the relative position of four groups of Nut columns is checked through accurate measurement Deviation and its relative position deviation with tooth bar, and be adjusted until meeting installation accuracy requirement, after acceptance(check), Fang Kejin Row PAGEL V1/50 mortar is irrigated, and after the perfusion of PAGEL V1/50 mortar is finished, then carries out repetition measurement, after repetition measurement is complete, carries out diameter Repetition measurement is carried out again after 32mm deformed bar tensioning, checks whether it is subjected to displacement;
4)Adjusting nut on the basis of the control mark identified when first segment Nut column is adjusted by first segment tooth bar manufacturing firm The control of Zhu Shang manufacturing firms mark marks contour, its error≤1mm, and respectively an adjacent pitch controls 450mm dimensional discrepancys successively ≤ 0.5mm, bridging head arbitrarily 7 pitch 3150mm dimensional discrepancys≤0.5mm of measurement, when hereafter often section is installed, with first segment On the basis of be adjusted, often save the joint adjustment internode of Nut column away from when should strictly control its pitch, often save elevation direction and exist Internode is adjusted using taper liner, after adjustment examination is finished, on request welding point cushion block, four groups of Nut column group installations Afterwards, its perpendicularity, Nut column cope level are checked, the mutual parallelism tolerance of four groups of Nut columns answers≤5mm;
5)Often section Nut column mounting and adjusting finish after, it is qualified by inspection after start PAGEL V1/50 mortar perfusion, Nut column It is 14cm with embedded part space, Nut column two ends are using sizing punching block sealing, and template is solid to drawing using a diameter of 16mm tie rods in both sides It is fixed;According to the characteristic of PAGEL V1/50 plaster materials, each influx height is that a Nut column installs section, i.e. 4.95m, grouting Pressure is 0.3MPa, and the water and air in slurry discharge pipe line is used before grouting, it is ensured that whole pipeline does not mix air, pours into Cheng Zhong, injection rate is 15L/min, and pressure limit is 0.3MPa, and filling process tries one's best holding continuously, occurs without improper interruption, After grout outlet emerges slurries, 5~10min of slurry is closed using 0.3MPa grouting pressure, makes slurries more closely knit, uniform;
High-lift tooth climbs formula ship lift nut column system installation accuracy control method, and installation accuracy control index mainly has:
A. nut mast axis to adjacent rack symmetrical center line fore-and-aft distance tolerance:±2mm;
B. nut mast axis to the axis of ship railway carriage or compartment room 7 apart from tolerance:±12mm;
C. nut mast axis to ship railway carriage or compartment room F axis apart from tolerance:±7mm;
D. squareness tolerance of the Nut column cross central line relative to ship railway carriage or compartment room longitudinal centre line:5mm;
E. Nut column axis verticality tolerance:5mm;
F. the squareness tolerance of the Nut column longitudinal center plane of symmetry:5mm;
G. parallelism tolerance of the Nut column longitudinal center symmetrical plane relative to the reverse guide pass of tooth bar:5mm;
H. Nut column transverse center plane of symmetry squareness tolerance:5mm;
I. Nut column guide pass linearity tolerance:2/3000(It is not more than 2mm in any 3m length ranges);
J. the altitude location mark on Nut column is relative to the discrepancy in elevation that the altitude location on same elevation tooth bar is marked:± 2mm;
K. it is same section Nut column two panels nut thread tip circle cylinder bus parallelism tolerance:0.5mm;
L. it is same section Nut column two panels nut guide pass parallelism tolerance:0.2mm;
M. it is same section Nut column two panels nut thread tip circle cylinder diameter tolerance:±0.5mm;
N. the distance between two panels Nut column top surface and bottom surface tolerance is 0.2mm;
O. two section Nut columns between thread pitch tolerance:0.5mm;
P. it is first to save Nut column bottom indicia height and position deviation:±2mm;
Q. it is first to save Nut column bottom indicia and adjacent most coxopodite tooth bar bottom indicia height variation:≤0.5mm;
R. the Nut column number of altitude is relative to same elevation tooth bar altitude location mark position deviation:±2mm;
S. 4 head save the relative deviation of Nut column bottom indicia elevation:2mm;
T. the terraced tooth in back and the terraced backlash in the second stage of embedded part back:≥20mm.

