CN105730867B - A kind of pin-connected panel modularization reinforcing bar lodging bench and its assembling method - Google Patents

A kind of pin-connected panel modularization reinforcing bar lodging bench and its assembling method Download PDF

Info

Publication number
CN105730867B
CN105730867B CN201610089669.1A CN201610089669A CN105730867B CN 105730867 B CN105730867 B CN 105730867B CN 201610089669 A CN201610089669 A CN 201610089669A CN 105730867 B CN105730867 B CN 105730867B
Authority
CN
China
Prior art keywords
merogenesis
column
pin
reinforcing bar
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610089669.1A
Other languages
Chinese (zh)
Other versions
CN105730867A (en
Inventor
程永志
张有军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU
Original Assignee
THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU filed Critical THIRD ENGINEERING Co Ltd OF CCCC SECOND HIGHWAY ENGINEERING BUREAU
Priority to CN201610089669.1A priority Critical patent/CN105730867B/en
Publication of CN105730867A publication Critical patent/CN105730867A/en
Application granted granted Critical
Publication of CN105730867B publication Critical patent/CN105730867B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65DCONTAINERS FOR STORAGE OR TRANSPORT OF ARTICLES OR MATERIALS, e.g. BAGS, BARRELS, BOTTLES, BOXES, CANS, CARTONS, CRATES, DRUMS, JARS, TANKS, HOPPERS, FORWARDING CONTAINERS; ACCESSORIES, CLOSURES, OR FITTINGS THEREFOR; PACKAGING ELEMENTS; PACKAGES
    • B65D61/00External frames or supports adapted to be assembled around, or applied to, articles

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of pin-connected panel modularization reinforcing bar lodging bench and its assembling methods, it is related to field of civil engineering, pin-connected panel modularization reinforcing bar lodging bench includes bottom beam and column, bottom beam is made of several tap beams, junction steel plate is equipped between merogenesis beam and merogenesis beam, the two sides of merogenesis beam are equipped with anchoring ear, the column bottom is located in merogenesis beam, the bottom of column is equipped with pin clamp, the middle overlapping of axles of pin clamp and pin hole, column is equipped with fixation steel plate above bottom beam, and the bottom of fixation steel plate is fixed on the upper surface of bottom beam., site planning and arrangement a kind of method of assembly reinforcing bar lodging bench, comprising the following steps: (1);(2), bottom beam is installed;(3), column is installed;(4), reinforcing bar is placed;(5), it removes.This lodging bench using double flute steel process, mainly by bottom beam, column, form.Bottom beam is made of merogenesis beam, and each section merogenesis beam can connect lengthening with previous merogenesis beam by the dovetail key of tail portion.

Description

A kind of pin-connected panel modularization reinforcing bar lodging bench and its assembling method
Technical field
The present invention relates to field of civil engineering, and in particular to a kind of pin-connected panel modularization reinforcing bar lodging bench.
Background technique
In Construction of Civil Engineering field, raw material of reinforcement rebar and processing semi-finished product, finished product required to be stored in centainly from On the storage pedestal of ground height, to prevent getting rusty and deforming, previous storage pedestal is all formed using concrete placings substantially, workload Greatly, need to consume a large amount of concrete, and the pedestal size, size, spacing are fixed, it can not be according to the reinforcing bar material stored Material strip part height, spacing, bad adaptability;Concrete lodging bench is disposable simultaneously, can not reuse after the completion of use, understand concrete Pedestal needs to expend a large amount of artificial, equipment, and generates many building wastes, welding, influences periphery ecology.How to solve Certainly pedestal is disposable, and waste is big, and pollution is basic principle of the invention greatly.
The present invention solves traditional lodging bench size and fixes defect that is unadjustable, can only disposably utilizing, has and saves money Efficiency, non-staining feature is turned up in source.
Summary of the invention
In view of the deficiencies of the prior art, the purpose of the present invention is to provide it is a kind of construction with it is detachable, reusable, can The pin-connected panel modularization reinforcing bar lodging bench arbitrarily extended.
Present invention solves the technical problem that can be realized using following technical scheme: a kind of pin-connected panel modularization reinforcing bar is deposited Platform, including bottom beam and column are put, wherein the bottom beam is made of several tap beams, connection steel is equipped between merogenesis beam and merogenesis beam Plate, for two end caps of junction steel plate in merogenesis beam, the two sides of merogenesis beam are equipped with anchoring ear, and merogenesis beam upper surface is equipped with several fixations Hole, merogenesis beam two sides are equipped with pin hole, and pin hole is located on identical vertical plane with the axis of fixation hole, and the column bottom is located at In fixation hole, the bottom of column is equipped with pin clamp, the middle overlapping of axles of pin clamp and pin hole, and column is equipped with fixed steel above bottom beam Plate, fixation steel plate are socketed on column, and the bottom of fixation steel plate is fixed on the upper surface of bottom beam.
Preferably, the merogenesis beam and column are formed by channel steel make-up.
Preferably, the both ends of the merogenesis beam are equipped with dovetail key, and the junction steel plate is connected on dovetail key, the fixation It is to be threadedly coupled between the two sides of steel plate and merogenesis beam.
A kind of method of assembly reinforcing bar lodging bench, including following steps: (1), site planning and arrangement: according to reinforcing bar Quantity, specification, length, tonnage of storage etc. select place, then plan lodging bench planar dimension, and bottom beam position is carried out setting-out Mark;
(2), bottom beam is installed: bottom beam being disposed according to setting-out position by row, first sequentially installs first row merogenesis beam by side It is good, then successively install other merogenesis beams;
(3), column is installed: it is unified on bottom beam to release stud, column is then installed one by one;
(4), it places reinforcing bar: successively storing all kinds of steel according to classification, specification on lodging bench;
(5), it removes: being removed after the completion of lodging bench use according to the sequence that first dismounting column removes bottom beam again.
Preferably, the installation bottom beam is first anchoring pins connecting bolt in the step (2), then installs anchor bolt.
Preferably, the installation column is to tighten pin joint bolt in the step (3), installs dovetail key and anchors.
Beneficial effect is: this lodging bench is processed using double flute steel, by bottom beam, column, connecting pin, dovetail key, anchoring ear group At.Bottom beam is made of merogenesis beam, and each section merogenesis beam can connect lengthening, root with previous merogenesis beam by the dovetail key of tail portion According to needing length arbitrarily to splice.Anchoring ear of the merogenesis beam by two sides is anchored directly to ground with expansion bolt.Merogenesis beam side There is one group of pin hole in face at interval of certain distance, to vertical columns, according to can arbitrarily be adjusted according to the quantity of storage, specification requirement The position of whole column;Column lower end has pin clamp, is directly inserted into bottom beam, then fixed by anchor bolt;Column Two sides are fixed on bottom beam by dovetail key, to increase rigidity and prevent compressive deformation.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of pin-connected panel modularization reinforcing bar lodging bench of the present invention;
Fig. 2 is the cross-sectional view at the I of a kind of pin-connected panel modularization reinforcing bar lodging bench of the present invention;
Fig. 3 is the cross-sectional view at the II of a kind of pin-connected panel modularization reinforcing bar lodging bench of the present invention;
Fig. 4 is the cross-sectional view at the III of a kind of pin-connected panel modularization reinforcing bar lodging bench of the present invention;
