CN105735087A - Garden ground surface decoration construction process - Google Patents
Garden ground surface decoration construction process Download PDFInfo
- Publication number
- CN105735087A CN105735087A CN201610057990.1A CN201610057990A CN105735087A CN 105735087 A CN105735087 A CN 105735087A CN 201610057990 A CN201610057990 A CN 201610057990A CN 105735087 A CN105735087 A CN 105735087A
- Authority
- CN
- China
- Prior art keywords
- ground
- garden
- mortar
- paving
- brush
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C15/00—Pavings specially adapted for footpaths, sidewalks or cycle tracks
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C5/00—Pavings made of prefabricated single units
- E01C5/02—Pavings made of prefabricated single units made of natural stones, e.g. sett stones
Abstract
The invention relates to the technical field of garden landscape, in particular a garden ground surface decoration construction process. The garden ground surface decoration construction process specifically comprises the following steps of first, cleaning a site, wherein sundries on the ground hardening are cleaned, mortar bonded on the ground hardening is brushed away by using a steel wire brush and the ground is cleaned up; second, controlling wiring elevation, wherein an elevation control pile is made according to design requirements and a control wire is pulled; third, brushing neat cement grout and laying a mortar binding course, wherein the neat cement grout is first brushed and then a course of 3.5 cm thick dry hard cement mortar is laid; and fourth, trial patching and composing, wherein the trial patching and composing are needed before final laying to be convenient for timely adjustment. According to the invention, through adoption of the construction process, the whole garden ground realizes good water permeability, the water is rapidly drained in rains and snows without being accumulated, the service life of the ground is greatly prolonged, the maintenance cost of the ground is also greatly reduced, the garden ground is beautiful and elegant and the aesthetic property of the garden is effectively improved.
Description
Technical field
The present invention relates to garden landscape technical field, be specifically related to a kind of ground, gardens facial ornament construction technology.
Background technology
Ground, gardens facial ornament is one of fundamental constituting gardens, is mainly used in organization space, the guiding visit of division scenic spot, sets off scenery and traffic connection.The structure on ground, existing gardens mostly is casting concrete layer on element soil matrix layer, then directly on concrete layer, surface layer is directly laid, this kind of garden line structure is not only easier to crack or depression occur, and due to its bad hydraulic permeability, it is allowed to damage through the erosion of rainwater for a long time, in turn results in aesthetic property difference and vehicle accident.Additionally, the laying construction technological operation of existing garden road is loaded down with trivial details, quantities is big, and time-consuming length and laying quality are unsatisfactory.
Summary of the invention
It is an object of the invention to provide one and can solve the problem that problems of the prior art, and effectively strengthen the water penetration on ground, texture and spatial landscape effect, extend ground, the gardens facial ornament construction technology in its service life.
In order to solve the problem existing for background technology, the present invention is by the following technical solutions: a kind of ground, gardens facial ornament construction technology, specifically includes following steps:
The first step, place cleaning, by peace and quiet for the foreign material on hardened ground, brush off the mortar being bonded in hardening with wire brush and clean up;
Second step, wiring absolute altitude controls, and according to design requirement, carries out absolute altitude and controls stake and drawn control line;
3rd step, brush lean concrete grout and mortar laying binder course, first brush one lean concrete grout, and then paving a layer thickness is the dry cement mortar of 3-5cm;
4th step, examination is composed and laid out version, before formal laying, need to carry out examination and compose and lay out version, in order to adjust in time;
5th step, paving stone material, first choose stone material, carry out paving according to according to absolute altitude control line;
6th step, the cementation of fissures, wiping seam, after stone material paving completes, carry out the cementation of fissures by the cement mortar of 1:1;
7th step, late maintaining.
The method have the advantages that a kind of ground, gardens of the present invention facial ornament construction technology, including place cleaning, the control of wiring absolute altitude, brush lean concrete grout and mortar laying binder course, the steps such as version, paving stone material, the cementation of fissures, wiping seam, late maintaining of trying to compose and lay out;The present invention uses above-mentioned construction technology so that whole landscape ground mask has good water penetration, at sleety weather draining the most not hydrops, substantially prolongs the service life on ground, and it has been greatly reduced its maintenance cost, and the most elegant in appearance, effectively enhance the aesthetic property in gardens.It addition, this ground, gardens facial ornament construction technology is simple, easy and simple to handle, efficiency is high, also improves construction quality while having saved construction cost.
Detailed description of the invention
Embodiment one:
A kind of ground, gardens facial ornament construction technology, specifically includes following steps:
The first step, place cleaning, by peace and quiet for the foreign material on hardened ground, brush off the mortar being bonded in hardening with wire brush and clean up;
Second step, wiring absolute altitude controls, and according to design requirement, carries out absolute altitude and controls stake and drawn control line;
3rd step, brush lean concrete grout and mortar laying binder course, first brush one lean concrete grout, and then paving a layer thickness is the dry cement mortar of 3cm;So so that processing solidifies;
4th step, examination is composed and laid out version, before formal laying, need to carry out examination and compose and lay out version, in order to adjust in time;
5th step, paving stone material, first choose stone material, carry out paving according to according to absolute altitude control line;Need to draw cross hairs before concrete paving, horizontal logical vertically without the fissure of displacement with the flatness and gap ensureing surface layer;Should take when paving stone material smear slurry and full stone material paving face need to be smeared, plasma burning should not be used, it is to avoid the quality problems such as hollowing occur;
6th step, the cementation of fissures, wiping seam, after stone material paving completes, carry out the cementation of fissures by the cement mortar of 1:1;When wiping seam, gap-grouting material should being filled gap, and clean out the dirty place of stone material surface layer, if there being accumulation of salt in the surface soil phenomenon, preferably cleaning up with vinegar, oxalic acid etc., wipe seam full flush with stone material, clean, attractive in appearance;
7th step, late maintaining, need after having constructed to isolate construction area, in order to avoid artificially trampling destruction, and surface layer need to be covered.
Embodiment two:
A kind of ground, gardens facial ornament construction technology, specifically includes following steps:
The first step, place cleaning, by peace and quiet for the foreign material on hardened ground, brush off the mortar being bonded in hardening with wire brush and clean up;
Second step, wiring absolute altitude controls, and according to design requirement, carries out absolute altitude and controls stake and drawn control line;
3rd step, brush lean concrete grout and mortar laying binder course, first brush one lean concrete grout, and then paving a layer thickness is the dry cement mortar of 4cm;
4th step, examination is composed and laid out version, before formal laying, need to carry out examination and compose and lay out version, in order to adjust in time;
5th step, paving stone material, first choose stone material, carry out paving according to according to absolute altitude control line;
6th step, the cementation of fissures, wiping seam, after stone material paving completes, carry out the cementation of fissures by the cement mortar of 1:1;
7th step, late maintaining.
In the present embodiment, other is all identical with embodiment one.
Embodiment three:
A kind of ground, gardens facial ornament construction technology, specifically includes following steps:
The first step, place cleaning, by peace and quiet for the foreign material on hardened ground, brush off the mortar being bonded in hardening with wire brush and clean up;
Second step, wiring absolute altitude controls, and according to design requirement, carries out absolute altitude and controls stake and drawn control line;
3rd step, brush lean concrete grout and mortar laying binder course, first brush one lean concrete grout, and then paving a layer thickness is the dry cement mortar of 5cm;
4th step, examination is composed and laid out version, before formal laying, need to carry out examination and compose and lay out version, in order to adjust in time;
5th step, paving stone material, first choose stone material, carry out paving according to according to absolute altitude control line;
6th step, the cementation of fissures, wiping seam, after stone material paving completes, carry out the cementation of fissures by the cement mortar of 1:1;
7th step, late maintaining.
In the present embodiment, other is all identical with embodiment one.
Finally illustrate is, above example is only in order to illustrate technical scheme and unrestricted, other amendment or equivalents that technical scheme is made by those of ordinary skill in the art, without departing from the spirit and scope of technical solution of the present invention, all should contain in the middle of scope of the presently claimed invention.
Claims (1)
1. ground, gardens facial ornament construction technology, it is characterised in that specifically include following steps:
The first step, place cleaning, by peace and quiet for the foreign material on hardened ground, brush off the mortar being bonded in hardening with wire brush and clean up;
Second step, wiring absolute altitude controls, and according to design requirement, carries out absolute altitude and controls stake and drawn control line;
3rd step, brush lean concrete grout and mortar laying binder course, first brush one lean concrete grout, and then paving a layer thickness is the dry cement mortar of 3-5cm;
4th step, examination is composed and laid out version, before formal laying, need to carry out examination and compose and lay out version, in order to adjust in time;
5th step, paving stone material, first choose stone material, carry out paving according to according to absolute altitude control line;
6th step, the cementation of fissures, wiping seam, after stone material paving completes, carry out the cementation of fissures by the cement mortar of 1:1;
7th step, late maintaining.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610057990.1A CN105735087A (en) | 2016-01-28 | 2016-01-28 | Garden ground surface decoration construction process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610057990.1A CN105735087A (en) | 2016-01-28 | 2016-01-28 | Garden ground surface decoration construction process |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105735087A true CN105735087A (en) | 2016-07-06 |
Family
ID=56246886
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610057990.1A Pending CN105735087A (en) | 2016-01-28 | 2016-01-28 | Garden ground surface decoration construction process |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105735087A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106400653A (en) * | 2016-10-31 | 2017-02-15 | 安徽汇顿电子科技有限公司 | Paving method for landscape garden road |
CN111622450A (en) * | 2020-06-05 | 2020-09-04 | 陕西福磊建设集团有限公司 | Stone ground construction process |
-
2016
- 2016-01-28 CN CN201610057990.1A patent/CN105735087A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106400653A (en) * | 2016-10-31 | 2017-02-15 | 安徽汇顿电子科技有限公司 | Paving method for landscape garden road |
CN111622450A (en) * | 2020-06-05 | 2020-09-04 | 陕西福磊建设集团有限公司 | Stone ground construction process |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103470067B (en) | Transformation and construction method used for facing bare concrete of existing building outer wall | |
CN103806356B (en) | A kind of preparation method of decorative concrete earth construction | |
CN106284706A (en) | The construction method of external wall outer insulation rock cotton board | |
CN107152145A (en) | A kind of stone material flooring construction method | |
CN108625252A (en) | Urban road laying construction method | |
CN105040554A (en) | Garden path structure and paving construction technology thereof | |
CN106758638A (en) | A kind of city sponge brick and its construction technology | |
CN103437521A (en) | Plastic external corner angle bead for inner wall of building and construction method for internal and external corners of inner wall of building | |
CN106284998A (en) | Plastering on inner walls completely spreads fiberglass gridding cloth construction method | |
CN103572931B (en) | Construction method of building ceramic thin plate hanging and cementing structure | |
CN110271355A (en) | A kind of construction method of plastic stone rockery | |
CN105735087A (en) | Garden ground surface decoration construction process | |
CN109930856A (en) | A kind of the old and new's wall concatenation construction method | |
CN203373918U (en) | Waterproofing work construction structure of pseudo-classic architecture roof cornice | |
CN107724642A (en) | The construction method of color wearing proof terrace | |
CN204326453U (en) | Thick-layer Self-leveling leveling layer structure | |
CN106639000A (en) | Dry-wet-area separation water proof structure and construction method | |
CN203795263U (en) | ECC durable colored pavement structure | |
CN206143550U (en) | Concrete mat formation piece or structure of mating formation on stone material road surface | |
CN113668885B (en) | Plastering anti-cracking construction method for large-area arc-shaped stand | |
CN105155388A (en) | Road surface laying method for exposed aggregate finish | |
CN105155387A (en) | Garden road structure | |
CN202466991U (en) | Waterproof ground beam | |
CN101565991A (en) | Construction method for large-area inverse parking and accessible roof layer | |
CN204356736U (en) | A kind of anti-accumulation of salt in the surface soil pond stone material paving structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20160706 |