Claims (9)

1. high-lift tooth climbs formula ship lift Nut column system construction method, it is characterised in that comprise the following steps:
1)Fist stage concrete and phase embedded part construction:One phase of Nut column embedded part includes mounting bracket and deformed bar harness sleeve, Designing and producing for mounting bracket is completed by concreting unit in factory, deformed bar harness sleeve is existed using spot-welded In mounting bracket;Lifted using wall-attachment tower crane, during in-site installation, in construction part relevant position measuring elevational point and Nut column One phase embedded part installation center line, installation center, elevation and the seamless steel pipe horizontal level of one phase of adjusting nut post embedded part;One phase buried Part is installed after the completion of positioning, then carries out reinforcing bar colligation;It is last to be installed according to a phase embedded part design cell merogenesis, adjust and reinforce, and Poured, wherein angle steel is buried in relevant position in storehouse, and the relevant position installed in Nut column sets dowel, is finally completed Whole fist stage concrete king-post is poured;
2)Second stage concrete and the second stage of embedded part construction:The embedded part construction of Nut column second phase, the Nut column second phase, embedded part was in fist stage concrete Pour to 196m and start construction, treat that king-post pours completion, while Second Construction is carried out after completing own vol deformation, first in tower Surveying setting-out on post, then erection construction framed bent;The second stage of embedded part is to connect I steel composite by many root beads to form, first segment Nut column two Before phase embedded part is installed, steel construction is installed in the second stage of embedded part bottom, measured after top of steel elevation, and plane adds on steel construction Cushion block is adjusted, its cope level is slightly below the Bottom Altitude of Nut column embedded part, after the embedded part lifting in place of Nut column second phase, by one Phase embedded dowel and the second stage of embedded part spot welding, tentatively fix, are finally completed the installation of whole the second stage of embedded part;The second stage of embedded part peace After installing into, a connecting tube and steel pipe are penetrated in the deformed bar harness sleeve of a phase embedded part, steel pipe is adjusted to peace Dress center elevation location, and make to fix after its holding level, then by the firm reinforcing of the second stage of embedded part and pre-buried iron plate, finally complete The pouring construction of second stage concrete;
3)Nut column installs preparation:Before Nut column lifting, the construction platform and safety top at erection construction position are prevented Protect platform, arrangement measurement net, it is ensured that various putting up platform meet construction needs;The terraced tooth of the corresponding the second stage of embedded part of Nut column will often be saved Face surface mortar and other debris are cleaned out, and are carried out at floor layer, groove inner concrete and the reinforcing bar of back correspondence PVC sleeve pipes Cleaning;The quality testing of Nut column is carried out according to design and code requirement, one tower body position of Nut column correspondence is often covered and is pacified Dress;The face that contacted with each other between having installed section, section two to be installed successively is cleared up before Nut column lifting;Section top is installed high Journey, steel diaphragm elevation and levelness are detected and recorded, analyzed, it is ensured that cope level can meet section nut pillar height to be installed Journey installation specification;First section Nut column bracket is finally carried out to install;
4)Nut column is installed:
4.1)Nut column is transported and lifted, and Nut column is lifted on flat car using truck crane and transports ship railway carriage or compartment room base plate correspondence Installation site is put;
4.2)Nut column is lifted using special hanger, suspender tightens high strong ties spiral shell between suspender and component lifting hole(eyelet) when installing Bolt, Nut column is lifted near installation site, and Nut column is furthered to installation position with guide chain, then connects adjusting bolt, Tooth bar and the second stage of embedded part are tentatively connected using internode adjusting bolt, supported on bottom bracket with 16T press, it is complete Carrying out tearing hook open after;
4.3)In every Nut column left and right banks both sides welding adjustment frock, Nut column is subjected to Primary Location and adjustment;
4.4)After Nut column lifting is in place, at top, welding coil holder measures cultellation, is hung using angle square, Steel Ruler, piano wire Vertical method again, on the basis of the corresponding coordinate value of every vertical line, according to every technical requirements control adjusting nut post mileage, Center, elevation, perpendicularity and depth of parallelism control size, just successive step is carried out to upstream and downstream two panels Nut column simultaneously;
4.5)After the completion of first successive step, Nut column accurate adjustment is carried out according to the every installation specification of Nut column with total powerstation, adjusted During Nut column installation site and the adjacent tooth bar installation site installed be positioning datum;
4.6)Installation personnel carries out upstream and downstream Nut column range difference using in-process measurement utensil and upstream and downstream depth displacement, inner circle are straight The 90 ° of control adjustment in footpath and double guide pass angles are checked and accepted;
4.6)After Nut column is accurately adjusted in place, jack is adjusted on locking fixture, regulating bolt is tightened and completes reinforcing, reinforce During Nut column installation site deviation is monitored using vertical line, such as varied widely in reinforcing process, stop plus Gu readjusted;
4.7)Accurate adjustment in place, reinforce complete and measure after acceptance(check), deformed bar installation site two ends hole is utilized into cotton Cloth carries out sealing blocking, is then transferred to gap formwork erection process, formwork erection complete and by filling water test after, deformed bar is installed Position two ends hole sealer is taken out, after moisture in pipe is drained, and deformed bar is carried out from Nut column back by workmen Install;
4.8)Carry out needing that Nut column installation site is carried out to check examination, qualified rear before cementing operations, grouting after the completion of formwork erection It can carry out carrying out deformation monitoring with dial gauge in gap grouting, filling process;
4.9)Gap grouting complete 14 days after, deformed bar is installed from Nut column back, deformed bar it is pre- Clamp force, which applies, overleaf to be carried out, and the installation of high-strength bolt is then installed before each bolt tensioning, will be right according to tension sequence Answer the adjusting screw rod at position to remove to install after high-strength bolt, carry out stretching construction;
4.10)It is positioning datum with the final check and acceptance result of Nut column for completing to install first, carries out remaining 3 tower body Nut columns Install, according to positioning datum during installation, the every physical dimension for carrying out four sets of nut intercolumniation relative positions is adjusted, and makes to own Size meets design requirement;
5)Check and accept, examination of being tested after all Nut column installations of four king-posts, check and accept after completing and carry out rising ship Machine operation experiments.
2. high-lift tooth according to claim 1 climbs formula ship lift Nut column system construction method, it is characterised in that described 1)Transverse pitch uses the method for ceiling hammer on Nut column central axis to be adjusted between middle deformed bar harness sleeve Longitudinal pitch carries out elevation adjustment control using the method for spirit level between control, sleeve pipe;As king-post pours the liter of height Height, after the completion of each storehouse concreting, measuring goes out center line and elevational point on wall, in order to the peace of next storehouse embedded part The installation site inspection of dress and upper storehouse embedded part.
3. high-lift tooth according to claim 1 climbs formula ship lift Nut column system construction method, it is characterised in that described 2)Middle construction framed bent is set up using steel pipe and fastener, sets up landing framed bent in below elevation 84m, more than elevation 84m sets up suspention Framed bent, often section suspention framed bent is set up elevation and determined according to each embedded part setting height(from bottom), sets windrow platform on often section suspention framed bent, hangs Framed bent is hung to mount using 63t maintenance bridges machine lifting in main equipment room;Described 2)The second stage of embedded part mounted in pairs of middle Nut column, it is preliminary fixed Afterwards, steelframe is installed in certain height and hangs piano wire progress installation accuracy control, adjustment is welded using a phase dowel during adjustment Screw rod or strainer, adjust its center line and perpendicularity, and the control mark that elevation is identified according to manufacturing firm is carried out with level meter Adjustment control, after adjustment is checked out, with lapping plate or angle bar by the second stage of embedded part of Nut column and a phase dowel reinforcement of weld.
4. high-lift tooth according to claim 1 climbs formula ship lift Nut column system construction method, it is characterised in that described 2)Middle Concrete Construction of Powerhouse comprises the following steps, the face processing of fist stage concrete seam:In fist stage concrete surface artificial dabbing, then Use high pressure water washing;Reinforcement installation:Reinforcement installation is carried out after the second stage of embedded part installation site is adjusted in place, reinforcement installation is main It is aided with using mechanical connection after manual electric arc welding, reinforcement installation, then the second stage of embedded part of repetition measurement and adjusts, reinforces;Model sheetinstallat:Utilize Pull head or embedded part on fist stage concrete are reinforced to template, and concrete vibrating hole is set in every 2m-3m of formwork erection;Second phase is mixed Solidifying soil is poured:Solidifying soil is poured using a grading concrete, slump 16cm~18cm, using trucd mixer horizontal transport concrete, Flexible pipe vibrator is vibrated, and concrete is poured using concrete pump and put in storage.
5. high-lift tooth according to claim 1 climbs formula ship lift Nut column system construction method, it is characterised in that described 3)Middle first section Nut column originates the low 10 ~ 20mm of elevation in the good bracket of bottom welding, pallet top elevation when installing than Nut column, just In utilize jack carry out elevation adjustment;When Nut column bracket is installed, carriage width is not more than Nut column thickness, and bracket is specifically pacified Holding position is determined according to the embedded datum mark position in scene.
6. high-lift tooth according to claim 1 climbs formula ship lift Nut column system construction method, it is characterised in that described 4.6)Middle upstream and downstream Nut column depth displacement is 225mm, when carrying out Nut column installation, first carries out carrying 3150mm using total powerstation The side Nut column elevation adjustment positioning of mark line, on the basis of its elevation, carries out corresponding opposite side Nut column elevation adjustment, Using two pieces of finishing standard cushion blocks during adjustment, frame level and clearance gauge is coordinated to carry out elevation adjustment control;The pad Block includes cushion block one and cushion block two, the length and width and height respectively 300 of the cushion block one, 50,225mm;The length and width of cushion block two and Height respectively 1500,50,50mm, two cushion block surface roughnesses are Ra1.6, depth of parallelism 0.02mm;
Described 4.6)Middle upstream and downstream Nut column range difference is 1142mm, when carrying out Nut column installation, is coordinated using inside micrometer Slide measure carries out two panels Nut column respective distances difference 1142mm measurement adjustment controls;
Described 4.6)The middle a diameter of 1365mm of inner circle, double 90 ° of guide pass angles, when measuring adjustment, measurement adjustment is upper and lower Two panels Nut column X, Y-axis line axiality, the depth of parallelism, perpendicularity and four angular separation 1142mm are swum, make upstream and downstream two panels Nut column pair The every deviation answered ensures trend in the same direction and controlled in design requirement, it is ensured that interior circular diameter 1365mm and double guide pass angles 90 ° of deviations meet design requirement.
7. high-lift tooth according to claim 1 climbs formula ship lift Nut column system construction method, it is characterised in that described 4)It is middle needed in the Nut column installation process of first section each of the above section in internode mounting and adjusting dividing plate, it is just accurate with dividing plate Control, is portrayed line and measured Nut column internode is reserved, measurement result is carried with producer with slide measure during installation to producer Fabrication data is contrasted in the factory of confession, and spacing is consistent with the fabrication data in factory between envoy, so as to meet adjacent nut post section Between pitch limit deviation reach 450 ± 0.5mm requirement;Two section Nut column gaps position Nut column after adjusting, and save up and down Between dividing plate should be with Nut column end face tightening, the filler for then carrying out internode gap according to design requirement is filled;
Monitoring is changed to guide-rail plate using dial gauge in the filling process, when monitoring data is varied widely, is more than 0.2mm, temporarily interrupts filling process, carries out site inspection, processing, grouting is proceeded after completion processing;Filling speed can not It is too fast, and want uniform and stable.
8. high-lift tooth according to claim 1 climbs formula ship lift Nut column system construction method, it is characterised in that described Deformed bar tensioning is carried out by the order of design drawing requirement, and the prestressing force of each deformed bar and high-strength bolt divides equally two It is secondary to apply:Defined order applying portion pretightning force and in order pretension are pressed for the first time, treat all answering in advance for same section Nut column Power reinforcing bar and high-strength bolt are completed after first time pretension, are carried out second of pretension again by design requirement, are made installed Nut column Whole deformed bars and the pretightning force of high-strength bolt reach respective setting value;After the completion of tensioning, exist according to installation requirement The two ends of deformed bar carry out Seal treatment using steel bowl and anti-corrosive mixture, and deformed bar exposed parts utilize glass Silk aluminium sheet carries out sealing protection.
9. using nut column system installation accuracy control method is carried out during claim 1-8 construction method, its feature exists In it comprises the following steps:
1)After Nut column is installed in place, steelframe is installed in Nut column certain altitude and hangs piano wire, it is accurate to survey four piano wires of inspection Position, wherein 3 points of straight line is precisely coincident with Nut column cross central line, piano wire position deviation should control ± In the range of 0.5mm, after piano wire has been checked, piano wire and the relative position between mounted rack central line should be checked simultaneously Put error;
2)When Nut column is adjusted, upstream and downstream direction center is adjusted with M30 screw rods, and left and right side direction is on Nut column embedded part Weldering adjustment support is adjusted with jack;
3)After the completion of Nut column adjustment, deformed bar and high-strength bolt are penetrated, and carries out just twisting in order, is entered again after just twisting Row checks adjustment, after four groups of Nut column first segment installations, and the relative position deviation of four groups of Nut columns is checked through accurate measurement With its relative position deviation with tooth bar, and be adjusted until meet installation accuracy requirement, after acceptance(check), can carry out PAGEL V1/50 mortar is irrigated, and after the perfusion of PAGEL V1/50 mortar is finished, then carries out repetition measurement, after repetition measurement is complete, carries out diameter Repetition measurement is carried out again after 32mm deformed bar tensioning, checks whether it is subjected to displacement;
4)On the basis of the control mark identified when first segment Nut column is adjusted by first segment tooth bar manufacturing firm on adjusting nut post The control of manufacturing firm's mark marks contour, its error≤1mm, respectively successively adjacent pitch control 450mm dimensional discrepancys≤ 0.5mm, bridging head arbitrarily measurement 7 pitch 3150mm dimensional discrepancys≤0.5mm, hereafter often section install when, using first segment as Benchmark is adjusted, often save Nut column joint adjustment internode away from when should strictly control its pitch, often save elevation direction section Between be adjusted using taper liner, after adjustment examination is finished, welding point cushion block on request, after four groups of Nut column group installations, Its perpendicularity, Nut column cope level are checked, the mutual parallelism tolerance of four groups of Nut columns answers≤5mm;
5)Often section Nut column mounting and adjusting finish after, it is qualified by inspection after start PAGEL V1/50 mortar perfusion, Nut column is with burying Part space is 14cm, and Nut column two ends are fixed using sizing punching block sealing, template using a diameter of 16mm tie rods in both sides to drawing;Root According to the characteristic of PAGEL V1/50 plaster materials, each influx height is that a Nut column installs section, i.e. 4.95m, and grouting pressure is 0.3MPa, uses the water and air in slurry discharge pipe line before grouting, it is ensured that whole pipeline does not mix air, during pouring into, Injection rate is 15L/min, and pressure limit is 0.3MPa, and filling process tries one's best holding continuously, improper interruption occurred without, in pulp Mouth is emerged after slurries, is closed 5~10min of slurry using 0.3MPa grouting pressure, is made slurries more closely knit, uniform.
CN201610129328.2A 2016-03-08 2016-03-08 High-lift tooth climbs formula ship lift Nut column system construction method and installation accuracy control method Active CN105735227B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610129328.2A CN105735227B (en) 2016-03-08 2016-03-08 High-lift tooth climbs formula ship lift Nut column system construction method and installation accuracy control method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610129328.2A CN105735227B (en) 2016-03-08 2016-03-08 High-lift tooth climbs formula ship lift Nut column system construction method and installation accuracy control method

Publications (2)

Publication Number Publication Date
CN105735227A CN105735227A (en) 2016-07-06
CN105735227B true CN105735227B (en) 2017-07-14

Family

ID=56249222

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610129328.2A Active CN105735227B (en) 2016-03-08 2016-03-08 High-lift tooth climbs formula ship lift Nut column system construction method and installation accuracy control method

Country Status (1)

Country Link
CN (1) CN105735227B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107285230B (en) * 2017-08-10 2019-10-25 中国十七冶集团有限公司 The installation method of RH refining furnace hydraulic lifting guide rail

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102007000241B4 (en) * 2007-04-25 2009-04-16 Ed. Züblin Ag Improved construction for securing system made of columnar parent jaws on vertical reinforced concrete ship lifts
FR2963367B1 (en) * 2010-07-30 2014-01-24 Cie Engrenages Et Reducteurs Messian Durand BOAT ELEVATOR
CN103669314B (en) * 2013-11-29 2015-02-25 葛洲坝集团机电建设有限公司 High-efficiency rack mounting method and auxiliary adjustment device of gear rack climbing type vertical ship lift
CN103696410B (en) * 2013-12-12 2015-10-21 中国葛洲坝集团股份有限公司 Rack-and-pinion climbing type vertical ship lift Nut column Efficient installation method and servicing unit
CN103643667A (en) * 2013-12-23 2014-03-19 中国葛洲坝集团股份有限公司 Ship lift nut column installation auxiliary adjustment method

Also Published As

Publication number Publication date
CN105735227A (en) 2016-07-06

Similar Documents

Publication Publication Date Title
CN108914785B (en) Hanging basket cantilever pouring construction method of multi-chamber corrugated steel web continuous beam bridge
CN102493603B (en) Prefabricated column of reserved concealed column channel, concealed column type complete assembled earthquake-resistant building and its method
CN106120568B (en) The construction method of cross a river Main Bridge bridge pier secondary locking temporary consolidation structure
CN103850363B (en) Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall
CN105040970A (en) Comprehensive gymnasium high formwork support system and construction method of comprehensive gymnasium high formwork support system
CN103981897B (en) A kind of waterproof construction method of outer wall of basement stiffened column
CN109736204B (en) Construction process for prefabricating section beam by adopting short line method
CN101481902A (en) V type pier inclined leg combined type support for continuous rigid frame bridge and layered cast-in-situ construction method
CN1978838A (en) Construction method for combined V-shape steel pipe concrete pile
CN103410269B (en) Prestressing without bondn cast-in-place reinforced concrete hollow slab constructing structure and construction method
CN111894204A (en) Steel pipe concrete composite column construction method
CN114150766A (en) Prefabricated reinforced concrete column connecting joint and construction method thereof
CN104975614B (en) Shaped steel combination formula single side formwork strengthening construction engineering method
CN113202222A (en) Construction method for assembled type superposed beam slab
CN105735228B (en) High-lift tooth climbs formula ship lift rack system construction method and installation accuracy control method
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN106759943A (en) A kind of pre-assembled Anchor Bolts in Steel Column Bases structure
CN103938871A (en) Method for constructing concrete-filled steel tube column and bonded prestressed frame beam structure adopting reinforced concrete ring beam joints
CN105735227B (en) High-lift tooth climbs formula ship lift Nut column system construction method and installation accuracy control method
CN112458905A (en) Splicing adjustment method for prefabricated capping beam and prefabricated stand column
CN202401667U (en) Prefabricated column with reserved embedded column porous channel and embedded column type full-assembly anti-seismic building
CN110374012A (en) A kind of prefabricated engineering method of T beam original position Support Method
CN114059714A (en) Construction process of bonded prestressed beam
CN104453013A (en) Prefabricated wall component and fabricated reinforced concrete shear wall
CN211499464U (en) Steel pipe concrete composite column for high-rise building and reinforcing system thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 100036 No.1 Yuyuantan South Road, Haidian District, Beijing

Patentee after: CHINA THREE GORGES Corp.

Address before: 443002 No. 1, Jianshe Road, Hubei, Yichang

Patentee before: CHINA THREE GORGES Corp.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20211203

Address after: 100036 No.1 Yuyuantan South Road, Haidian District, Beijing

Patentee after: CHINA THREE GORGES Corp.

Patentee after: Three Gorges Technology Co.,Ltd.