Fig. 5 is a kind of structural schematic diagram of the column of pin-connected panel modularization reinforcing bar lodging bench of the present invention;
Wherein 1, bottom beam;2, merogenesis beam;3, column;4, junction steel plate;5, fixation steel plate;6, dovetail key;7, pin hole;8, it inserts Lock-joint.
Specific embodiment
The preferred embodiment that the invention will now be described in detail with reference to the accompanying drawings.
Fig. 1-Fig. 5 shows a kind of a kind of specific embodiment of pin-connected panel modularization reinforcing bar lodging bench of the present invention: pin-connected panel Modularization reinforcing bar lodging bench, including bottom beam 1 and column 3, wherein the bottom beam 1 is made of several tap beams, merogenesis beam 2 and merogenesis Junction steel plate 4 is equipped between beam 2, for two end caps of junction steel plate 4 in merogenesis beam 2, the two sides of merogenesis beam 2 are equipped with anchoring ear, point It saves 2 upper surface of beam and is equipped with several fixation holes, 2 two sides of merogenesis beam are equipped with pin hole 7, and pin hole 7 and the axis of fixation hole are located at phase With on vertical plane, 3 bottom of column is located in mounting hole, and the bottom of column 3 is equipped with pin clamp 8, pin clamp 8 and pin hole 7 Middle overlapping of axles, column 3 are equipped with fixation steel plate 5 above bottom beam 1, and fixation steel plate 5 is socketed on column 3, the bottom of fixation steel plate 5 It is fixed on the upper surface of bottom beam 1.
In conjunction with attached drawing, the merogenesis beam 2 is formed with column 3 by channel steel make-up.The bottom beam 1 is by two panels channel steel make-up It forms, monolithic size is fixed, and one end is incoming end, and one end is to pick out end;The column 3 also has the slot with 1 same specification of bottom beam Steel make-up forms, and thickness is slightly thick, and one end is pin end, guarantees 1 outside of discrepancy bottom beam that can be convenient and is anchored.Described point The both ends for saving beam 2 are equipped with dovetail key 6, and the junction steel plate 4 is connected on dovetail key 6, the two sides of the fixation steel plate 5 and merogenesis It is pin connection between beam 2, it is all Slotted bores that all connecting pins, which are enhancing size adaptability,.Main member is rectangle, convenient Transport and dismounting.
This lodging bench is processed using double flute steel, is made of bottom beam 1, column 3, connecting pin, dovetail key 6, anchoring ear.Bottom beam 1 It being made of merogenesis beam 2, each section merogenesis beam 2 can be lengthened by the dovetail key 6 and the previous connection of merogenesis beam 2 of tail portion, according to Length is needed arbitrarily to splice.Anchoring ear of the merogenesis beam 2 by two sides is anchored directly to ground with expansion bolt.2 side of merogenesis beam There is one group of pin hole 7 in face at interval of certain distance, to vertical columns 3, according to can be random according to the quantity of storage, specification requirement Adjust the position of column 3;There is pin clamp 8 in 3 lower end of column, is directly inserted into bottom beam 1, is then by anchor bolt fixation It can;3 two sides of column are fixed on bottom beam 1 by dovetail key 6, to increase rigidity and prevent compressive deformation
A kind of method of assembly reinforcing bar lodging bench, including following steps: (1), site planning and arrangement: according to reinforcing bar Quantity, specification, length, tonnage of storage etc. select place, then plan lodging bench planar dimension, 1 position of bottom beam is put Sample mark;(2), bottom beam 1 is installed: bottom beam 1 being disposed according to setting-out position by row, first sequentially pacifies first row merogenesis beam 2 by side It installs, then successively installs other merogenesis beams 2, bottom beam 1 is first anchoring pins connecting bolt, then installs anchor bolt;(3), Column 3 is installed: it is unified on bottom beam 1 to release 3 position of column, column 3 is then installed one by one, column 3 is to tighten pin joint bolt, Dovetail key 6 is installed to anchor;(4), it places reinforcing bar: successively storing all kinds of steel according to classification, specification on lodging bench; (5), it removes: being removed after the completion of lodging bench use according to the sequence that first dismounting column 3 removes bottom beam 1 again.
Based on above-mentioned, all components of this lodging bench are all the modularization steel members of combinable uniform sizes, when processing It is efficient, convenient when simplicity, installation and disassembly;All materials have all kinds of national standard shape extrusions, and all material can take on the spot Material is processed on the spot, easy to process;The transverse and longitudinal size of pedestal and indirectly can be according to deposited reinforcing bar, the length of bar material, number Amount is arbitrarily adjusted, and has very strong scalability;All components can be used in turn repeatedly, and the proportion of goods damageds are extremely low, improve material Expect utilization rate;Processing, use process do not have any pollution.
The above description is only an embodiment of the present invention, is not intended to limit the scope of the invention, all to utilize this hair Equivalent structure or equivalent flow shift made by bright specification and accompanying drawing content is applied directly or indirectly in other relevant skills Art field, is included within the scope of the present invention.

Claims (2)

1. a kind of pin-connected panel modularization reinforcing bar lodging bench, including bottom beam and column, it is characterised in that: the bottom beam is by several taps Beam composition, is equipped with junction steel plate, two end caps of junction steel plate are in merogenesis beam, the two sides of merogenesis beam between merogenesis beam and merogenesis beam Equipped with anchoring ear, merogenesis beam upper surface is equipped with several fixation holes, and merogenesis beam two sides are equipped with pin hole, in pin hole and fixation hole In on identical vertical plane, the column bottom is located in mounting hole axle position, and the bottom of column is equipped with pin clamp, pin clamp and pin hole Middle overlapping of axles, column is equipped with fixation steel plate above bottom beam, and fixation steel plate is socketed on column, and the bottom of fixation steel plate is fixed On the upper surface of bottom beam;
The both ends of the merogenesis beam are equipped with dovetail key, and the junction steel plate is connected on dovetail key, the two sides of the fixation steel plate It is to be threadedly coupled between merogenesis beam;
Column two sides are fixed on bottom beam by dovetail key, to increase rigidity and prevent compressive deformation;
The two sides of merogenesis beam are equipped with anchoring ear, and anchoring ear of the merogenesis beam by two sides is anchored directly to ground with expansion bolt;
The merogenesis beam and column are formed by channel steel make-up.
, place 2. a kind of method of reinforcing bar lodging bench described in assembly claim 1, which comprises the following steps: (1) Planning and arrangement: according to the selection such as quantity, specification, length, tonnage of reinforcing bar storage place, lodging bench plane meter is then planned It is very little, bottom beam position is subjected to setting-out mark;
(2), bottom beam is installed: bottom beam being disposed according to setting-out position by row, is first sequentially installed first row merogenesis beam by side, so Other merogenesis beams are successively installed afterwards;
(3), column is installed: it is unified on bottom beam to release stud, column is then installed one by one;
(4), it places reinforcing bar: successively storing all kinds of steel according to classification, specification on lodging bench;
(5), it removes: being removed after the completion of lodging bench use according to the sequence that first dismounting column removes bottom beam again;
The installation bottom beam is first anchoring pins connecting bolt in the step (2), then installs anchor bolt;
The installation column is to tighten pin joint bolt in the step (3), installs dovetail key and anchors.
CN201610089669.1A 2016-02-18 2016-02-18 A kind of pin-connected panel modularization reinforcing bar lodging bench and its assembling method Active CN105730867B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610089669.1A CN105730867B (en) 2016-02-18 2016-02-18 A kind of pin-connected panel modularization reinforcing bar lodging bench and its assembling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610089669.1A CN105730867B (en) 2016-02-18 2016-02-18 A kind of pin-connected panel modularization reinforcing bar lodging bench and its assembling method

Publications (2)

Publication Number Publication Date
CN105730867A CN105730867A (en) 2016-07-06
CN105730867B true CN105730867B (en) 2019-02-26

Family

ID=56245255

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610089669.1A Active CN105730867B (en) 2016-02-18 2016-02-18 A kind of pin-connected panel modularization reinforcing bar lodging bench and its assembling method

Country Status (1)

Country Link
CN (1) CN105730867B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114435778B (en) * 2022-03-07 2024-03-29 浙江路捷顺汽车制造有限公司 Vertical goods shelf for carriage side plate storage and transportation

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004092497A2 (en) * 2003-04-11 2004-10-28 Rizzotto John L Rapid steel frame assembly
CN2802048Y (en) * 2005-03-10 2006-08-02 黎顺焘 Connector of rolling shutter door
CN201546488U (en) * 2009-11-12 2010-08-11 中国建筑第六工程局有限公司 Connecting device for square steel beams and square steel columns of temporary construction fence
CN204726870U (en) * 2015-05-22 2015-10-28 中建三局第一建设工程有限责任公司 A kind of dismantled and assembled extendible reinforcing bar pushes away puts support

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7677522B2 (en) * 2008-05-07 2010-03-16 Bakos Stephen M Support bracket for a column

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004092497A2 (en) * 2003-04-11 2004-10-28 Rizzotto John L Rapid steel frame assembly
CN2802048Y (en) * 2005-03-10 2006-08-02 黎顺焘 Connector of rolling shutter door
CN201546488U (en) * 2009-11-12 2010-08-11 中国建筑第六工程局有限公司 Connecting device for square steel beams and square steel columns of temporary construction fence
CN204726870U (en) * 2015-05-22 2015-10-28 中建三局第一建设工程有限责任公司 A kind of dismantled and assembled extendible reinforcing bar pushes away puts support

Also Published As

Publication number Publication date
CN105730867A (en) 2016-07-06

Similar Documents

Publication Publication Date Title
CN108677685B (en) Ultra-high-performance concrete-part steel beam combined bent cap and construction method thereof
CN208668721U (en) Detachable prefabricated assembled steel-concrete composite beam plate
CN101251448B (en) Construction method of inverse force wall and inverse force dado
US20210048380A1 (en) Multi-functional support capable of transferring horizontal and multi-point local vertical load and implementation method
CN106758856A (en) The construction method of the pretensioned prestressing corrugated steel web plate composite box girder of precast block
CN110983968B (en) Prefabricated assembled FRP (fiber reinforced plastic) -section steel-concrete combined bridge deck and construction method thereof
CN102943481A (en) Reinforced concrete beam and steel beam combined connecting structure for foundation pit supporting and construction method thereof
CN110359452A (en) A kind of nodal-connection components, frame pre-stress cable bolting structure and construction method
CN201953070U (en) Repeatedly usable assembly type processing shed on building construction sites
CN112982142A (en) Cold-formed thin-walled steel web plate combined PC box girder
CN105730867B (en) A kind of pin-connected panel modularization reinforcing bar lodging bench and its assembling method
CN111236517A (en) Detachable prestressed reinforcement truss superimposed sheet
CN207891714U (en) Abdomen packet bottom is trapezoidal/corrugated sheet steel combined box beam
CN211621625U (en) Assembled lattice beam side slope supporting construction
CN201176366Y (en) Hook structure for suspensing transportation device added in buildings
CN202097833U (en) Steel-concrete girder fabricating pedestal with small independent concrete foundations
CN109773960B (en) Multi-size assembled T-beam tooth block steel bar pre-binding device
CN204825945U (en) A fixture for fixing buried bolt in advance
CN208052253U (en) A kind of positioning moulding bed prefabricated for T beam web reinforced frames
CN206418410U (en) A kind of compressor wire anchor system
CN214170072U (en) Steel construction factory building structure based on exposed foundation
CN211872631U (en) Connecting device for bridge panels
CN104612030B (en) Small-span steel mixed composite bridge plate and construction technology thereof
CN209308165U (en) A kind of pin-connected panel lightweight steel construction face construction apply in feed bin canopy
CN109555310B (en) Integral template of wall column and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant