CN105735128A - Linear control mold for main arch ring construction - Google Patents

Linear control mold for main arch ring construction Download PDF

Info

Publication number
CN105735128A
CN105735128A CN201410744030.3A CN201410744030A CN105735128A CN 105735128 A CN105735128 A CN 105735128A CN 201410744030 A CN201410744030 A CN 201410744030A CN 105735128 A CN105735128 A CN 105735128A
Authority
CN
China
Prior art keywords
chevron
main
main muscle
arch ring
muscle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410744030.3A
Other languages
Chinese (zh)
Other versions
CN105735128B (en
Inventor
任宗福
苏洪彬
陈琳
邵友建
汤中良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Huanghe Luqiao Engineering Co
Original Assignee
Jinan Huanghe Luqiao Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Huanghe Luqiao Engineering Co filed Critical Jinan Huanghe Luqiao Engineering Co
Priority to CN201410744030.3A priority Critical patent/CN105735128B/en
Publication of CN105735128A publication Critical patent/CN105735128A/en
Application granted granted Critical
Publication of CN105735128B publication Critical patent/CN105735128B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides a linear control mold for main arch ring construction. The mold comprises a top main reinforced bar, a bottom main reinforced bar, multiple first V-shaped parts and multiple second V-shaped parts which are located on the same plane, wherein the top main reinforced bar and the bottom main reinforced bar are made through span and camber bending of a main arch ring; openings of the first V-shaped parts and the second V-shaped parts face the bottom main reinforced bar; in the length direction of the arc area, the first V-shaped parts and the second V-shaped parts are arranged successively and alternately; the tip end of each first V-shaped part is firmly connected to the top main reinforced bar; two opened ends of each first V-shaped part are firmly connected to the bottom main reinforced bar; two opened ends of each second V-shaped part are firmly connected to the bottom main reinforced bar; and two adjacent opened ends which belong to each first V-shaped part and each second V-shaped part respectively coincide with fixed connecting points of the bottom main reinforced bar. The mold is characterized in that the linear control mold of the main arch ring has a stable structure because of triangular stability; the structure has high resistance to deformation; and the problem of difficult linear control of the main arch ring can be solved effectively.

Description

Main arch ring geometric control mould
Technical field
The present invention relates to cast-in-situ steel reinforced concrete arch bridge and main arch ring technical field of construction, is specifically related to a kind of main arch ring outward appearance alignment control mould.
Background technology
In the work progress of arch bridge, main arch ring construction is the emphasis of bridge construction, and is frequently run onto the linear unmanageable problem of arch ring in the work progress of main arch ring, encircles particularly in clay model in the construction method of tire.Because the method for hanging wire construction has instability and difficulty to control, bring great inconvenience to construction, usually because arch tire and bed die are linear inaccurate, cause whole main arch ring alignment control bad, affect the presentation quality of arch bridge.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of main arch ring geometric control mould, can effectively solve linear problem rambunctious in main arch ring work progress.
In order to solve above-mentioned technical problem, the technical scheme is that
nullA kind of main arch ring geometric control mould,Including the main muscle in top in the same plane、The main muscle in the end、Multiple first chevron and multiple second chevron,Push up the main muscle of main muscle and the end to form all in accordance with main arch ring span and camber bending,Push up the radial spacing between the main muscle of main muscle and the end equal to the main arch ring thickness removing top side protective layer,Push up the arc area formed between the main muscle of main muscle and the end and the main arch ring shape removing top side protective layer to coincide,The opening of the first chevron and the second chevron is the main muscle end of towards all,Arcuately zone length direction,First chevron and the second chevron are sequentially alternately arranged,The tip of the first chevron is fixing with the main muscle in top to be connected,Two openings of the first chevron are all fixing with the main muscle in the end to be connected,Two openings of the second chevron are all fixing with the main muscle in the end to be connected,The fixed connection point of two adjacent open end and the main muscle in the end that are belonging respectively to the first chevron and the second chevron overlaps.
Above-mentioned main arch ring geometric control mould, the symmetrical center line of the first chevron and the equal radial arrangement of symmetrical center line of the second chevron.
Above-mentioned main arch ring geometric control mould, for being positioned at first chevron at arc area length direction two ends, its most advanced and sophisticated fixing with main muscle end, top is connected, and an opening is fixed with main muscle end, the end and is connected, and another opening is fixing with the main muscle in the end to be connected.
Above-mentioned main arch ring geometric control mould, the second chevron is little compared with the first chevron, and the second chevron is most advanced and sophisticated to be pushed up between main muscle and the main muscle in the end.
Above-mentioned main arch ring geometric control mould, many compared with the second chevron one of the first chevron.
Pushing up and adopt the first chevron to connect between the main muscle of main muscle and the end, the first chevron and the triangle structure of main muscle, bulk strength is high, and the second chevron is same with the triangle structure of main muscle, improves bulk strength further.The stability utilizing triangle makes main arch ring alignment control mould structure consolidate, and resistance capacity to deformation is strong, it is possible to the effective problem solving main arch ring alignment control difficulty.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, the present invention is described in more detail:
Fig. 1 is the structural representation of the present invention.
In figure: 1 pushes up main muscle, the 2 main muscle in the end, 3 first chevron, 4 second chevron.
Detailed description of the invention
As it is shown in figure 1, main arch ring geometric control mould includes the main muscle in top in the same plane 1, the main muscle in the end 2, multiple first chevron 3 and multiple second chevron 4.Push up the main muscle of main muscle and the end to form all in accordance with main arch ring span and camber bending; push up the radial spacing between the main muscle of main muscle and the end equal to the arch ring thickness removing top side protective layer, push up the arc area formed between the main muscle of main muscle and the end and the main arch ring shape removing top side protective layer and coincide.The opening of the first chevron and the second chevron is main muscle, arcuately zone length the direction end of towards all, and the first chevron and the second chevron are sequentially alternately arranged.The tip of the first chevron is fixing with the main muscle in top to be connected, two openings of the first chevron are all fixing with the main muscle in the end to be connected, two openings of the second chevron are all fixing with the main muscle in the end to be connected, and the fixed connection point of two adjacent open end and the main muscle in the end that are belonging respectively to the first chevron and the second chevron overlaps.
Specifically, the equal radial arrangement of symmetrical center line of the symmetrical center line of the first chevron and the second chevron.
Specifically, for being positioned at first chevron at arc area length direction two ends, its most advanced and sophisticated fixing with main muscle end, top is connected, and an opening is fixed with main muscle end, the end and is connected, and another opening is fixing with the main muscle in the end to be connected.
Specifically, the second chevron is little compared with the first chevron, and the second chevron is most advanced and sophisticated to be pushed up between main muscle and the main muscle in the end.
Specifically, many compared with the second chevron one of the first chevron.
Main arch ring geometric control Mold Making process:
First the main muscle in the end is made according to main arch ring span and camber; main arch ring thickness deducts top side protective layer thickness and is the radial spacing pushed up between main muscle and the main muscle in the end; then make and push up main muscle; pushing up and adopt the first chevron connection, the first chevron and the triangle structure of main muscle between the main muscle of main muscle and the end, bulk strength is high; finally; second chevron is connected with main muscle, and the second chevron is same with the triangle structure of main muscle, improves bulk strength further.Mould adopts the modelling of simply supported beam, has stable firmly characteristic, and has simple in construction, the feature of use light, easily controllable.
Main arch ring geometric control method:
In bed die work progress, main arch ring geometric control mould is stuck on arch tire or bed die and just can find out deviation, thickness of protection tier can also be controlled in the process that arch ring reinforcing bar side is pricked.It is particularly suited in the method that clay model encircles tire method construction main arch ring, both can be used to control the linear of bottom arch tire, and the linear of bed die can have been controlled again and can also control thickness of protection tier, decrease the error problem that hanging wire construction brings.

Claims (5)

  1. null1. a main arch ring geometric control mould,It is characterized in that: include the main muscle in top in the same plane、The main muscle in the end、Multiple first chevron and multiple second chevron,Push up the main muscle of main muscle and the end to form all in accordance with main arch ring span and camber bending,Push up the radial spacing between the main muscle of main muscle and the end equal to the main arch ring thickness removing top side protective layer,Push up the arc area formed between the main muscle of main muscle and the end and the main arch ring shape removing top side protective layer to coincide,The opening of the first chevron and the second chevron is the main muscle end of towards all,Arcuately zone length direction,First chevron and the second chevron are sequentially alternately arranged,The tip of the first chevron is fixing with the main muscle in top to be connected,Two openings of the first chevron are all fixing with the main muscle in the end to be connected,Two openings of the second chevron are all fixing with the main muscle in the end to be connected,The fixed connection point of two adjacent open end and the main muscle in the end that are belonging respectively to the first chevron and the second chevron overlaps.
  2. 2. main arch ring geometric control mould according to claim 1, it is characterised in that: the symmetrical center line of the first chevron and the equal radial arrangement of symmetrical center line of the second chevron.
  3. 3. main arch ring geometric control mould according to claim 1 and 2, it is characterized in that: for being positioned at first chevron at arc area length direction two ends, its most advanced and sophisticated fixing with main muscle end, top is connected, one opening is fixed with main muscle end, the end and is connected, and another opening is fixing with the main muscle in the end to be connected.
  4. 4. main arch ring geometric control mould according to claim 1, it is characterised in that: the second chevron is little compared with the first chevron, and the second chevron is most advanced and sophisticated to be pushed up between main muscle and the main muscle in the end.
  5. 5. main arch ring geometric control mould according to claim 1, it is characterised in that: many compared with the second chevron one of the first chevron.
CN201410744030.3A 2014-12-09 2014-12-09 Main arch ring geometric control mould Active CN105735128B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410744030.3A CN105735128B (en) 2014-12-09 2014-12-09 Main arch ring geometric control mould

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410744030.3A CN105735128B (en) 2014-12-09 2014-12-09 Main arch ring geometric control mould

Publications (2)

Publication Number Publication Date
CN105735128A true CN105735128A (en) 2016-07-06
CN105735128B CN105735128B (en) 2017-07-07

Family

ID=56237816

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410744030.3A Active CN105735128B (en) 2014-12-09 2014-12-09 Main arch ring geometric control mould

Country Status (1)

Country Link
CN (1) CN105735128B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004204572A (en) * 2002-12-26 2004-07-22 Shimizu Corp Construction method of arched structure
CN202369931U (en) * 2011-12-29 2012-08-08 浙江大东吴集团建设有限公司 Arch ring bracket
RU2485243C1 (en) * 2011-12-23 2013-06-20 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Arched span
CN103243691A (en) * 2013-04-24 2013-08-14 葛洲坝集团第五工程有限公司 Prefabricated steel formwork for gallery top arch of dam absorption basin
CN104099871A (en) * 2014-06-19 2014-10-15 中铁十一局集团第二工程有限公司 Arching structure of high large-span bridge bailey beams and construction method thereof
CN204298744U (en) * 2014-12-09 2015-04-29 济南黄河路桥工程公司 Main arch ring geometric control mould

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004204572A (en) * 2002-12-26 2004-07-22 Shimizu Corp Construction method of arched structure
RU2485243C1 (en) * 2011-12-23 2013-06-20 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Arched span
CN202369931U (en) * 2011-12-29 2012-08-08 浙江大东吴集团建设有限公司 Arch ring bracket
CN103243691A (en) * 2013-04-24 2013-08-14 葛洲坝集团第五工程有限公司 Prefabricated steel formwork for gallery top arch of dam absorption basin
CN104099871A (en) * 2014-06-19 2014-10-15 中铁十一局集团第二工程有限公司 Arching structure of high large-span bridge bailey beams and construction method thereof
CN204298744U (en) * 2014-12-09 2015-04-29 济南黄河路桥工程公司 Main arch ring geometric control mould

Also Published As

Publication number Publication date
CN105735128B (en) 2017-07-07

Similar Documents

Publication Publication Date Title
CN105292678B (en) A kind of pallet
CN203729343U (en) Connector device for underground continuous walls
CN204996979U (en) Automatic bar straightener of unsmooth seamless formula
CN204298744U (en) Main arch ring geometric control mould
CN103911950B (en) A kind of large-scale combined joist steel girder whole hole preparation method
CN203729202U (en) Combined bridge deck
CN207205010U (en) A kind of sliceable bending die
CN105735128A (en) Linear control mold for main arch ring construction
CN104325080B (en) A kind of shrinkage factor method for designing of leafy group of stator precision casting mould
CN208934441U (en) A kind of English truss assembly tooling
CN105268761A (en) Large-diameter thick-walled longitudinal submerged-arc welding pipe based on J-forming C-forming O-forming and Compression to make round (JCOC) forming process
GB2411183A (en) Bar for reinforced concrete
CN107974921B (en) Viaduct, bridge pier and special-shaped variable-section bent cap
CN104014705B (en) A kind of star-wheel mould
CN106147800B (en) A kind of coke oven flue lining construction method
CN104164933B (en) Steel frame prestressing force junked tire residential building board
CN204185019U (en) Integral type winding roll
CN204549232U (en) A kind of spliced abrasion-proof helical blade
CN208978068U (en) A kind of Spliced type bay window mold
CN105677944B (en) The overall size of stretch bending mold determines method
CN204846002U (en) Arc spare transport vechicle
CN205248597U (en) Wire and cable linear engine
CN221000572U (en) Asymmetric butterfly-shaped multi-arch foot structure
CN204998995U (en) L type glass support
CN204057862U (en) Pneulift

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: The northern section of Huanggang Flyover District of Shandong province Ji'nan City Road 250000 No. 1

Applicant after: Jinan Yellow River Construction Group Co., Ltd.

Address before: 250032 Ji'nan City, Central District, Shandong City, the town of Li Li Li River District, No. sixteen District, building No. 3, building No. 8

Applicant before: Jinan Huanghe Luqiao Engineering Company

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant